HomeMy WebLinkAboutContract 40540-CO2 CITY SECRETARY
City of Fort worth CONTRACT NO. 4�5AO
Change Order Request
Change Order No. Date TPW Project No. Funding(FAC)
2 (two) 10/5/11 C 295 541200
208110073980-00004868
Facility and Project Description City Secretary Contract No.
Fire Station 5 40540
ORIGINAL CONTRACT AMOUNT................................................................ $2,413,807
EXTRASTO DATE..................................................................... $ 14,166
CREDITSTO DATE.................................................................... $ 0
CONTRACTCOST TO DATE.................................................................................................. $ 2,427,973
AMOUNT OF PROPOSED CHANGE ORDER............................................................................ $ 22,485
REVISED CONTRACT AMOUNT............................................................................................. $ 2,450,485
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS............................................................ $ 150,000
REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS......................................................... $ 113,349
ADDITIONAL FUNDING (IF NECESSARY)................................................................................ 0
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL:
Provide all labor and materials as per attached PCR's: 8, 9, 11, 12, 13, 14 and 17 as per the
attached Proposed Change Requests.
ADD $ 22,485
--------------------------------------------------------------------------------------------------------------
PCR's 10 and 11 are REJECTED TOTAL ADD $ 22,485
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time
and money)for all costs arising out of,or incidental to,the above Change Order
Contractor's Name
Imperial Construction, Inc.
Original Contract Time Additional Approved Time To Date Approved Contract Time To Date Additional Time For This Change Order
287cd 65 cd 352 cd 65 cd
Contr or-Imperial nstr ' n,Inc Date Co ucti na r Date
oq��>
Chief,Archite ral Services Division Date r,Transportation and Public works Date
Pro t Architect/ PGA % ate C _ y Date
►Ole
City Ma Date Counci ion(If Required) Date1/8/08
❑ Approved ❑Disapproved
Aftelstt.—FW IM
�� ❑ Other
cr�'�FOA��
Distribution /9 °u��o0.;,- 'i;t
File <:/ , r ,� _.._ %
Cons iO1Uanag r� ��� ti� �' --- OFFICIAL RECORD
°•� ' Hendrix. Ci Secre
coy 1�►0- o=�M�Y ty tary CITY SECT SECRETARY
0,00 o
T. Y4 0( �'•}� TX
o° oa° t�i�me,�Q °o u �j em nt Division -1 1 P 4
00000°° 4Y
TID Y r Form(1 /19/01)
�a,._ p�a
Change Order 2
Fire Station #5 District No. 8
PCR 8 - Changes to door hardware. ADD $ 782.00
PCR 9R- Changes to masonry wall in apparatus bay. ADD $1,742.00
PCR 1 OR—Cast concrete changes. (REJECTED) No Change
PCR 11 —Install sprinkler heads at back porch. (REJECTED) No Change
PCR 12—Relocate masonry wall. ADD $1,444.00
PCR 13 -Block net flashing not used at apparatus bay. ADD $ 536.00
PCR 14—Revise concrete and fence. ADD $ 6,029.00
PCR 17 - Changes to concrete flume, add handrail. ADD $ 11,952.00
------------------------------------------------------------------------------------
Total This Change ADD $ 22,485.00
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME: Fire Station #5
BuySpeed No: PO-10-00060917
Contract No: CS40640
D.O.E. No: N/A
Attachment to Change Order No: 2
Today's Date: 10120111
TOTAL
Original Contract Amount: $ 2,413,807.00
Extras to Date: $ 14,166.00
Credits to Date: $ -
Contract Amount to Date: $ 2,427,973.00
Amount of Proposed Change Order: $ 22,485.00
Revised Contract Amount: $ 2,450,458.00
Original Funds Avail. for Admin. Change Orders: $ 150,000.00
Remaining Funds Available for Change Orders: $ 113,349.00
Additional Funding (if necessary):
Prepared By: Karen Striker T/PW Mgmt Svs.
TO: City f Fort Worth
Y 2/23/2011
JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTORS
ATTENTION:Jack Durham CHANGE PROPOSAL 1�Z•t�
10-0413
The following is a detailed cost breakdown,including both materials 8 labor, PROJECT NO.
for all additions to and/or deductions from the contract sum.
SCOPE: Changes to door hardware per returned submittals 8
CHANGE
PROPOSAL NO.
1. LABOR
NUMBER RATE
LABOR CATEGORY MAN HOURS PER HOUR COST
SUPERVISION 0 $ 59.00 $
CARPENTER 0 $ 37.00 $ _
LABORER 0 $ 24.00 $ _
0 $ $
LABOR SUB TOTAL $
LABOR BURDEN $
: $ _
2. MATERIALS/EQUIPMENT RENTALS TOTAL ITEM 1
DESCRIPTION QUANTITY UNIT PRICE
3. SUBCONTRACTS TOTAL ITEM 2 : $ _
SUBCONTRACTOR DESCRIPTION
DFW Door Door hardware changes per returned submittals $ 660.53
TOTAL ITEM 3 : $ 660.53
4.SUBTOTAL WITHOUT MARKUP (ITEMS 1,2, $3) M$ 1 53
5. G&A OVERHEAD 05
6. SUBTOTAL INCLUDING OVERHEAD 58
7. PROFIT 3
8. SUBTOTAL INCLUDING OVERHEAD AND PROFIT 1
9. PERFORMANCE AND PAYMENT BOND 7 10. SALES TAX 11.TOTAL(ADDITION/DEDUCTION)TO CONTRACT SUM IF ACCEPTED 8
REQUEST IS MADE FOR ADDITION OF 0 CALENDAR DAYS TO THE CONTRACT PERIOD
The above proposal is subbmitted for your consideration. The undersigned contractor understands and agrees
that this proposal is validated only by the Owners signature.
This change proposal for subject work requires your approval by( ASAP }.
Jimmy Tuley A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project Manager in this original change order price. Each day beyond the required date additional
items will be added to the change proposal to reflect the acrued change. This will be
ICI (Imperial Construction Inc) determined after your authorization is finally received Accordingly,upon receipt of
NAME OF CONTRACTING FIRM your approval,all cost resulting from these additional factors will be submitted to
correct the final change order price
Change Order Approval by Owner Architect Date
IDFVV1 1 1 3TH STREET
'RAN D PRAIRIE.TX 750.50 CHANGE ORDER
PHONE: 972.988.3070 Page 1 of 2
FAX: 972.606.0607
■ - Matt agan 8/18/ 9013.001
Biala]= • - _ � . ,�� T .
