HomeMy WebLinkAbout054099-CO5 - Construction-Related - Contract - Crescent Contractors, Inc.FORT WORTH
Project Name:� VCWRF Grit Removal Facility
Project No.(s):� 560171070043011780
DOE No. � n/a
City Secretary Copy
54099-005
I City Sec No.: I 54099
� City Proj. No.: � 100075
Project Description;IThe project consist of a new Grii Facility with 8 stacked iray vorrtex grit removal units, siruciural modifications to existing Headwork Facility,
modificataions to Otlor Control Biofilter System, and ElectricallHVAC/PlumbinglYard Piping
Contractor:� Crescent Contractors, Inc � Change Order # � 5 � Date: � 12117/2025 �
City Project Mgr.� Farida Goderya � City Inspector: � K. Sidebottom (FNI) �
Phone Number:l 817-392-8214 � Phone Number:l 817-874-9330 �
Dept.
Original Contract Amount
Extras to Date
Cretlits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
�Amount of Proposed Change Order
Revisetl Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
Sewer
$25,797,000.00
$521,025.00
$26,318,025.00
-$142,100.00
$26,175,925,00
$332,463.00
$0.00
$26,318,025.00 �909
-$142,100.00 �g8
$26,175, 925.00 1, 507
$332,463.00
$0.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT � 2.02% �
MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $32,246,250.00
�
JUSTIFICATION (REASONS) FOR CHANGE ORDER �
Change Order No. 05 (C05 includes six CMRs with a total cost of $131,g00. In additio to the extra work and associated
costs of this change order, �he Contractor has requested an extension of the substantia� and final completion dates.
The cqntractual substantial completion, ds� te was Noyember 30, 2022. The Cit is willi to recogpize an early substantial
cop�pletion date �ased on when the �rit t cility was tirst started up on June 1� 2023 �1�5 days atter contractual
substantial comp etion). The contrac ual �inal completion date was January 28', 2023.
The.Ci� is willin� t� ex�en�l th� fin�l co�npleti�r� c�a�� and waive Biofilter�erf rmanc�e r�tes�n�. �o poses of the
equip ent war n y, t e ity is wi ing o esta is e equipment warra ty cPate as ep em e 1,�L(���.
an�hen oe°cfe°�rtdol omp nsat�e��he City�°o�rr°adt��i� os�ts�ina�rae� ��ies�onfria°� mwn�gte�e�eU���l�,8�st�{���I�i����e ��y.
P
As part of this Chan e Order No. 5, the City agrees to accept the CREDIT, a�rees to extend the Substantial Completion
�I afe to lune 13, 20�3, establishes an equipment warranty date of Septem er 18, 2024, and waives liquidated damages
or late delivery.
It is anticipated that a final payment request will be submitted following approval of this Change Order.
�FFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood antl agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
� Contractor's Company Name Contractor Name j�' � �� Contractor Si nature Date
9
� Crescent Contractors, Inc Ryan Glanz _z��,, ,��� 12 . 19 . 2 5
� Inspector
I L�— C���"
birector (Water Dept)
ci2Ni�E-v�GceY ttarr7et^
Assistant City Attorney
. t�'�
, Date
12/19/25
, Date
Ts 12/19/2025
�� Date
12/19/2025
Water Totals Contract Time
(Calender days)
$25,797,000.00 730
$521,025.00 179
Project Manager
Fa-Yi,da- Go�l.e,�ya�
Construction Supervisor
Assistant City Manager
;
�����
Council Action (If Required)
M&C Number � N/A � M&C Date Approved �
City of Fort Worth
Change Order Request
,� Date �
12/19/2025I
� Date �
�
�' Date
12/22/2025
N/A I I
Fo �r �V� �-r x
Project Name
Project No.(s):
Project
Description
Contractor
City Project Mgr.
