HomeMy WebLinkAbout063375-CO1 - Construction-Related - Contract - PRELOADFO RT WC� RT H City of Fort Worth
Change Order Request
CSC No. 63375-CO1
Project Name:l Sendera Ranch 5.5 MG Ground Storage Tank � City Sec No.: � 63375 �
Project No.(s):� 61018480 � DOE No. � N/A � City Proj. No.: � 105781 �
Project Description:l 5.5 Million Gallon (MG) AWWA D110 Concrete Prestressed Ground Storage Tank
Contractor:� PRELOAD I Change Order# � 1 � Date: � 11712025 �
City Project Mgr.� Dena Johnson, PE � City Inspector. � Nicodem Momo 1 Ivan Rocha, P.E. (KHA) �
Phone Number:� 817-991-8820 � Phone Number.� 682-234-2767 �
Dept. Water Sewer
Original Contract Amount $11,937,000.00
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $11,937,000.00
�Amount of Proposed Change Order $0.00
Revised Contract Amount $11,937,000.00
Original Funds Available for Change Ortlers $298,425.00
Remaining Funds Available for this CO $298,425.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Totals Contract Time
(Calender days)
$11,937,000.00 460
$11,937,000.00 460
$0.00
$11,937,000.00 460
$298,425.00 f
$298,425.00
�$14,921, 250.00
Change Order No. 1 provides for the additional cast iron involved with replacing the originally proposed Val-Matic
42-inch and 48-inch Class 250B Butterfly valves with Crispin 42-inch and 48-inch Class 1506 ButterFly valves in
order to expedite the manufacture and delivery of the butterfly valves and avoid delays with completing the
ground storage tank on time.
C�7 � � Cy 1,1 �:� X�%]:a �7
C«] � i'�'i xy:� � ��1:�'1
FT. WORTH, TX
It is untlerstood and agreetl that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time antl money) for all costs arising out of, or incitlental to, the above Change Order.
Contractor's Company Name I Contractor Name I �ntractq�Si ature _ I Date
PRELOAD Ryan J. Leisey, P.E. '/ �,, V,� 1/8/2026
J"
In pec�or
������� ���
�irector (Water Dept)
�L7Aii/fi4�f7DA, OY�n�"OA.
_,�� ,� ��.���
�Assistant City Attomey
. �
� / —
� Date LProject Manager �'
�
i�
M&C Number � nla
/ � o�,�j ��N�CL %!'./2d8rL
Date Construction Su�� iso �
T S. �(i ���mF 7�,.�. �/- ��
Date Assistant City Ma a er
O1/1�,��F '� � ca- ���� .
-��(���. �
Council Action (If Required)
� M&C Date Approved � n/a
Date
1 /8/26
Date
� �-z�
Date
1/23/2026
FO RT WO R� 1-3 City of Fort Worth
--1'� s � Change Order Additions
Project Name � Sendera Ranch 5.5 MG Ground Storage Tank � City Sec No.: � 63375
Project No.(s): � 61018480 � DOE Na� N/A � City Proj. No.: � 105781
Project
Description 5.5 Million Gallon (MG) AWWA D110 Concrete Prestressed Ground Storage Tank
Contractor � PRELOAD � Change Order: �1� Date: � 1I712025 �
City Project Mgr. � Dena Johnson, PE � City Inspector � Nicodem Momo I Ivan Rocha, P.E. �
ADDITIONS
I l tM utSCftIN I lUN DEPT
Additional cost involved with delivery ot 41-inch and 4�-inch Grispin Butterfly
8 Valves Water
Qty Unit Unit Cost
1.00 LS $20,553.00
Total
$20,553.00
�Water
�Sewer
!$20,553.00
Page 1 of 1 �Additions Sub Total $20,553.00
FC�RT WORTH City of Fort Worth
Change Order Deletions
Project Name � Sendera Ranch 5.5 MG Ground Storage Tank
Project No.(s): � 61018480 � DOE No
Project Description I
�
� City Sec No.: � 63375
N/A � City Proj. No.: � 105781
5.5 Million Gallon (MG) AWWA D110 Concrete Prestressed Ground Storage Tank �
Contractor I PRELOAD � Change Order: � Date � 117/2025 �
ivi�vucin ivi�iiwi ivaii iw��ia, r.�..
