HomeMy WebLinkAbout057860-A2 - Construction-Related - Contract - LJA Engineering, Inc.CSC No. 57860-A2
AMENDMENT No . 2
TO CITY SECRETARY CONTRACT No. 57860
WHEREAS, the City of Fort Worth (CITY) and LJA Engineering, Inc.,
(ENGINEER) made and entered into City Secretary Contract No. 57860, (the
CONTRACT) which was administratively authorized on the 20th day of July,
2022 in the amount of $ 96,395.00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment Number
1 in the amount of $34,724.00 which was authorized by M&C 23-1056
on December 12th, 2023; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Basswood Boulevard and Old Santa Fe Trail Intersection
Improvements, CPA[ 103998; and
WHEREAS, it has become necessary to execute Amendment No. 2 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $9,150.00. (See Attached Funding Breakdown Sheet, Page
-4-)
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $140,269.00.
OFFICIAL RECORD
City of Fort Worth, Texas CITY SECRETARY Sass wood Blvd & Old Santa Fe Trail Intersection Improvements
Prof Services Agreement Amendment Template FT. WORTH, TX CPN 103998
Revision Date: June 13, 2025
Page 1 of 4
1911
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date subscribed by the City"s
designated Assistant City Manager.
APPROVED:
City of Fort Worth
Jesica McEachern
Assistant City Manager
DATE: 12/05/2025
ATTEST:
Pva
Jannette Goodall ova
City Secretary
aat
APPROVAL RECOMMENDED:
...i,.:.
Lauren Prieur (Nov 26, 2025 07:22:23 CST)
ENGINEER
LJA Engineering, Inc.
Anthony Kimmey, PE
Sr. Vice President
DATE: 11/21/2025
Lauren Prieur
Director, Transportation and Public Works Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
I-ascta Ka6m
Fanta Kaba, PE
Sr. Professional Engineer
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 2 of 4
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Basswood Blvd & Old Santa Fe Trail Intersection Improvements
CPN 103998
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Nov 26, 2025 16:16:56 CST)
Douglas W. Black
Sr. Assistant City Attorney
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 3 of 4
M&C No.#: N/A
M&C Date: N/A
Basswood Blvd & Old Santa Fe Trail Intersection Improvements
CPN 103998
FUNDING BREAKDOWN SHEET
City Secretary No. 57860
Amendment No. 2
Fund
Dept ID
Account
Project
ID
CF1-
Activity
CF2 - Bond
Reference
Amount
52002
0200431
5330500
103998
007130
9999
$9,150.00
Total:
$9,150.00
City of Fort Worth, Texas Basswood Blvd & Old Santa Be Trail Intersection Improvements
Prof Services Agreement Amendment Template CPN 103998
Revision Date: June 13, 2025
Page 4 of 4
RT WORTH,,,
ATTACHMENT "A"
Scope for Engineering Design Related Services for Supplemental Services to Include
Construction Phase Services and Protect Closeout
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
The objective of the Basswood Blvd and Old Santa Fe Trail Intersection project is to improve
capacity of intersection by Signalization of the intersection. In addition to signalization,
drainage design to reducing ponding of water in roadway just east of the intersection.
WORK TO BE PERFORMED
Task 1. Design Management (Drainage)
Task 2f GRGepti al De6igR (300 )
Task 4 DrelimiRaFy Desig!R /GCVO%\
T-;;Tc4�- rPaIrvc6ig•iT ii%anr'VV%1 /irainnre7
T''ipd PT,.Cp�Qr`vr— HdT—iYes (D rvra i aage )
Task 6. Construction Phase Services (Drainage)
Task 10. Quality Control/ Quality Assurance
City of Fort Worth, Texas Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
Attachment A 103998
PMO Release Date: 07.23.2012
Page 1 of 26
RT WORTH,,,
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources. ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the work.
1.1. Managing the Team
• Lead, manage and direct design team activities
• Ensure Quality Control / Quality Assurance (QC/QA) is practiced in performance
of the work. Refer to Task 10 for further details.