City of Fort Worth
Change Order Additions
VCWRF Grit Removal Facility � City Sec No.: � 54099
56017/0700430/1780 � DOE No.� n/a � City Proj. No.: � 100075
The project consist of a new Grit Facility with 8 stacked tray vorrtex grit removal units, structural modifications to existing Headwork �
Facility, modificataions to Odor Control Biofilter System, and Electrical/HVAC/Plumbing/Yard Piping
Crescent Contractors, Inc � Change Order: �J Date: � 12/17/2025 �
Farida Goderya � City Inspector � K. Sidebottom (FNI) �
ADDITIONS
DEPT Qty Unit Unit Cost Total
1 CMR 17 - 480V Power for Gantry Crane Sewer
2 CMR 18 - Grit Pump Control Changes for Drain Operation Sewer
3 CMR 21 - Additional power circuit for heat trace to wash hydrants & sump pu Sewer
4 CMR 24.1 - Biofilter Media Sample Ports Sewer
5 CMR 25.1 - Grit Pump Room solenoid valves & strainer changes, 99 days Sewer
6 CMR 26 - Biofilter System Balance & Testing Sewer
'7 Credit to the City, in lieu of Liquidated Damages
1.00 LS $20,000.00 $20,000.00
1.00 LS $25,000.00 $25,000.00
1.00 LS $11,900.00 $11,900.00
1.00 LS $4,000.00 $4,000.00
1.00 LS $58,000.00 $58,000.00
1.00 LS $13,000.00 $13,000.00
Sewer 1.00 LS -$274,000.00 -$274,000.00
Sewer ($142,100.00)
Water
Page 1 of 1 Additions Sub Total
F�RT �VQRTH City of Fort Worth
Change Order Deletions
Project Name � VCWRF Grit Removal Facility � City Sec No.: � 54099 �
Project No.(s): � 560171070043011780 � DOE No. I n/a � City Proj. No.: � 100075 �
Project Description
Contractor �
City Project Mgr. �
The project consist of a new Grit Facility with 8 stacked tray vorrtex grit removal units, structural modifications to �
existing Headwork Facility, modificataions to Odor Control Biofilter System, and ElectricallHVAC/Plumbing/Yard
Crescent Contractors, Inc � Change Order: �5 Date � 12/1712025 �
Farida Goderya � City Inspector: � K. Sidebottom (FNI) I
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
ISewer
IWater
Page 1 of 1 IDeletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub
Tvpe of Service
Same as Original Contract Multiple
Amount for this CO
$131,900.00
Total $131,900.00
Previous Change Orders
Co # DATE AMOUNT
1 12/15/2020 $19,965.00
11 /15/2021
5/24/2022
2/15/2023
$77,630.00
$77,750.00
$345,680.00
Total I $521,025.00 �
Page 1 of 1
CDM
Sm�th
801 Cherry Street, Unit 33, Suite 1820
Fort Worth, Texas 76102
tel: 817 332-8727
June 20, 2023
Farida Goderya, PhD, P.E.
Fort Worth Water Department
200 Texas Street
Fort Worth, Texas 76102
Subject: Village Creek Water Reclamation Facility
Grit Removal Facility Project
CMR-17 Stationary Gantry Crane Power Supply
Dear Farida:
Transmitted here within please find a copy of Crescent's June 20, 2023 contract modification
request (CMR) for providing 480V power supply to the stationary gantry crane provided under
PCM 7. The stationary gantry crane requested in PCM 7 included a 208V power selection. During
shop drawing review the manufacturer said 208V power is not available for this type crane.
Therefore CDM Smith requested Crescent use the existing 30A, 480V circuit breaker in existing
panelboard SHP-1 and field route 3#10, 1#10G, and 3/4" conduit from existing panelboard SHP-1 to
the gantry crane control panel. The cost associated with this work is $20,000 with no additional
days.
CDM Smith has reviewed the price proposal and is of the opinion that it is fair and reasonable. CDM
Smith recommends the City accept this cost and issue a Change Order in the amount of $20,000.
Please advise if the Water Department desires this CMR-17 be incorporated into a Change Order.
Sincerely,
���.�..�,���--�
Amy Robinson, P.E., BCEE
Project Manager
CDM Smith Inc.
cc: Kevin Sidebottom, Freese & Nichols
Ryan Glanz, Crescent Constructors
..
t,r
WATER t ENVIRQHMENT f TRANSPORTATIaN i ENERGY t FAClLITIES I
2560 Technology Drive #400
Plano, TX 75074
CONTRACT M IFICATION REQUEST:
PROJECT: VILLAGE CREEK GRIT FACILITY
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
Pricing to Incorporate 480 Volt power supply and circuits for Gantry Crane in PCM 07
(From 04.20 AR email)
To accommodate the winch:
DATE: � 06.20.23
Use existing spare 30A, 480V, 3 pole circuit breaker in existing Panelboard SHP-1 located in existing Headworks Facility
Electrical Room. Provide new nameplate "STOP LOG N0.3 DAVIT CRANE" for the repurposed breaker in the panelboard.
