AMENDMENT No.5
TO CITY SECRETARY CONTRACT No. 60591
WIIEIU:AS, the City of Fort Worth (CITY) and K.imley-Born and Aaaociatea, Inc:.,
(ENGINEER) made and entered into City Secretary Contract No. 60591, (the CONTRACT)
which was authorized by M&C 23-0908 on the 31" day of October, 2023 in the amount
of$ 974,121.00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No. 1 in the
amount of $ 69,185.00 which was adminiatrati ve/y authorized on February 22nd,
2024, Amendment No. 2 in the amount of $ 83, 003. 00 which was authorized by M&C
25-0011 on January 14th, 2025, and Amendment No. 3 in the amount of $92,145.00
administratively authorized on July 25th, 2025, and Amendment No. 4 in the amount
of $258,440.00 authorized by M&C 25-0904 on September 16th, 2025; and
WlllmEAS, the CONTRACT involves engineering services for the following
project:
Water and Sanitary Sewer Rep.lacement on Caq:, Bowie Bou.levard, CPN 105062;
and
WIIEIU:AS, it has become necessary to execute Amendment No. 5 to the CONTRACT
to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
CONTRACT:
1.
Article I of the CONTRAC'l' is amended to include the additional engineering
services specified in proposal attached hereto and incoq,orated herein. The cost
to City for the additional design services to be perfoniec:l by Engineer totals
$31,290.00. (Water: $3,400.00; TPW: $27,890.00(l'ID 30100-0201000-4611010-tJNSPEC))
2.
Article II of the CONTRACT is amended to provide for an increase in the fee
to be paid to Engineer for all work and services perfoniec:l under the Contract, as
amended, so that the total fee paid by the City for all work and services shall
be an amount of $1,508,184.00.
3.
All other provisions of the Contract, which are not expressly amended herein,
shall remain in full force and effect.
City of Fort Worth, Texas
Prof Services Agreement Amendment Template Revision Date: June 13, 2025 Page 1 of 2
W&SS Repl on Camp bowie Boulevard
105062
EXECUTED and EFFECTIVE as of the date subscribed by the City's designated
Assistant City Manager.
APPROVED:
City of Fort Worth
Jesica McEachern
Assistant City Manager
11/11/2025 DATE:
ATTEST:
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
�
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
Kiml.ey-Horn and Associates, Inc. A�l1�
Anthony Samarripas, P.E.
Vice President
DATE: 10-16-2025
By signing, I acknowledge that I am the person responsible for the monitoring
and administration of this contract, including ensuring all performance and
reporting requirements.
10/16/2025
Parvathi Sreekumaran Unnithan, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Oct 29, 2025 14:27:31 CDT)
Douglas W. Black
Sr. Assistant City Attorney
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 2 of 2
M&C No.#:
M&C Date:
N/A ______ _
N/A _____ _
W&SS Repl on Camp bowie Boulevard
105062
Kimley>>> Horn
October 15, 2025
Ms. Parvathi Sreekumaran Unnithan, P.E.
Project Manager
City of Fort Worth Water Department
100 Fort Worth Trail
Fort Worth, TX 76102
Re: WATER AND SANITARY SEWER REPLACEMENTS ON CAMP BOWIE BOULEVARD
Amendment No. 5
KHA No. 061018457
City Project No. 105062 / City Secretary No. 60591
Dear Parvathi:
The City of Fort Worth (CITY) has requested that Kimley-Horn perform additional services under
Amendment Number 5 for the WATER AND SANITARY SEWER REPLACEMENTS ON CAMP
BOWIE BOULEVARD project. This amendment includes additional design associated with
reconstruction of the medians between the bike lanes and West 7th Street due to increasing concerns
of drivers hitting the medians and curbs. These improvements are further described as follows:
TASK 4.0 - FI NAL DESIGN : (WATER $3,400, SEWER $0, TPW $27,890)
ENGINEER will complete Final Design in accordance with the Original Contract for the following:
•The CITY requested the addition of revised median plans associated with the reconstruction
of the medians between West 7th Street and the existing bike lanes. This will include an
Autoturn evaluation of 18 medians and updated paving and surface repair/pavement marking
plans. This assumes revision of one (1) sheet of the existing surface repair and pavement
marking sheet, one (1) additional sheet for surface repair and pavement markings, four (4)
sheets for the paving plans, and detail sheets. (TPW: $27,890)
•The Original Contract did not include full specifications for the Van Zandt Water Line
replacement project and are being included as part of this Addendum. (Water: $3,400)
We recommend that the CITY increase the budget by $31,290 for these additional services. The