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting:
• ATP—Ad a PF8 G186igRFG8Gt kiGkA-ff/rhar4e-.r 11:188tiRg With CITY staff to rnrifirm apol
nlarify s pe ni-1 sta Rd f ITV Gbje es I d f I
crurn��C-6pc-'cr' ncrer cC�lvcoand reNvaf�ecvnvrrrC-arana�urrct6=a
d8GigRG that meet GITV req iireme#
• 4tterid gale () field meetings With CITY repFeceFltatiyec iFlGludirig Trnffin
Manag8Ment o Prier to the 2004
and 9-004
si 1hmittals
• Conduct and document monthly project update meetings with CITY Project
Manager
• (;enr•I6 int review meetings With the GITV at the eRd of eanh design Phase
• GGRd int and dOG Ument h�nieel lei design team meetings
• Conduct QC/QA reviews and document those activities. Refer to Task 10 for
further details
• Prepare invoices, in accordance with Attachment B to this Standard Agreement
and submit monthly in the format requested by the CITY.
• Prepare and submit monthly Project Status Reports in the format provided by the
respective Transportation and Public Works Department.
• Prepare and submit baseline Dreient Cashed ile iRitialhi and Project Schedule
updates with a schedule narrative monthly, as required in Attachment D to this
Standard Agreement in compliance with the City's Specification 00 31 15 entitled
Engineer Project Schedule. This PROJECT requires a Tier 3 schedule as
defined in the City's Specification 00 31 15 entitled Engineer Project Schedule.
Register, P�} rt (gem t'GRS Plan CITY to Fnedify and
,T i� eA e„TEa�, �,�
fib
• Complete Monthly M/WBE Report Form and Final Summary Payment Report
Form at the end of the project
City of Fort Worth, Texas Page 2 of 26
Attachment A Traffic Signal Design - Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 2 of 26
RT WO
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare
the design
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements
are appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to
meet their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub -consultants shall carry readily visible
information identifying the name of the company and the company
representative.
ASSUMPTIONS
• Two (2) field review meetings
• Project construction phase is anticipated to take six (6) months.
• Three (3) monthly updates of Project Status Reports, MWBE forms, TPBE, Risk
Register, and project Schedule.
DELIVERABLES
A. Meeting summaries with action items
B. QC/QA documentation
C. Baseline design schedule
D. Preliminary Project Risk Register, preliminary Stakeholder Register, and
preliminary Project Communications Plan
E. Monthly Schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly Project Status Reports
G. Monthly TPBE spreadsheet updates
H. Monthly Project Risk Register updates
Plan Submittal Checklists (See Task 10)
City of Fort Worth, Texas Page 3 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 3 of 26
RT WO
J. Monthly invoices
K. Monthly M/WBE Report Form and Final Summary Payment Report Form
City of Fort Worth, Texas Page 4 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 4 of 26
RT WORTH,,,
_min the ease E)f a private Utility C;eRfli^+�ENGINEER .,ill n vide a PDF= set e
nlanc with the Utility nenflintc highlighted anal a Utility f nnflin4c Table ref these
nfli,,+,, e h n pled in a Utility Gl panne I e++ fep GGGFdinatien T�
�i-rrrrGts��r.7e--IrrGYI-iaCq �rarrc��crt�Tvr Ftic
City of Fort worth, Texas Page 5 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 5 of 26
RT WORTH,,,
PDF= filet nreated from decioo CAD rpawiooc will he i plea ded to the decipated
PFGje6t fe'der in the Gity'S dGG McRt m nt system (BIM 360) ENGINEER
shall net p ed With DreliMiRaFy Design aGtiVitieS Witho It WFitteR oppF
,I h
the f ITV of the GGRGept al Decig!R PaGka e
City of Fort Worth, Texas Page 6 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 6 of 26
RT WO
City of Fort Worth, Texas Page 7 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 7 of 26
RT WORTH,,,
Jv^mrarrrc2iAiuys, sidewalks, -aRa- pavement -details.
