Change Order Request
CSC No. 61420-CO3
Project Name: Q�ty Boulevard Phase 2 -Salado Trail t�hames Trail
Project No.(s):! 103280 DOE No.
I City Sec No.: :::I =6=1=4=2=0========:::_N_/_A ____ I City Proj. No.:._! _1_0_3_28_0 _____,
Project Trinity Boulevard Phase 2 Salado Trail to Thames Trail -Roadway, Drainage, Waterline, Landscape and Description: Illumination Improvements
Contractor: I Jackson Construction, Ltd.;:· ==================.------City Project Mgr.! Mitch Aiton/Preeti KC
Phone Number: I 682-715-9424
Dept. Water Sewer
Original Contract Amount $4,981,705.00 Extras to Date $37,870.79 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $5,019,575.79
IAmount of Proposed Change Order $0.00 Revised Contract Amount $5,019,575.79 Original Funds Available for Change Order $250,000.00 Remaining Funds Available for this CO $212,129.21 Additional Funding (if necessary)
Change Order# 0 Date:
,-----------, City Inspector: Mark Kitts ::===============::::: Phone Number:! (214) 746-5004
TPW Totals
$7,117,637.00 $12,099,342.00 $37,870.79
$7,117,637.00 $12,137,212.79
$0.00 $0.00 $7,117,637.00 $12,137,212.79 $550,000.00 $800,000.00 $550,000.00 $762,129.21
CHANGE ORDERS to DATE {INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT {ORIGINAL CONTRACT COST+ 25%}
0.31% $15,124,177.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
8/7/2025
Contract Time
(Calender days) 730
730
730
Change Order No. 3 will provide for an increased quantity of Waterline Grouting and decreased quantity of
waterline removal. The City of Fort Worth needs to delay the switch from the existing 33" water line to the
new 36" water line until the fall due to water demand from the City of Hurst. This will allow the contractor
to pave over the existing live 33" waterline that was intended to be removed. The contractor can move
forward with paving the North half of the proposed lanes and use the increased quantity of waterline
grouting to abandon the 33" waterline that will be paved over. The contractor has agreed to a price for
increased waterline grouting that results in a $0.00 change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
Jackson Construction, Ltd. Ali Jones Sep 4, 202S
Inspector Date Project Manager Date .... Sep 4, 2025 p..,;;;,<(!, Sep 4, 2025 M1ri<Kittl(sep,,202513'Dl$CDT)
Director (Water Dept) Date Construction Supervisor (Water) Date
ChJ;irl£Jlfwt l(qp(et Sep 22, 2025 -�·Sep 4, 2025 Christopher Harder (Sep 22, 202515:26:41 con Oon•llto)'!Stp',l0251':ZS:Jttol)
Senior Assistant City Attorney Date Assistant City Manager Date
-� Sep 23, 2025 �Sep 24,2025 llo•cl .. 8i.cl<t:..Pll.lmll�OllCOT)
Council Action (If Require::!}
A TT EST: '1J"...-.c1 � I M&C Numbe� N/A IM&C Date Approved I N/A I Jannette Goodall, City Secretary
FC]KT �'VORTH City of Fort Worth
Change Order Additions
Project Name Trinity Boulevard Phase 2- Salado Trail to Thames Trail City Sec No.: 61420
Project No.(s): 103280 DOE No. N/A City Proj. No.: 103280
Project
Description
Trinity Boulevard Phase 2 Salado Trail to Thames Trail - Roadway, Drainage, Waterline, Landscape and
Illumination Improvements
Contractor Jackson Construction, Ltd. hange Order� 3� Date: 8/7/2025
City Project Mgr. Mitch Aiton/Preeti KC City Inspector Mark Kitts
ADDITIONS
� , . . . ���� �
� --�--
„ . • ... . ��' � ��. �� �. : ��
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
� --�--
�. : ��
-
., �, � -
�.. . . . . -
FORT �V�ORTH City of Fort Worth
Change Order Deletions
Project Name Trinity Boulevard Phase 2- Salado Trail to Thames Trail City Sec No.: 61420
Project No.(s): 103280 DOE No. N/A City Proj. No.: 103280
Project
Description
Trinity Boulevard Phase 2 Salado Trail to Thames Trail - Roadway, Drainage, Waterline, Landscape and
Illumination Improvements
Contractor Jackson Construction, Ltd. Change Order: � Date 8/7/2025
City Project Mgr. Mitch Aiton/Preeti KC City Inspector: Mark Kitts
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
II-24 9999.0009 Remove 33" Water Line Water 708.00 LF $62.00 $43,896.00
II-25 0241.1021 Remove 36" Water Line Water 34.00 LF $83.00 $2,822.00
Water
Sewer
718.00
Page 3 of 4 �Deletions Sub Total �$46,718.00
BE Breakdown for this Chan�e Order
MWBE Sub I Tvpe of Service I Amount for this CO
Total � $0.00
Co #
Previous Chan�e Orders
DATE
3/10/2025
AMOUNT
$37,870.79
$0.00
3/27/2025
Total � $37,870.79
Page 4 of 4
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE:Trinity Blvd Ph 2 CO #3
M&C: N/A CPN: 103280 CSO: 61420 DOC#: N/A
Date: 8/7/2025
To: Name Department Initials Date Out
1. Jessica Rodriquez TPW - Approval
2. Mitch Aiton TPW - Approval
3. Ali Jones Jackson - Signature
4. Mark Kitts (Inspector) TPW - Signature
5.Daniel Roy (Const Super)TPW - Signature
6. Preeti KC (PM Sign) Water - Signature
7. Tony Sholola Water - Approval
8. Chris Harder (Director)– Water Signature
9. Doug Black – Legal Signature
10. Jesica McEachern (ACM)– Water Signature
11. Jannette Goodall CSO - Signature
12. TPW Contracts
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW
Contracts
DOCUMENTS FOR CITY MANAGER’S SIGNATURE: All documents received from any and all
’City Departments requesting City Manager s signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, will review
and take the next steps.
NEEDS TO BE NOTARIZED: YES No
RUSH:YES No SAME DAY:YES No NEXT DAY:YES No
ROUTING TO CSO: YES No
Action Required: Attach Signature, Initial and Notary Tabs
As Requested
For Your Information
Signature/Routing and or Recording
Comment
File
Return To: Please notify TPWContracts@fortworthtexas.gov for pickup when complete. Call ext.
7233 or ext. 8363 with questions. Thank you!