HomeMy WebLinkAbout061299-FP2 - Construction-Related - Contract - Bean ElectricalPage 1 of 2
City Secretary
Contract No.__________________
Date Received ______________
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Kedplasma Plasmapheresis Center
City Project No.: 104997
Improvement Type(s): Water Sewer
Developer Costs City Costs Total Cost
Original Contract Price: Water $36,338.32 $69,314.12 $105,652.44
Original Contract Price: Sewer $22,313.00 $0.00 $22,313.00
Original Contract Price Total $58,651.32 $69,314.12 $127,965.44
Approved Change Order: Water $2,191.00 $0.00 $2,191.00
Approved Change Order: Sewer $0.00 $0.00 $0.00
Revised Contract Amount: Water $38,529.32 $69,314.12 $107,843.44
Revised Contract Amount: Sewer $22,313.00 $0.00 $22,313.00
Total Cost of Work Complete:$60,842.32 $69,314.12 $130,156.44
Contractor Date
Title.
Calvo Construction, Inc.
Company Name
Project Inspector Date
Project Manager Date
CFA Manager Date
_______________________________________ __________________________________
TPW Director Date
Page 2 of 2
Asst. City Manager Date
Notice of Project Completion
Project Name: Kedplasma Plasmapheresis Center
City Project No.: 104997
City’s Attachments
Final Pay Estimate
Change Order(s):Yes N/A
Pipe Report:Yes N/A
Contractor’s Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 63
Work Start Date: 4/23/2025
Days Charged: 48
Work Complete Date:8/18/2025
Completed number of Soil Lab Test: 38
Completed number of Water Test: 7
CITY OF FORT WORTH
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type WATER & SEWER
DOE Number 4997
Estimate Number 1 Payment Number 1 For Period Ending 8/18/2025
FINAL PAYMENT REQUEST
City Secretary Contract Number
48
WD
Contract Date
CALVO CONSTRUCTION INC
NA
621 N. MAIN STREET, SUITE 415
GRAPEVINE TX 76051
G.DEYON C.GARCIA
63WDContract Time
Days Charged to Date
CompleteContract is 100.00
Contractor
,
/Inspectors
Project Manager
City Project Numbers 104997
Wednesday, September 24, 2025 Page 1 of 4
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type WATER & SEWER
DOE Number 4997
Estimate Number 1
Payment Number 1
For Period Ending 8/18/2025
Project Funding
City Project Numbers 104997
UNIT I: WATER IMPROVEMENTS
Item
No.Description of Items Estimated
Quanity Unit Unit Cost Estimated
Total
Completed
Quanity
Completed
Total
1 CONNECTION TO EXISTING 4"-12" WATER
MAIN
2 EA $2,135.00 $4,270.00 2 $4,270.00
2 1" WATER SERVICE 2 EA $2,317.00 $4,634.00 2 $4,634.00
3 PVC WATER PIPE, SELECT BACKFILL: ROCK 30 LF $70.00 $2,100.00 30 $2,100.00
4 TRENCH SAFETY 350 LF $1.00 $350.00 350 $350.00
5 8" WATER PIPE, SELECT BACKFILL: ROCK IS 292 LF $129.57 $37,834.44 292 $37,834.44
6 8" GATE VALVE 2 EA $2,594.00 $5,188.00 2 $5,188.00
7 4"-12" PRESSURE PLUG 1 EA $500.00 $500.00 1 $500.00
8 WATER LINE GROUTING 241 LF $27.00 $6,507.00 241 $6,507.00
9 8" WATER LINE LOWERING 4 EA $6,864.00 $27,456.00 4 $27,456.00
10 ROAD PLATES 17 EA $989.00 $16,813.00 17 $16,813.00
11 8" PVC C900 DR14 (CO#1)5 LF $260.00 $1,300.00 5 $1,300.00
12 RELOCATE EXISTING GATE VALVE (CO#1)1 EA $891.00 $891.00 1 $891.00
$107,843.44 $107,843.44Sub-Total of Previous Unit
UNIT II: SANITARY SEWER IMPROVEMENTS
Item
