HomeMy WebLinkAbout057155-A3 - Construction-Related - Contract - Lockwood, Andrews & Newnam, Inc.CSC No. 57155-A3
AMENDMENT No . 3
TO CITY SECRETARY CONTRACT No. 57155
WHEREAS, the City of Fort Worth (CITY) and Lockwood, Andrews & Newnam,
Inc., (ENGINEER) made and entered into City Secretary Contract No. 57155,
(the CONTRACT) which was authorized by M&C 22-0046 on the llth day of
January, 2022 in the amount of $ 485,380.00; and
WHEREAS, the CONTRACT was subsequently revised by:Amendment No. 1 in
the amount of $261,093.00 which was authorized by M&C # 22-0596 on August
9, 2022, and Amendment No. 2 in the amount of $ 167,774.00 which was
authorized by M&C # 23-0185 on February 28, 2023; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Water and Sanitary Sewer Contract 2019 WSM-L, CPN 103380; and
WHEREAS, it has become necessary to execute Amendment No. 3 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $81,120.00. (Water: $53,926.53; Sewer: $27,193.47)
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $995,367.00.
3.
Al1 other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 1 of 2
OFFICIp►L RECt7RD
CITY SECRETARY
FT. WORTH, TX
W&SS Contract 2019 WSM-L
103380
EXECUTED and EFFECTIVE as
designated Assistant City Manager.
APPROVED:
City of Fort Worth
,�
Jesica McEachern
Assistant City Manager
DATE:
02/06/2026
ATTEST:
/� .�'�a.e�
C��
Jannette Goodall
City Secretary
4doavnnIl�
,�poF �ORr�aa
��'�� °°�►°d
o!�� o-�o
°��o o=d
O�a * o00 000 *�
a��� nEXA?o4o
APPROVAL RECONIl��lENDED :
�� �� �� �
C�opher Harder (J 28, 202615:59:3 CST)
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
of the date subscribed by the City's
& Newnam, Inc.
Just� �'.1Reeves, P. E.
Vice resident
DATE : January 22, 2026
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
i
/ ,. / ..
Jaikson Jacob
Project Manager
APPROVED AS TO FORM AND LEGALITY:
�vr❑C��
Douglas Black (Feb 2, 2026 13:43:59 CST)
Douglas W. Black
Sr. Assistant City Attorney
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 2 of 2
M&C No.#: N/A
M&C Date: N/A
�FFICIAL RECORQ
CITY SECRETARY
FT. WORTH, TX
&SS Contract 2019 WSM-=
_03380
� TM
��� L
January 21, 2026
City of Fort Worth � Water Department
Attention: Jaikson Jacob
100 Fort Worth Trail
Fort Worth, Texas 76102
RE: REQUEST FOR CONTRACT AMENDMENT No. 3
City of Fort Worth Project Number 103380
City Sec Number: 57155
Water & Sanitary Sewer Replacement Contract 2019, WSM-L — Project Number 103380
Dear Mr. Jacob:
The following amendment is submitted to support additional engineering services requested by
the City of Fort Worth (City) to separate the WSM-L project into two (2) separate construction
contracts at the 90% design phase. The additional design effort rendered requires additional
engineering design for 90% and 100% plans preparation, bid phase services, and construction
phase services. The task/hour breakdown for specific activities within this requested
Amendment 3 is attached; however, in summary, the following items are included in this request
of $81,120.00.
• Additional Engineering Services ($81,120.00) for engineering redesign:
Additional Engineering
Services
Engineering Design
Bid Phase Services
Construction Phase Services
Cost ($)
$ 37,010.00
$ 15,150.00
$ 28,960.00
Total Cost
CONTINUED ON THE NEXT PAGE
$ 81,120.00
1300 Summit Avenue, Suite 300 � Fort Worth, TX 76102 � 817.820.0420 � Fax: 817.820.0441 � www.lan-inc.com
-1-
� TM
��� �
The following presents the project fee summary to date, including this request:
Original Contract
Amendment No. 1
Amendment No. 2
Amendment No. 3
$
$
$
$
485,380 �
261,093 �
167,774 �
87,720 I
�
995,367 I
Revised Contract Amount $
Please review this as a formal request to consider and process Amendment 3 to City
Project Number 103380 in the amount of $87,120.00. Should you require further
information for this request to support your consideration or have any questions, please contact
me at 817-338-7512.