IM Imperial Construction Fire Station No 5 Fort Worth
Station No ---
Attn: Jimmy Tule'
--�_ -Y _2 _- 8SO Irma Street
187 Cod Road
—
Fort Worth, TX
Weatherford TX 76087
(817) 341-8886 (817) 341-0191
PHONE 7AX
Quantity Description
Revisions per returned submittals,Incorporated into S02 submittals
Opening Number(s): 02,03, 16, 18, 209 21, 22, 23, 24, 25,26,28,29, 309 31, 329 33, 34, 359 369 37, 39
Per notations with returned SO1 submittals, we are adding kick plates at all wood doors. Please
note, we schedule hardware per the hardware sets specified.
Kick Plate
--
Rock-A-ood
KIOSO 10"x 34-1/2"US32D
Opening Number(s): 04
Per notations with returned SO1 submittals, adding threshold
Threshold
Pemko
171A 42"
Opening Number(s): 10, 15, 19, 27
Per notations with returned SO] submittals, adding exterior floor stop with holder
4 Floor Stop w/Holder
Rockwood
473 US26D
Opening Number(s): 22,23,26, 28, 29, 32, 33
Per notations with returned SO] submittals, changing from a passage latchset to a privacy set
-7 Passage Latchset
Schlage
NDIOS ATH 626
7 Privacy Latchset – —
Schlage
ND40S ATH 626
TERMS AND CONDITIONS:
1 Upon acceptance, this proposal will become part of the official contract documents.
2, valid for acceptance within 30 days.
3. Glazing is not included unless noted otherwise
1 Shipping Is not Included unless noted other ose
S 'nstallation is not Included unless noted otbel-vvtse
G Shlpmenr of nnarerial mad be[,io 8 weeks after recenp! of approval to prutced
1 173 1 13Th STREET
GRAND PRAIRIE.TX 75050 CHANGE ORDER
PHONE: 972.986.3070 Page 2 of 2
FAX: 972,606-0607
Matt Feaga-7--i 8;18/2010 9013.001 Imperial Constniction • Fire Station No 5 - Fort Worth
Attn:jimilly'ruley -50 Irma Sweet
ti
187 Coy Road
Fort Worth,TX
V%leatherford,TX 760
17(817) 341-8886 (817) 341-0191
PHONE FAX
•
Quantity Description
Opening Number(s): 36
Per notations with returned So I submittals, changing from a privacy function latciiset to a passage
set
Privacy LaTchsei
Schlage
ND40S ATH 626
Passage Latchset
Schlage
NDI OS ATH 626
Misc. Opening(s):
Administrative&Engineering
Sub Total $660.53
T ax (OK 50.00
Freight 50.00
Accepted: Grand Total $66033
SM I
No will be Ordered, Processed,
Signature Date r Delivered Plivered without Written Ai2proval.
(
TERMS AND CONDITIONS:
I Upon acceptance,this proposal will become part of the official contract documents.
2. Valid for acceptance within 30 days,
3 Glazing is not included unless noted otherwise
4 Shipping is not included unless noted otherwise.
in,,tattation is not included unless noted otherwise
lrjjpjrient of ijidt(,j ial inad, be ()to 8 weeks after I e(vll)t of approval to proceed
TO: City of Fort Worth 03/22/2011 " t'V%aZ
JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTORS C-V-w C'•0•462
ATTENTION:Jack Durham CHANGE PROPOSAL �� 41_.00
10-0413
The following is a detailed cost breakdown, including both materials&labor, PROJECT NO.
for all additions to and/or deductions from the contract sum.
SCOPE: Changes to masonry per ASI 10 9 REVISED
CHANGE
]PROPOSAL NO.
1. LABOR
NUMBER RATE
LABOR CATEGORY MAN HOURS PER HOUR COST
SUPERVISION 0 $ 59.00 $
CARPENTER 0 $ 37.00 $
LABORER 0 $ 24.00 $ _
0 $ - $ -
LABOR SUB TOTAL $ _
LABOR BURDEN Is _
: _
2. MATERIALS/EQUIPMENT RENTALS TOTAL ITEM 1 $
DESCRIPTION QUANTITY UNIT PRICE
3.SUBCONTRACTS TOTAL ITEM 2 : $ _
SUBCONTRACTOR DESCRIPTION
Father and Sons Extend CMU in room per ASI 9 $ 1,471.35
$ -
TOTAL ITEM 3 : $ 1,471.35
4.SUBTOTAL WITHOUT MARKUP (ITEMS 1,2, &3) $ 1,471.35
5. G&A OVERHEAD 10% $ 147.14
6.SUBTOTAL INCLUDING OVERHEAD $ 1,618.49
7. PROFIT 5% $ 80.92
8.SUBTOTAL INCLUDING OVERHEAD AND PROFIT $ 1,699.41
9. PERFORMANCE AND PAYMENT BOND 2.50% $ 42.49
10. SALES TAX 0.00% $ -
11.TOTAL(ADDITION/DEDUCTION )TO CONTRACT SUM IF ACCEPTED $ 1,741.89
REQUEST IS MADE FOR ADDITION OF 0 CALENDAR DAYS TO THE CONTRACT PERIOD
The above proposal is subbmitted for your consideration.The undersigned contractor understands and agrees
that this proposal is validated only by the Owners signature.
This change proposal for subject work requires your approval by( ASAP ).
,jimmy Tuley A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project Manager in this original change order price. Each day beyond the required date additional
items will be added to the change proposal to reflect the acrued change.This will t
ICI(Imperial Construction, Inc) determined after your authorization is finally received.Accordingly, upon receipt of
NAME OF CONTRACTING FIRM your approval,all cost resulting from these additional factors will be submitted to
correct the final change order price.
Change Order Approval by Owner/Architect Date
TM V.-
Document G710
AIA - 1992
Architect's Supplemental Instructions
PROJECT(Name and address): ARCHITECT'S SUPPLEMENTAL OWNER:
City of Fort Worth Fire Station#5 INSTRUCTION NO:010
850 Irma Street ARCHITECT:
Fort Worth,Texas 76104 CONSULTANT:❑
OWNER(Name and address): DATE OF ISSUANCE:January 14,2011 CONTRACTOR:
City of Fort Worth FIELD:❑
401 W. 13th Street CONTRACT FOR:General Construction
Fort Worth,Texas 76102 OTHER:❑
FROM ARCHITECT(Name and CONTRACT DATE:
address):
RPGA Design Group,Inc.
101 S.Jennings Avenue,Suite 100
Fort Worth,Texas 76104
TO CONTRACTOR(Name and ARCHITECT'S PROJECT"NUMBER:
address):
Imperial Construction,Inc.