City of Fort Worth, Texas Page 8 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 8 of 26
RT WORTH,,,
City of Fort Worth, Texas Page 9 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 9 of 26
RT WORTH,,,
_ MU
City of Fort worth, Texas Page 10 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 10 of 26
RT WORTH,,,
TASK 4. FINAL DESIGN
.0
CONSTRUCTION DOCUMENTS
00
...
the appreved PFejeGt
-.
per
-
Utility GGRfIiGts Table
ef these
GE)RfliGtG to be iRGIuded OR a Utility GleapaRGe Letter fap
pIaR F8VieW MeetiRg with the CITY, the ENGINEER shall
..• GenStFUGtien
...
sheet shall be stamped,
dated,
and GigRed by the FENIG;INIFEFER regilstered on State A-f
. „
, 14 A4
0
€ Ghde6igRt eeoGT f�Ge package shall i,rRGIude a quantity fake off fable
Q0-04aPrd 1000% deSig RpaGkageSTTrhrTs; p—sti. .-ate sh-all ase st-apdard- CITY or TvnnT hid
items as applirahle
Three (3) sets A-f I I ")d 7" size drawiRgs and GRe (I) Set Gf Gp8GifiGat0A-IPc-; �.AAII he delivered
ry
far the 900% nesinr, r skage
A, DnC and DVVF= file for the a0%yT will be -created fro gs GAD drawirirr and
�T
TeR (IQ) sets of 11417" size drawiRgs aREI tWe (2) set of speGif'GatiORS will be delivered
fer the 1 nn0i nesioo paokaoe
A DIIC and n\A/C file fer the 1001% nesinr, will be fFem deSigR CAD drawings and
A. 90074 oor,stri,ofior, olaRs and soeoifioatie% iRGIu JiRg of /nA dGGUmeRtatien
n
9. ciTrcy GattGi-r-crvGUrrreR tCtlivPr.
o.PRal iSVVIM plan ( CiRal GheGk 106t)
D. l nnoi nonotr, intioR pIar,s and spedfinatienc iRGIU JiRg QGQA dE)GUmentatiGR
n, iaRtitiec , o the f ITV's or TVnnT's sfaR dapd hid items and formatas ar,olioahle
P. ari�nal '1 1'41 7" size we,F my!ar fer the mats ,res of authorized CITY
City of Fort Worth, Texas Page 11 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 11 of 26
RT WORTH,,,
Tabulate and ew II hid fer the tri t the GITY.-
0 - re`vTcw-^an-prc��-Feeelir �vnr,�^cvrer�.nrcrc�+errpF^vjec�,-&s�Jrcrrc-vr-r
n eval6latiRg bids and reGE)PRmeRd aWaFd of fhe GerFaa Gt. A GGPY of the Rid
Tahu latien and the GF=V / Data Spreadsheet are to he u plea.de.d irate the r eGt'S
Ri.d Results felder en the Gity's .JeeUmeRt m Rt S Stem (RIBA 360)
I RGeppGrate all arddeRda irate the neritrant rler•i 1meRtc and iccue ne Rferrrmed cetc
City of Fort worth, Texas Page 12 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 12 of 26
RT WO
City of Fort Worth, Texas Page 13 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 13 of 26
RT WO
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1. Construction Support
• The ENGINEER shall prepare one (1) task order package for the CITY's Unit
Price Contractor.
• The ENGINEER shall attend the pre -construction conference.
• After the pre -construction conference, the ENGINEER shall provide project
exhibits and attend one (1) public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation letters
to the affected customers.
• The ENGINEER shall attend bi-weekly construction progress meetings during the
duration of construction. The ENGINEER will prepare meeting notes with action
items and distribute there to the project team.
• The ENGINEER will prepare a Construction Communication Plan detailing the
procedure for communicating between the Project Delivery Team members and
the Contractors.
• The ENGINEER will meet with concerned citizens as needed.
• The ENGINEER shall review shop drawings, samples and other submittals
submitted by the contractor for general conformance with the design concepts and
general compliance with the requirements of the contract for construction. Such
review shall not relieve the Contractor from its responsibility for performance in
accordance with the contract for construction, nor is such review a guarantee that
the work covered by the shop drawings, samples and submittals is free of errors,
inconsistencies or omissions. The ENGINEER shall log and track all shop
drawings, samples and other submittals in Buzzsaw.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents, respond to Request for Information (RIF)
from the contractor, review change orders, and make recommendations as to the
acceptability of the work.
• The ENGIENER will meet with the Project Delivery Team and Contractor on -site
to review any field changes.
• The ENGINEER will coordinate with the TPW department as necessary
• The Engineer will update and submit monthly the Project Status Report, Risk
Register, TPBE and Project Schedule.
• The ENGINEER shall attend the "Final" project walk through and assist with
preparation of final punch list.
