HomeMy WebLinkAboutContract 57939-CO3CSC No. 57939-CO3
FORT WORTH • • City of Fort Worth
Change Order Request
Project Name:! Clear Fork Lift Station
Project No.(s):j 56020 / 0600430 / 001680
j City Sec No.: l
:==5=79=3=9========: .--N-/ A----.1 City Proj. No.: L-1_10_0_99_6 ___ _, DOE No.
P . t O . ti Lift Station wetwell piping and appurtenances; Three 10,500 gpm submersible sewage pumps; An electrical building and electrical and controlsroiec escnp on: improvements, 750 kW standby generator, yard piping, vaults and site work, etc.
Contractor:! Eagle Contracting, LLC
City Project Mgr.j Bljay Upretl, P.E., PSC-I
Phone Number:! 817-392-8909
Change Order# 3 Date: I 9/12/2025
City Inspector: Ronnie Cardenas / Ivan Rocha (KHA)
Phone Number:! 682-234-2767
Dept. Water Sewer
Original Contract Amount $12,969,865.00 Extras lo Date $42,335.55 Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $13,012,200.55 !Amount of Proposed Change Order $41,068.85 Revised Contract Amount $13,053,269.40 Original Funds Available for Change Orders $259,397.00 Remaining Funds Available for this CO $217,061.45 Additional Funding (if necessary)
CHANGE ORDERS to DA TE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
Jli.1S1ilFICATION {REASONS) FOR Cl!tANGE ORDER
Change Order No. 3 Is for the following that are necessary on the project:
Totals
$12,969,865.00
$42,335.55
$13,012,200.55
$41,068.85
$13,053,269.40
$259,397.00
$217,061.45
0.64%
$16,212,331.25
Contract Time
(Calender days)
480
0174
654
317
I 971
•The addition of a 1/2 HP 120V sump pump complete with a check valve and ball type shutoff valve to be Installed In the meter vault sump. See RFI 055 for
additional Information.
•The addition of 21 additional bollards around the generator and air unit condenser as required by the City of Fort Worth Fire Department.
•The replacement of the lift station level transmitter as requested by the City of Fort Worth operations staff.
• The addition of wetwell air vent piping to allow the odor control fan to operate as Intended.
Staff concurs request for an additional 265 calendar days on the projecvt due to delays resulting from lack of power to the site after substantial was
achieved, and 42 days to Install additional bollards around the generator for a total of 317 days.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
C0ntractor's Compan� Name Contractor Name
Eagle Contracting, LLC Andrew Howard
lnsp.ec_wn -7X. ' c�,.... o-\L
Director {Wate� Depij
Chr/rtoJ:Jher lfanter
Christo her Harder SeD 30, 2025 09:41:35 CDT)
Atslstant bliy AltorneYi ·, ---
DouglasBl�k(Octl,2D2517;47;27COT)
. .
-
T·S, --
no.ate .. _
c, I '4-I 2. s·' 0ate
09/30/2025 - r .. ·-l!late
10/01/2025
Contractor Signature
Andy Howard
• t, ProJticl Man�g�n ·-·- .
Bijay Upreri [gf-:-:;::.:.:.:-··
c-onstruct1on supervisor
Wade Miller ' Asslslanr'Clly, Manager �v
f'n11nr,il Af"fiAn (If Ron11irorl\
.---@ate.
Date
9/16/2025 � Date
10/07/2025 -
FOPT WORTH
City of Fort Worth
Change Order Additions
Project Name Clear Fork Lift Station City Sec No.: 57939
Project No.(s): 56020 / 0600430 / 001680 DOE No. N/A City Proj. No.: 100996
Project
Description
Lift Station wetwell piping and appurtenances; Three 10,500 gpm submersible sewage pumps; An electrical building
and electrical and controls improvements, 750 kW standby generator, yard piping, vaults and site work, etc.