PO Box 967
Weatherford,Texas 76086
The Work shall be carried out in accordance with the following supplemental instructions issued in accordance with
the Contract Documents without change in Contract Sum or Contract Time. Proceeding with the Work in accordance
with these instructions indicates your acknowledgment that there will be no change in the Contract Sum or Contract
Time.
DESCRIPTION:
Apparatus bay interior masonry wall details
ATTACHMENTS:
(Here insert listing of documents that support description)
SK-9
ISSUED BY THE ARCHITECT:
�&'UlhgdAv Heather Hall, Project Designer
(Signature) (Printed name and title)
_—__-
AIA Document G71101-—7992.Copyright m 1979 and 1992 by The American Institute of Architects.All rights reserved.WARNING.Th.Al ocument Is
protected by U.S.Copyright Law and International Treaties.Unauthorized reproduction or distribution of this AIA` Document,or any portion of it,may .�
result In severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law this document was produced by AIA
software at 1/ 11 54 on 010412011 under Order No 0618801040_1 which expires on 0212112011 and is not for resale
User Notes.
(134/054442)
AT BUNKER GEAR PARTITION
DIAL. STEEL BRACING
REF. STRUCTURAL
AT RM 127 EAST W AT BUNKER GEAR PARTITION
LS % }L-771- LLV
WELDED TO BEAM L5% 3 % 1 4 LLV
(ANCHORS k VERTICAL WELDED TO BEAM
SLOTS ARE NOT REO'D) ,ado W/ 1/2"0 HIL71 HUS-H
�o SCREW ANCHOR INTO
CMU O 48" O.0
AT RM 127 EAST WALL k ^� (4"EMBEDMENT)
AT BUNKER=WALL PROVIDE 1•' VERTICAL SLOTS
CONTINUOUS BOND BEAM i IN ANGLE LEG
GROUTED AND REINFORCED 'p O n�
AT BUNKER GEAR PARTITION
O O O PROVIDE 1"VERTICAL SLOTS
J 1 5 IN ANGLE LEG
02 A-7.06 I A
GUARDRAIL 03 ANGLE DETAIL
1
SCALE,1' 1'-0'
JOIST, REF. STRUCTURAL
MUST BE WITHIN 4"FROM
LADDER OPENING
CONCRETE K I BRACES LOCATIONS REWIRED, CONCRETE ON
REFASTRUCTURAL I COORDINATE LOCATIONS METAL DECK h
TO CLEAR MEZZANINE REF. STRUCTURAL
ACCESS LADDER
I�
STEEL FRAMING DIAL STEEL BRACING I'
REF. STRUCTURAL AT BUNKER GEAR —
EXPOSED SURFACES CONT. BOND BEAM PARTITION ONLY,
TO BE PAINTED REF. STRUCTURAL REF. STRUCTURAL,
EXPOSED SURFACES
TO BE PAINTED
MOISTURE RESISTANT MOISTURE RESISTANT
ACCOUSTICAL TILE ACCOUSTICAL TILE
8"CMU 8"CMU
Y
I 1
k K 1'-6" f4 K T-6„
OWL.O 48"O.C. DWL O 48"O.C.
GROUT CELLS AT OWLS. GROU T CELLS AT OWLS.
61/2KBK 16 61/2 KBK 16
STARTER COURSE STARTER COURSE
CONCRETE FOUNDATION CONCRETE FOUNDATION
REF. STRUCTURAL REF. STRUCTURAL
CARTON FORMS CARTON FORMS
1 VAPOR BARRIER VAPOR BARRIER
° -- �NIlt
CONCRETE PIER _ CONCRETE PIER
REF. STRUCTURAL REF. STRUCTURAL
I
RM 127 EAST WALL SECTION
01 RM 127 NORTH WALL SECTION 02 BUNKER GEAR PARTITION WALL (SIM.)
SCALE.1/4'-1'4' SCALE:1/4'-1'4'
ASI 10- APPARATUS MASONRY WALL DETAILS CD SHEET NO.
RPGA DESIGN GROUP, INC. FORT WORTH FIRE DEPARTMENT DATE:
101 S. JENNINGS AVE, STE. 100 FIRE STATION #5 1/14/11
FT. WORTH, TEXAS 76104 850 IRMA STREET
817- 332- 9477 FORT WORTH, TEXAS 76104 SK-9
AT SUHM WM►ARTI M
DIAG. STEEL BRACING
AT RM t27 gAg WAl.\' REF. STRUCTURAL
L5X3X 1/4 LLV
WELDED TO BEAM % 3 X 1 ! LL(ANCHORS @ VERTICAL 71-D
WELDED TO BEAM
SLOTS ARE NOT REO'D) W/ 1/2"0 HILTI HUS-H
SCREW ANCHOR INTO
CMU O 48"O.C.
AT W 127 EAST MALL! (4"EMBEDMENT)
AT IILRMC L OEM PM7, M PROVIDE 1" VERTICAL SLOTS
CONTINUOUS BOND BEAM i IN ANGLE LEG
GROUTED AND REINFORCED ' AT SU11QJt OIAR PAR11110M PROVIDE 1" VERTICAL SLOTS
ANGLE LEG
D2 A-7.D6 I
GUARDRAIL OJ' ANGLE DETAIL
]
ANCHORING CHANNEL - SCALE.1••1'4'
JOIST, REF. STRUCTURAL
MUST BE WITHIN 4"FROM
LADDER OPENING
I � I
CONCRETE GN 2 LOCATIONS REWIRED, CONCRETE ON I I I
METL DECK REF.A STRUCTURAL BRACES
U METAL DECK
COORDINATE LOCATIONS
TO CLEAR MEZZANINE REF. STRUCTURAL
ACCESS LADDER I
II
--J 03 SK-9
STEEL FRAMING DIAG STEEL BRACING I)
REF. STRUCTURAL AT BUNKER GEAR L.
EXPOSED SURFACES PARTITION ONLY,
TO BE PAINTED SOUND BATTS REF. STRUCTURAL,
5/8"GYP. BOARD EXPOSED SURFACES
TO BE PAINTED
ANCHORING CHANNEL
CUP L4x3 x 1/4x0'-5"
MOISTURE RESISTANT (LLV) W/(2)- 5/8 x 2 VERT. MOISTURE RESISTANT
ACCOUSTICAL TILE SLOTTED HOLES ACCOUSTICAL TILE
8"CMU CONT. BOND BEAM 8"CMU
REF. STRUCTURAL
I I
Y
A4 X P-6" 114 X 1'-6"
DWL.O 48" O.C. DWL.O 48" C.
