HomeMy WebLinkAbout055405-FP3 - Construction-Related - Contract - Chris Harp Construction, LLCFORTWORTH�
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Hanna Ranch Two
City Project No.: 102443
Improvement Type(s): ❑x Paving ❑ Drainage ❑ Street Lights ❑ Turn Lane
Original Contract Price: $712,901.00
Amount of Approved Change Order(s)
Revised Contract Amount:
Total Cost of Work Complete:
��4 i/'yl ,�A�.O.
�tfi J(1�f15 <;ST',
Contractor
Vice President of Estimating
Title
Chris Harp Construction, LLC
$27,572.50
$740,473.50
$740,473.50
02/11/2026
Date
Company Name
G���e��
Project Inspector
�
Project Manager
e���
CFA Manager
����
Lauren Prieur (Feb 12, 2026 11 �.44�.57 CST)
TPW Director
-FP3
City Secretary 55405
Contract No.
Date Received 2�12/2026
AT
02/11/2026
Date
02/12/2026
Date
02/12/2026
Date
02/12/2026
Date
QFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name: Hanna Ranch Two
City Project No.: 102443
City's Attachments
Final Pay Estimate ❑x
Change Order(s): 0 Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
��
Consent of Surety �
Statement of Contract Time
Contract Time: 100 WD Days Charged: 100 WD
Work Start Date: 4/7/2021 Work Complete Date: 8/25/2025
Completed number of Soil Lab Test: 282
Completed number of Water Test: 16
Page 2 of 2
F���r ���Tx
CITY OF FORT WORTH
F1NAL PAYMENT REQUEST
Contract Name HANNA RANCH TWO
Contract Limits
Project Type PAVING
City Project Numbers 102443
DOE Number 2443
Estimate Number 1 Payment Number 1
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor CHRIS HARP CONSTRUCTION , LL,C
17388 CR 543
Inspectors
NEVADA � TX 75137
GLOVER / FUENTES
For Period Ending 8/25/2025
WD
Contract Time l O�JD
Days Charged to Date 100
Contract is 100.00 Complete
Friday, January 9, 2026 Page 1 of 4
City Project Numbers 102443
Contract Name HANNA RANCH TWO
Contract Limits
Project Type PAVING
Project Funding
UNIT N: PAVING
DOE Number 2443
Estimate Number 1
Payment Number 1
For Period Ending 8/25/2025
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
1 6" CONC PVMT (CO#2) 5410 SY $45.90 $248,319.00 5410 $248,319.00
2 7.5" CONC PVMT(CO#2) 3935 SY $54.75 �215,441.25 3935 $215,441.25
3 6° LIME TREATMENT 7700 SY $3.65 $28,105.00 7700 $28,105.00
4 8" LIME TREATMENT 4100 SY $3.65 $14,965.00 4100 $14,965.00
5 HYDRATED LIME @ 32LBS 146 TN $175.00 $25,550.00 146 $25,550.00
6 HYDRATED LIME @ 32LBS 78 TN $175.00 $13,650.00 78 $13,650.00
7 6" CONC PVMT iJNREINFORCED 1790 SY $55.00 $98,450.00 1790 $98,450.00
8 5" CONC SIDEWALK (CO#2) 7053 SF $5.75 $40,554.75 7053 $40,554.75
9 FURNISH/INSTALL SIGN POST & FOLTNDATION 4 EA $435.00 $1,740.00 4 $1,740.00
10 FURNISH/INSTALL SIGN POST & FOLTNATION 1 EA $355.00 $355.00 1 $355.00
W/NAME BLADES
ll TRAFFIC CONTROL 1 LS $3,500.00 $3,500.00 1 $3,500.00
12 REMOVE CONC PVMT (CO#2) 0 SY $25.00 $0.00 0 $0.00
13 CONC PVMT REPAIR(CO#2) 0 SY $56.50 $0.00 0 $0.00