No.Description of Items Estimated
Quanity Unit Unit Cost Estimated
Total
Completed
Quanity
Completed
Total
1 8" SEWER PIPE 50 LF $64.90 $3,245.00 50 $3,245.00
2 4' MANHOLE 1 EA $12,953.00 $12,953.00 1 $12,953.00
3 TRENCH SAFETY 50 LF $1.00 $50.00 50 $50.00
4 MANHOLE VACUUM TESTING 1 EA $350.00 $350.00 1 $350.00
5 POST-CCTV INSPECTION 50 LF $3.00 $150.00 50 $150.00
6 UTILITY SERVICE SURFACE RESTORATION
SODDING
60 SY $25.00 $1,500.00 60 $1,500.00
7 CONCRETE COLLAR FOR MANHOLE 1 EA $4,065.00 $4,065.00 1 $4,065.00
$22,313.00 $22,313.00Sub-Total of Previous Unit
Wednesday, September 24, 2025 Page 2 of 4
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type WATER & SEWER
DOE Number 4997
Estimate Number 1
Payment Number 1
For Period Ending 8/18/2025
Project Funding
City Project Numbers 104997
Contract Information Summary
Change Orders
$127,965.44Original Contract Amount
$130,156.44Total Contract Price
$130,156.44
Less
Total Cost of Work Completed
% Retained $0.00
Net Earned $130,156.44
Plus Material on Hand Less 15%$0.00
Balance Due This Payment $130,156.44
Less Liquidated Damages
Days @ / Day
$0.00
Less Penalty
LessPavement Deficiency $0.00
$0.00
$0.00Less Previous Payment
Earned This Period
Retainage This Period
$130,156.44
$0.00
1 $2,191.00Change Order Number
Wednesday, September 24, 2025 Page 3 of 4
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type WATER & SEWER
DOE Number 4997
Estimate Number 1
Payment Number 1
For Period Ending 8/18/2025
Project Funding
City Project Numbers 104997
Line Fund Account Center
Amount
Funded Gross Retainage Net
CITY OF FORT WORTH
SUMMARY OF CHARGES
$130,156.44
Less
Total Cost of Work Completed
% Retained $0.00
Net Earned $130,156.44
Plus Material on Hand Less 15%$0.00
Balance Due This Payment $130,156.44
Less Liquidated Damages
0 Days @ $0.00 / Day $0.00
Less Penalty
LessPavement Deficiency $0.00
$0.00
$0.00Less Previous Payment
Earned This Period
Retainage This Period
$130,156.44
$0.00
City Secretary Contract Number
48
WD
Contract Date
CALVO CONSTRUCTION INC
NA
621 N. MAIN STREET, SUITE 415
GRAPEVINE TX 76051
G.DEYON C.GARCIA
63
WD
Contract Time
Days Charged to Date
CompleteContract is 100.000000
Contractor
,
/Inspectors
Project Manager
Wednesday, September 24, 2025 Page 4 of 4
�--�
0
V
�
�
�
N
�--I
CD
0
z
U
N
U
W �
�, Z
Z �
Q LLJ T
S �
U�
�
W
�
z
0
�
Q
a
� v
� —
N
� �
°� a
o a
� �
N U
m
N
N
� �
d �
C C �
N N pp
U � c�o
N °� o
N C w
N - �
� � �
� m 6)
� C �
m o
E �
� @
�6 a r�
� � v
@ o
3 0
@ �n o � o � �
O_ N O � � V ap �
O � � �
_p @ � � � N N
Y � N � co � X �
�
H
U
�
H
Z
O
U
� }
� U ¢
Z H � �
U
� Q O U
�
� w
� � � a � �
�
� Z Q F F �� w
� O �
d U U U U� X�
� N
00 M
� N
� V
N CO
� �
� �
O O
z z
N N
C C
0 0
t �
a �
�
N
fV
� �
cv Q
C� c
N �
� �
i �
� N
U
�
W
�
Q
Z
Q
�
H
U
w
O
�
d
�
z �
� Q N N � N
� �
�
N
(n � O O O O O O
r U
2 �' u�4 u�9 u�4 u�4 u�4 �M �n
� U �
J �
F
W � � �
W 1� 1� 1� �
� Q uj o o uj o uj �
� O pp O O pp O pp
> N fR fR fR pp
� U t» t» t» n
�
� � � ti
�j o 0 0 0 �'+ M �
�, o 0 0 0 � �
us v3 v3 v3 �n
� U u�s u�s �
z �
> �
m
a ��o, ��o, m r°',,
y N O O N OD M �
O � O O � �
M
O � � O N �
N O � �
� U � � �
w
U o 0 0 0 0 0
� o 0 0 0 0 0
Z W « � � � � � u�s ..