Provide NEMA 7, 480V, 30A disconnect switch for the davit crane control panel.
Field route 3#10, 1#10G, 3/4"C from existing Panelboard SHP-1 to Stop Log No.3 Davit Crane Control Panel.
TOTAL AM NT � $ 20,000 �
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased
Decreased
� Unchanged
�
n
By 0 Calendar Days
� mman
ACCEPTED my Robinson, PE, BCEE, CC
REJECTED CDM Smith
CMR-17
06/20/2023
Date
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # PCM-07.3 Job #: � 2020-02 �
Description Labor Material Equipment Subcontract Total
DIRECT COSTS - 6,785 3,045 7,795 17,626
LABOR BURDEN & FRINGES 55% - -
SUBTOTALS - 6,785 3,045 7,795 17,626
1
2
3
4
CONTRACTOR MARKUP 15% 1,475
CONTRACTOR MARKUP 5% (SUBS) 390
BONDS & INSURANCE 3% 585
(75)
CDM
Sm�th
801 Cherry Street, Unit 33, Suite 1820
Fort Worth, Texas 76102
tel: 817 332-8727
July 13, 2023
Farida Goderya, PhD, P.E.
Fort Worth Water Department
200 Texas Street
Fort Worth, Texas 76102
Subject: Village Creek Water Reclamation Facility
Grit Removal Facility Project
CMR-18 I&C Modifications at Grit Pumps
Dear Farida:
Transmitted here within please find a copy of Crescent's June 22, 2023 contract modification
request (CMR) for replacing the discharge pressure gauges and flow switches for the grit pumps;
add maintenance isolation ball valves at the grit pump seal water solenoid valves, and making
PLC/HMI modifications to add Headcell drain sequence.
Upon completing the start-up of grit pumps, the Flowserve (Wemco) field representative brought to
our attention that the seal water pressure gauges and flow switches were incorrect sizes and the
they recommended replacing them. Additionally, after reviewing the seal water solenoid valve
configuration for the HeadCell flushing water system, it was determined that even though the
flushing water system is used during start-up and shut-down of a grit unit, providing additional ball
valves at the solenoid valves would provide for better maintenance access of the solenoid valve
while keeping the flushing system in service. CDM Smith requested a cost proposal for the ball
valves and it is included herein.
Furthermore, after reviewing the HeadCell drain sequence, CDM Smith provided clarifications in
Field Order 004 for the drain sequence that requires modifications at the PLC and HMI. The cost
associated with this work is $25,000 with no additional days.
CDM Smith has reviewed the price proposal and is of the opinion that it is fair and reasonable. CDM
Smith requests that Crescent salvage and turn over the pressure gauges and flow switches to plant
staff. CDM Smith recommends the City accept this cost and issue a Change Order in the amount of
$25,000. Please advise if the Water Department desires this CMR-18 be incorporated into a Change
Order.
Sincerely,
`� � R .� r
�
n
��
WATER t ENVIRQhEMEl�i t TRAI�ISPORTAT�QN + EiVERGY t FACILIl1E5 I
CDM
Sm�th
Farida Goderya, PhD, PE
July 13, 2023
Page 2
Amy Robinson, P.E., BCEE, CCM
Project Manager IV
CDM Smith Inc.
cc: Kevin Sidebottom, Freese & Nichols
Ryan Glanz, Crescent Constructors
n
`�
CMR-18 Recommendation of Approval Letter
2560 Technology Drive #400
Plano, TX 75074
CONTRACT M IFICATION REQUEST:
PROJECT: VILLAGE CREEK GRIT FACILITY
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
Misc I&C and small bore piping modifications for Grit Pump operations
DATE: � 06.22.23 �
(1) RFI 129/130 --- Replace Pressure guages to range up to SO psi at grit pumps
(2) Field Order 004 --- PLC/HMI mods to add Headcell Drain Sequence
(3) RFI 128/129 --- Replace flow switches to a flow rate of 0.20-0.50 gpm on grit pump seal water lines
(4) RFI 03.09 email --- Add in mantainence isolation ball valves at grit pump seal water solenoid valves
TOTAL AM NT � $ 25,000 �
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased
Decreased
� Unchanged
�
n
By 0 Calendar Days
� mmPn
ACCEPTED my Robinson, PE, BCEE, CC .