Respectfully submitted,
.
/ ' I
Project Manager
ROJohnson@lan-inc.com
CC: Tony Sholola, P.E.
Attachments: CPN 103380, Amendment No. 3— Level of Effort (1 Page)
1300 Summit Avenue, Suite 300 � Fort Worth, TX 76102 � 817.820.0420 � Fax: 817.820.0441 � www.lan-inc.com
-2-
Task No. Task Description
1.0 Prqect Management
2.0 Route Analvsis
Amendment#3
Level Of Effort Task/Hour Breakdown
Additional Services for Water and Sanitary Sewer Replacements Contract 2019, WSM-L, Part 2
City of Fort Worth - Water Department
City Project No. 703380
Labor(hours� Expeqse Total Task
Project Sr. Project Project Total Labor �^_� Subconsultant Expense Sub % Complete Budget Remaining
Principal Manager Engineer Engineer EIT CADD Admin SBE Non-SBE Travel Reproduction Cost 7otal
Kate $290 $230 $230 $145 $125 $135 $1��
- S - S - S - S - S - E - S #oivlo! E
- $ - $ - $ - $ - $ - E - S 0% E
- S - S - S - S - S - E - 8 xoivla! S
- S - 8 - 8 - 8 - S - E - S uoivio! S -
� 30.0 3.0 62.0 78.0 60.0 3.0 $ 36,900 $ - $ - $ - $ 100 b 110 $ 37,010 0% b 37,010.00
5 � Prepare and Submit Final Draft (90%) & Construction (100 %) PS&E 30.0 3.0 62.0 78.0 60.0 3.0 $ 34,850 $ -$ -$ -$ -$ -$ 34,850 0%� $ 34,850
5.1.1 90% Final Design Meetin $ - $ - $ - $ - $ - $ - $ 0% $ -
5.1.2 Utillt Confllct Matrix S lit 2.0 4.0 12.0 $ 2,550 $ -$ -$ -$ -$ -$ 2,550 0"/0 $ 2,550
5.1.3 Prepare and Submlt Final Draft 90% PS&E 6A 20 12.0 24.0 36.0 1.0 $ 11,550 $ -$ -$ -$ -$ -$ 11,550 0"/0 $ 11,550
5.1.4 Prepare and Su6mlt Final (100% ) PS&E 6.0 8.0 16.0 24.0 1.0 $ 7,900 $ -$ -$ -$ -$ -$ 7,900 0"/0 $ 7,900
5.1.5 Part2Specificatlons 6D 16.0 1.0 $ 3,800 $ - $ - $ - $ - $ - $ 3,800 0% $ 3,800
5.1.6 Part 2 Utility Clearance Coordlna[ion 2.0 8 0 6 0 $ 2,400 $ -$ -$ -$ -$ -$ 2.400 0% $ 2,400
5.1.7 Part 2 Publlc Meeting Preparation $ - $ - $ - $ - $ - $ - $ 0 %� $ -
5.1.8 Part 2 Engineer Opinion of Probable Constmction Cost 4.0 1 0 8.0 12.0 $ 3,850 $ -$ -$ -$ -$ -$ 3,850 0%� $ 3,850
5.1.9 TPW Coordination and Modifications 4.0 6.0 8.0 $ 2,800 $ -$ -$ -$ -$ -$ 2,800 0% $ 2,800
5.2 Prepare for, Atlend, 8 Respond to Review Meetinqs - 2.0 - 4.0 8.0 - - $ 2,050 $ -$ -$ -$ 100 $ 110 $ 2,160 0%� $ 2,160
6.0 Bid Phase Services - 11A 2.0 36.0 24.0 20.0 10.0 $ 15.150 $ -$ -$ -$ - E - S 15.150 0% E 15,150.00
6.1.3 Receive Bldder Questions and Issue Adc
6.1.4 Tabulate Blds and Recommend Award
6.2 Preoare and Issue Conformed Documents
7.1.2 Prepare Exhlbits and Attend Public Meetings (i)
7.1.3 Support Submittal Review, Response, and Conshuction Site Visit
7.1.4 Maintain Submittal Log
7.L5 Respond to Contractor Requests for Clarification
Review Lab Results for Compllance with Clty Specrficahons and