Contractor Eagle Contracting, LLC Change Order:�3 Date: 9/28/2025
City Project Mgr. Bijay Upreti, P.E., PSC-I City Inspector Ronnie Cardenas / Ivan Rocha
ADDITIONS
DEPT Qty Unit Unit Cost Total
48 CMR-005 - SUMP PUMP Sewer 1.00 LS $7,526.66 $7,526.66
49 CMR-006 - ADDITIONAL BOLLARDS Sewer 1.00 LS $24,935.00 $24,935.00
50 PCM-006 - LEVEL TRANSMITTER Sewer 1.00 LS $3,417.85 $3,417.85
51 PCM-007 - WETWELL AIR VENTING IMPROVEMENTS Sewer 1.00 LS $5,189.34 $5,189.34
Water
Sewer $41,068.85
Page 2 of 4 Additions Sub Total $41,068.85
FC�RT WCjRTH City of Fort Worth
Change Order Deletions
Project Name Clear Fork Lift Station City Sec No.: 57939
Project No.(s): 56020 / 0600430 / 001680 DOE No. N/A City Proj. No.: 100996
Project Description Lift Station wetwell piping and appurtenances; Three 10,500 gpm submersible sewage pumps; An electrical
buildinq antl electrical and controls improvements, 750 kW standbv Qenerator, vard qipinp. vaults and site work.
Contractor Eagle Contracting, LLC Change Order: �3 Date 9/28/2025
City Project Mgr. Bijay Upreti, P.E., PSC-I City Inspector: Ronnie Cardenas / Ivan Rocha (KHA)
ITEM IDESCRIPTION
DELETIONS
DEPT
Qty �Unit �Unit Cost
otal
Water
Sewer
Page 3 of 4
Deletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub
Tvpe of Service
Amount for this CO
Same as original Contract
Miscellaneous
Total
Page 4 of 4
$36,750.76
$36,750.76
Clear Fork Lift Station
Eagle Change Proposal No. 5
Date: March 04, 2024
Owner: Engineer: Contractor:
City of Ft. Worth Water Department Kimley Horn Eagle Contracting
200 Texas St. 801 Cherry St., Suite 1300 5700 Park Vista Circle
Ft. Worth, Texas 76102 Fort Worth, Texas 76102 Ft Worth, Texas 76244
Labor Material GC Material Equipment Subcontractor
TOTALS: 3,298.40$ 985.02$ 249.94$ -$ 2,056.03$ $6,589.39
Overhead & Profit - 5% Subcontracted Work $102.80
Overhead & Profit - 15% Self Performed Work $642.51
Subtotal $7,334.70
Eagle Insurance 1.8% $118.61
Bond @ 1% $73.35
Subtotal $7,526.66
Total Amount This Cost Proposal $7,526.66
Time Extension Required Days
Days Required to Complete Work 0 Days
As requested per RFI-055.
Additional sump sump at the meter vault.
City of Fort Worth Project# 10
Clear Fork Lift Station
Date: 07//2024
PCO No.: 6
Owner: Engineer: Contractor:
The City of Fort Worth Kimley-Horn and Associates,Inc. Eagle Contracting
200 Texas Street 801 Cherry Street, Unit 11 5700 Park Vista Circle
Fort Worth , Texas 76102 Fort Worth, TX 76102 Ft Worth, Texas 76244
QTY UNIT UNIT PRICE TOTAL
1.00 LS 24,935.00$ 24,935.00$
24,935.00$
Time Extension Required 42 Days
Days Required to Complete Work 7 Days
19 Additional bollards around the and 2 around the condenser . Per request from the owner to avoid damage to
the Eagle is to add two additional bollards for protection. Per the fire specifications additional bollards
around the generator are required All costs for installing 21 total bollards are include .
Inclusions/Exclusions:
Work Description: Additional Bollards
Additional Bollards
Total Amount This Cost Proposal
DESCRIPTION
guidance to the contractor for the placement of the bollards but wanted to confirm our assumptions prior to issuing our guidance. See below
for the proposed bollard layout.
Please note the following assumptions:
3’-0” measurement is from the fuel tank and sound enclosure for generator. Not from the foundation or catwalk.
Bollards are only required on the sides and front of the generator as vehicles are not expected to need to access the backside of the
generator. Also, there is an antenna base and fence on the backside of the generator that should discourage vehicle operators from
driving to that area.
