HomeMy WebLinkAboutContract 56750-R1CITY OF FORT WORTH
CONTRACT RENEWAL NOTICE
July 11, 2025
Alan Plummer Associates, Inc.
Attn: Mr. Shawn Dankenbring, P.E.
1320 S. University Dr, Suite 300
Fort Worth, TX 76107
Re: Contract Renewal Notice — First Renewal
2021 Citywide Drainage Improvements Design
Contract CSC No. 56750
September 14, 2021
Original Contract Amount: $300,000.00
1" Amendment Amount: $99,000.00 (CSC No. 56750-A1)
Renewal Term No. 1: July 1, 2025 to September 14, 2026
The above referenced contract with the City of Fort Worth, as renewed, expires with the expenditure
of funds. The funds for the contract have been expanded or programmed. This letter is to inform you
that the City has appropriated funding and is exercising its right to renew the contract in total contract
amount, which will be effective upon execution by the designated Assistant City Manager. All other
terms and conditions of the contract remain unchanged. Please sign in the space indicated below and
return this document, along with a copy of your current insurance certificate, to the undersigned.
Please log onto Peoplesoft Purchasing at http://fortworthtexas.2ov/nurchain2 to ensure that your
company information is correct and up-to-date.
If you have any questions concerning this Contract Renewal Notice, please contact me at the
telephone number listed below.
Sincerely,
Benjamin Thompson, P.E., CFM
Stormwater Capital Delivery
Sr. Professional Engineer
(817) 392-7952
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
CSC No. 56750-R1
FIRST RENEWAL TO CITY SECRETARY
CONTRACT NO. 56750
WHEREAS, the City of Fort Worth ("City") and Alan Plummer Associates, Inc.
("Engineer"), collectively the ("Parties"), made and entered into City Secretary Contract No.
56750 (M&C 21-0670, September 14, 2021) (the "Contract") for 2021 Citywide Drainage
Improvements Design City Project No.: 100092; and
WHEREAS the Contract was amended in the amount of $99,000.00, administratively
authorized on February 20, 2024 to increase funds and amend labor rates; and
WHEREAS, funds for the original Contract, as amended, have been expended or
programmed; and
WHEREAS the Contract may be renewed up to one time as per M&C 21-0670;
NOW, THEREFORE, the Parties, hereby agree as follows:
I.
a. The Contract is hereby renewed in the amount up to $399,000.00 at the same terms,
conditions, and unit prices as amended, thus creating a new "original term" for
purposes of Article III.
b. Task orders will be issued and remain contingent upon the availability of funds and
the availability of the contractor.
II.
All other terms and conditions of the Contract remain unaffected and in full force and
effect.
IN WITNESS WHEREOF, the City and the Contractor have each executed this First
Renewal by and through each Party's duly authorized signatory, effective as of the date subscribed
by the City's designated Assistant City Manager.
BY:
CITY OF FORT WORTH
Jesica McEachern
Assistant City Manager
Date:
09/06/2025
BY:
ENGINEER
Plummer Associates, Inc.
Shawn DanKbrina
Shawn Dankbring (Aug 14, 202515:31:50 MDT) -If
Shawn Dankenbring
Stormwater Team Leader
Date: 08/14/2025
CONTRACT RENEWAL No. 1 CS NO. 56750
Citywide Drainage Improvements Design, City Project No. 100092
OFFICIAL RECORD
CITY SECRETARY
Page 1
FT. WORTH, TX
APPROVAL RECOMMENDED:
By:
Lauren Prieur
Director, TPW
Contract Compliance Manager:
By signing, I acknowledge that I am responsible
for monitoring and administering this contract,
including ensuring all performance and
reporting requirements.