6.2 Record Drawings
• The ENGINEER shall prepare record drawings from information provided by the
CITY depicting any changes made to the Final Drawings during construction.
Information provided by the CITY may include, but is not limited to the following:
City of Fort Worth, Texas Page 14 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 14 of 26
RT WO
o As -Built Survey
o Red -Line Markups from the Contractor
o Red -Line Markups from City Inspector
o Copies of Approved Change Orders
o Approved Substitutions
The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
as constructed. The stamp shall be signed and dated by the ENGINEER and
shall be placed on each plan sheet, whether there are any revisions on the sheet
or not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
These Record Drawings were prepared using information
provided by others and represent the as constructed
conditions to the extent that documented changes were
provided for recording. The ENGINEER assumes no liability
for undocumented changes and certifies only that the
documented changes are accurately depicted on these
drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, in Adobe Acrobat PDF format (version 6.0 or
higher) and in DWF format. The ENGINEER may keep copies of the
information provided by the CITY for their files, but all original red -lined drawings
shall be returned to the CITY with the digital files.
• There shall be one (1) PDF file and one (1) DWF file for the TPW plan set and a
separate PDF and DWF file for the Water plan set, if required. Each PDF and
DWF file shall contain all associated sheets of the particular plan set. Singular
PDF and DWF files for each sheet of a plan set will not be accepted. PDF
and DWF files shall conform to naming conventions as follows:
I. TPW file name example — "W-1956_org47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file is
of an original plan set, "47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36" shall be the total number of
sheets in this file.
Example: X-12755_orgl8.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawing folder
in the City's document management system (BIM 360).
City of Fort Worth, Texas Page 15 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 15 of 26
RT WO
For information on the proper manner to submit files and to obtain a file number for
the project, the ENGINEER should coordinate with the City project manager. File
numbers will not be issued to a project unless the appropriate project numbers and
fund codes have been assigned and are in the Department of Transportation and
Public Works database.
ASSUMPTIONS
• i Re (1) D6 ihlin Meeti.., is Heel m
• Three (3) site visits are assumed
• Two (2) s uhmitt;;l rwii ceic nro nc
• Two (2) RFI's are assumed.
• QRe (I ) GhaRge QFder ie �cci ime
DELIVERABLES
C. Response to Contractor's Request for Information
D. Review of Change Orders
E. Review of shop drawings
F. Final Punch List items
G. Record Drawings in digital format
City of Fort Worth, Texas Page 16 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 16 of 26
RT WORTH,,,
City of Fort worth, Texas Page 17 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 17 of 26
RT WORTH,,,
PpGymde S suFfaa% Utili�E TeeF g (SIDE) to Quality Level 9C ig and /1 as
deSGFibed belew. The SUE shall he peFfer Ted in aGGerdanGe with GI/ACGC 38 02M
City of Fort worth, Texas Page 18 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 18 of 26
RT WORTH,,,
Dr,,v 0de Quality Level y-G to identify v eFhead utilities n the pFejeet and r Vide
the overhead Utility iRfE)FFFlatieR eR tho SUE pIaR sheets
City of Fort worth, Texas Page 19 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 19 of 26
RT WORTH,,,
City of Fort worth, Texas Page 20 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 20 of 26
RT WORTH,,,
All Gents a ated with TD R pIaR FeVieW Rd i eGtieRs a, a to he paid by the
ENGINEER d lFiR 9 the nei use of the preient
City of Fort worth, Texas Page 21 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 21 of 26
RT WORTH,,,
City of Fort worth, Texas Page 22 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 22 of 26
RT WO
City of Fort Worth, Texas Page 23 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 23 of 26
RT WO
TASK 10. QUALITY CONTROL / QUALITY ASSURANCE
ENGINEER to provide to the City a Quality Control/ Quality Assurance Plan (QC/QA Plan)
outlining the ENGINEER's method of ensuring the highest levels of design and accuracy are
incorporated into the calculations, plans, specifications, and estimates.
ENGINEER is responsible for and shall coordinate all subconsultant activity to include
quality and consistency of plans.
If, at any time, during the course of reviewing a submittal of any item it becomes apparent to
the CITY that the submittal contains errors, omissions, and inconsistencies, the CITY may
cease its review and return the submittal to the ENGINEER immediately for appropriate
action. A submittal returned to the ENGINEER for this reason may be rejected by the CITY
Project Manager.
