HomeMy WebLinkAbout27398-01-2025 - City Council - OrdinanceOrdinance No. 27398-01-2025
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE PARD GAS LEASE CAPITAL PROJECT FUND, IN
THE AMOUNT OF $73,854.31, FROM AVAILABLE GAS LEASE BONUS, FOR
THE PURPOSE OF FUNDING THE IMPROVEMENTS AT RIVERSIDE PARK
PROJECT (CITY PROJECT NO. 105822); PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2024-2025 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the PARD
Gas Lease Capital Project Fund in the amount of $73,854.31, from available Gas Lease Bonus, for the
purpose of funding the Improvements at Riverside Park project (City Project No. 105822).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court ofcompetent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27107-09-2024 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Feb 3, 2025 17:16 CST)
Assistant City Attorney
ADOPTED AND EFFECTIVE: January 14, 2025
CITY SECRETARY
Jannette S. Goodall
City Secretary
on
000000000*
L P J
` 0 °CP 0.
0
000
o°=d
o °
�a * ° o° d�
8' CONCRETE TRAILS
RESURFACED PARKING LOTS a
1
0
PARKING LOT EXTENSION.
8' CONCRETE TRAIL
24' X 24' PAVILION
NConcrete trail be
0 � .` 'i'- built with this ILA
'4- - j' >
Kayak Launch to be
..:-
i built with this ILA
i
ADULT SOCCER FIELD
EXISTING 11' TRAIL
YOUTH SOCCER FIELD r
\ A PARKING LOT WITH ER
SPACES &DROP-OFF ZONE
KAYAK LAUNCH DOCK
! BASEBALL PRACTICE FIELDS
PLAYGROUND WITH SEATING
24' X 24' PAVILION
BASKETBALLCOURT
WILDFLOWER AREA
STEEL PEDESTRIAN BRIDGE
\LL CO pTkjLAYGROUNND[KAYAK LAUNCH DOCK
STEEL PEDESTRIAN BRIDGE
FORT WORTH
RIVERSIDE PARK CONCEPT PLAN F° ��r- Kirnlev>+brn
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 01/14/25 M&C FILE NUMBER: M&C 25-0002
LOG NAME: 80RIVERSIDE PARK ILA WITH TRWD
SUBJECT
(CD 11) Authorize Execution of an Interlocal Agreement with Tarrant Regional Water District for Reimbursement of Construction Costs in an
Amount Not to Exceed $550,000.00 for the Improvements at Riverside Park, Adopt Appropriation Ordinances Totaling $600,000.00 from
Available Funds, and Amend the Fiscal Year 2025-2029 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an Interlocal Agreement with Tarrant Regional Water District in an amount not to exceed $550,000.00 for the City's
reimbursement of eligible construction costs for the purpose of funding the improvements at Riverside Park project (City Project No.
105822);
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the PARO Dedication Fees Fund in the
amount of$89,901.80, from available Park Planning Fee, for the purpose of funding the Improvements at Riverside Park project (City Project
No. 105822);
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the PARO Dedication Fees Fund in the
amount of $436,244.00, from available Park Planning Fee within the Park Planning District 4.1-1 (City Project No. LIN8088), 4.1-2 (City
Project No. LIN8089), 4.1-4 (City Project No. LIN8091) and 4.13-4 (City Project No. LIN8154), for the purpose of funding the Improvements at
Riverside Park project (City Project No. 105822);
4. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the PARO Gas Lease Capital Project Fund
in the amount of$73,854.31, from available Gas Lease Bonus, for the purpose of funding the Improvements at Riverside Park project (City
Project No. 105822); and
5. Amend the Fiscal Year 2025-2029 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to authorize the execution of an Interlocal Agreement (ILA) with the Tarrant
Regional Water District (TRWD) in an amount not to exceed $550,000.00 for the City's reimbursement of eligible construction costs for the
improvements at Riverside Park (City Project No. 105822).
On October 12, 2010, the City Council adopted the River Connect Concept Plan as the Riverside Park Master Plan (M&C L-15080). The
proposed plan is consistent with the use and development offloodplain land for parks throughout the Fort Worth park system and throughout the
country.
The Park & Recreation Department engaged Kimley-Horn and Associates, Inc., to design Riverside Park Phase I Improvements in 2018 and 2019
(CSC No. 50377 ). On May 19, 2020, the City Council authorized the execution of a contract with Northstar Construction, LLC, for the construction
of Riverside Park Phase I Improvements (M&C 20-0349).
Due to funding limitations, Phase I Improvements scope did not include the installation of a canoe/kayak launch and a 1,500-foot long and 8-foot
wide concrete trail on the northeast side of the park. Funding has since been identified, and staff recommends an ILAwith the TRWD, which has
the technical experience, to complete the installation of these improvements.
The table below summarizes funding sources for this ILA:
Fund
!Park Dedication Fees Funds (Unspecified -All Funds)
PARD Gas Lease Capital Project Funds (Unspecified -All
Funds)
(Park Dedication Fees Funds
!Total
The table below summarizes project expenditures:
Amount
$89,901.801
$73,854.311
$436,243.89
$600,000.001
Amount
Riverside Park ILA wl'thTRWD I $550,000.00
!Project Contingency
!Project Total
$50,000.001
$S00,000.001
Funding for this project was not included in the FY2025-2029 Capital Improvement Program. This M&C will amend the FY2025-2029 Capital
Improvement Program as approved in connection with Ordinance 27107-09-2024.
After completion of construction, TRWD will maintain the canoe/ kayak launch, and the City will maintain the 1,500-foot long and 8-footwide
concrete trail along with the other park amenities. This new concrete trail is estimated to increase the department's annual maintenance by
$4,500.00 beginning in FY2025.
A business equity goal is not assigned when purchasing from an approved purchasing cooperative or public entity.
This project is located in COUNCIL DISTRICT 11.
A Form 1295 is not required because: This contract will be with a governmental entity, state agency or public institution of higher education: Tarrant
Regional Water District
FISCAL INFORMATION/ CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Riverside Park TRV Reno & Dev project within the PARO Dedication Fees
and PARO Gas Lease Capital Project Funds and in the PPD 4.1-1, PPD 4.1-2, PPD 4.1-4 and PPD 4.13-4 projects within the PARO Dedication
Fees Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinances, funds will be available in the
PARO Dedication Fees and PARO Gas Lease Capital Project Funds for the 25 TRWD Riverside ILA project to support the above
recommendations and execution of the agreement. Prior to an expenditure being incurred, the Park & Recreation Department has the
responsibility of verifying the availability of funds.
Submitted for Citv Manaaer's Office bv: Jesica L McEachem 5804
Oriainatina Business Unit Head: Richard Zavala 5704
Additional Information Contact: Joel McElhany 5745