� Z V � U �
H �
Q Q °° « m
K � � U ri
� � �
Z O O O N
� N �
U 0 � O O � O �
pp O O pp O pp
W O tA �� tA � tA
� U
N
0 0 0 0 0 o a
V o 0 0 0 0 0
�, o 0 0 0 0 0
V3 v3 v3 u3 v3 E9
U o co
� O M
� M n
M n
W y I�
� O O O O N �p
V o 0 o N ap
� � � � 0 � �
d O O O �
O. M p p M p M
� N � � N � N
y N N N
> U3 U3 V3
�
H
� � �
U � o o � o �
0 0 0
a M O O M O M
m � � m � m �
� V �» �» � M
w �
� �
� �
N N N O
M M � M ��
0 0 � in
p_ M O O M � N O
O M O O M � N U
� �
N
m O u4 u4 � t9 N
❑ U ❑
�
a
r
� Z r
� U
� � � K
o � ¢ Q r
w � U ai O
� O ¢
U
� = a Z Z O w
U W U H 0� U N
Q w Q a Q v o >
H
� w � p� � w
� � o O a z� w ¢
��� U� o W � O
z `n � � z ow � ~
� � �w z o > �
�
O W U O Q� O
�
�
a
O �
J O O O O O O O O O O O O O O O O O
F� O O O O O O O O O O O O O O O
� M OD Ef) fA ElT fA Ef) fA fA fA ElT fA ElT fA ElT fA Ef)
F �
V)
N
O O O O O O O O O O O O O O O O O O
(J O O O O O O O O O O O O O O O O O
w fA fA fn fA fn fA fn fA fA fA f9 d-1 V3 d-1 fn fA fn
U
0
o-.. � o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
o m o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
> U � omo � � � � � � � � � � � � � � �
� :/T �
W
z w
U
� � o 0
Q ~ � °°
� z d,v'
7
C�
z
� w
w �
� � U O O
O �a`o 0
J � �
� U
O
�
�
; W
i
W -�
� �
� O � Q
O �oc9
z a o �
O U � Z
I- tn U y
U ❑ j X
� � a W
w� r°°a
� �
O �
� w
� �
W
O
�
O
W
(� J a
z W
Q �
� �
�
�
z
w
� } O O
W F � �
i �
O z
2 Q
a �
� CJ
�
W
a ��
?� m � ''�
� (O O
.. } w NO O
� ~ �
H U— � c �
Z M M
�
�
�
w ,
H N
} �
Q
a
�
C
�
�
0
�
U
m
c
O
�
C
�
@
U
O O Q� [O O
J � a N O O O O O O O O O O
FO���� m O O O O O O O O
Q � M ln M u1 N fA ER fA EA fA fA ER fA
F � N N N �
E!T EA ElT EA V)
N O O � �
(J O � O�� � O O O O O O O O
>, O O O �� N O O O O O O O O
d-1 � EA �� fA fn fA fn fA fA fn fA
OW U y> iH
�
� o m
� o-.. o v N� o� o 0 0 0 0 0 0 0
o N o o � o� o 0 0 0 0 0 0 0
���j o ��� o� o 0 0 0 0 0 0 0
() � EA CO N tA � EA v) fA u3 fA fA u3 fA
� � � EA E/)
j
aW
V �n o
Q� � vtDi, m r� co
z � ���NN
o z �����
ti �
O
O
Q
00
z�� g0000
¢ 2� a 'n o � � �
� � � � � �
fW- U
W
�
U
z
O r
U 1° v
� C � �
O a m .o
ti Z �� � �� �
W z Q�� v d
d 'm Q a�i �
U a � w a � �
Q � Q � Z .� �
a � a E p y m
� p Q a U � 'R
.' W p_
Q W O�- Q a a'
J � Q W C �
� � °'�va
O � �'
� � A
t
W v °-
� Q
W
ti
� > � > > r
� � J � � N
� �
w �
0
�
0
W
(� O O (D (O �
z � O O �f) � O
Q O L() � 7 �
_ � N � N N
U z
¢
� �
F �
Z
W
�
w g �
> m o � o v
� g o � o 0
� � � � O � O O
a �- �
� a o a o 0
� N N N N N
� O M O M M
Z
i
a
a
H
z
� �
�
w
H � O N M
}
Q
a
e
a
�.