14 REMOVE ASPHALT PVMT(CO#2) 0 SY $25.00 $0.00 0 $0.00
15 ASPHALT PVMT REPAIR BEYOND DEFINED 133 SY $105.00 $13,965.00 133 $13,965.00
WIDTH(CO#2)
16 CONC RET WALL ADJACENT TO SIDEWALK 615 LF $40.00 $24,600.00 615 $24,600.00
17 CON TO STR HEADER AND SALVAGE 4 EA $750.00 $3,000.00 4 $3,000.00
BARRICADE
18 6" CONC PVMT (READY MIX) (CO#2) 80 SY $67.65 $5,412.00 80 $5,412.00
19 7.5" CONC. PVMT (READY MIX) (CO#2) 35 SY $81.90 $2,866.50 35 $2,866.50
Sub-Total of Previous Unit $740,473.50 $740,473.50
Friday, January 9, 2026 Page 2 of 4
City Project Numbers 102443
Contract Name HANNA RANCH TWO
Contract Limits
Project Type PAVING
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 2
Total Contract Price
DOE Number 2443
Estimate Number 1
Payment Number 1
For Period Ending 8/25/2025
��12,9oi.00
�z�,s�2.so
$740,473.50
Total Cost of Work Completed $740,473.50
Less % Retained $0.00
Net Earned $740,473.50
Earned This Period $740,473.50
Retainage This Period �0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$740,473.50
Friday, January 9, 2026 Page 3 of 4
City Project Numbers 102443
Contract Name HANNA RANCH TWO
Contract Limits
Project Type PAVING
Project Funding
Project Manager NA
InspeCtors GLOVER / FUENTES
Contractor CHRIS HARP CONSTRUCTION , LLC
17388 CR 543
NEVADA, TX 75137
Line Fund Account Center
DOE Number 2443
Estimate Number 1
Payment Number 1
For Period Ending 8/25/2025
City Secretary Contract Number
Contract Date
Contract Time 100 WD
Days Charged to Date 100 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Amount Gross Retainage
Funded
Total Cost of Work Completed
Less % Retained
Net Earned
Earned This Period $740,473.50
Retainage This Period �0.00
Less Liquidated Damages
� Days @ $0.00 / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
Net
$740,473.50
$0.00
$740,473.50
$0.00
$0.00
$0.00
$0.00
$0.00
$740,473.50
Friday, January 9, 2026 Page 4 of 4
Hanna Ranch Two
DEVELOPER-AWARDED-PROJECT CHANGE ORDER
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
DOE #
FID #
FILE #
Hanna Ranch Two
Water, Sewer, Drainage (A), Paving (B), Street LightS (C)
CFA20-0090 � CITY PARTICIPATION:I
102443
N/A
30114-0200431-102443-E07685
X-26283, W-2672
CHANGE
ORDER No:
No
1
INSPECTOR: Christobal Fuentes Phone No: (817) 392-2222
PROJECT MANAGER: Yogesh Patel Phone No: (817) 392-2373
CONTRACT UNIT
WATER SEWER DRAINAGE PAVINC� STREET LIGHTS CONTRACT
DAYS
Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost
ORIGINAL CONTRACT $235,4D7.67 $262,927.50 $146,413.25 �y712,901.00 $100,137.20 35
EXTRAS TO DATE
CREDITS TO DATE �_
CONTRACT TO DATE $235,4D7.67 �
AMOUNT OF PROP. CHANGE ORDER $32,918.50 �
REVISED CONTRACT AMOUNT $268,326.17
TOTAL REVISED CONTRACT AMOUNT
PER UNIT $268,326.17
REVISED COST SHARE Dev. Cost:
TOTAL REVISED CONTRACT
$262.927.50 _� $146,4'13.25 =
$11,166.43 � �
$274,113.93 $146,413.25
$274,113.93 $146,413.25