O.
GROUT CELLS AT DWLS. GROUT CELLS C' DWLS.
61/2 %8X 16 61/2 %8X 16
STARTER COURSE STARTER COURSE
CONCRETE FOUNDATION CONCRETE FOUNDATION
REF. STRUCTURAL REF. STRUCTURAL
CARTON FORMS 7, CARTON FORMS
VAPOR BARRIER VAPOR BARRIER
I �_- �• �-ill I � 1- -I-I II � r I 9
I
CONCRETE PIER -11-II
REF. STRUCTURAL CONCRETE PIER
REF. STRUCTURAL
RM 127 EAST WALL SECTION
O1 RM 127 NORTH WALL SECTION 02 BUNKER GEAR PARTITION WALL (SIM.)
SCAM S 1/4•.1'-0' SG1LE:1/4'.1'-0'
ASI 10- APPARATUS MASONRY WALL DETAILS CD SHEET NO.
RPGA DESIGN GROUP, INC. FORT WORTH FIRE DEPARTMENT DATE:
101 S. JENNINGS AVE, STE. 100 FIRE STATION #5 3/4/11
FT. WORTH, TEXAS 76104 850 IRMA STREET
817-332-9477 FORT WORTH, TEXAS 76104 SK-9R
TO:City of Fort Worth 03/22/2011
JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTORS
ATTENTION:Jack Durham CHANGE PROPOSAL
10.0413
The follows is a detailed cost breakdown,including both materials&labor, PROJECT NO.
for all to and/or deductions from the contract sum.
SCOPE: Ca concrete changes 10 Revised
CHANG
PROPOS NO.
1.LABOR
NUMBER RATE
LABOR CATEGORY \ MAN HOURS PER HOUR COST -
SUPERVISION 0 $ 59.00 $
CARPENTER \ 0 $ 37.00 $ =
LABORER 0 $ 24.00 $
\ U $ - $ -
LABOR SUB TOTAL $
LABOR BURDEN $
TOTAL ITEM $
2.MATERIALS/EQUIPMENT RENTALS \
DESCRIPTION UANTITY\ UNIT P E
3.SUBCONTRACTS OTAL ITEM 2: $ -
SUBCONTRACTOR DESCRIPTION \,\
Father and Sons Cast concrete changes $ 1,805.50
$ -
TOTAL EM 3: $ 1,805.50
4.SUBTOTAL WITHOUT MARKUP (ITEMS 1,2,&3) $ 1,805.50
5.G&A OVERHEAD 10% $ 180.55
6.SUBTOTAL INCLUDING OV HEAD $ 1,986.05
7.PROFIT 5% $ 99.30
8.SUBTOTAL INCLUDIN VERHEAD AND PROFIT $ 2,085.35
9.PERFORMANCE AN AYMENT BOND 2.50% $ 52.13
10.SALES TAX 0 00% $ -
11.TOTAL(ADDIT N/DEDUCTION)TO CONTRACT SUM IF ACCEPTED $ 2,137.49
REQUEST I MADE FOR ADDITION OF 0 CALENDAR DAYS TO THE NTRACT PERIOD
The ab proposal is subbmitted for your consideration.The undersigned contractor understands and rees
that t proposal is validated only by the Owners signature.
This change proposal for subject work requires your approva y( ASAP ).
,jimmy 7ufey A delinquent response will accrue additional cost that is not inc ed
Jimmy Tuley Project Manager in this original change order price.Each day beyond the required to additional
items will be added to the change proposal to reflect the acrued c e.This will t
ICI(Imperial Construction,Inc) determined after your authorization is finally received.Accordingly,u receipt of
NAME OF CONTRACTING FIRM your approval,all cost resulting from these additional factors will be submitted to
correct the final change order price.
Change Order Approval by Owner/Architect Date
TO:City of Fort Worth 03/03/2011
B NAME: Fort Worth Fire Station#5 DATE CONTRACTORS
A NTION:Jack Durham CHANGE PROPOSAL
10-0413
The followin a detailed cost breakdown,including both materials&labor, PROJECT NO.
for all additions ,and/or deductions from the contract sum.
SCOPE: Install' a protection ads at rear patio. Please see attached information sheet 11
CHANGE
]PROPOSAL NO
1. LABOR
NUMBER RATE
LABOR CATEGORY AN HOURS PER HOUR C T
SUPERVISION 0 $ 59.00 $
CARPENTER 0 $ 37.00 $
LABORER 0 $ 24.00 $ _
0 $ _
LABOR SUB TOTAL $ _
LABOR BURDEN $ _
:
2. MATERIALS!EQUIPMENT RENTALS TOTAL ITEM 1 $
DESCRIPTION QUANTITY UNIT PRICE
3. SUBCONTRACTS TOTAL ITE 2: $ "
SUBCONTRACTOR DESCRIPTION
EFS install six additonal heads at rea atio $ 3,104.00
�+ TOTAL ITE $ 3,104.00
4.SUBTOTAL VV'ITHOUT(MARKUP (ITEIVIJ 1, 2, �
5. G&A OVERHEAD $ 3,104.00
6. SUBTOTAL INCLUDING OVERHEAD 10% $ 310.40
7. PROFIT $ 3,414.40
8. SUBTOTAL INCLUDING OVERHEAD AND OFIT 5% $ 170.72
9. PERFORMANCE AND PAYMENT BOND $ 31585.12
10.SALES TAX 2.5 ° $ 89.63
11.TOTAL(ADDITION/DEDUCTION ) CONTRACT SUM IF ACCEPTED 0.00°° $
3,674.75
REQUEST IS MADE FOR ADDIT N OF 0 CALENDAR DAYS TO THE CONTRA T PERIOD
The above proposal is subbmi d for your consideration.The undersigned contractor understands and agrees
that this proposal is validate my by the Owners signature.
This change proposal for subject work requires your approval by( SAP ).
-7immy Tuley A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project M ager in this original change order price.Each day beyond the required date add ' nal
items will be added to the change proposal to reflect the acrued change.This ill t
ICI(Imperial C struction, Inc determined after your authorization is finally received.Accordingly, upon receipt
'AME OF CON CTING FIRM your approval,all cost resulting from these additional factors will be submitted to
correct the final change order price.
Change Order Approval by Owner/Architect Date
i
TO: City of Fort Worth 03J22/2011
JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTOR'S
ATTENTION:Jack Durham CHANGE PROPOSAL
10-0413
The following is a detailed cost breakdown,including both materials&labor, PROJECT NO.
for all additions to and/or deductions from the contract sum.
