NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Kedplasma Plasmapheresis Center
City Project No.: 104997
Improvement Type(s): □ Paving IZI Drainage □Street Lights
Original Contract Price: $2,818.00
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $2,818.00
� 11/05/2025
Contractor Date
President
Title
Calvo Construction, Inc.
Company Name
Car™0:18:40CST) 11/05/2025
Project Inspector Date
1]_�.<1� Pc 11/05/2025
Project Manager Date
11/05/2025
CFA Manager Date �-� 11/05/2025 Lauren Prieur !Nov 51 202513:32:55 CST!
TPW Director Date
� 11/05/2025
Asst. City Manager Date
□Traffic Signals
Page 1 of 2
Notice of Project Completion
Project Name: Kedplasma Plasmapheresis Center
City Project No.: 104997
City's Attachments
Final Pay Estimate 0
Change Order(s): ❑ Yes 0 N/A
Contractor's Attachments
Affidavit of Bills Paid �
Consent of Surety �
Statement of Contract Time
Contract Time: 63
Days Charged: 48
Work Start Date: 4/23/2025 Work Complete Date: 8/18/2025
Completed number of Soil Lab Test: 38
Completed number of Water Test: 7
Page 2 of 2
CITY OF FORT WORTH
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type DRAINAGE
DOE Number 4997
Estimate Number 1 Payment Number 1 For Period Ending 8/18/2025
FINAL PAYMENT REQUEST
City Secretary Contract Number
48
WD
Contract Date
CALVO CONSTRUCTION INC
NA
621 N. MAIN STREET, SUITE 415
GRAPEVINE TX 76051
G.DEYON C.GARCIA
63WDContract Time
Days Charged to Date
CompleteContract is 100.00
Contractor
,
/Inspectors
Project Manager
City Project Numbers 104997
Wednesday, September 24, 2025 Page 1 of 4
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type DRAINAGE
DOE Number 4997
Estimate Number 1
Payment Number 1
For Period Ending 8/18/2025
Project Funding
City Project Numbers 104997
UNIT III: DRAINAGE IMPROVEMENTS
Item
No.Description of Items Estimated
Quanity Unit Unit Cost Estimated
Total
Completed
Quanity
Completed
Total
1 CONNECTION TO PUBLIC MANHOLE 1 EA $2,818.00 $2,818.00 1 $2,818.00
$2,818.00 $2,818.00Sub-Total of Previous Unit
Wednesday, September 24, 2025 Page 2 of 4
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type DRAINAGE
DOE Number 4997
Estimate Number 1
Payment Number 1
For Period Ending 8/18/2025
Project Funding
City Project Numbers 104997
Contract Information Summary
Change Orders
$2,818.00Original Contract Amount
$2,818.00Total Contract Price
$2,818.00
Less
Total Cost of Work Completed
% Retained $0.00
Net Earned $2,818.00
Plus Material on Hand Less 15%$0.00
Balance Due This Payment $2,818.00
Less Liquidated Damages
Days @ / Day
$0.00
Less Penalty
LessPavement Deficiency $0.00
$0.00
$0.00Less Previous Payment
Earned This Period
Retainage This Period
$2,818.00
$0.00
Wednesday, September 24, 2025 Page 3 of 4
Contract Name KEDPLASMA PLASMAPHERESIS CENTER
Contract Limits
Project Type DRAINAGE
DOE Number 4997
Estimate Number 1
Payment Number 1
For Period Ending 8/18/2025
Project Funding
City Project Numbers 104997
Line Fund Account Center
Amount
Funded Gross Retainage Net
CITY OF FORT WORTH
SUMMARY OF CHARGES
$2,818.00
Less
Total Cost of Work Completed
% Retained $0.00
Net Earned $2,818.00
Plus Material on Hand Less 15%$0.00
Balance Due This Payment $2,818.00
Less Liquidated Damages
0 Days @ $0.00 / Day $0.00
Less Penalty
LessPavement Deficiency $0.00
$0.00
$0.00Less Previous Payment
Earned This Period
Retainage This Period
$2,818.00
$0.00
City Secretary Contract Number
48
WD
Contract Date
CALVO CONSTRUCTION INC
NA
621 N. MAIN STREET, SUITE 415
GRAPEVINE TX 76051
G.DEYON C.GARCIA
63
WD
Contract Time
Days Charged to Date
CompleteContract is 100.000000
Contractor
,
/Inspectors
Project Manager
Wednesday, September 24, 2025 Page 4 of 4
Rev. 9/15/16
TRANSPORTATION AND PUBLIC WORKS
August 27, 2025
Calvo Construction, Inc.
621 Main St. Ste 200
Grapevine, Texas 76051
RE: Acceptance Letter
Project Name: KEDPLASMA
Project Type: Water, Sewer, Paving, Drainage, Street lights
City Project No.: 104997
To Whom It May Concern:
On August 26, 2025 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on August 26, 2025,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-7830.
Sincerely,
Ahmed Izeldeen, Project Manager
Cc: Carlos Garcia, Inspector
Gary Deyon, Inspection Supervisor
Lorrie Pitts , Senior Inspector
Andrew Goodman, Program Manager
Ntirr, Peters & Associates, Consultant
Calvo Construction Inc., Contractor
Four Roses, Developer
File
E-Mail:
Douglas W. Wiersig, P.E., PhD., Director, TPW
Richard Martinez, Assistant Director, TPW
Marisa Conlin, Traffic Engineering
Allen Hall, Superintendent, TPW
John Robert Carman, P.E., Director, Water
Chris Harder, P.E., Assistant Director, Water
Wendy Chi-Babulal, P.E., Water
Tony Sholola, P.E., Water
Richard Zavala, Director, PARD
David Creek, Assistant Director, PARD
www.
AFFIDAVIT OF ALL BILLS PAID
STATE OF TEXAS §
§
COUNTY OF ______________§
BEFORE ME, the undersigned authority, on this day personally appeared
_______________________________ [name], _________________________ [title] of
_______________________________ [Subcontractor/Supplier]
By ___________________________________ [Signature]
_________________________________ [Title]
______________________________________ [name], _____________________________ [title] of
________________________________ [subcontractor/supplier], on behalf of said company.
(NOTARY SEAL)
_____________________________________
Notary Signature
Notary Public in and for the State of _______
___________________________________ [subcontractor/supplier], and, upon oath, after first being duly
Date __________________
This instrument was acknowledged before me ________, by
City of Fort Worth / Stough Development
Corporation
100 Fort Worth Trail
Fort Worth, TX 76102
November 4, 2025.
Employers Mutual Casualty Company
Sam Sealer, attorney in fact
Kedplasma Plasmapheresis Center
Kedplasma Plasmapheresis Center
September 18, 2024
City of Fort Worth / Stough Development
Corporation
100 Fort Worth Trail
Fort Worth, TX 76102
Employers Mutual Casualty Company
717 Mulberry Street
Des Moines, IA 50309
Calvo Construction Inc
621 N Main St, Ste 200
Grapevine, TX 76051
Bond No. S047325
Sam Sealer
Surety Bond
Number
S047325
Principal:
Calvo Construction, Inc.
22nd September 2022
22nd September 2022
22nd September 2022
S047325-NA I0123 902 AC 009129
4th November 2025