$1,501,891.55 City Cost:
$1,501,891.55
_, - �.- ��
$712,901.00 �_ $'100,'137.20 �
� �
$712,901.00 $100,137.20
$712,901.00 $100,137.20
35
35
REVIEWED
By Shawn Garner, PE at 8:49 am, May 06, 2025
Revised: 10-12-201 I Page 1
Y�� are o�reCee to make the `a��aorin� ci,ar•aes �r ,ne co�tra� ao:.umenu
I CITY BID ITEM
PAY lTcM iF # �UANTlTY UNff
� I-8 3372.2Q03 -2.0 EA
1-13' 3305. t i 02 45.6 LF
II t-�<• �ss.000� ? o Fa I
i II`1� � 5999.C�2 j 10 ` EA
f
I I!-i2' 23.�'i.� I SF �
I -
Asferisk (•) indicates new pay item
REASONS FOR CliANGE ORDER
ITEM D�S.^.RIP ,-1,^.�:
1� Wri[P.f SGNiC�£
� 8� (�.35lt:C L%V m11G( T11�1 fJ'JCn r.Ui
`wJ,�j�rSenncetocx�xv?n'M W Bore
4� IY7R�7.'�
;AasshoSe Va�(um �estinc
RemrnrP ar.� �iealace Exis2inc Corsuete P-evement
T07AL - - �
UN{TPRfCE � TQ'�;L
S782.?0 -S � S65.a0
5432.a2 S79.455.9�
57.512.50 � S75.025.CJ
S3.0�2.0� � S3.Ob2.CC
S�2E�s S728.75
533.88 57.995.68
544.104.93
�-�S Quanti7� reduced tc ad9 lter,: !- tti
1-'3' b»ssing Irom cic Quznt;;res
!-T�' :flSS=nfy` 5'G^- aiC' wJ2r�!;:;ES
!(-4 N,�'SSi.^.a FG.^7 Sew' l,r.:3•^•i:".�QS
ll-�D �issrng.'ro,^.� B,"o Quant':es
1i-12' Pdissmg f.�.�-r 8r� Quan:'ines
NO ClTY FUNDS fNVOLVcD IN THIS GO�tFRACT. CEVE�OPER iS RESt�ON51BLE FOR tOD i� OF THE GHAItiGE ORDER COST ANO NC
f2ElMBURSEMENT FRONi THE CITY Wf! L�E SOUG!iT BY T1�E DEVELOPER.
RECOMMENDED:
Hu:^-2ciiars
sv � ���L�--
Name: Jordan Marlia
TiUe: Desiqn Enqmeer
APPROVED:
.4czdemy .�7eva+�pme,�t
sY �
/
Name: Kyle IGricland
Title: Area Land Develooment Manaae�
APPROVED:
C l•V Y��ng �^�^S: ��::,, ']�
�Y ��/ f +G� ��C.G[li���
c �-
Name: Trey Stewan.
Title: Gene2t Manaoer
Rewsed. 1 �12-2611 Pa9= 2
Hanna Ranch Two
DEVELOPER-AWARDED-PROJECT CHANGE ORDER
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
DOE #
FID #
FILE #
INSPECTOR:
PROJECT MANAGER:
Hanna Ranch Two
Water, Sewer, Drainage (A), Paving (B), Street LightS (C)
CFA20-0090 � CITY PARTICIPATION:
102443
N/A
30114-0200431-102443-E07685
X-26283. W-2672
CHANGE
ORDER No:
No
�
Christobal Fuentes Phone No: (817) 392-2222
Yogesh Patel Phone No: (817) 392-2373
CONTRACT UNIT
WATER SEWER DRAINAGE PAVING STREET LIGHTS
Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost Developer Cost City Cosf Developer Cost City Cost
ORIGINAL CONTRACT $235,407.67 $262,927.50 $146,413.25 $712,901.00 y100,'137.20
EXTRAS TO DATE $32,9'18.50 $11,186.43
CREDITS TO DATE �, �_ i, �
CONTRACT TO DATE $268,326.17 � $274,113.93 � $'146,413.25 � $712,901.00 � $100,137.20 �
AMOUNT OF PROP. CHANGE ORDER $782.7D � � � $27,572.50 � �
REVISED CONTRACT AMOUNT $269,106.87 $274,113.93 $146,413.25 $740,473.50 $100,137.20
TOTAL REVISED CONTRACT AMOUNT
PER UNIT $269,108.87 $274,113.93 $146,4'13.25 $740,473.50 $100,137.20
REVISED COST SHARE Dev. Cost: $1,530,246.75 City Cost:
TOTAL REVISED CONTRACT $1,530,246.75
CONTRACT
DAYS
35
35
14
49
. .
REVIEWED
By Shawn Garner, PE at 8:52 am, May 06, 2025
. .