SCOPE: relocate masonry wall after partial construction. 12
CHANGE
PROPOSAL NO.
1. LABOR
NUMBER RATE
LABOR CATEGORY MAN HOURS PER HOUR COST
SUPERVISION 0 $ 59.00 $ _
CARPENTER 0 $ 37.00 $ _
LABORER 0 $ 24.00 $ _
0 $ - $ -
LABOR SUB TOTAL $ _
LABOR BURDEN $ _
: _
2.MATERIALS/EQUIPMENT RENTALS TOTAL ITEM 1 $
DESCRIPTION QUANTITY UNIT PRICE
TOTAL ITEM 2: $
3.SUBCONTRACTS
SUBCONTRACTOR DESCRIPTION
Father and Sons move 6"wall $ 1,219.74
TOTAL ITEM 3 : $ 1,219.74
4.SUBTOTAL WITHOUT MARKUP (ITEMS 1,2,&3) $ 1,219.74
5.G&A OVERHEAD 10% $ 121.97
6.SUBTOTAL INCLUDING OVERHEAD $ 1,341.71
7.PROFIT 5% $ 67.09
8.SUBTOTAL INCLUDING OVERHEAD AND PROFIT $ 1,408.80
9. PERFORMANCE AND PAYMENT BOND 2.50% !Ea
10.SALES TAX 0.00%
11.TOTAL(ADDITION/DEDUCTION)TO CONTRACT SUM IF ACCEPTED
REQUEST IS MADE FOR ADDITION OF 0 CALENDAR DAYS TO THE CONTRACT PERIOD
The above proposal Is subbmitted for your consideration.The undersigned contractor understands and agrees
that this proposal Is validated only by the Owners signature.
This change proposal for subject work requires your approval by( ASAP ).
,jimmy Tueey A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project Manager in this original change order price.Each day beyond the required date additional
items will be added to the change proposal to reflect the acrued change.This will t
ICI(Imperial Construction,Inc) determined after your authorization is finally received.Accordingly,upon receipt of
NAME OF CONTRACTING FIRM your approval,all cost resulting from these additional factors will be submitted to
correct the final change order price.
Change Order Approval by Owner/Architect Date
TO:City of Fort Worth 03/22/2011 CFW GO. 2-
r JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTORS
ATTENTION:Jack Durham CHANGE PROPOSAL 53(o.Ot7
10-0413
The following is a detailed cost breakdown,including both materials&labor, PROJECT NO.
for all additions to and/or deductions from the contract sum.
SCOPE: Per PR 10 Block net is not to be used. 13
CHANGE
PROPOSAL NO.
1.LABOR
NUMBER RATE
LABOR CATEGORY MAN HOURS PER HOUR COST
SUPERVISION 0 $ 59.00 $
CARPENTER 0 $ 37.00 $
LABORER 0 $ 24.00 $ _
0 $ $ -
LABOR SUB TOTAL $ _
LABOR BURDEN $ _
:
2.MATERIALS/EQUIPMENT RENTALS TOTAL ITEM 1 $
DESCRIPTION QUANTITY UNIT PRICE
TOTAL ITEM 2: $
3.SUBCONTRACTS
SUBCONTRACTOR DESCRIPTION
Father and Sons Credit for block net and cost of demo installed block net $ 452.70
TOTAL ITEM 3: $ 452.70
4.SUBTOTAL WITHOUT MARKUP (ITEMS 1,2,&3) $ 452.70
5.G&A OVERHEAD 10% $ 45.27
6.SUBTOTAL INCLUDING OVERHEAD $ 497.97
7. PROFIT 5% $ 24.90
8.SUBTOTAL INCLUDING OVERHEAD AND PROFIT $ 52-2.87
9.PERFORMANCE AND PAYMENT BOND 2.50% $ 13.07
10.SALES TAX 0.00% $ -
11.TOTAL(ADDITION/DEDUCTION)TO CONTRACT SUM IF ACCEPTED $ 535.94
REQUEST IS MADE FOR ADDITION OF 1 CALENDAR DAYS TO THE CONTRACT PERIOD
The above proposal is subbmitted for your consideration.The undersigned contractor understands and agrees
that this proposal is validated only by the Owners signature.
This change proposal for subject work requires your approval by( ASAP }.
Jimmy 7uky A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project Manager in this original change order price.Each day beyond the required date additional
items will be added to the change proposal to reflect the acrued change.This will t
ICI(Imperial Construction Inc) determined after your authorization is finally received.Accordingly,upon receipt of
NAME OF CONTRACTING FIRM your approval,all cost resulting from time additional factors wilt be submitted to
correct the final change order price.
Change Order Approval by Owner/Architect Date
FF
11
., f,-AIA Document G709'm 2001
Work Changes Proposal Request
PROJECT(A'arne andat/dress). PROPOSAL REQUEST NUMBER:010 OWNER:
City of ort: Worth Fire Station#15 ARCHITECT:
856 Irma Street DATE OF ISSUANCE: March 22,2011
Fort Worth,Texas 76104 CONSULTANT:❑
OWNER(flame and address): CONTRACT FOR:General Consn-uction CONTRACTOR:
City of Fort Worth FIELD:❑
401 W. 13th Street CONTRACT DATE:JuIv 15,201 I
OTHER:
Fort Worth,Texas'7610') ❑
FROM ARCHITECT 6,Vame and ARCHITECT'S PROJECT NUMBER:
address)•
RPGA Design 0roup,Inc.
101 S. Jennings Avenue,Suite 100
Fort Worth,Texas 76104
TO CONTRACTOR t'.,k"anic and
address).
Imperial Construction,Inc.
PO Box 967
Weatherford,Texas 76086
Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications to
the Contract Documents described herein.Within Fourteen(14)days, the Contractor must submit this proposal or
notify the Architect,in writing*.of the date oil which proposal submission is anticipated.
THIS IS NOT A CHANGE ORDER,A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS.
DESCRIPTION(lnsei-i a written description qfthe ff'brk):
Provide pricint,for a credit to eliminate the Block\ct at the apparatus bay.
c
ATTACHMENTS(List attached ekwuniews that supjwt dusci-intion):
REQUESTED BY THE ARCHITECT:
n+ Heather Hall, Prp�jcct Designer
Ab �
(Sig,hamrei 'Printed name and title)
AJ A Document G7091w-2001 CopvngnN 993 anti 200',by The Amertcan Institule of Archoacts.All rights reserved.
as t ood,.ed tv AIA
,,,PwAre a•"'q S3 �2 -nde,0,J • Yo 25)3'AFW4 whwl V'?,'2C"1 All, s 113t
User Notes
TO:City of Fort Worth 10!5/2011
JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTORS CJP1,3 C'o'w-Z
ATTENTION:Jack Durham CHANGE PROPOSAL
(p�OZ�t.oc7
10-0413
The following is a detailed cost breakdown,including both materials&labor, PROJECT NO.
for all additions to and/or deductions from the contract sum.