REJECTED CDM Smith
CMR-18
07/13/2023
Date
Salvage pressure gauges and flow switches and turn over to the City.
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # CMR-18
Description
DIRECT COSTS
LABOR BURDEN & FRINGES 55%
SUBTOTALS
CONTRACTOR MARKUP 15%
CONTRACTOR MARKUP 5% (SUBS)
BONDS & INSURANCE 3%
TOTAL�
CLARIFICATIONS:
1
2
3
4
Labor Material
1,656 2,687
911
2,567 2,687
Job #: � 2020-02 �
Equipment Subcontract
- 17,543
17,543
Total
21,886
911
22, 797
788
877
734
(196)
25,000
CDM
Sm�th
801 Cherry Street, Unit 33, Suite 1820
Fort Worth, Texas 76102
tel: 817 332-8727
December 13, 2023
Farida Goderya, PhD, P.E.
Fort Worth Water Department
200 Texas Street
Fort Worth, Texas 76102
Subject: Village Creek Water Reclamation Facility
Grit Removal Facility Project
CMR-21 Additional Circuits for Heat Tracing
Dear Farida:
Transmitted here within please find a copy of Crescent's September 14, 2023 contract modification
request (CMR) for extending electrical conduits to feed the heat trace and thermostats to the wash
hydrants on top of the grit structure and to the grit pump room sump pump drain lines that are
routed on top of the grit structure. These two piping systems were not included in the heat tracing
electrical schedule.
CDM Smith has reviewed the price proposal and is of the opinion that it is fair and reasonable. CDM
Smith recommends the City accept this cost and issue a Change Order in the amount of $11,900.
Please advise if the Water Department desires this CMR-21 be incorporated into a Change Order.
Sincerely,
���.�..�,�ti�--�
Amy Robinson, P.E., BCEE, CCM
Project Manager IV
CDM Smith Inc.
cc: Kevin Sidebottom, Freese & Nichols
Ryan Glanz, Crescent Constructors
..
t,r
WATER t ENVIRQHMENT f TRANSPORTATIaN i ENERGY t FAClLITIES I
2560 Technology Drive #400
Plano, TX 75074
CONTRACT M IFICATION REQUEST:
PROJECT: VILLAGE CREEK GRIT FACILITY
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
DATE: � 09.14.23 �
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
Extend electrical curcuits to feed the heat trace and thermostats to the wash hydrants shown on
drawings M-5, M-6 and the drain lines shown on P-3. (RFI 133)
TOTAL AM NT � $ 11,900 �
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased By 0 Calendar Days
Decreased
� Unchanged � Recommended for Approval B:
� ACCEPTED IAmy Robinson, PE, BCEE, CC�M
� REJECTED CDM Smith Inc.
CMR-21
Ryan Glanz
Crescent
12/13/2023
Date
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # CMR-21 Job #: � 2020-02 �
Description Labor Material Equipment Subcontract Total
DIRECT COSTS 560 - - 10,037 10,591
LABOR BURDEN & FRINGES 55% 308 308
SUBTOTALS 868 - - 10,031 10,899
1
2
3
4
CONTRACTOR MARKUP 15% 130
CONTRACTOR MARKUP 5% (SUBS) 502
BONDS & INSURANCE 3% 346
23
CDM
Sm�th
801 Cherry Street, Unit 33, Suite 1820
Fort Worth, Texas 76102
tel: 817 332-8727
May 3, 2024
Farida Goderya, PhD, P.E.
Fort Worth Water Department
200 Texas Street
Fort Worth, Texas 76102
Subject: Village Creek Water Reclamation Facility
Grit Removal Facility Project
CMR-24.1 Media Bed Sample Ports
Dear Farida:
Transmitted here within please find a copy of Crescent's Apri124, 2024 price proposal for installing
permanent sample ports for the Headworks Biofilter. The sample ports help facilitate balancing the
air flow between the biofilter beds for testing and balancing. During the testing and balancing call, it
was decided that these ports would be helpful to plant staff for future balancing activities so they
will be permanently installed for plant staff to use in the future. The cost associated for this work is
$4,000.