Revised: 10-12-20 � 1 Page �
DocuSign Envelope ID: 021BDD46-649D-4B93-B7BF-6EEA3F6CEEB6
Hanna Ranch Two
You are directed to make the following changes in the contract documents:
PAY ITEM # CITY BID ITEM # QUANTITY UNIT
A WATERI
I-B � 1- 8 I 1.00 � EA � 33� 2.2003 �" ater Service
IV -1
IV-2
IV-7
IV - 'I2
IV-13
IV-14
IV-15
IV-18
IV-19
REASONS FOR CHANGE ORDER
4- 1
4- 2
4- 7
4- 12
4- 13
4- 14
4- 15
NEW 18
NEW 19
-80.00
-35.00
5,203.00
-80.00
-80.00
-96.00
37.00
80.00
35.00
SY
SY
SF
SY
SY
SY
SY
SY
SY
ITEM DESCRIPTION
D (PAVING)
3213.010'I 6" Conc Pvmt
9999.0005 7.5" Conc Pvmt
32�3.0302 5" Conc Sidewalk
0241.1000 Remove Conc Pvmt
3201.0614 Conc Pvmt Repair, Residential
0241.11 DO Remove Asphalt Pvmt
3201.0202 AsPhalt Pvmt Repair Be�. ond Defined Width, Arterial
9999.0012 6" Conc Pvmt (Ready Mix)
9999.0013 7.5" Conc. Pvmt (Ready Mix)
UNIT PRICE
$762.70
A( ATER)TOTAL
545.90
$54.75
�5.75
$25.00
$56.50
$25.00
$105.00
$67.65
$81.90
D ( AVING) TOTAL
TOTAL
$762.70
$762.70
�3.0%2.00
-51,916.25
$29,917.25
-�_. 000.00
-,= szo.oe
-52400. GC
�3,865.00
$5,412.00
�2, 866.50
$27,572.50
1 1-8 Added 1" Irrigation meter 4 IV-7 Missing f�om Bid Quantities 7 IV - l4 Item no /onger needed
2 IV - 1 Replaced by ready-mix conc. 5 IV - 12 Item no longerneeded 8 IV-15 Missing from Bid Quantities
3 IV - 2 Replaced 6y ready-mix conc. 6 1V - 131tem no longerneeded 9 IV - 18 Added ready mix conc.
10 IV - 19 Added ready mix conc.
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100 % OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER.
RECOMMENDED:
, �.
B . Ja►da.�. V . Mr.�G�c
79666E03C412442...
Name: Jordan V. Marlia, P.E.
Title: Project Manager
APPROVED:
Academy bned by.
y:��. �►�c�.,c
E97F76CAC18A4F3...
Name: Kyle Kirkland
Title: Area Land Development Manager
APPROVED:
C.W Youg �q�Le9�Y
B : .�e� U1itti.�l,�,t.sft.v'
ABB1159D�B1F408...
Name: Joe Winchester
Title: General Manager
APPROVED:
Chns Harp C ns r��iN`,�SL'L� ey�
B„� J�� 1/IM' U�.l l
r�5653532D94944B7...
Name: Jamey Burchett
Title: Project Manager
Revised: '10-12-2011 Page 2
DocuSign Envelope ID: B2EEA28B-DOD2-436F-83C6-8649338A8F89
Hanna Ranch Two
DEVELOPER-AWARDED-PROJECT CHANGE ORDER
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
DOE #
FID #
FILE #
Hanna Ranch Two
Water, Sewer, Drainage (A), Paving (B), Street LightS (C)
CFA20-0090 I CITY PARTICIPATION:
102443
N/A
30114-0200431-102443-E07685
X-26283, W-2672
CHANGE
ORDER No:
No
3
INSPECTOR: Christobal Fuentes Phone No: (817) 392-2222
PROJECT MANAGER: Yogesh Patel Phone No: (817) 392-2373
CONTRACT UNIT
WATER SEWER DR.4INAGE PAVING STREET LIGHTS
Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost
ORIGINAL CONTRACT $235,407.67 $262,927.50 $146,413.25 $712,901.00 $100,'137.20
EXTRAS TO DATE $33,701.20 $11,186.43 $27,572.50
CREDITS TO DATE ,,,�, �, �. �. �'iE_
CONTRACTTODATE $269,108.87 � $274,113.93 �_ $146,413.25 � $740,473.50 _�_ $10D,137.20 �
AMOUNT OF PROP. CHANGE ORDER � � (5�,3'.9.92'i � � �
REVISED CONTRACTAMOUNT $269,108.87 $274,113.93 5743,093.33 $740,473.50 $100,137.20
TOTAL REVISED CONTRACT AMOUNT
PER UNIT $269,108.87 $274,113.93 $'143,093.33 $740,473.50 5100,137.20
REVISED COST SHARE Dev. Cost: $1,526,926.83 City Cost:
TOTAL REVISED CONTRACT $1,526,926.83
CONTRACT
DAYS
35
14
49
49
. a
REVIEWED
By Shawn Garner, PE at 8:53 am, May 06, 2025
Revised: 10-12-201'I Page 1
-B2EEA2gg-�OD2-436F-83C6-g649338A8F89
pocuSign �nvelope ID.