m
a
a
z
a`�,
R
V
�
C
N
N
al
@
a
� �y�-�
� } � 4 y
�
y � � I}
� � y ro . �
����"x
}� b
� i L •-"4 LL �
����.: 4
t �=�-
5
�� � �
�—�*xy�
2 3� t �x9
� � s � ��
�����
� � L
� � � f �
� {�2�
��T���
�
� i � �'
�t���R
S C V .�
� � � � ` e
� � �� � �
_ � � � � 7
�����{
�,,�-� '
� � � 4� ht
4 3 7i S =
- n � � { �:
��� `� -
�����:
p������
���R�o
�� � ' �
� £
������
� � 5
� e��
��o �„
� �
e
�����Q
�����_
t u s � � �
�
�o����
�'�L€��
�,��a���
� ����p°
M � � � g S FF
4 t 4 y
�4 � � �
' � + [
L 7i �' r p � �
F- � � r C {n �£
�
O
�
U
�
�
�
��
8
� �
�
a
d -
�
�
�
r �
�
N
0
N
�
O
0
� )
_ G
O
�
0
W
0
�
c1 � `�:
�� � � �
� �
H q � 4
G
� J
`u
c �,i
� �ri
4 L
W�
��
0
N
�
O
6
W
� _ aw
� ? q
� 4
� r �
� � �
� y �
li o
�
�
� t�
�
� _
{� �
��
�#
'� `a_
� �
� �
E
r
U
N
W
U
�
.0
N
�
�
�
a
`w
�
�
U
�
�
�
J
v �
{ry 4�
� �
W
N n
� i
, � �� �
� �
� �
�5��� � �
� � l� � � �
��y a �s �
� �
� L � � � S
���� � �
� � �� � �
_ � � ��
si �' � � � w
N E � k �
E;.=� � �
U����' � �
� �� � �
���� � �
���� � �
�-
�
9
� I �
� � �
� �:' �
�
0
�
O
O
�
i
:
i-
� �
'� �
. �
2�
� �
� � o
F ,
�
x
� �
��
C {S �
W � �
�� � r�
� F
d
�
C
4�
t�
��
� H
u
�
z
�
�
�
LF
SEWER
50
292
30
LF
LF
NEW SERVICES:
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 7941 • Fax: (817) 392 - 7845
DENSITIES:
WATER
PIPE ABANDONED SIZE TYPE OF PIPE
TYPE OF PIPE
PVC 8 SDR-26
SIZEPIPE LAID
NEW SERVICES:
DENSITIES:
216
SIZE TYPE OF PIPE
Cast Iron 6 Cast Iron
FIRE HYDRANTS:0 VALVES (16" OR LARGER)0
LF
PIPE ABANDONED
8" C900
PVC 6" C900
PIPE LAID SIZE TYPE OF PIPE
PVC
PROJECT NUMBER:
PROJECT NAME:KEDPLASMA
104997
DOE NUMBER:
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
Rev. 9/15/16
TRANSPORTATION AND PUBLIC WORKS
August 27, 2025
Calvo Construction, Inc.
621 Main St. Ste 200
Grapevine, Texas 76051
RE: Acceptance Letter
Project Name: KEDPLASMA
Project Type: Water, Sewer, Paving, Drainage, Street lights
City Project No.: 104997
To Whom It May Concern:
On August 26, 2025 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on August 26, 2025,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-7830.
