HomeMy WebLinkAbout056320-A2 - Construction-Related - Contract - Arredondo, Zepeda & Brunz, LLCCSC No. 56320-A2
AMENDMENT No . 2
TO CITY SECRETARY CONTRACT No. 56320
WHEREAS, the City of Fort Worth (CITY) and Arredondo, Zepeda & Brunz., LLC,
(ENGINEER) made and entered into City Secretary Contract No. 56320, (the CONTRACT)
which was authorized by M&C 21-0538 on the 3rd day of August, 2021 in the amount
of $ 302,590.50; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No. 1 in
the amount of $39,081.85 administratively authorized on May 22nd, 2024; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Sanitary Sewer Rehabilitation Contract 118, CPN 102789; and
WHEREAS, it has become necessary to execute Amendment No. 2 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $ 7,847.36. (Water: $941.68 ; Sewer: $6,905.68)
2.
Article II of the CONTRACT is amended to provide for an increase in the
fee to be paid to Engineer for all work and services performed under the
Contract, as amended, so that the total fee paid by the City for all work and
services shall be an amount of $349,519.71.
OFFICIAL RECORD
CITY SECRETARY
3 • FT. WORTH, TX
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
City of Fort Worth, Texas Sani�a-�y Se��.aer Rehab Ccr�ract 118
Prof Services Agreement Amendment Template 1C2,u9
Revision Date: June 13, 2025
Page 1 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City's designated
Assistant City Manager.
APPROVED:
City of Fort Worth
;�
Jesica McEachern
Assistant City Manager
02/08/2026
DATE:
ATTEST:
�����A
/J .Jo�_��x
Jannette Goodall
City Secretary
�p4�a�nu
bb F�RT���
� OF�°° °o �L dd
v �� o �O��I�d
�o
°��o �=o
p�p'f °oo �° �`d
a�° p
a� �'EXA54ba
�nnaaoo
APPROVAL RECONIl��NDED :
Cl��rJto,�G��� �fa��f��
Christopher Hard�r (Feb 2, 2026 1328:15 CST)
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
Arredondo, Zepeda & Brunz, LLC.
�
Al onso P. G za, P.E.
Managing Principal
DATE : 2-2-2OZG
By signing, I acknowledge that I am the person responsible for the monitoring
and administration of this contract, including ensuring all performance and
reporting requirements.
a� �
02/02/2026
Parvathi Sreekumaran Unnithan, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY:
`�P���'IL��
Douglas Black (Feb 3, 2026 17:57:07 CST)
Douglas W. Black
Sr. Assistant City Attorney
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 2 of 2
M&C No.#: N/A
M&C Date: N/A
�FFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Sanitary Sewer Rehab Contract ll8
1C�789
����_:,=�
.—.�..�■
a� � ARDURRAcomne�y
December 16, 2025
Parvathi Sreekumaran-Unnithan, PE
City of Fort Worth Water Department
100 Fort Worth Trail
Fort Worth, TX 76102
Re: Water and Sanitary Sewer Replacement Contract 118
City Project No. 102789
Amendment No. 2
Ms. Sreekumaran-Unnithan:
AZ&B proposes to perform the following additional tasks requested by the City of Fort Worth Water Department that
were not originally included in the project scope:
• Perform a walkthrough of each water or sanitary sewer replacement segment to identify any major above ground
structures or constraints (i.e. Vaults) built after topographic survey was done in Fall 2021— Winter 2022 that could
impact the utility alignments.
• Any major above ground structures or constraints identified during site walkthroughs will be generally located in the
design plans.
• Update property owner names on the plans for lots within the replacement project limits that are found to have
been sold since initial deed research was done in Fall 2021— Winter 2022.
• Compile property owner addresses for public meeting. Ardurra will obtain current property owner names from the
Tarrant County Appraisal District GIS map. Generally, research limits will extend one block beyond the beginning
and end points of each water or sanitary sewer replacement segment. Approximate limits shall be as indicated by
the Water Department on aerial maps provided by email September 17, 2025. Addresses for community facilities
near the project limits that may be impacted by street closures, including schools and churches will be included. For
apartment complexes or condominiums, only the main office address will be included.