Hanna Ranch TWo
documen�:
.. ��
�-
— -. �
es in tne c��,.. _ UNIT C��n,.,,.. -
chan � Straighti Headw<
the foilowin9 QUANTIn 3349 3009 42
You are directen to make CIT�' g� JTEM# ��' EA .._ �— �
_100 �
PAY IiEM # 3 - `' � _�---�—.:...
lll 5— "� �
I
1= �.
page 2
�
{�evised:'10-12�2�11 _ � — -
DocuSign Envelope ID: B2EEA286-DOD2-436F-83C6-8649338A8F89
Hanna Ranch Two
REASONS FOR CHANGE ORDER
1 III - 5 Headwall removed for future phase
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100 % OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER.
RECOMMENDED:
DoeuSlgned by:
Huitt-Zollars, Inc.
Jd►�L�.,. V. M,��I:.E
By:
` / tlO00CUJlA IG99L...
Name: Jordan V. Marlia, P.E.
Title: Project Manager
APPROVED:
DoeuSlgned by:
Academy Deve pment ���
�U.
Bv:
y i r r oi,hi, i anrra...
Name: Kyle Kirkland
Title: Area Land Development Manager
APPROVED:
DoeuSlgned by.
C.W. Youg Cons ction, L.P.
,9ac. Ukwc(�.c,Sf�,r
ey:
�—Hnn n oau � n i raun...
Name: Joe Winchester
Title: General Manager
Revised: 10-�2-20� 1 Page 3
FORTWORTH��
TRANSPORTATION AND PUBLIC WORKS
August 25, 2025
Chris Harp Construction, LLC
17388 CR 543
Nevada, TX 75137
RE: Acceptance Letter
Project Name: Hanna Ranch Two
Project Type: Paving
City Project No.: 102443
To Whom It May Concern:
On August 25, 2025 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on August 25, 2025,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2084.
Sincerely,
�
Ahmed Musa, Project Manager
Cc: Cristobal Fuentes, Inspector
Mike Glover, Inspection Supervisor
Randy Horton, Senior Inspector
Andrew Goodman, Program Manager
Huitt-Zollars, Consultant
Chris Harp Construction, LLC, Contractor
Academy Development, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
AFFIDAVIT
STATE OF Texas
COIJNTY OF Collin
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Brian Cottle, Vice
President of Estimating Of Chris Harp Construction, LLC, known to me to
be a credible person, who being by me duly sworn, upon his oath deposed
and said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
CPN 102443 Hanna Ranch Phase 2 ' g improvements)
� BY
� �_ Brian Cottle, Vice President of Estimating
Sub,�cribed �nd swqfn J�1�'fore m� p'n thi,� date 9th of February, 2026.
Not�ary I�blic
Collin County, T
RY P� HANNAH HARP
�" y�� Pdotary ID #134604962
P h4y Commission Expires
''� o��J OGtober 16, 2027 �
- w.u,�„�..,�w��.� kii�.�,a� �,� ��. �� �, r ��
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
AIA DOCUMENT C707
OWNER C�f
ARCHITECT ❑
CONTRACTOR ❑
SURETY ❑
oTHER ❑ Bond # 118573H
PR0IECT: Hanna Ranch Two City Project No. 102443, Fort Worth
(name, address)
TO (Owner) Academy Development, INC
10410 Windemere Lakes Blvd
Houston, TX
77065
CONTRACTOR: Chris Harp Construction, LLC
ARCHITECT' S PROJECT NO:
CONTRACT FOR:
CONTRACT DATE: 12/18/2020
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(here insert name and address of Surety Company)
WestCeld Insurance Company
P O Box 5001
West�eld Center, OH 44251-5001
on bond of
(here insert name and address of Contractor)
Chris Harp Construction, LLC
17388 CR 543
Nevada, TX 75173
,SURETY COMPANY,
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall
not relieve the Surety company of any of its obligations to
(here insert name and address of Owner)
Academy Development, INC
10410 Windemere Lakes Blvd, Houston, TX 77065
,OWNER,
as set forth in the said Surety Company's bond
IN WITNESS WHEROF,
The Surety Company has hereunto set its hand this 6th day of February, 2026.