Please advise.
Thanks,
Ivan Rocha
(682)234-2767
From: Karen Vargas <k.vargas@eaglecontracting.com>
Sent: Thursday, June 27, 2024 9:58 AM
To: Rocha, Ivan <Ivan.Rocha@kimley-horn.com>; Cardenas II., Ronnie A. <Ronald.Cardenas@fortworthtexas.gov>; Zamora, Ray <Ray.Zamora@kimley-
horn.com>
Cc: Todd Smith <t.smith@eaglecontracting.com>; Jose Flores <j.flores@eaglecontracting.com>; Jorge Fraire <jorge.fraire@eaglecontracting.com>
Subject: Clearfork Lift Station - Fire department Bollards
Team ,
Please see email chain below, it looks like the fire department is requesting additional bollards before the final inspection. Are we good to add
these bollards to the change order for additional bollards requested at the condensers?
From: Todd Smith <t.smith@eaglecontracting.com>
Sent: Friday, June 21, 2024 10:11 AM
�
��'i�� f�l f� �,
� �
�
��
�
CMR-006 - ADDITIONAL
= L R�S
�
�
F� ��� L i r� �
� �
- _ ��� � .
��� + ��_�
,
�
_ �
s_��
� ��� :�� � [� � 1 r �}f�ti ��U It� ������L�� ��d F
� " �"
� � � - -
�
��k3�t1�3� ��������
Please note the following assumptions:
�
• 3'-0" measurement is from the fuel tank and sound enclosure for generator. Not from the foundation or
catwalk.
• Bollards are only required on the sides and front of the generator as vehicles are not expected to need to
access the backside of the generator. Also, there is an antenna base and fence on the backside of the
generator that should discourage vehicle operators from driving to that area.
Please advise.
Thanks,
Ivan Rocha
(682)234-2767
4
Clear Fork Lift Station
Eagle Change Proposal No. 6
Date: October 10, 2024
Owner: Engineer: Contractor:
City of Ft. Worth Water Department Kimley Horn Eagle Contracting
200 Texas St. 801 Cherry St., Suite 1300 5700 Park Vista Circle
Ft. Worth, Texas 76102 Fort Worth, Texas 76102 Ft Worth, Texas 76244
Labor Material GC Material Equipment Subcontractor
TOTALS: -$ -$ -$ -$ 3,169.08$ $3,169.08
Overhead & Profit - 5% Subcontracted Work $158.45
Overhead & Profit - 15% Self Performed Work $0.00
Subtotal $3,327.53
Eagle Insurance 1.8% $57.04
Bond @ 1% $33.28
Subtotal $3,417.85
Total Amount This Cost Proposal $3,417.85
Time Extension Required 0 Days
Days Required to Complete Work 0 Days
Change the current Siemens Radar Level
Transmitter with a newer transmitter that has a
birdcage to assist with level readings. This
proposal includes material and labor.
PCM-007 - WETWELL AIR
VENTING IMPROVEMENTS
Clear Fork Lift Station
Change Order - 07
Date: 04/24/2025
Work Description
Install 6" vent piping at wet well for odor control
Owner:
