HomeMy WebLinkAboutContract 40169-CO1 ,FCC RT WORTH City of Fort Worth CITY
Change Order Request CONTRACT
ProjectNamel Medical District Water Distribution System Improvements,Part 4 lCity Sec No. 1 40169
Project No.(s)P265-7091700247&P275-709170024787 DOE No. 6288 City Proj.No. 1 00247
Project Descxip' Installation of a 30/42 inch water main from South Holly Water Treatment Plant to the Medical District and 30 inch sewer
main from I1-130/15th Street intersection southerly 1,580 It.
Contractorl Oscar Renda Contracting, Inc. Change Order# Date: 3/1/2011
City Project Mgr.1 Liam Conlon City Inspector Raymond Brice
Phone Number.1 817-392-6824 Phone Number. 817-392-7943
Dept. Water Sewer Totals Contract Time
Calendar days)
Original Contract Amount $4,433,920. ,00 , .00 540
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date ,920.00M-- 00 --1 5,440,305.00 540,
ount o Proposed Change Order ,
Revised Contract Amount _ 540°Original Funds Available for Change Orders $2,500.00 00 $27,500.00 Remaining Funds Available for this CO 2, .00 00 "4W.Additional Funding(lf necessary) ° $152;50100 10 '`'
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $6,800,381.25
n - 0 per;
The change order will provide compensation for the following:
• Additional water gate valve and appurtenances as requested by Water Field Operations to provide
operational flexibility in the system.
• Hand tunneling to remove abandoned 8 and 16-inch cast iron pipes that were encountered in direct.
conflict during machine boring operations to install a project sewer main.
• Stand-by sanitary sewer by-pass to I raw sewage discharge In the event public sewer main
C1W7 (a 48-inch pipe) is inad 0 during drilling operations on UPPR property. The
City will be subject to a substs y sewage spill were to occur.
AftsW O . 0 0
° o� OFFICIAL REC p
oy
¢ CITY SE. Y
Mgy
7. , City Secr �� o,*a FT. WORTH
000000
It is understood and agreed that the accep ce of this Ch —tractor constitutes an accord and satisfactio nt
in full(both time and money)for all costs arising out of,or in " above Change Order.
Contraefor's: Namts "` t�►i ael7oe �� Da A
Renda Co acting,Inc. Rudy Renda
In .., D �D
COUrlgl Action 1�r k
M&C Number C-24734 M&C Date Approved 2/15/2011
fll�-10-17 nin • ro im
FO thtx WO RT H City of Fort Worth
Change Order Additions
Project Name Medical District Water Distribution System Improvements,Part 4 City Sec No. 40169
Project No.(s) P265-7091700247&P275-709170024787 = DOE No. 6288 City Proj.No. 00247
Project Installation of a 30/42 inch water main from South Holly Water Treatment Plant to the Medical District and 30 inch
Description sewer main from I1-130/15th Street intersection southerly 1,580 ft.
Contractor Oscar Renda Contracting, Inc. Change Order# Date: 3/1/2011
City Project Mgr. Liam Conlon City Inspector F-Raymond Brice
ADDITIONS
DEPT Qty Unit Unit Cost Total
Valve-42= esi ient Seated)gate valve Water 2.00 EA $45,000.00 $90,000.00
82 16'Outlet Water 1.00 EA $12,000.00 $12,000.00
83 30'Outlet Water 1.00 EA $12,000.00 $12,000.00
84 Additional pipe fittings for 2-42'gate valve Water 1.00 LS $41,000.00 $41,000.00
50 Mobilization setup Sewer 2.00 EA 15,000.001 $30,000.00
51 Weekly stand by rate Sewer 2.00 EA $25,000.00 $50,000.00
52 Weekly operation cost Sewer 1.00 EA $75,000.00 $75,000.00
53 Demobilization Sewer 2.00 EA $11,000.00 $22,000.00
54 Hand tunnel to remove obstruction in bore tunnel Sewer 1.00 LS $49,988.10 $49,988.10
Water $155,000.00
LAddftnEsSub $226,988.10
Page 2 of 4 Total $381,988.10
FORT WORTH City of Fort worth
Change Order Deletions
Project Name Medical District Water Distribution System Improvements,Part 4 City Sec No. 40169
Project No.(s) P265-7091700247&P275-709170024787 1 DOE No. 6288 City Proj.No. 00247
Project Description Installation of a 30142 inch water main from South Holly Water Treatment Plant to the Medical District and 30 inch
sewer main from IH30115th Street intersection southerly 1,580 ft.
Contractor Oscar Renda Contracting, Inc. Change Order#= Date 31112011
City Project Mgr. Liam Conlon City Inspector Raymond Brice
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water
Sewer
Page 3 of 4 Deletions Sub Total
NIMBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.0
Previous Change Orders
CO DATA AMOU14T
Total $0.00:
Page 4 of 4
Official
CITY COUNCIL AGENDA = FoRT�'�oRTll
COUNCIL ACTION. Approved on 211512011
DATE: 2/15/2011 REFERENCE NO.: *'`C-24735 LOG NAME: 60MEDP4COl-RENDA
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Change Order No. 1 in the Amount of$381,988.10 to the City
Secretary Contract No. 40169 With Oscar Renda Contracting, Inc. for Medical District
Water Distribution System Improvements, Part 4 from South Holly Water Treatment Plant
to the Medical District, thereby Increasing the Contract Amount to $5,822,293.10
(COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Change Order No. 1
in the amount of$381,988.10 to City Secretary Contract No. 40169 with Oscar Renda Contracting,
Inc., for Medical District Water Distribution System Improvements, Part 4 from South Holly Water
Treatment Plant to the Medical District, thereby increasing the contract amount to $5,822,293.10.
DISCUSSION:
On April 6, 2010, (M&C C-24164) the City Council authorized a contract in the amount of
$5,440,305.00 with Oscar Renda Contracting, Inc. for Medical District Water Distribution System
Improvements, Part 4 from South Holly Water Treatment Plant to the Medical District.
Change Order No. 1 will provide compensation for the following:
Additional water gate valve and appurtenances as requested by Water Field Operations to provide
operational flexibility in the system.
Hand tunneling to remove previously unknown 8 and 16-inch cast iron pipes that were
encountered in direct conflict during machine boring operations to install a project sewer main.
Stand-by sanitary sewer by-pass to prevent raw sewage discharge in the event that sewer main
C1W7 (a 48-inch pipe) is inadvertently ruptured during drilling operations on Union Pacific Railroad
property. The City will be subject to a substantial fine by Texas Commission on Environmental
Quality if a sewage spill were to occur.
M/WBE - Oscar Renda Contracting, Inc. is in compliance with the City's M/WBE Ordinance by
committing to an additional nine percent M/WBE participation on the Change Order No. 1. The City's
goal on this project is nine percent.
This project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budgets, as appropriated, of the Water Capital Projects Fund and the Sewer Capital Projects Fund.
TO Fund/AccountICenters FROM Fund/Account/Centers
P275 541200 709170024787 $226,988.10
Logname: 604061000I-SJLOUIS Page 1 of 2
t
P265 541200 609140024787 $155 000.00
Submitted for CitvManager's Office bv: Fernando Costa (6122)
Originating Department Head: S. Frank Crumb (8207)