Deliverables
• Property owner address list using Microsoft Excel file provided by the Water Department.
• Changes in property ownership and improvements/changes identified as potentially having an impact on
construction during site walkthroughs will be shown on the final review submittal before the project is advertised.
Not Included in this Scope and Fee
Notification letters to property owners. These will be mailed by the City of Fort Worth.
Additional topographic or right-of-way survey.
The additional lump sum fee requested for the additional design effort identified above is $7,847.36 as summarized in the
table below.
I Task Description
I Additional Design Effort
Compile Property Owner Addresses for
Public Meeting
I TOTAL AMENDMENT #2
Water Fee
$821.30
$120.38
$941.68
Sewer Fee
$6022.86
$882.82
$6,905.68
Tota I
$6,844.16
$1,003.20
$7,847.36
����_:,=�
.—.�..�■
a� � �RDURRAcomne�y
Please refer to the attached Scope of Services and Task/Hour Breakdown for additional details.
The adjusted overall contract amount will be as follows
�
I ORIGINAL CONTRACT
I AMENDMENT#1
I AMENDMENT#2
I TOTAL
Sincerely,
Arredondo, Zepeda & Brunz, LLC
� A�t"S° � � /ani v
Alf �so P. Garza,'��E, RPLS
Water Fee Sewer Fee Total
$36,182.21 $266,408.29 $302,590.50
$0 $39,081.85 $39,081.85
$941.68 $6,905.68 $7,847.36
$37,123.89 $312,395.82 $349,519.71
Managing Principal
agarza@ardurra.com
(214) 908-7493
Task Description
Rat�
Additional Water and SaniWry Sewer Design Effort
Pertorm walkthrough of each replacement segment to idenfiy ma�or above ground
structures or constraints (i.e. Vautts) buitt after topographic survey that wuld impact
[he utiliry alignments
Locate major above ground stmctures or constraints in design plans
Update property owner names on the design plans for properties sold after initial deed
research
Compile Property Owner Addresses for Public Meeting
Research Tarran[ Counry Appraisal Distnct GIS Map
Compile Properry Owner Address List for Public Meeting
Cretlit for Public Meeting Hours Alreatly Billetl Untler 60 % Milestone
Ciry of Fort Worth, Texas
Attachment B- Level of Effor[ Supplement
PMO Official Release Date: 8.09.2012
Level of Effort Spreadsheet
Additional Services
TASK/HOUR BREAKDOWN
Water Department Design Services for
Sanitary Sewer and Water Rehabilitation Contract 118
City Project No. 102789 - Amendment No. 2
�bor(hou s) I
Senior Senior P ect Pro'ect Sen
Project roj � E�T ior Technician ToWI Labor
,__ ____ Enginee� Manager Enginee� Technician I
8 8 � 3
4 S I �
2 4 1
0 4 18 0 0 1
4 10
e I 1
Subconsultant E�{pense
Subconsukant I Total Expense Task Sub ToWI % Complete Remaining
Reproduction Cost Budget
NBE SBE
0.00 0.00 0.00 0.00 6,844.16 0/ $6,844.16
I
0%� $1,003.20
7,847.36� 0%
ect Summary
Total Hours
Total Labor
Total ExpeR �ey@E y �( (
M S&E Su�consuNanf
MBE/SBE Partiapa0on
Total Project Cost
56
$7,847.36
$0.00
0
$o.00
0.0 %
87,847.36
�
FORT ��RTH�
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name
Arredondo, Zepeda & Brunz., LLC
Subject of the Agreement: Sanitary Sewer Rehabilitation Contract 118, CPN 102789
M&C Approved by the Council? * Yes ❑ No 0
If �so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ 56320-A2
If so, provide the original contract number and the amendment number.
Is the Contract "PermanenY'? *Yes 0 No ❑
If �unsure, see back page for pernianent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: N/A Expiration Date: N/A
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No 0
*If �so, please ensure it is attached to the approving M&C or attached to the contract.
Proj ect Number: If applicable. 102789
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processin� in the followin� order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.