City of Ft. Worth Water Department
200 Texas St.
Ft. Worth, Texas 76102
Engineer:
Kimley Horn
801 Cherry St., Suite 1300
Fort Worth, Texas 76102
Labor Material
_ �'
��� y� -
�
� ..���
�1�� �
•x �
_ _ _ �W
�����
�[��1T����.TI�1G
Contractor:
Eagle Contracting
5700 Park Vista Circle
Ft Worth, Texas 76244
Equipment Subcontractor
TOTALS: $ 1,969.92 $ 2,429.02 $ - $ - $4,398.94
Eagle Insurance 1.8% $79.18
Overhead & Profit - 5% Subcontracted Work $0.00
Overhead & Profit - 15% Self Performed Work $659.84
Subtotal $5,137.96
Bond 1% $51.38
Subtotal $5,189.34
Subtotal $5,189.34
Time Extension Required -
PROPOSED CONTRACT MODIFICATION (PCM)
OWNER: City of Fort Worth PROJECT NO.: 100996
PROJECT: Clear Fork Lift Station
CONTRACTOR: Eagle Contracting (CSC # 57939) Description: Wetwell Air Venting
Improvements ENGINEER: Kimley-Horn and Associates, Inc
ENGINEER'S CONTACT: Josh Kercho, P.E. / William Weidman, P.E. PCM NO. 007
NOTIFICATION TO CONTRACTOR:
WE ARE CONSIDERING MAKING THE CHANGE TO THE CONTRACT DESCRIBED IN THE ATTACHED
MATERIALS AND REQUEST THAT YOU TAKE THE FOLLOWING ACTION:
NOTIFY US THAT YOU CONCUR THAT THIS CHANGE DOES NOT REQUIRE A CHANGE IN CONTRACT
TIME OR AMOUNT. A FIELD ORDER WILL BE ISSUED.
SUBMIT A PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED SCHEDULE FOR
PERFORMING THE DESCRIBED CHANGE.
A CHANGE ORDER WILL BE ISSUED FOR PAYMENT AT THE UNIT PRICE BID
PROCEED WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE CONTRACT.
BY: Josh Kercho, P.E. DATE April 15, 2025
DESCRIPTION OF PROPOSED CHANGE: DESCRIBED HEREIN SEE ATTACHED
Per punchlist walk through on 4/7/25 and at direction from City Plant Operations staff, additional Schedule 80
PVC air venting piping is required on the wetwell prior to final acceptance.
CONTRACTOR'S RESPONSE:
WE RESPOND TO YOUR REQUEST AS FOLLOWS:
WE CONCUR THAT THIS IS A NO COST OR TIME CHANGE, ISSUE FIELD ORDER.
WE SUBMIT THE ATTACHED PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED
SCHEDULE FOR PERFORMING THE DESCRIBED CHANGE.
WE ARE PROCEEDING WITH THE CHANGE AT THE UNIT PRICE BID
WE ARE PROCEEDING WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE
CONTRACT.
BY: DATE:
ACTION TAKEN: RECOMMENDED NOT ACCEPTED REVISE AND RESUBMIT CANCELLED
COMMENTS:
BY: DATE:
Clear Fork Lift Station
CMR #6 - Time Extension Oncor
Date: 04/24/2025
Work Description
Owner: Engineer: Contractor:
City of Ft. Worth Water Department Kimley Horn Eagle Contracting
200 Texas St. 801 Cherry St., Suite 1300 5700 Park Vista Circle
Ft. Worth, Texas 76102 Fort Worth, Texas 76102 Ft Worth, Texas 76244
Labor Material Equipment Subcontractor
TOTALS: -$ -$ -$ -$ $0.00
Eagle Insurance 1.8% $0.00
Overhead & Profit - 5% Subcontracted Work $0.00
Overhead & Profit - 15% Self Performed Work $0.00
Subtotal $0.00
Bond @ 1% $0.00
Subtotal $0.00
Subtotal $0.00
Time Extension Required - 275 Days
Ocnor Work 73 Days
Eagle Work 202 Days
Time extension due to Oncor equipment delay
We request 73 additional days directly related to the delay of Oncor installing and energizing permanent power at the site, we
originally asked for anticipated days in change order #2 giving us a date of May 7, 2024 but Oncor took longer than originally expected
and they completed the installation of the transformers on July 19, 2024 which is 73 days. Additionally we request 202 days for Eagle
to organize and complete the activities that could not be performed on temporary power such as pulling and terminating power
conductors, HMI integration, HVAC start up, Odor Contol start up, work associated with MH-272 & MH-479 along with cordination and
scheduling Rail Pros observer, repair of the 48" waterline and FDT, ORT and SAT testing.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
_____________________________________
Signature
______________________________________
Name of Employee
______________________________________
Title
ATTEST:
______________________________________
Jannette S. Goodall
City Secretary
Sr. Professional Engineer
Bijay Upreti, P.E.