City Project Mgr. Dena Johnson, PE City Inspector: ,,,��� �
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
1 Construction Allowance Water 0.13702 LS $150,000.00 $20,553.00
Page 1 of 1
;Water
iSewer
�
Deletions Sub Total
$20,553.00
$20,553.00
MIWBE Breakdown for this Change Order
MWBE Sub � Type of Service � Amount for this CO
Same as original Contract
co #
Miscellaneous
Previous Change Orders
DATE I
Total
Totai
AMOUNT
$0.00
$0.00 I
$0.00 �
Page 1 of 1
P' R E LOA�
Prestressed Concrete Tanlcs
October 23, 2025
Kyle Welden
ICimley-Horn and Associates, Inc.
801 Cherry Street, Unit 11
Suite 1300
Fort Worth, TX 76102
Reference:
Deac� ICyle Welden,
PCO No. O1 - Crispin Butterfly Valve
Sendera Ranch 5.5 MG Ground Storage Tank — Foi•t Worth, TX
Preload LLC. • 4000 Tower Road
Louisville, I{Y 40219
631.644.6430 • Fax 631.231.8881
Bsmith r)preload.com
www.preload.com
Please find below the costs associated with switching from the originally submitted 54" and 42" butterfly valves to
Crispin valves.
CLW was asked to provide an option for a valve with a faster delivery time than the valve listed in the
specifications. Municipal Valve has proposed a K-Flo class 150B butterfly valve for this installation. The below
price is for this work.
CLW Labor, Material, and Equipment Costs
Contractor Fee per EJCDC C-700 12.O1.C.2.a (15%)
Contractor Fee per EJCDC C-700 11.04.C.2.b (5%)
Subtotal PCO
Contractor Bond Fee (2.0°/o)
Grand Total PCO No. O1 - Crispin Butterfly Valve
20,150.00
0.00
0.00
20,150.00
403.00
20,553.00
An additional thirty (30) calendar days a�•e being requested for this Work to be added to the Contract Time.
Due to the current economic climate including fi•equent fluctuations in both material prices and procurement lead
times this quote is only valid for ten (10) days fi•om the date of this letter unless otherwise defined within the
attached backup.
Exclusions to the above also include, but are not limited to, labor othe►• than listed, material other than listed, equipment
other than listed, engineering other than listed, material escalation other than listed, material sales tax, winter
conditions other than listed, extended overhead, demobifization othe►• than listed, remobilization other than listed,
winter shutdown other than listed, additional safety items other than listed, Time other than listed, additional costs
other than listed, all work shall be completed du►•ing normal working hours (i.e. 8 hour days & 40 hour weeks). If
through no fault of Preload or our subcontractors' ovei•time is required to complete/meet project deadlines, all hours
will be kept track on a T&M basis and charged accordingly.
If you have any questions, please feel fi•ee to contact me at your earliest convenience.
Thank you,
Blake Smith
Project Manager
PRELOA�
Wire-Wrapped Prestressed Concrete Tanks
M: 631.644.6430 � F: 631.231.8881
Em: bsmitha,pereload.com
www.oreload.com
4000 Tower Road • Louisville, Kentucky 40219 • 135 Engineers Road, Ste.120 • Hauppauge, New York 11788
631-231-8100 • Fax 631-231-8881 • w�vw.preload.com
/ �
�
� W A T E R G R O U P
CONTRACT CHANGE PROPOSAL:
001
PROJECT: Sendera Ranch 5.5 MG Ground Storage Tank
City of Fort Worth
Kimley Horn
ATTENTION: Preload
1219 Digital Drive
STE. 120 Richardson, TX 75081
A breakdoivn of cosl SHALL be atfached.
I-Vo�•k shn!! not commence tu�ti! authorized bp the Oid'NER.
DATE: I 23-Oct-25 �
Description of the Proposed Change & Clarifications
CLW is submitting this change proposal for switching from the originally submitted 54" and 42" butterfly valves to
Crispin valves.