10.1. QC/QA of Survey and SUE Data
• The ENGINEER's Surveyor shall perform Quality Control/ Quality Assurance on
all procedures, field surveys, data, and products prior to delivery to the CITY. The
CITY may also require the ENGINEER's Surveyor to perform a Quality
Assurance review of the survey and/or subsurface utility engineering (SUE) work
performed by other surveyors and SUE providers.
• ENGINEER's Surveyor shall certify in writing via a letter that the survey
information provided has undergone a Quality Control/ Quality Assurance
process.
• ENGINEER's Subsurface Utility Engineering provider shall certify in writing via a
letter that the SUE information provided has undergone a Quality Control/ Quality
Assurance process.
10.2. QC/QA of Design Documentation
• ENGINEER shall perform a QC/QA review of all documents being submitted for
review at all stages of the design including the 30%, 60%, and 90% and Final
Document design review submittals. QA should be performed by an individual
within the firm who is not on the design team.
ENGINEER is to acknowledge that each item on the Detailed Checklist has been
included by checking "done" on the checklist. If a particular checklist item is not
applicable, this should be indicated by checking "N/A". If an entire checklist is
not applicable, this should be indicated by checking every item on the list as
"N/A" and still included with the submittal. The ENGINEER shall use the Detailed
Checklist provided by CITY.
• A Comment Resolution Log must be used to document conflicting comments
between reviewers and to highlight comments made by the CITY that the
ENGINEER is not incorporating into the design documents along with the
associated explanation. The ENGINEER shall use the Comment Resolution Log
provided by CITY.
• The documentation of a QC/QA review includes (1) a copy of the color -coded,
original marked -up document (or "check print") developed during the QA
checking process and/or review forms which sequentially list documents and
associated comments; and (2) a QC sign -off sheet with signatures of the
City of Fort Worth, Texas Page 24 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 24 of 26
RT WO
personnel involved in the checking process. Mark-ups may also be documented
using the Comment Resolution Log.
• Evidence of the QC/QA review will be required to accompany all submittals.
Documentation shall include, but is not limited to, the following items:
- PDF of the completed Detailed Checklists
- PDF of the QC/QA check print of the calculations, plans, specifications, and
estimates demonstrating that a review has been undertaken;
- PDF of previous review comments (if any) and the ENGINERR's responses
to those comments in the Comment Resolution Log.
• If any of the above information is missing, is incomplete or if any comments are
not adequately addressed; the CITY may contact the ENGINEER and request
the missing information. If the ENGINEER does not respond to the request
within 24 hours, the CITY shall reject the submittal. No additional time will be
granted for a returned submittal.
• If the ENGINEER has not adequately addressed the comments, the submittal
shall be rejected and returned to the ENGINEER immediately to address the
issues.
ASSUMPTIONS
• All submittals to the City will be Quality checked prior to submission.
• A PDF of the QC/QA documentation will be uploaded to the project folder in
Buzzsaw.
DELIVERABLES
A. QC/QA documentation
City of Fort Worth, Texas Page 25 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 25 of 26
RT WO
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon — be sure
to track changes. the CITY's written request. Any additional amounts paid to the ENGINEER
as a result of any material change to the Scope of the Project shall be agreed upon — be sure
to track changes. in writing by both parties before the services are performed. These
additional services include the following:
• Negotiation of easements or property acquisition.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre -qualification, bid protests, bid rejection and re-
bidding of the contract for construction.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of God.
• Services related to warranty claims, enforcement and inspection after final completion.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
City of Fort Worth, Texas Page 26 of 26
Attachment A Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
PMO Release Date: 02.06.2015 103998
Page 26 of 26
ATTACHMENT B
COMPENSATION
Design Services for
Traffic Signal Design - Basswood Blvd and Old Santa Fe Trail
City Project No. 103998
Time and Materials with Rate Schedule Project
Compensation
A. The ENGINEER shall be compensated for personnel time, non -labor expenses,
and subcontract expenses in performing services enumerated in Attachment A as
follows:
i. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate Labor
Category Rate for the ENGINEER's team member performing the work.
Labor Category Rate as presented in the rate schedule table below is the rate for
each labor category performing the work and includes all direct salaries, overhead,
and profit.