Sincerely,
Ahmed Izeldeen, Project Manager
Cc: Carlos Garcia, Inspector
Gary Deyon, Inspection Supervisor
Lorrie Pitts , Senior Inspector
Andrew Goodman, Program Manager
Ntirr, Peters & Associates, Consultant
Calvo Construction Inc., Contractor
Four Roses, Developer
File
E-Mail:
Douglas W. Wiersig, P.E., PhD., Director, TPW
Richard Martinez, Assistant Director, TPW
Marisa Conlin, Traffic Engineering
Allen Hall, Superintendent, TPW
John Robert Carman, P.E., Director, Water
Chris Harder, P.E., Assistant Director, Water
Wendy Chi-Babulal, P.E., Water
Tony Sholola, P.E., Water
Richard Zavala, Director, PARD
David Creek, Assistant Director, PARD
TEXAS CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
Project: KEDPlasma Fort Worth
Job No.22018
On receipt by the Signer of this document of a check from Stough Development
Corporation (maker of check) in the sum of $, payable to
(payee or payees of check) and when
the check has been properly endorsed and has been paid by the bank on which it is
drawn, this document becomes effective to release any mechanic's lien right, any right
arising from a payment bond that complies with a state or federal statute, any common
law payment bond right, any claim for payment, and any rights under any similar
ordinance, rule, or statute related to claim or payment rights for persons in the signer's
position that the signer has on the property of Four Roses Private Select, LLC
(Owner) located at 4 North Riverside Drive, Fort Worth, TX 76111
(location) to the following extent: KEDPlasma Center (project description).
This release covers the Final payment for all labor, services, equipment, or
materials furnished to the property or to Stough Development Corporation and Four
Roses Private Select, LLC (person with whom signer contracted) as indicated in the
attached statement(s) or progress payment request(s), except for unpaid retention,
pending modifications and changes, or other items furnished.
Before any recipient of this document relies on this document, the recipient should verify
evidence of payment to the signer.
The Signer warrants that the signer has already paid or will use the funds received from
this progress payment to promptly pay in full all of the signer's Laborers,
Subcontractors, Materialmen, and Suppliers for all work, materials, equipment, or
services provided for or to the above referenced project up to the date of this waiver and
release.
Company (Signer) Name:
__________________________________
__________________________________ (Signature)
__________________________________ (Title)
__________________________________ (Date)
DALLAS FORT WORTH, TEXAS
T (972) 979-3138 WWW. SBGBONDING.COM
09/20/2024
Re: Calvo Construction Inc
Obligee: City of Fort Worth
Project: Kedplasma Plasmapheresis Center
Bond#: S047325
Dear Sir or Madam,
Please let this letter serve as authorization to date the bonds and powers of attorney for the
above captioned bonds. This authority may be extended by you to the owner, architect, or
designated representatives.
Sincerely,
Sam Sealer
Attorney in Fact, Employers Mutual Casualty Company
sam@sbgbonding.com
Surety & Construction Specialists
Sincerely,
S S l
00 62 19 - 1
MAINTENANCE BOND
Page 1 of 5
CITY OF FORT WORTH Kedplasma Plasmapheresis Center
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS[Insert Project Number]
Revised January 31, 2012
SECTION 00 62 19 1
MAINTENANCE BOND 2
3
THE STATE OF TEXAS § 4
§ KNOW ALL BY THESE PRESENTS:5
COUNTY OF TARRANT § 6
[Text in Blue is for information or guidance. Remove all blue text in the project final document.] 7
That we_____________________________________________________, known as 8
Principal herein and ____________________________________________, a corporate surety 9
(sureties, if more than one) duly authorized to do business in the State of Texas, known as 10
Surety herein (whether one or more), are held and firmly bound unto the Developer, Stough 11
Development Corporation, authorized to do business in Texas (Developer) and the City of Fort 12
Worth, a Texas municipal corporation (City), in the sum 13
of_________________________________________ Dollars ($_______________________), 14
lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for payment 15
of which sum well and truly be made jointly unto the Developer and the City as dual obligees 16
and their successors, we bind ourselves, our heirs, executors, administrators, successors and 17
assigns, jointly and severally, firmly by these presents. 18
19
WHEREAS, Developer and City have entered into an Agreement for the construction of 20
community facilities in the City of Fort Worth by and through a Community Facilities Agreement, 21
CFA Number and 22
WHEREAS, the Principal has entered into a certain written contract with the Developer 23
awarded the_____ day of , 20 , which Contract is 24
hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish 25
all materials, equipment labor and other accessories as defined by law, in the prosecution of the 26
Work, including any Work resulting from a duly authorized Change Order (collectively herein, 27
the Work) as provided for in said Contract and designated as Kedplasma Plasmapheresis 28
Center; and 29
Calvo Construction, Inc.