TOTAL AMOUNT I $ 20,150 �
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased By 0 Calendar Days
Decreased
� Unchanged �
❑ ACCEPTED I
Da�rie� (/ar�ae
Daniel Vargas
CLW Water Group
Date
❑ REJECTED
CHANGEORDER SUMMARY
Front Sheet
CHANGE DESCRIPTION: Crispin Butterfly Valves
CONTRACTORS CHANGE PROPOSAL #'001
Description Labor Material
DIRECT COSTS - 19,563
LABOR BURDEN & FRINGES 55% -
SMALL TOOLS 8% OF LABOR
SAFETY SUPPLIES 3% OF LABOR
SUBTOTALS -
CONTRACTOR MARKUP
BONDS & INSURANCE 3%
�
TOTALI � I
CLARIFICATIONS:
19,563
. I
Job #: � 2503 �
Equipment Subcontract
' � - �
Other
'
Total
19,563
I
19,563
587
20,150
1
Description
LABOR
Project Superintendent
Assistant Superintendent
Carpenter Foreman
Mechanical Foreman
Project Manager
Assistant Project Manager
Surveyor
Safety Coordinator
Skilled Laborer (2 Men x 2 Days)
Rodman
Form Setters
Pipe Fitters
Crane Operator
Operator (1 Operator x 2 Days)
MATERIAL
MVE Quote
EQUIPMENT (Daily i Weekly / Monthly) Cost
(Fuel, Oil, Grease, & Mainfenance Included)
Rubber Tire Backhoe (285 / 927 / 2,782)
Wheel Loader (3 cy) (480 ! 2,398 / 7,194)
Dozer (419 / 2,094 / 6,281)
Compactor (383 / 1,916 / 5,748)
Trench Compactor (239 ! 1,194 / 3,582)
Air Compressor (78 / 388 / 1,163)
Excavator 210X
Excavator 78k Ib (330) (882 / 4,411 / 13,232)
Excavator 82k Ib (340) (980 / 4,899 / 14,696)
30 Ton Crane 756 / 3,779 / 11,337)
60 Ton Crane (924 / 4,619 / 13,857)
80 Ton Crane (1,400 / 5,599 / 16,796)
Welding Machine (168 / 840 / 2,519)
Pickup Trucks (128 / 637 / 1910)
Equipment Delivery
Jobsite O�ce (45 / 220 / 655)
Engineering Office (45 / 220 / 655)
Warehouse Storage (15 / 65 / 200)
Jobsite Phone
Jobsite Utilities
Temporary Toilets (32 / 160 / 480)
Dumpsters (60 / 280 / 815)
Concrete Pump Truck
Skid Steer
Trucking
SUBCONTRACTORS
Job: Sendera Ranch 5.5 MG Ground Storage Tank
Unit
Qty Un Labor
MH
MH
MH
MH
MH
MH
MH
MH
MH
MH
MH
MH
MH
MH
1.0 LS
95.00
65.00
60.00
60.00
87.00
60.00
55.00
55.00
30.00
30.00
30.00
30.00
42.50
35.00
Item:
u
Total
Unit Unit Unit
Mat'I Equipment Labor
19, 563.00
0
1/1
Total Total
Mat'I Equipment
19, 563
19,563 0
1 /1
Subs
0
1 /1
,
��� � �
�+ � �
MUNICIPALVALVE
& EQUIPMENT COMPANY
� a UFT Company
4010 BILLY MITCHELL DR,, ADDISON, TX 75001 PHONE: 972-248-2600 FAX: 972-767-4414
October 22, 2025
Crescent Constructois
2560 Technology Drive, Suite 400
Plano, Texas 75074
Attn: Daniel Vargas
RE: Fort Worth — Sendera Ranch S.SMG Ground Storage Tank City Project 105781
We are pi•oposing K-Flo Class 150B buttei•fly valves with Rotork IW worm gears dii•ect mounted to the valves in the vault
with a pedestal mounted Beck Model 11-489 multi-tui•n EMO.
The cost increase includes the following:
42" K-Flo Sei•ies 47 Class I50 B Flanged ............... 1 each
Beck Model 11-489 multi-turn EMO ..................... 1 each
30" Carbon Steel Pedestal ................................. 1 each
304 SS extension stem, DI couplings ..................... 1 each
DI Stem Guides ............................................. 1 each
54" K-Flo Series 47 Class 150 B Flanged ...............1 each
Beck Model 11-489 multi-turn EMO .................. 1 each
30" Carbon Steel Pedestal ..................................1 each
304 SS extension stem, DI couplings .....................1 each
DI Stem Guides ............................................. 1 each
Total Price increase is ..............................$19,563.00
Regards,
Jim Andeeson
V.P. of Operations
PRI;LOAU LLC PRELOAa
4000 To�ver Road
Louisville, KY 40219 "W ire-Wound Prestressed Concrete Tanks"
Ph: 502.9G2.2262
Project 25PD007 Port Worth, TX - 5.5 MG Ciearn�ell Date I/6/2026
Reference: Proposed Change Order No. 01 - Crispin ButterFly Valve
DCSCRIPTION:
The following labor, equipment, materials and design/engineering breakdown is in association with switching from the originally submitted 54" and 42" butterfly valves to
Crispin valves.