Westfield Insurance Company
Surety Company
�i�� ,.,� I�--
Attest
(seal):
Amy�er, Sr. Client Manager, Surety
Signature of Authorized Representative
Brady Wilson, Attorney-in-Pact
Title
NOTE: This fonn is to be used as a companion document to AIA DOCUMENT G706, CONi RACTOR'S AFFIDAVI7 OF PAYMENT OF DEBT A^df� C.'LAIM�,
Current Edition
AIA DOCUMENT G707 * CONSENT OF SURETY COMPANY TO FINAL PAYMENT *APRIL 1970 EDITION *A]A
1970 THE AMERICAN WSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE. NW WASHING'1'ON, D.C. 2006
WARNING: Unlicensed photocopying violates U.S. copyright laws antl is subject to legal prosecution.
THIS PQWER OF ATTORNEY SUPERCEQES ANY PREVIOUS POWER BEARING THIS SAME
POWER # AND ISSUED PRIOR TO 10/10124, FOR ANY PERSON OR PERSONS NAMED BELOW.
General
Power
of Attorney
CERTIFIED COPY
Westfield National Insurance Co.
Uhio Farmers Insurance Co.
Westfield Center, Ohio
Kr;ow ,4/l Men f�y Tnesa Pre.sents, That WESTFIELD lNSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIQ
FARMERS INSURANCE COMPANY, cof�parations, herein�ftar referreci ta individually as a"Company" and coflactively as `Companies," dufy
organized and existing under the laws of the 5tate of Ohio, and hauinc� its prir�cipai office in Westfield Center, Medina County, Ohia, do by thase
presents make, c�nstitute and appoint
TONY FIERRO, JOHNNY MOSS, JAY JdRDAN, JEREMY BARNETT, JADE PORTER, ROBERT G. KANUTH, JARRETT WILLSON,
JACK NOTTINGHAM, BRADY WILSON, BRENNAN WILLIAMSON, JAROD JAGGERS, CALEB HALE, RYAN COX, JOINTLY OR
SEVERALLY
of ROCKWALL and State of TX its tru� ar��d 1�1,vf�al Rttorney(s}-iri-Fact, with full p�wer and authority hereby conferred in its name,
plac.e ancl stead, to exer,ute, acknowledge and deliver any and all bonds, recognizances, undertakings, ar other instruments or contracts of
suretyship in any penal limit, ancl to bind any of the Cornpanies the��eby as fu(ly and to the �ame extent as if such bonds were signed by the
President, sealed with the corporate seal of the ap�licab[e Cnmpany and duly attested f�y its Secretary, hereby ratifying and confirming all that the
saici Attarney(sl-in-Fact may do in tPie pr�mises. Sai�! appointrnent is made under and by autf-iority of the followiny resolution adoptec! by the
Board of Dir�ectors af each af the WESTFIELD fNSURANCE COMPANY, WESTFIELd NATiONAL INSURANCE COMPANY ar�d OHIO FARMERS
INSl1RANCE COMPRNY:
"Be 1t Resolved, that the President; ar�ry Senior Executive, any Secretary ar any Fidelity & Surety Operations Executive or ather Executive sl7all
be and is hereby vesteci with full power ai�rd authority to a�point any� one or more suitable persons as Attorney�(sj-in-Fact to represent and act for
and �n bel�alf of the Corr�pany subject to the following provisior��s:
The Attorr,ey-rn-Fact may be given fulf F�ower anci a�athority for� and iri the nam� of and on behalf of the C�rripany, to execut�,, acknawlpdge and
deliver; any and all bonds, recognizances, contracts, agreements af indemnity and other conditional or obligatar�}� unciertak:ings and any and all
notices and documei�ts canceling or terminatinq the Com{�any's liability thereunder, and any such instruments so e;<ecuted by any such
Attor�ney-in-Fact shall be as bi��cling upon the Company as if signecl by the Fresident and sealed and attested by the Cor��orate Secretary."