CDM Smith has reviewed the price proposal and is of the opinion that it is a fair and reasonable
price. CDM Smith recommends the City accept this cost and issue a Change Order in the amount of
$4,000. Please advise if the Water Department desires this CMR-24.1 be incorporated into a Change
Order.
Sincerely,
b
Amy Robinson, P.E., BCEE
Project Manager
CDM Smith Inc.
cc: Kevin Sidebottom, Freese & Nichols
Ryan Glanz, Crescent Constructors
�
i0
WATER + ENVIRONMENT +TRANSPORTATION + ENERGY + FACILITIES
2560 Technology Drive #400
Plano, TX 75074
CONTRACT M IFICATION REQUEST:
PROJECT: VILLAGE CREEK GRIT FACILITY
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
DATE: � 04/24/24 �
INSTALL 8 SAMPLE PORTS FOR AIR FLOW READINGS IN MEDIA BEDS
AIR FLOW T&B ON MEDIA BED SYSTEM: EXISTING FANS, NEW FANS, AND MEDIA AIR CHANNEL
TO BE COMPLETED AFTER SAMPLE PORT INSTALLATION
TOTAL AM NT � $ 4,000 �
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased
Decreased
� Unchanged
�u
�
By 0 Calendar Days
� mmPn
ACCEPTED my Robinson, PE, BCEE, CC
REJECTED CDM Smith
C M R-24.1
05/03/2024
Date
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # CMR-24.1 Job #: � 2020-02 �
Description Labor Material Equipment Subcontract Total
DIRECT COSTS 1,800 600 - - 2,400
LABOR BURDEN & FRINGES 55% 990 990
SUBTOTALS 2,790 600 - - 3,390
1
2
3
4
CONTRACTOR MARKUP 15% 509
CONTRACTOR MARKUP 5% (SUBS) -
BONDS & INSURANCE 3% 117
(15)
CDM
Sm�th
801 Cherry Street, Unit 33, Suite 1820
Fort Worth, Texas 76102
tel: 817 332-8727
July 8, 2024
Farida Goderya, PhD, P.E.
Fort Worth Water Department
200 Texas Street
Fort Worth, Texas 76102
Subject: Village Creek Water Reclamation Facility
Grit Removal Facility Project
CMR-25.1 Solenoid Valve and Strainer Changes
Dear Farida:
Transmitted here within please find a copy of Crescent's July 8, 2024 contract modification request
(CMR) and related RFIs 135, 136, and 137 for replacing the Magnetrol solenoid valves with ASCO
solenoid valves for the grit pump seal water, grit pump flushing, and headcell flushing systems. The
1/z" seal water solenoid valves need replaced with normally closed (NC), energized to open (EO) to
match the pump control logic. The 1-1/2" Magentrol valves are malfunctioning and causing
oveheating. Each size of valve was sent back to Magentrol and their report in RFI 137 suspected the
service water quality is gunking the piston and causing the valve to not close/open properly. Plant
staff indicated they have not had any issues with the ASCO valves and service water quality. RFI
135, 136, and 137 directed Crescent to replace all the Magnetrol solenoid valves with ASCO valves
and replace all the provided strainers with mesh sizes recommended by valve manufacturer.
Crescent is requesting 99 calendar days be added to the final completion date.
CDM Smith has reviewed the price proposal and time extension and is of the opinion that it is fair
and reasonable. CDM Smith recommends the City accept this cost and issue a Change Order in the
amount of $58,000 and extend the Final Completion date by 99 calendar days. Please advise if the
Water Department desires this CMR-25.1 be incorporated into a Change Order.
