Loading...
HomeMy WebLinkAboutContract 40243-A7 AMENDMENT NO. 7 TO AGREEMENT FOR ARCHITECTURAL DESIGN SERVICES RENOVATE and EXPAND the GENERAL TERMINAL BUILDING at MEACHAM INTERNATIONAL AIRPORT STATE OF TEXAS § § CITY SECRETARY CONTRACT NO. 4k)2°r3- A+ COUNTY OF TARRANT § WHEREAS, The City of Fort Worth and Hahnfeld Hoffer Stanford (Architect) made and entered into City Secretary Contract No. 40243 (The Contract) which was authorized by the City Council by M&C C-24215, the 11th day of May, 2010; and Amendment Nos. 1, 2, 3, 4 and 6 were administratively executed in the amount of$22,350.00 for additional topographic surveys, cost estimates and underground utilities survey; and Amendment No. 5 was approved by M&C C-24980 on June 14, 2011 to complete the design and provide construction administration services in the additional amount of $985,732.50 plus up to $63,680.00 in reimbursable expenses; and WHEREAS, further amendment is necessary for Phase II additional design services to increase the scope of work for additional topographic survey of approximately 2-acres; and NOW THEREFORE, City and Architect, acting herein by and through their duly authorized representatives, enter into the following agreement which amends the Contract: 1. Article 1.1, SECTION I —SERVICES OF THE ARCHITECT, a paragraph is added to read as follows: "Provide additional design services for Phase II services thus increasing the Civil Engineering Consultant's proposed scope of work to include the additional topographic survey of approximately 2-acres. The cost of this additional service is $4,500.00. The scope of services is described more fully in the Hahnfeld Hoffer Stanford's letter dated September 27, 2011 subject: Revised Proposal for Civil Survey Work, City of Fort Worth, Texas, Meacham Airport Terminal Building Renovation — Phase 2 including attachments noted as Exhibits "A" and "B", which are attached hereto and as Attachment"A" made a part of this Agreement." 2. Paragraph 1 of SECTION V-COMPENSATION TO ARCHITECT, is amended as follows: "The total compensation for all of the assignments to be performed by Architect to complete the Projects as described in CHARACTER AND EXTENT of ARCHITECT'S SERVICES as addressed in City Secretary Contract No. 40243 and Amendment Nos. 1 through 7 and hereof shall be $1,247,257.50, hereinafter referred to as the 'total fee', plus up to $76,880.00 in reimbursable expenses." 3. All other provisions of this Contract which are not expressly amended herein shall remain in full force and effect. XXXXXXXXXXXXXXXX The Remainder of This Page Is Intentionally Left Blank XXXXXXXXXXXXXXXX OFFICIAL RECORD CITY KC1C 1,ETARY FT. WORTH, TX Amendment No 7 Page 1 of 2 General Aviation Terminal Building at Meacham International Airport January 2012 EXECUTED this the day of ZZA"Mom 2012, in Fort Worth, Tarrant County, Texas. Hahnfeld Hoffer Stanford APPROVED: By: G By: Michael J. Hoffer, ,$[A Fernando Costa Principal (77 Assistant City Manager a�oza�tLh APPRO ECOMMENDED: RECOR p 10�OR� c��� 000 By. (rte. W By: AtIL P � . a °o'A� C� Dougl W. Wiersig, PE, Dir ,or, Ronald Gonzales U 0.0 Transportation & Public Worl Dept. Assistant City Secretary v o o Y APPROV TO OR AND LEGALITY: M&C is Not Required Qa 00 000 a Contract Authorization , �.� R �4y 4 By. Douglas W. Black Date: Assistant City Attorney OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Amendment No 7 Page 2 of 2 General Aviation Terminal Building at Meacham International Airport January 2012 Hahnfeld r Hoffer Stanford eptem er 27,2011 Mr. Dalton Murayama Architectural Service Manager Facilities Management Group Transportation and Public Works Department City of Fort Worth 401 West 13th Street Fort Worth,Texas 76102 RE: Revised Proposal for Civil Survey Work City of Fort Worth,Texas Meacham Airport Terminal Building Renovation-Phase 2 Dear Mr. Muruyama: As discussed earlier I am sending you a revised proposal for the Civil Survey portion of the Phase 2 work. As you may remember during the proposal phase the limits of our site work were undetermined. The Master Plan for Meacham Airport was not yet to the final selection phase and there were multiple planning options for the Terminal Building site. We originally proposed the landscape and Civil work on an assumed project site boundary of approximately 6.6 acres during the contract phase. During Phase 1 the site survey boundary was increased to supplement the Taxiway extension project, and again during Phase 2 to include the Underground Utilities Survey (SUE).An area of approximately 2 acres has not been included in the previous surveys and is the final area needed to complete the topographical survey of our entire project site, (see attachment"Exhibit B"). The revised proposal from Teague Nall Perkins is attached as Exhibit"A". Sincerely, HAHNFELD HOFFER STANFORD architects planners Interiors 6 Eric A.Claycamp,Al , LEED BD+C Associate Principal/Project Manager Accepted: Title: Date: Cc: David Stanford-Hahnfeld Hoffer Stanford Michael Hoffer-Hahnfeld Hoffer Stanford Eric Hahnfeld-Hahnfeld Hoffer Stanford Attachments: Exhibit A-Teauge Nall Perkins Proposal Exhibit B-New Limit of Civil/landscpe Services eCOLLABORATION. X* TEAGUE NALL AND PERKINS September 13,2011 Mr. Alfonso Meza Registered Architect City of Fort Worth TPW/Facilities Management—Arch. Services 1000 Throckmorton Street Fort Worth,Texas 76102 Re: Meacham Airport Terminal Improvements Topographic Survey—Contract Amendment Mr. Meza: As requested by Eric Claycamp with Hahnfeld Hoffer Stanford Architects, this letter agreement serves as an amendment to the Professional Services Agreement for Meacham Airport Terminal Improvements to expand the limits of the topographic surveying for this project. Per the attached exhibit,the additional topographic survey is approximately 2-acres and will be provided and included with the original survey for the Terminal Expansion and will be provided under the terms of the original agreement. The previous survey for approximately 14.5 acres has been completed and delivered to the architect and owner. With this additional survey, the survey will be updated to make this an all inclusive survey totally approximately 16.5-acres Based on the project description the additional survey will be: Expanded Scope of Surveying for Meacham Airport Terminal Addition: Four Thousand Five Dollars($4.500) This is for additional topographic survey only and no additional boundary,platting, easements, or S.U.E. are included in the scope of this work. Once this amendment is signed and returned, the survey work will begin within three working days. Sincerely, TEAGUE NALL AND PERKINS,INC. Torn Rutledge Tom Rutledge Principal Approved by Owner Representative Date Attachments 1100 Macon Street •Fort Worth,Texas 76102•817.336.5773 phone•817.336.2813 fax www.tnp-onitrie.com 41, Xl TI, op K V t, ti M