Benjamin Thompson
Sr. Professional Engineer
APPROVED AS TO FORM AND LEGALITY
By: Douglas Black (Aug 18, 202518:20:17 CDT)
Douglas W. Black
Sr. Assistant City Attorney
aIlIl
p� .f..... d0
ATTEST:
Oro S�1d
Jannette Goodall
City Secretary
Form 1295 No.: 2025-1326827
M&C No.: 21-0670
M&C Date: 09/14/2021
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
CONTRACT RENEWAL No. 1 CS NO. 56750 Page 2
Citywide Drainage Improvements Design, City Project No. 100092
City of Fort Worth, Texas
Mayor and Council Communication
I T,i I =;��Ja,900i1
M&C FILE NUMBER: M&C 21-0E70
LOG NAME: 20SWM ALAN PLUMMER CITYWIDE DRAINAGE IMPROVEMENTS DESIGN
SUBJECT
(ALL) Authorize Execution of an Engineering Agreement with Alan Plummer Associates, Inc. in an
Amount Not to Exceed $300,000.00 for Drainage Improvement Projects Citywide
RECOMMENDATION:
It is recommended that the City Council authorize execution of an engineering agreement with
Alan Plummer Associates. Inc. in an amount not to exceed $300,000.00 for the Citywide ❑ra1nage
Improvements project (City Project No. P00043) with one renewal at the City's sole option and a
maximum contract duration of five years.
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to provide for task -ordered
engineering services to design various citywide minor drainage improvement projects that may be
needed from time to time. These projects may involve storm drain extensions, inlets and outfalls,
correcting drainage deficiencies and other minor drainage improvements. This contract is a tool
to quickly respond to small, yet high priority drainage improvement design needs throughout the
City that are identified by community members or staff.
In May 2018, the Transportation and Public Works Department (TPW), Stormwater Management
Division, published a Request for Qualifications (RFQ) for various engineering consulting
services. Based on the results of the RFQ, Alan Plummer Associates, Inc. was selected as the
most qualified consultant to perform these services.
Individual task orders will be SSUed for each project identified to address a local flooding or
drainage need. The cost of each task order will be based on the hours worked at agreed -upon
hourly rates. The total cost of all task orders performed will not exceed $300,000.00. Staff
considers the proposed hourly rates to be fair and reasonable for the size and complexity of the
contemplated projects. This agreement may be renewed one additional time at the City's sole
option subject to available funding.
Business Equity - Alan Plummer Associates, Inc., is in compliance with the City's Business Equity
Ordinance by committing to 10.00% Business Equity participation on this project. The City's
Business Equity goal on this project is 9%.
This project is located in ALL COUNCIL DISTRICTS.
FISCAL INFORMATION 1 CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendation and adoution of
the Fiscal Year 2022 Budget by the City Council, funds will be available in the Fiscal Year CAymdE!Ominagelmvoj rnentg 0009z
2022 capital budget, as previously appropriated, in the Stormwater Capital Projects Fund for
future identified task order projects related to the Drainage Improvement Projects programmable
project to support the approval of the above recommendation and execution of the engineering
agreement. Prior to any expenditure being incurred, the Transportation & Public Works Department
has the responsibility to validate the availability of funds.
Submitted for Cit►i Manager's Office bv:
Oriainatina Business Unit Head:
Additional Information Contact:
Dana Burghdoff 8018
William Johnson 7801
Linda Young 2485
Citywide Drainage Improvements Design
City Project No. 100092
FORT WORTH.:;
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: Alan Plummer Associates, Inc. Ist Renewal
M&C: 21-0670 CPN: 100092 CSO: 56750 DOC#:
Date:
To: Name
Department
Initials
Date Out
1 Shawn Dankenbring — Signature
Engineer
scD
SCD
08/14/202
(sdankenbring@plummer.com)
2. Ben Thompson - Signature
TPW Project Mgr.
8,
08/14/2025
3. Thanaa Maksimos — Review
TPW Program Mgr.
T-.
08/14/2025
4. Lissette Acevedo — Review
TPW Sr. CPO
A
08/18/2025
5. Patricia Wadsack - Review
TPW Asst. Dir.
08/18/2025
6. Lauren Prieur - Signature
TPW Dir.
IMF(
08/18/2025
7. Doug Black - Signature
Legal
-QL--
08/18/2025
8. Jesica McEachern - Signature
CMO
09/06/2025
9. Ronald Gonzales - Review
CSO
09/09/2025
10. Jannette Goodall - Signature
CSO
09/10/2025
11. Allison Tidwell - Review
CSO
09/16/2025
12. TPW—SW—Contracts
TPW SW
CC: Program Manager — Thanaa Maksimos, Sr. CPO — Lissette Acevedo, TPW BSPAP Recon
Team — Cindy Sengathith
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing
slip, David
will review
and take the next steps.
NEEDS TO BE NOTARIZED: []YES ®No
RUSH: []YES ®No SAME DAY: []YES ®No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: tvw sw contracts(i fortworthtexas.eov Call 817-229-3283 with questions. Thank you!