7.1.6 Pravide Reports
7.17 Attend Flnal ProjectWalk Through
7.2 Prepare and Submit Record Drawinqs
8.0 ROW/Easement Services a - a - a - a
9.0 Survey antl Subsurface Utility Engineering Services $ -$ -$ -$
SUBTOTAL(WITHOUTALLOWANCES) 75.0 5.0 184.0 132.0 104.0 28.0 $ 80,900.00 $ $
I
10.0 Allowances $ - $ - $ - $
10.1 Additional Deslgn Services (As directed by City) - - - - - - - $ - $ - $ - $
75.0 5.0 184.0 132.0 104.0 28.0 $ 80,900.00 $ $ $
Projecl Stats Description Water Sewer
W ater Line Footage 9,370 66 % 31 - Conceptual Design (30 %) $0.00 $0.00
Sewer Line Footage 4725 34 % 32 - Preliminary Design (60 %) $0.00 $0.00
7otal 14,095 100% 33-FinalDesign(100%) $34,674.65 $17,485.35
42-Negotiations/Easements/LegalFees $0.00 $0.00
(A) Total Fee $ 81,120.00 51 -Preliminary5urvey $0.00 $0.00
85 - Construction Services $19,251.88 $9,708.12
Water Fee 66 % of A Sewer Fee 34 % of A Subtotal $53,926.53 $27,193.47
$ 53,926.53 I $ 27,193.47 I Total(w/o Additional Services) $81,120.00
Total (Including Additional Services) $87,120.00
4.0 8.0 16.0 120 $ 6,700 $
4.0 8.0 16.0 12.0 $ 5,700 $
'�4.0 86.0 30.0 24.0 15.0 $ 28,850 $
'AD 74.0 30.0 13.0 $ 22,750 $
2.0 2.0 2.0 2.0 $ 1,200 $
20 4.0 1.0 $ 1,150 $
4.0 24.0 16.0 2.0 $ 6,600 $
2.0 - 12 0 - - 1 0 $ 2.300 $ -
11
150
1
0%� $ 9,450
0%I $ 1,700
0%I $ 1,400
�'� I $ 3,750
0"/0l $ �,600
0"/0� $ 5,700
0'% I $ 5.700
4 � E 28,960.00
0 % $ 22,750
0"/0 $ 1,200
0"/a $ 1,160
0% $ 6,600
0% $ 2,300
0%� $ 4,600
0% $ 2,200
0'% $ 4,700
0% $ 6,210
$ - $ - $ -I �$ -
�
$ 200.00 $ 220.00 $ 81,120.00 #DIV/0! $ 81,120.00
Project Summary
Total Hours 528
TotalLabor � 80,900
Total Ex ense 220
Na�_�������g�o�s�?�'� $ -
10% SubMarkup $ -
MBE/SBEParticipation 0.0%
Total Project Cost $ 81,120.00
F�RT��RTHo
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Lockwood, Andrews & Newnam, Inc.
Subject of the Agreement: Water and Sanitary Sewer Contract 2019 WSM-L
M&C Approved by the Council? * Yes ❑ No ❑✓
If �so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑✓ No ❑ 57155-A3
If �so, provide the original contract number and the amendment number.
Is the Contract "PermanenY'? *Yes 0 No ❑
If �unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No ❑✓ If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 1/22/2026 Expiration Date: N/A
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No ❑✓
*If �so, please ensure it is attached to the approving M&C or attached to the contract.
Proj ect Number: If applicable. 103380
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ❑✓ No ❑
Contracts need to be routed for CSO processin� in the followin� order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.