Sincerely,
a�.�d�,�
Amy Robinson, P.E., BCEE, CCM
Project Manager IV
CDM Smith Inc.
cc: Kevin Sidebottom, Freese & Nichols
Ryan Glanz, Crescent Constructors
i~.1
WATER + ENVlRONMEIVT +TRAIVSPORTATION + ENERGY + FACILITIES
2560 Technology Drive #400
Plano, TX 75074
CONTRACT M IFICATION REQUEST:
PROJECT: VILLAGE CREEK GRIT FACILITY
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
REPLACE SOLENOID VALVES IN GRIT PUMP ROOM
DATE: � 07.08.24 �
(1) REPLACE 8 EA 1/2" SV (GRIT PUMP SEAL WATER) WITH ASCO
(2) REPLACE 8 EA 1-1/2" SV (HEADCELL FLUSH WATER) WITHASCO --- NO CHARGE
(3) REPLACE 8 EA 2" SV (GRIT LINE FLUCH WATER) WITH ASCO
(4) REPLACE 8 EA - 1/2" STRAINERS, 8 EA 1-1/2" STRAINERS, 8 EA 2" STRAINERS FROM
TOTAL AM NT � $ 58,000 �
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by RFI 135
Change Order, the time of completion will be: STRAINER LEAD TIME ( 3-4 WKS )
INSTALLATION (PROJECTED)
� Increased � By 9 9 Calendar Days
Decreased
Unchanged
�
C
Recommended Bv:
ACCEPTED IAmy Robinson, PE, BCEE, CC�M
i.%y J� �vi l �r�'QT�T
REJECTED CDM Smith Inc.
CMR-25.1
07/08/2024
Date
= 05.09.24
= 08.05.24
= 08.16.24
+ 99 DAYS
Salvage and return all 2", 1-1/2", and 1/2" Mangetrol valves and associated strainers to City.
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # CMR-25.1 Job #: � 2020-02 �
Description Labor Material Equipment Subcontract Total
DIRECT COSTS 13,704 27,656 - - 41,360
LABOR BURDEN & FRINGES 55% 7,537 7,537
SUBTOTALS 21,241 27,656 - - 48,897
CONTRACTOR MARKUP 15% 7,335
CONTRACTOR MARKUP 5% (SUBS) -
BONDS & INSURANCE 3%
1
2
3
4
1,687
81
Ryan Glanz
From: Robinson, Amy <RobinsonAR@cdmsmith.com>
Sent: Monday, July 8, 2024 11:25 AM
To: Ryan Glanz; Farida Goderya
Cc: Kevin Sidebottom; Brad Little; David Caldwell; Edgar Vargas; Mike Daigre
Subject: RE: Grit --- CMR-26 PRECISION FLOW T AND B OF MEDIA BEDS
kyan, Faricia a��ruve�' ihis Lr�Ylk-2� cust at the consiructiori pr�gr�ss nieeting. She had requested to revise and
add appropriate time extension. Do you agree that if this CMR gets approved today that you can complete the
balancing and media performance testing by 8/16/2024 when CMR-25 is projected to be complete?
Amy Robinson, PE, BCEE, CCM
Associate
CDM Smith
801 Cherry Street, Unit 33, Suite 1820, Fort Worth, Texas 76102
(cell) 817.914.2511, (office) 817.916.2927
Connect with me on Linkedln and Twitter @AmyRobinson
cdmsmith.com
What happens NEXT is happening NOW. Learn more
CDM
Smith
�_a�_
From: Robinson, Amy <RobinsonAR@cdmsmith.com>
Sent: Thursday, June 27, 2024 2:50 PM
To: Ryan Glanz <ryan.glanz@crescentconstructors.com>; Farida Goderya <Farida.Goderya@fortworthtexas.gov>
Cc: Kevin Sidebottom <kps@freese.com>; Brad Little <brad@crescentconstructors.com>; David Caldwell
<david@crescentconstructors.com>; Edgar Vargas <edgar.vargas@crescentconstructors.com>; Mike Daigre
<miked@crescentconstructors.com>
Subject: RE: Grit --- CMR-26 PRECISION FLOW T AND B OF MEDIA BEDS
Ryan, per discussion in our meeting today, please revise and resubmit CMR-26 to include time extension related to
work.
Amy R. Robinson, PE, BCEE, CCM
Associate
CDM Smith
801 Cherry Street, Unit 33, Suite 1820
Fort Worth, Texas 76102
Direct 817.916.2927
Cell 817 914-2511
Connect with me on Linkedln and Twitter @AmyRobinson
cdmsmith.com
�
�O�O�J��7�0�
From: Ryan Glanz <rvan.�lanz@crescentconstructors.com>
Sent: Monday, June 10, 2024 1:50 PM
To: Farida Goderya <Farida.Goderva(�fortworthtexas.�ov>
Cc: Robinson, Amy <RobinsonAR@cdmsmith.com>; Kevin Sidebottom <kps@freese.com>; Brad Little
<brad(a�crescentconstructors.com>; David Caldwell <davidCa)crescentconstructors.com>; Edgar Vargas
<ed�ar.var�as(�crescentconstructors.com>; Mike Daigre <miked(�crescentconstructors.com>
Subject: Grit --- CMR-26 PRECISION FLOW T AND B OF MEDIA BEDS
Attached is CMR for the additional costs for Precision Flow to do the T&B the Media beds.