SCOPE: Revised concrete/fence and parking bumper scope of work per Change request 11 R2 14
CHANGE
PROPOSAL NO.
1. LABOR
NUMBER RATE
LABOR CATEGORY MAN HOURS PER HOUR COST
SUPERVISION 0 $ 59.00 $
CARPENTER 0 $ 37.00 $
LABORER 0 $ 24.00
0 $ - $
LABOR SUB TOTAL $ _
LABOR BURDEN $
TOTAL ITEM 1 : $
2. MATERIALS/EQUIPMENT RENTALS
DESCRIPTION QUANTITY UNIT PRICE
T _
3. SUBCONTRACTS TOTAL ITEM 2: $
SUBCONTRACTOR DESCRIPTION
Consys Added concrete per attached breakout $ 3,891.30
F&F composite Fence fenceing per attached breakout $ 1,081.02
Superior Striping parking bumpers $ 120.00
S -
S -
TOTAL ITEM 3: $ 5,092,32
4.SUBTOTAL WITHOUT MARKUP (ITEMS 1,2,&3) S 5_092 32
5.G&A OVERHEAD _ 10%1 $ 509.23
6.SUBTOTAL INCLUDING OVERHEAD S 5,601.55
7. PROFIT 5% S 2$0.08
8.SUBTOTAL INCLUDING OVERHEAD AND PROFIT 5 5,881.63
9. PERFORMANCE AND PAYMENT BOND 2.50% S 147.04
10.SALES TAX 0 00% $
11.TOTAL(ADDITION/DEDUCTION)TO CONTRACT SUM IF ACCEPTED 1$ 6,028.67
REQUEST IS MADE FOR ADDITION OF 0 CALENDAR DAYS TO THE CONTRACT PERIOD
The above proposal is subbmitted for your consideration.The undersigned contractor understands and agrees
that this proposal is validated only by the Owners signature.
This change proposal for subject work requires your approval by( ASAP ).
jimmy q- Ce A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project Manager in this original change order price.Each day beyond the required date additional
items will be added to the change proposal to reflect the acrued change.This will be
ICI(imperial Construction,Inc) determined after your authorization is finally received.Accordingly,upon receipt of
NAME OF CONTRACTING FIRM your approval,all cost resulting from these additional factors will be submitted to
correct the final change order price.
Change Order Approval by Owner/Architect Date
QAIADocument r" - 2001
Work Changes Proposal Request
PROJECT(Name and address): PROPOSAL REQUEST NUMBER:011 R2 OWNER:(�
City of Fort Worth Fire Station#5
850 Irma Street DATE Or ISSUANCE:May 17,2011 ARCHITECT:
Fort Worth,Texas 76104 CONSULTANT:❑
OWNER(Marne and address): CONTRACT FOR:General Construction CONTRACTOR:
City of Fort Worth FIELD:
❑
4Dl W. 13th Street CONTRACT DATE:July 15,2011
Fort Worth,Texas 76102 OTHER:❑
FROM ARCHITECT tWame and ARCHITECT'S PROJECT NUMBER:
address):
RPGA Design Group,Inc.
101 S.Jennings Avenue,Suite 100
Fort Worth,Texas 76104
TO CONTRACTOR(Name and
address):
Imperial Construction,Inc,
PO Box 967
Weatherford,Texas 76086
Pleasc submit an itemized proposal for changes in the Contract Stun and Contract Time for proposed modifications to
the Contract Documents described herein.Within Fourteen(14)days,the Contractor must submit this proposal or
notify the Architect,in writing,of the date on which proposal submission is anticipated.
THIS IS NOT A CHANGE ORDER,A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS,
DESCRIPTION(Insert a written description of the Work):
Provide pricing for adding the following(as indicated in the attached drawing):
1. a concrete gate pad
2. four(4)parking bumpers
3. ornamental picket fiberfence panels
At no additional cost,relocate the sliding gate to thte edge of the parking curb and locate the keypads as indicated in
L
attached drawing,
ATTACHMENTS(List attached documents that support description):
SK-I I R2-5/17/2011
REQUESTED BY THE ARCHITECT:
Heather Hall,Project Designer
(Signature) (Printed name and title)
AJA Document G709-—2001.Copyright 81 1993 and 2001 by The American irls"AS of Architects.All rights reserved.WARNING Thit AIAe Doeuatsnt is
protaetad by U.9.Copyright Lew and International T oatias.Unauthorized reproduction w distribution of this AtA`Document,or any portion of It,may
rtsuh it&Overt clvl;and criminal penalties,and wilt be prosecuted to the maximum extant potsiblo under the trw.This document was produced by AlA
eahwere et 1-54:28 or O5r1712011 under Order No.251a149474 1 which Mirea on 02/22/2012,and is not for resale
User Notes: —
(2037801579)
s I s EXIT GATE —6'—D" HIGH
' KEY PAD FENCE!
PANELI
PA KING
—� BU PERS i CONCRETE �j
�--� GATE iv
s
_----- PAD
6'-0'' HIGH FENCE
PANEL o
ENTRY GATE
KEY PAD
O
/I\
CONCRETE GATE PAD PLAN
SLIDING GATE
's
1/2" PREMOLDED
JOINT FILLER W/.
SEALANT
_4
4
r�i i iu iltJ� 1/8" PER FT. -
Z—L Ili DRIVE—ELEVATION
NK� I it i I I tl I Ii-f ,HIL... 2'—4"
l�i i 1 i 1 i� i� —iris si i o f
ru
is�t n�a 1011 i
� L—" PARKING�BUMPER
—
i
A s i it i ss �is� sr
�a , � � � — —
TURN D OWN CONCRETE
=lf 6-=� AT EDGE OF PAVEMENT
LI=III A�I� I C1 (IILI�(il I �� q
uiLU ii `w 911 Fs i sis —s
CONCRETE GATE PAD SECTION
suu:Un.ra
PR 11R- CONCRETE GATE PAD CD SHEET NO.