Labor Category
2025 Rate
($/hour)
2026 Rate
($/hour)
Project Manager
$235.00
$240.00
Sr. Engineer
$215.00
$220.00
Design Engineer
$180.00
$185.00
Engineer -in -Training
$115.00
$125.00
CADD Operator (CADD Technician)
$110.00
$115.00
Administrative
$100.00
$100.00
ii. Non -Labor Expenses. Non -labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost.
Direct Expenses (non -labor) include, but are not limited to, mileage, travel and
lodging expenses, mail, supplies, printing and reproduction services, other direct
expenses associated with delivery of the work; plus applicable sales, use, value
added, business transfer, gross receipts, or other similar taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall be
reimbursed at cost to ENGINEER plus a markup of ten percent (10%).
City of Fort Worth, Texas
Attachment B
Revised Date: 8/18/2025
Page 1 of 4
ATTACHMENT B
COMPENSATION
iv. Budgets. ENGINEER will make reasonable efforts to complete the work within
the budget and will keep the City informed of progress toward that end so that
the budget or work effort can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may be
adjusted, nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services, that the
PROJECT cost presented in Article 2 of this Agreement will be exceeded, whether
by change in scope of the project, increased costs or other conditions, the
ENGINEER shall immediately report such fact to the City and, if so instructed by the
City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior
to such increase will be allowable to the same extent as if such costs had been
incurred after the approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER in
performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1.
D. Payment of invoices will be subject to certification by the City that such work has
been performed.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
City of Fort Worth, Texas
Attachment B
Revised Date: 8/18/2025
Page 2 of 4
B-2
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm
Primary Responsibility
Fee Amount
%
Prime Consultant
LJA Engineering
Original Agreement
$50,720.00
Addendum No. 1
Supplemental Design
$24,724.00
Addendum No. 2
Additional Services
$9,150.00
Combined
$84,594.00
60.3
Proposed Sub -Consultants
Lamb -Star Engineering
Original Agreement
$22,050.00
Addendum No. 1
Supplemental SUE (LVL A)
$4,000.00
Addendum No. 2
$0.00
Combined
$26,050.00
18.6
GRAM NTX
Traffic Data
$525.00
Addendum No. 1
$0.00
Addendum No. 2
$0.00
Combined
$525.00
0.4
Virtonnel, LLC
TDLR Review/Inspections
$2,100.00
Addendum No. 1
$0.00
Addendum No. 2
$0.00
Combined
$2,100.00
1.5
TOTAL (ORIGINAL)
$96,395.00
TOTAL ADDENDUM NO. 1
$34,724.00
TOTAL ADDENDUM NO. 2
$9,150.00
TOTAL COMBINED
$140,269.00
100%
Project Number & Name
Total Fee
Sub Fee
Basswood Blvd and Old Santa Fe
Trail, Project No. 103998.
$96,395.00
$23,500
Addendum No. 1
$34,724.00
$4,000
Addendum No. 2
$9,150.00
-
Combined
$140,269.00
$27,500
City of Fort Worth, Texas
Attachment B
Revised Date: 8/18/2025
Page 3 of 4
B-3
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across desired work types and work phases.
City of Fort Worth, Texas
Attachment B
Revised Date: 8/18/2025
Page 4 of 4
B-4
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Additional Design Services for
Basswood at Santa Fe Traffic Signal Design
City Project No. 103998
Task No.