Employers Mutual Casualty Company
One Hundred Thirty Thousand Seven Hundred Eighty Three and 44/100 130,783.44
Bond Number: S047325
00 62 19 - 2
MAINTENANCE BOND
Page 2 of 5
CITY OF FORT WORTH Kedplasma Plasmapheresis Center
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS[Insert Project Number]
Revised January 31, 2012
1
WHEREAS, Principal binds itself to use such materials and to so construct the Work in 2
accordance with the plans, specifications and Contract Documents that the Work is and will 3
remain free from defects in materials or workmanship for and during the period of two (2) years 4
after the date of Final Acceptance of the Work by the City (Maintenance Period); and 5
6
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part upon 7
receiving notice from the Developer and/or City of the need thereof at any time within the 8
Maintenance Period. 9
10
NOW THEREFORE, the condition of this obligation is such that if Principal shall remedy 11
any defective Work, for which timely notice was provided by Developer or City, to a completion 12
satisfactory to the City, then this obligation shall become null and void; otherwise to remain in 13
full force and effect. 14
15
PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely 16
noticed defective Work, it is agreed that the Developer or City may cause any and all such 17
defective Work to be repaired and/or reconstructed with all associated costs thereof being 18
borne by the Principal and the Surety under this Maintenance Bond; and 19
20
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 21
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 22
Worth Division; and 23
24
PROVIDED FURTHER, that this obligation shall be continuous in nature and successive 25
recoveries may be had hereon for successive breaches. 26
00 62 19 - 3
MAINTENANCE BOND
Page 3 of 5
CITY OF FORT WORTH Kedplasma Plasmapheresis Center
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS[Insert Project Number]
Revised January 31, 2012
1
2
3
00 62 19 - 4
MAINTENANCE BOND
Page 4 of 5
CITY OF FORT WORTH Kedplasma Plasmapheresis Center
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS[Insert Project Number]
Revised January 31, 2012
IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this 1
instrument by duly authorized agents and officers on this the day of 2
, 20 __. 3
4
PRINCIPAL:5
6
____________________________________7
8
____________________________________9
10
11
BY:________________________________12
Signature13
ATTEST: 14
15
______________________________ 16
____________________________________17
(Principal) Secretary Name and Title 18
19
20
Address:____________________________21
22
____________________________23
24
____________________________25
_____________________________ 26
Witness as to Principal 27
28
29
Calvo Construction, Inc.
00 62 19 - 5
MAINTENANCE BOND
Page 5 of 5
CITY OF FORT WORTH Kedplasma Plasmapheresis Center
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS[Insert Project Number]
Revised January 31, 2012
SURETY: 1
2
____________________________________ 3
4
____________________________________ 5
6
7
BY:________________________________ 8
Signature 9
10
11
____________________________________ 12
ATTEST: Name and Title13
14
_____________________________ Address: ____________________________15
(Surety) Secretary ____________________________ 16
____________________________ 17
_____________________________ 18
Witness as to Surety Telephone Number:___________________ 19
20
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract21
from the by-laws showing that this person has authority to sign such obligation. If 22
Suretys physical address is different from its mailing address, both must be provided. 23
24
The date of the bond shall not be prior to the date the Contract is awarded. 25
26
___________________
Si t
___________
(S ) S
_______________
Employers Mutual Casualty Company
Sam Sealer, Attorney in Fact
4020 N MacArthur Blvd, ste 122
Irving, TX 75038
972-979-3138
Sam Sealer
Surety Bond
Number
S047325
Principal:
Calvo Construction, Inc.
22nd September 2022
22nd September 2022
22nd September 2022
S047325-NA I0123 902 AC 009129