"Be if Fur�ther Re�ol+,�ed, that the signature of any suc;h desic�nated per�on and the seal of the Company heretofore or 17eredfter affixed to ar�y
power �f attarney or any certific:ate relatiny thPreto hy facsirr�ile, and any pov�rer of attarney or cer[ificate bearin�3 facsimile siynatures or facsimile
seal shail be valid and binding upon the Company with respect to any bond or undertaking to which it is attached." (Each adopted at a meeting
f�eld on February 8, 2000�.
Ir1 Wiiness Whereof, WESTFfELD INSl1RANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY ar�d OHIO FARMERS INSURANCE
COMPANY have caused thase presents to be signed by tPieir National Surety Leader and Senior F�cecutive and their corporate seals to be hereto
�ffixPd this ldth day of OCTOBER A.D., 2024 .
C;orparate NM��9���l��y�`„
Seals •°��'S�1$�tjf�;'•
Affixed ; �`O; • � ��' . M1�`+'i
�(� 'i� �
= a° ��•i�4.L ro
�;,'Y'��'•,,, '7R ,,e' �'�.i
State of Ohio '"'�+�+��""
County of Medin� ss.:
.•"�.`��'i?Nf1?� Ir, �''�,
•_:�: ,..�,,
A y '
'�� SE�1L .�:��
iJ!• � ;
..* .
POWER NO. 4220012 14
Westfield Insurance Co.
UVESTFIELD INSURANCE COMPANY
;SiIIP,���'"'��. WESTFIELD NATIONAL INSURANCE COMPANY
q. '•y�",,:�_ OHIO FARMERS INSURANCE COMPANY
: u�........,� ;r,•
, ;�3
.
, ..a _ : _
►% i�<ie .i�e;= 6�t ¢'� �4 '
q• .o. • � .. ., . .
�,�;,,��,,,•�°�`�� By: _
Gary W. °Stumper, National Surety Leader and
Senior Execcrtive
On this 10th day of OCTOBER A.D., 2024 , before me personally came Gary W. Stumper ta me k.nown; who, being by me duly sworn,
dfd depose �nd �ay, that he re�ides in Medina, OH; that he is National Surety Leader and Senior Executive of UVESTFIELD INSURANCE
COMPANY, WESTFIELD NRTIONAL INSURANCE COMPANY and ONIO FARMERS INSURANCE COMPANY, the companies described in and tivhich
ex�cuted tf��e above instrumer�t: that he kna�vs the seals �f said Com�anies; that the seals affixed to said instrument are su�h cor�orate seals; that
th��y were s� affixed k�y order of the B�af�ds �f DirPr,t�rs of said Companies: anci that he signed t7is name thereto by like of�der.
Notarial
Seal
Affixed
State of Ohio
County of Medina
�•`'� R 1 A !� '',.
'���'\���1�J."•`4 �',
� � \ �% 9'
Z `= � ` =` r
. : �.:,,, .
ss.: � ' � • ��.r�:
4Tf Of �.
David A. Kotnik, Attornay at Law, Notary Public
My Commission Does Not Expire (Sec. 1�l.03 �hio Revised Codej
I, Frank A. Carrino, Secretary of WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY �nd OHIO FARMERS
INSURANCE COMPA��Y; do hereby certify that the above anci foregoing is a true anci carrect copy of a Power of Attorney, executed by said
Compar�iEs, whic,h is still in full force ar�d effec.t: and furthermore, the re5oluti�ns of the Boards of Directors, set out in the Power of Attorney are
irr full force and eifect,
1�7 Wit+?zss bVnc���e��f, I have hereunto set my hand anci affixeci the seals of sair� Companies at Westfield Center, Ohi�, this 6th day of
Feb.raacy A•`��� 2026 •
'���in�41N���h,, ���f14t�r�����
P��sust,�y ,, � ,�"�„�N�,L,;;'-,
#��� . ..C�•� `;'�.�- ..•� ',,
�. ' �; � i .. `'. ; C�. `:
i� • �• '�Q x ` ��• • • a '-
�L �,�,t�.. � � � ' � � ; SF�1I, : �,' `
�y,,�'•�.'�r` • `r$'� - : ,a:
����.,,.,,��� .* ..••�
.,, �,,,,,,.,.,
.�
��:. 1�48
+' a '�
�� ��.,..,,;,. � „�„�•�'��
�i�+l.y�/� � `
se�.�r�ry
Frank A. Carrino, Secretary
BPOAC2 (combined} (05-24)