A-2.01
RPGA DESIGN GROUP, INC. FORT WORTH FIRE DEPARTMENT DATE:
101 S. JENNINGS AVE, STE. 100 FIRE STATION #5 5--17-11
FT. WORTH, TEXAS 76104 850 IRMA STREET
817-332- 9477 FORT WORTH, TEXAS 76104 SK-11 R2
„o,o-ftc ie.”, sum,�,
Delos, 7523a, C p L-ri JC
rec
Pt-214-349-3782 W 214•349•0080
www.com7scnncrere.cml
PROPOSAL
Work performed by: PROJECT: Fire Station No.5
( )General Contractor (x)Subcontractor CONTRACTOR: Imperial Construction
ConSys Concrete Corp.'s Proposal Number P-004 Pco#
.��
Time Extension(If any): none PRO
A5t A ��
��.
Description of Change: Revised gate pad
ADDITIONS AND/OR[CREDITS)
EXTENSION
scn ton anti nit ota ateria Labor quip.
Mu4n,ntendan,
JF
ac tin
oncr
're"
u ment s
P e ar 7 1
e r 1
ace an inis Add 1571st V13.
u in s 1
u m s
u oas
Rates%
Line I Enter total of Columns A+B+C+D+E $2,975.44
Line II Enter%of Col B for Workman's Comp.,
Social Security,and like taxes 40.98
$554.08
Line III Benefits and Vacation/Holiday 0,00 $0.00
Line IV Overhead 5.00 $17648
Line V Total Line i thru IV $3,706.00
Line VI Fee/Profit 5.00 $185.30
Line VII Bond Costs 0100 $0.00
Line VIII Total
53.891.30
SIGNATURE: DATE: October 5,2011
n s Concrete Corp.
May 26 11 02:44p F&F COMPOSITES 6173794296
p.2
is n v n n
m x o
N N 01 W W N W 1 l 7
� � n
o v '" 3 3
fD
td d C1 O S N V< m
w O ar
d
Yl ? ynj f°E N N 97 O
CL m 'a a p ti uy.
co
a
3 °
N O O
a d ro �% s n
m Im »
w m o rn a
N
O A v:
p- m N cn Ln t• io In co rZ
m
D !I
ro
m taJ m
3 c N Y o
07 � N N O p W at ? a Q
.-r Q
ep
V LO
J N O�1 A Q
N Vf µ1 N GAD N
t'9
C L
a \
CL cm
� N -
S
as to
N T
N m �
go
N
O
� � Fl
C)
D Q
�S O"
C O
N
-n
A
O �+ O
T
0
7
4
I
Page 1 of 2
Jimmy Tuley
From: Hotly Donaldson
Sent: Wednesday, May 11, 2011 1:37 PM
To: Jimmy Tuley
Subject: FW: FS 5-PR 11
Pricing from Superior Striping for PR 11
Holly Donaldson
Assistant Project Manager
Imperial Construction, Inc.
817-341-8886 office
817-341-0191 fax
From: Marirose Goocher[mail to:marirose @superiorstriping.com]
Sent: Wednesday, May 11, 2011 1:35 PM
To., Holly Donaldson
Subject: RE: FS 5-PR 11
Holly,
Do you want just the price to add the 3 wheelstops that will be needed in addition
to the ones already in the contract? If so that would be $120.00 total. Please let
me know if you need anything else.
Thanks,
Marirose Goocher
From: Holly Donaldson jmallto:HDonaidson @imperial-construction.comj
Sent: Wednesday, May 11, 20118:47 AM
To: Melissa Westmoreland (mwestmoreland @consysconcrete.com); Marirose Goocher
(marirose@superiorstriping.com)
Subject: FW: FS 5-PR 11
Importance: High
All,
Please see attached PR 11for the Fire Station#5 project. Please send in the requested pricing ASAP so
that we can get this to the architect for review.
Thank you
Holly Donaldson
Assistant Project Manager
Imperial Construction:, Inc.
6/10/2011
TO: City of Fort Worth 10/05/2011
JOB NAME: Fort Worth Fire Station#5 DATE CONTRACTORS
ATTENTION: Jack Durham CHANGE PROPOSAL CA.�-Z
10-0413 I� Z.QO
following is a detailed cost breakdown, including both materials&labor, PROJECT NO.
r all additions to and/or deductions from the contract sum.
SCOPE: Changes to Flume per ASI wc.P R� t4
CHANGE
PROPOSAL NO.
1. LABOR
NUMBER RATE
LABOR CATEGORY MAN HOURS PER HOUR COST
SUPERVISION 0 $ 59.00 $
CARPENTER 0 $ 37.00 $ _
LABORER 0 $ 24.00 $
0 $ - $ -
LABOR SUB TOTAL $ _
LABOR BURDEN $
: _
2. MATERIALS/EQUIPMENT RENTALS TOTAL ITEM 1 $
DESCRIPTION QUANTITY UNIT PRICE
T _
3. SUBCONTRACTS TOTAL ITEM 2 : $
SUBCONTRACTOR DESCRIPTION
A&S steel handrail $ 3,450.00
Consys Concrete concrete work at flume/handrail $ 6,645.49
TOTAL ITEM 3 : $ 10,095.49
4. SUBTOTAL WITHOUT MARKUP (ITEMS 1, 2, &3) $ 10,095.49
5. G&A OVERHEAD 10%'$ 1,009.55
6. SUBTOTAL INCLUDING OVERHEAD $ 11,105.04
7. PROFIT 5% $ 555.25
8. SUBTOTAL INCLUDING OVERHEAD AND PROFIT $ 11,660.29
9. PERFORMANCE AND PAYMENT BOND 2.50% $ 291.51
10. SALES TAX 0.00% $
11. TOTAL (ADDITION/DEDUCTION)TO CONTRACT SUM IF ACCEPTED $ 11,951.80
It ,95Z .00
REQUEST IS MADE FOR ADDITION OF 2 CALENDAR DAYS TO THE CONTRACT PERIOD
The above proposal is subbmitted for your consideration. The undersigned contractor understands and agrees
that this proposal is validated only by the Owners signature.
This change proposal for subject work requires your approval by( ASAP ).