Task Description
Labor (hours)
Total Labor
Cost
Expense
Total Expense
Cost
Task Sub Total
Project
Director
Project
Manager
Project
Engineer
EIT
CADD
Administrative
Subconsultant
Travel
Reproduction
Kate
$290
$236
$185
$115
$120
$100
MWBE
Non-MWBE
1.0
Design Management (L)rainagej
0
8
0
0
0
4
$2,280
$0
$0
$0
$0
$0
$2,280
1.1
Management
4
2
$1,140
$0
$1,140
1.2
Communications and Reporting
4
2
$1,140
$0
$1,140
$0
$0
$0
2.0
Construction Phase Services
0
8
0
16
2
4
$4,360
$0
$0
$0
$0
$0
$4,360
2.1
Construction Support (Drainage)
4
8
2
4
$2,500
$0
$2,500
2,2Additional
site visits
2
4
$930
$0
$930
2.3
Coordination meetings with contractor
2
4
10.0
QC/QA
0
2
0
16
0
2
$2,510
$0
$0
$0
$0
$0
$2,510
10.1
21
16
2
$2,510
$0
$2,510
$0
$0
$0
10/27/2026
' Lissette Acevedo, PE, PTOE, PMP
Sr. Capital Projects Officer
Transportation and Public Works
Project Summary
Total Hours
12
Total Labor
$9,10
Total Expense
$0
MBE/SBE Subconsultant
$0
$
Non-MBE/SBE Subconsultant
$0
5% Sub Markup
$0
MBE/SBE Participation
0.0
Total Project Costi
$9,150
City of Fort Worth, Texas
Attachment C - Level of Effort Amendment 1
PMO Official Release Date: 8.09.2012
1 of 1
Attachement D
UPDATED PROJECT SCHEDULE
TASK Month
Aug Oct. Dec 24-Feb Apr Jun Aug Oct. Dec 25-Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 26-Jan Feb Mar
N.T.P*
Site investiagtion/Due Diligence IIIIIIIIIIIIII�
Topographic/Design Survey
SUE Level B
SUE Level A
Public Involvement
IIIIIIIIIIIII■
IIIIIIIIIIIII■
Traffic Signal Design
• • 11
• •
0 • •
• •
• • •
• •
• •
• •
• • •
• •
30 percent submittal
in field/30 percent review
Public Meeting
60 percent submittal
60 percent review
90 percent submittal
90 percent review
Supplemental Drainage Design
Public Meeting
Final Bid Documents
Drainage Construction
Construction Phase Services
Traffic Signal Design — Basswood Blvd and Old Santa Fe Trail
City Project No. 103998
FORT WORTH,,.,
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: Basswood Blvd & Old Santa Fe Trail Intersection Improvements -
Engineering Contract Amendment #2
M&C: 23-1056 CPN: 103998 CSO: 57860 DOC#: 1
Date:
To:
Name
Department
Initials
Date Out
1.
Sophia Flores
TPW - initial
11/25/25
2.
Fanta Kaba
TPW - signature
Fes"
11/24/25
3.
Anthony Kimmey
Consultant - signature
11/21/25
4.
Chad Allen
TPW - initial
11/25/25
5.
Lissette Acevedo
TPW -initial
11/25/25
6.
Patricia Wadsack
TPW - initial
�(.,�/
11/25/25
7.
Lauren Prieur
TPW - signature
a
11/26/25
8.
Doug Black
Legal - signature
11/26/25
9.
Jesica McEachern
CMO - signature
CM
12/05/25
10.
Jannette Goodall
CSO - signature
12/05/2025
11.
TPW Contracts
TPW
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and take
the next steps.
NEEDS TO BE NOTARIZED: DYES E]No
RUSH: ❑YES ❑No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ❑No
ROUTING TO CSO: ❑YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
❑ Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Updated 08.22.2022,
Return To: TPWContracts n,FortWorthTexas.gov at ext. 7233 or 8363, for pick up when mdhm
completed. Thank you!
Amendment Purpose Statement:
The purpose of this amendment is to authorize additional professional services for CPN 103998: Basswood
Boulevard & Old Santa Fe Trail. The original scope of work included installation of a new traffic signal,
ADA-compliant ramps, sidewalk improvements, pedestrian accessible push buttons, and storm drainage
improvements. While the traffic signal installation has been completed, the drainage improvements
remain outstanding beyond the original completion date. The revised drainage scope consists of
constructing a series of sidewalk flumes to convey runoff from Basswood Boulevard into an existing
drainage ditch.
To support project completion, the consultant provided services beyond the original scope, including
attending bi-weekly on -site meetings throughout construction, field meetings for the traffic signal
activation ceremony and coordination with City staff to reevaluate and redesign the storm drainage
improvements. This amendment will provide for continued professional support during construction of
the drainage improvements, including site visits for construction update meetings, participation in the
final inspection and walkthrough with City staff, and preparation of record drawings.
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: LJA Engineering, Inc.
Subject of the Agreement: Amendment No. 2 to CSC No. 57860, an Engineering Services Agreement
for Basswood Boulevard and Old Santa Fe Trail
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ 57860-A2
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
Expiration Date:
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No 8
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103998
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following _ order:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.