A. LABOR INCLUDING INSUI2ANCC, Tr1XGS AND PI2INGF.S
AMOUNT QTY UOM RATE UOM TOTAL
Preload Foreman - 24.00 hours $ 100.00 hour $ -
Carpenter - 24.00 hours $ 60.49 hour $ -
Forklift Operator - 24.00 hours $ 80.28 hour $ -
Shop Worker - 10.00 hours $ 50.49 hour $ -
$ -
Burden (82%) I.00 - Is $ 0.82 Is $ -
$ -
Preload Foreman Subsistence - 3.00 day $ 1 14.00 day $ -
Preload Crew Subsistence - 3.00 day $ 84.00 day $ -
$ -
TOTAL A - hours $ -
B.SUBCONTRACTORS
AMOUNT QTY UOM RATE UOM TOTAL
CLW 42" Valve 1.00 I.00 LS $ 9,014.60 LS $ 9,014.60
CLW 54" Valve I.00 1.00 LS $ 11,135.40 LS $ 11,135.40
TOTAL B
C. NIATGRIALS/CQUIPNI�NT/OTHCR
Section of Rail
Exterior Ladder
Exterior Ladder and Railing Freight
Shotcrete
1-1/4" 316SS Sample Taps
Water Stop Plate
20' of 1-1/4" 316SS piping, threaded on one end
1-I/4" 316SS elbow
B rackets/Fasteners/StrapslBolts
MISC Construction Tools & Equipment
8K Forkl ift ($610wk = 7day = $88day)
Manlift ($485wk + 7day = $70day)
Compressor ($235wk = 7day = $34day)
Shotcrete Pump ($400wk = 7day = $58day)
TOTAL C
D. �NGINGGRING/DESIGN
Senior Professional Engineer - Design Review & Calculations
EIT Engineer - Dimensioning & Detailing
Drafter - Drawings & Asbuilts
TOTAL D
TOTALA+B+C+D
CONTRACTOR FEE PER SC-11.04.C.2.a
CONTRACTOR FEE PER SC-] 1.04.C.2.b
SUBTOTAL W[TH ALLOWABLE FEE
BOND FEE (2.0%)
1'O'1'�V_ �',U.l�l•:
AMOUNT QTY UOM
- ] 0.00 ft
- 15.00 ft
- I.00 ea
- o.ao �y
- 1.00 ea
- 4.00 ea
- 20.00 ft
- 2.00 ea
- 1.00 Iot
- I.00 Is
- 3.00 day
- 3.00 day
- 1.00 day
- 1.00 day
AMOUNT QTY UOM
- 8.00 hrs
- 8.00 hrs
- 8.00 hrs
$ -
$ -
$ -
$ 20, I 50.00
RATE UOM
$
$ 11520 ea $
$ 129.80 ea $
$ 600.00 ea $
$ 150.00 cy $
$ 185.16 ea $
$ 100.00 ea $
$ 22.00 ea $
$ 9.02 ea $
$ 2,920.00 lot $
$ 500.00 Is $
$ 88.00 day $
$ 70.00 day $
$ 34.00 day $
$ 58.00 day $
$
$
TOTAL
RATE UOM TOTAL
$200.00 hr $ -
$175.00 hr $ -
$90.00 hr $ -
$ -
$ 20, I 50.00
15% $ -
0% $ -
$ 20,150.00
2.0% $ 403.00
S 20,553.011
.Contract Compliance Mana�er
By signing I acicnowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensui•ing all pei•formance and i•eporting requirements.
�2�1a �]o�tt�fon
Signature
DenaJohnson
Name of Employee
Project Manager
Title
an4
ATTEST: `��``� F�Rr�o°d
a'�° a9dd
l.g
PVo 0=4
C��� /� � �P�*o�� ��o*dd
°aQIl�r�°E°��°Asaa
Jannette Goodail
City Secretary
C}FFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
F�RT�OI�TH��
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Preload
Subject of the Agreement: Sendera Ranch 5.5 MGD Ground Storage Tank
M&C Approved by the Council? * Yes ❑ No ✓❑
If so, the M&C must be attachecl to the cont�act.
Is this an Amendment to an Existing contract? Yes ❑✓ No ❑ 63375-CO1
If so, p�ovide the original contract nurnber and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsuNe, see back page fo� permanent cont�^act listing.
Is this entire contract Confidentiial? *Yes ❑ No ❑✓ Ifonly specific info�mation is
Confidential, please list what information is Confidential and the page it is loeated.
Effective Date: N/A Expiration Date: N/A
If �different from the approval date. If �applicable.
Is a 1295 Form required? * Yes ❑ No ❑✓
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Proj eCt Number: If applicable. 105781
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ✓❑ No ❑
Contracts need to be routed for CSO nrocessin� in the followin� order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
�eturned to the department.