Change Order No. 02
Date: December 13, 2010
Project Name: Fort Worth Phase I P25-TX-091171A
Customer Name: City of Fort Worth
Customer Project Mgr: Alan Girton
The purpose of this Change Order is to:
Provide for electrical improvement work at the Burnett Plaza radio site.This work has been
quoted by the Burnett Plaza electrician and is required to install the communications equipment.
Contract# City of Fort Worth: Contract Date: 6/28/10
Contract 40526
Motorola Contract:
10-15074/RH/CB
In accordance with the terms and conditions of the contract identified above between
The City of Fort Worth and Motorola, Inc., the following changes are approved:
Contract Price Adjustments
Original Contract Value: $1,649,850.04
Previous Change Order amounts for Change Order
numbers 0 through, 1 $0.00
This Change Order: $6,711.50
New Contract Value: $1,656,561.54
Completion Date Adjustments
Original Completion Date: 7/8/2011
Current Completion Date prior to this Change Order: 7/8/2011
New Completion Date: 7/8/2011
Changes in Equipment: (additions,deletions or modificafions
There are no equipment changes, other than materials to be provided by the electrician (electrical
panel, breakers, electrical wire).
Changes in Services: additions,deletions or modifications
OFFICIAL RECORD
CITY SECCRETARY
Form: WDSIPM04-12C ver 3.0 Page 1 of 2 Fort Worth Pliasi Ti 1p
,09117
® MOrOROLA CHANGE ORDER
Service changes include electrical improvement work at the Burnett Plaza site, including:
1. Install new Uninterruptible Power Supply(UPS), Make Before Break switch, and Type I
surge protector. The UPS, MBB, and Type I protectors are already provided within the
scope of the project.
2. Install new electrical panel with twenty 20-amp circuits
3. Wire 20-amp circuits to racked communications equipment
Schedule Chan describe change or WA
There are no schedule changes.
Pricing Changes: describe change or N/A
Pricing for this additional work is$6,711.50
Customer Responsibilities: (describe than,go or WA
There are no customer responsibility changes.
Payment Schedule for this Change Order:
describe new payment terms applicable to this change order
There is no change in payment schedule
Unless amended above, all other terms and conditions of the Contract shall remain in full force. If there
are any inconsistencies between the provisions of this Change Order and the provisions of the Contract,
the provisions of the Change Order will prevail.
IN WITNESS WHEREOF the parties havR executed this Change Order as of the last date signed below.
Reviewed by: Date: I L61 2
t ola Project Manager
Reviewed by: Date:
City of Fort Worth Project Manager
MOTOROLA, INC. CITY OF FORT
WORTH
By: JV By: .
Printed Name: #jL L Printed Name:
Karen L. Montguniery
Title: AIGAML syn. ' Title: Assf sta.nt (3i tv Manager
Date: / Z�gr Z20 // a4eORT O�tt""��� Date: gI I1
XY
Xy U _
Attested by:
ZL oZ' APPRQ " ?�, DO-' �.=' Ai\�� ,,r;v 1LITY;
0
o�
_ ao
o _ _. _...
Mart) ll�...��., :� �y .a �.re °°°°ooa°°S a r�.
44r4- X
Form: WDSIPM04-12C ver 3.0 Page 2 of 2 Fort Worth Phase I WMAL RECORD
WtVtECRETARY
P, NO A4&C REQUIRED FT NORTH, TX