Thanks & Have a Great Day,
Ryan Glanz, PE
2560 Technology Drive, Suite 400
Plano, TX 75074
214-783-8007 cell
2560 Technology Drive #400
Piano, TX 75074
CONTRACT MQDIFICATI4N REQUEST:
PROJECT: VILLAGE CREEK GRIT FACILITY
PROJECT NO. 100075
ATTENTION: C1TY OF FORT WORTH
1000 THROCKMORTON STREET
F4RT W4RTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdmvn of cost SHALL be attached.
lYork shall not commence :rntil authorized by the Ob�ti'ER.
Description of the Praposed Change & Clarifications
Pricing for the following
AIR FL4W T&B ON MEDIA BED SYSTEM BY PRECISI�N FLOW ENGINEERING
: EXISTING FANS, NEW FANS, AND MED1A AiR CHANNEL
TO BE COMPLETED AFTER SAMPLE PORT INSTALLATION
DATE: � 06.10.24 �
COFW asks to revise and resubmit to include time extension related to CMR request. Provide detailed schedule
justifying time extension request including but not limited to when B&T was completed, when submittal was
submitted and returned by Engineer, when B&T company quit, when Crescent received proposal from new B&T
subcontract, any other pertinent dates, and also include time frame for retesting biofilter media.
TOTAL AMOUNT � $ 13,Q00
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
increased
Decreased
� Unchange8
u
By 0 Calendar Days
Recommended By:
ACCEPTED � Amy Robinson, PE. BCEE, CC�M
orl�,
� REJECTED CDM Smith Inc.
REVISE AND RESUBMIT
see comment above
cnnR-Zs
� 6/27/2024
Date
CHANGE ORDER SUMMARY
Front Sheet
VtLLAGE CREEK GRiT FACILITY
CHAlVGE DESCR(PTION:
CONTRAC7 MOpIFiCAT10N REQUEST # CMR-26
Description
DIRECT COS7S
L.ASOR BllRDEN & FRWGES 55%
SUBTOTALS
CONTRACTOR MARKUP 15%
CQNTRACTOR MARKUP 5% (SUBS)
BQNDS & INSURANCE 3%
TOTAL�
CLARIFICATIONS:
1
2
3
4
Job #: � z020-02 �
Labor Material Equipment
1,800 b00 -
990
2,790 fi60 -
- � - � - �
Subcontract Tofal
8,500 74,900
990
_ --- -1
8,500 - 11,890 _
509
425
, 385
(208�
- I - -- 13,04d
�
.Contract Compliance Mana�er
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
�,,1;. - — -- - _ . ..
�-�- " � C � �-��y �-- '� _ __.
i
Signature
Farida Goderya, PhD, PE
Name of Employee
Senior Project Manager
Title
ATTEST:
� ���
C��
p OFFORT Ila
ooe0000a �YOd
a �° o9-��d
�o
°o�o �=d
poQ�000 o°,��
dIIa4 pEXp?op
Jannette Goodall
City Secretary
�FFICIAL RECQRQ
CITY SECRETARY
FT. WORTH, TX
F�RT��RTHo
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Crescent Contractors, Inc.
Subject of the Agreement: Village Creek Water Reclamation Facility Grit Removal
M&C Approved by the Council? * Yes ❑ No ❑✓
If �so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑✓ No ❑ 54099-005
If �so, provide the original contract number and the amendment number.
Is the Contract "PermanenY'? *Yes 0 No ❑
If �unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No ❑✓ If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: N/A Expiration Date: N/A
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No ❑✓
*If �so, please ensure it is attached to the approving M&C or attached to the contract.
Proj ect Number: If applicable. 100075
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ❑✓ No ❑
Contracts need to be routed for CSO processin� in the followin� order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)