following tables summarize our recommended budget revisions, water and sanitary sewer design
fees, and revised contract amount:
Description Water Sewer TPW Total
Task 4-Final Design $3,400 $0 $27,890 $31,290
Total $3,400 $0 $27,890 $31,290
kimley-horn.com 801 Cherry Street, Unit 11, Suite 1300, Ft. Worth, TX 76102 817-335-6511
Kimley>>> Horn Page2
The following breakdown for water and sewer services is recommended:
WATER TPW
Water Fee Sewer Fee Survey TPWFee Total Fee
Original Contract $648,216 $172,310 $153,595 $0 $974,121
Amendment No. 1 $69,185 $0 $0 $0 $69,185
Amendment No. 2 $69,128 $0 $13,875 $0 $83,003
Amendment No. 3 $79,749 $12,396 $0 $0 $92,145
Amendment No. 4 $203,346 $55,094 $0 $0 $258,440
Amendment No. 5 $3,400 $0 $0 $27,890 $31,290
Total $1,073,024 $239,800 $167,470 $27,890 $1,508,184
The following table summarizes our recommended budget revisions and shows the revised contract
amount:
Task Original Amend Amend Amend Amend Amend Revised
Number Contract No.1 No. 2 No. 3 No.4 No. 5 Contract
Task 1 $42,795 $0 $1,745 $0 $16,260 $0 $60,800
Task2 $100,346 $0 $0 $0 $3,090 $0 $103,436
Task 3 $277,740 $0 $21,590 $0 $22,505 $0 $321,835
$3,400
(Water)
Task4 $232,080 $8,490 $23,385 $0 $106,410 $401,655
$27,890
(TPW)
Task 5 $45,475 $21,330 $9,745 $18,925 $0 $0 $95,475
Task6 $0 $39,365 $0 $73,220 $108,525 $0 $221,110
Task? $7,650 $0 $0 $0 $1,650 $0 $9,300
Task 8 $238,035 $0 $21,538 $0 $0 $0 $259,573
Task9 $0 $0 $0 $0 $0 $0 $0
Task 10 $30,000 $0 $5,000 $0 $0 $0 $35,000
Total $974,121 $69,185 $83,003 $92,145 $258,440 $31,290 $1,508,184 Project
kimley-horn.com 801 Cherry Street, Unit 11, Suite 1300, Ft. Worth, TX 76102 817-335-6511
Kimley>>> Horn Page3
We appreciate the opportunity to be of continued service to the CITY. Please contact us if we need
to provide any further information.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, INC.
Anthony Samarripas, P.E.
Vice President
Attachments:
Level of Effort Summary
K:IFTW_Utilities\061018457 -Camp Bowie W-SS Replacements - Hulen to Montgomery\PPP\POST_NTP\Final Contract\Amend 05\2025-10-13_Amend5_Camp
Bowie.doc
kimley-horn.com 801 Cherry Street, Unit 11, Suite 1300, Ft. Worth, TX 76102 817-335-6511
Task No. Task Description .....
4.0a mal oes1gn {Median Modif1cat1ons) • 1 rn
l"\\.ll.litiOOSI ;;urvey IOfUU Lt)
,-..utotum c.va.uca 10n
.::;unace t<epair & t"avemem Mancmg --RIM!le1aheet
-Creala19heet
avmg t"ian - 4 sneets (A-..ma ,e median modric.tlon•J
l-'tn81 �lltftl'l.3
m.:u "'IU8111u1es
4.0b ma, ues1gn • water
lVV�ner)
Full Specifications -Van Zandt Water Line
City of Fort Worth, Texas
Attachment B -Level of Effort Supplement
Typical Water and Sewer Replacement
FWWTR Official Release Date: 8.09.2012
·-�·
Senior
Professional
$370
3
1
2
.
EXHIBIT B-2
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
W 7th St (Currie St to Harold St)
City Project No. 105062-Van Zandt Medians
Labor (hours)
Project EIT Administrative Total Labor
Manager/Engineer Cost
$295 $245 $130
13 62 $0 $20,135
1 4 $1,275
2 10 $3,040
2 8 $2,920
4 32 $9,760
1 2 $785
3 6 $2,355 • 8 2 $3,400
4 8 2 $3,400
lJ .. . .......
Expense
Subconsultant Total Expense Task Sub Total Travel Reproduction Cost
$7,050 $0 $0 $7,050 $27,185
$7,050 $7,050 $8,325
$0 $3,040
$0 $2,920
$0 $9,760
$0 $785
$0 $2,355
$3,400
$0 $3,400 . ,, ... •• •• . ,, ... ... , ...
t"roJect �ummary
Total Hours 78
Total Labor $23,535
Total Expense $7,050
10% Sub Markup $705
Water Tota $3,400.00
1r-vvTota �r,o�u.OC
Total Project Cost $31,290.0ll
FORT WORTH@
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Kimley-Horn and Associates, Inc.
Subject of the Agreement: Water and Sanitary Sewer Replacement on Camp Bowie Boulevard, CPN 105062 M&C Approved by the Council?* Yes D No Ill
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes Ill No D 60591-A5 -----------If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes Ill No □
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes D No Ill If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 9/30/2025 Expiration Date: NIA --------------------If different from the approval date. If applicable.
Is a 1295 Form required? * Yes D No Ill
* If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 105062 -----------
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes Ill No D
Contracts need to be routed for CSO processing in the following order:
1.Katherine Cenicola (Approver)
2.Jannette S. Goodall (Signer)
3.Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.