,jimmy Tueey A delinquent response will accrue additional cost that is not included
Jimmy Tuley Project Manager in this original change order price. Each day beyond the required date additional
items will be added to the change proposal to reflect the acrued change. This will be
ICI (imperial Construction, Inc determined after your authorization is finally received. Accordingly, upon receipt of
aME OF CONTRACTING FIRM your approval all cost resulting from these additional factors will be submitted to
correct the final change order price
Change Order Approval by Owner/Architect Date
r
j- -� Document G709T11 - 2001
Work Changes Proposal Request
PROJECT('Warne and address): PROPOSAL REQUEST NUMBER:014 OWNER:
City of Fort Worth Fire Station 15 ARCHITECT:
850 Irma Street DATE OF ISSUANCE: 8i31i201 I
Fort Worth,Texas 76104 CONSULTANT:❑
OWNER(Name and address): CONTRACT FOR:General Construction CONTRACTOR:
City of Fort Worth FIELD:❑
401 W. 13th Street CONTRACT DATE:July 15,2011 OTHER:❑
Fort Worth,Texas 76102
FROM ARCHITECT(7Vame and ARCHITECT'S PROJECT NUMBER:
address):
RPGA Design Group,Inc.
101 S.Jennings Avenue,Suite 100
Fort Worth,Texas 76104
TO CONTRACTOR(Name and
address):
Imperial Construction,Inc.
PO Box 967
Weatherford,Texas 76086
Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposal modifications
to the Contract Documents described herein. Within Zero(0)days,the Contractor must submit this proposal or
notify the Architect,in writing,of the date on which proposal submission is anticipated.
THIS IS NOT A CHANGE ORDER,A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE
WORK DESCRIBED IN THE PROPOSED MODIFICATIONS.
DESCRIPTION(Insert a written description of the: Work);
Please provide pricing for the work outlined in the attached sheets,regarding revisions made to the flume on the
north side of the site.
ATTACHMENTS(Gist attached documents that support description):
PR 14-SK-21; PR 14-SK-22:PR 14-SK-23
REQVESTED BTI T ARCHITECT:
11 r
(i
Colin Wright, Project Designer
(Stgri7t ure) (Printed name and title)
AlA Document G709— - 2001 Copynyhl:c:1993 and 2001 by The American Inslih,le of Arehgecl%.All rights reserved.wA ,,N:, 1 is AIA
�n- rr,s.to—mew was pro0ucec.ray 1
AiA 9c tlwwr a 1 5"f iii rnrn b 11'21 ,u„ar')'d-No?f,'q 1494731 which naaues ur 02 22 20*2 fro mate
User Notes 18990,572221
Lij
�A\ w 00
V) Q o
ui
a GO
X
O/VA/VA WL-0 W W
OC:�*z L J F-
U
O G I
pQ < O
GO O �
Lij O of
00 LL O
LJ_J
iw
LJ
Q � 0
m Z W U O
LL- O v� Q
OC O w I�
O VZ � r�
V f�
- - ao �
0 oc L 00
"- EZ-)IS -VOL9L SVX31 `H180M 1803 LL-V6-ZCC-Ll8
13381S VV461 O98 M9L SVX31 `H180M '13
<<-«-e S# NOLLViS 3813 OOl'31S `3AV SONINN3r 'S Loi
:31VO 1N3WlbVd3a 3113 HISOM 121Od 'JNI 'dnOND NJIS30 VOM
`:133HS STVi3o 3H I A — tb ad
OD
\\
0
w
Ir
\\
J
�O
zu \\ N
o \\30
w a
oa
Of
�U
00 Oa \\ Nc0
�\ \ w
OD
LU
0
N
< OD
w
o
LLI
m
J\\ o
LL Z
O
ZZ-)IS -VOL9L SVX31 `H12JOM 12j03 LL-V6—ZC2—Ll8
1338iS VV481 092 VOL91- S`dX31 `H180M '13
9# N011`d1S 32113 001'31S `3AV SONINN3f'S LOL
:31VO .LN3Wf bVd3(3 3111) HMM lbOJ 'JM 'dnow) NJIS34 VDA
`1
:133HS sidlaa ivc�A
o
N,
O \ a V \
F
LU
cl
0
cn
o
>
> ce
0
r ,
Z
-
J Q N
z-
Z U U O W
Ow w 0
a 00� O
U lD
�Q O � J
OZ co
a� < o
LL N
O
A & S Steel
(all 1701 Brennan Avenue Tel 817-626-
7720
Fort Worth, Texas 76106 Fax 817-626-
0267
10/10/2011
Company: Imperial Construction
Attn: Jimmy/ Freddy
Reference: FS#5 Flume Handrail
Scope of Work: Furnish labor, equipment and material for the following:
Fabricate and install handrail/guardrail as per drawing.
Material to be prime painted
Post to be core drilled and poured after flume is complete.
Price=$3,450.00
Exclusions: Taxes, permits, engineering,
Lee Bristow
Project Manager
817-996-3490
Lee a�ASFabrication.com
NCTRCA CERTIFIED DBE
HUB - STATE OF TEXAS
i
,}I 11010 Swit—Avenue,Suite 100 C O T
Dallis,Texas 75238
Phone 214•349•3782 but 214•349,4084
www.c0nsyso0MMts.cam
PROPOSAL
PROJECT: Fire Station No.5
Work performed by:
( )General Contractor (X)Subcontractor CONTRACTOR: Imperial Construction
ConSys Concrete Corp.'s Proposal Number P-004 Pco#
Time Extension(if any): none PR#ASI#
Description of Change: Revised flume
ADDITIONS AND/OR[CREDITS]
eSCrl tlon Quantity nit Total Material Labor ul U con. fora e
U rinten eii s
ra a eams
ormin 90111f -
Foncre Ing an ac ing e
ui ment g
e ar $500.001
4
ear 72011b $0.071 -TRM
Ask ace an Finish g
u in 1 s
u in 1 s
Elu otoas
Rates%
Line I Enter total of Columns A+B+C+D+E $4,971.05
Line II Enter%of Col B for Workman's Comp.,
Social Security,and like taxes 40.98 $1,056.61
Line III Benefits and Vacation/Holiday 0,00 $0.00
Line IV Overhead 5.00 $301.38
Line V Total Line I thru IV $6,329.04
Line VI Fee/Profit 5.00 _ $316.45
Line VII Bond Costs 0.00 SO 00
Line VIII Total $6,645.49
SIGNATURE: DATE: October 5, 2011
n s Concrete Corp.
I
C I
IMPERIAL
construction inc
Jack Durham
Senior Construction Manager
T/PW Architectural Services
Mr. Durham
Imperial would like to request a time extension for the Fire Station #5 project. I am requesting an additional 65
days due to slow production from the Cast Concrete supplier. As you are aware the manufacturer could not
provide acceptable submittals in a timely manner. The other issue with the manufacturer was their productions
time was slow and several items had to be remade due to in correct forms they built. Please let this serve as a
official request for 65 additional days.
Respectfully,
Jimmy Tuley
Project Manager