HomeMy WebLinkAbout062398-CO2 - Construction-Related - Contract - Peachtree Construction, Ltd.CSC No. 62398-0O2
FoR,�� ,v
Project Name� 2025 Asphalt Resurfacing Contract 3
Client Project #(s)I 105639
Project
Description
Contractorl
City Project Mgr.
City of Fort Worth
Change Order Request
� City Sec # � 62398
Asphalt resurfacing at various locations
Peachtree Construction, Ltd � Change Order #I 2 I Datel
Iretomiwa Otuyelu � City Inspectorl
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
�Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
TPW
$3,605,084.95
$206,779.50
1 /26/2026
Stephen Barnard
Contract Time
Totals (CD)
$3,605,084.95 210
$206,779.50 30
$3,811,864.45 240
$46,702.50 170
$3,858,566.95 410
$0.00
Additional Funding (if necessary) $46,702.50 � � � � $46,702.50
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 7.03%
MAXALLOWABLE CONTRACTAMOUNT (ORIGINAL CONTRACT COST+ 25%) $4,506,356.19
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order will adtl new bitl items to increase the hot mix asphalt pavement section on Deen Road from 3 inches to 4 inches, and revise the subgrade stabilization material to Cement
due to CEMLIME material shortages and limitetl availability. The revised asphalt section will consist of 2.5" of Asphalt Type B and 1.5" of Superpave. This motlification was recommentled by
staff due to the high volume of truck traffic on Deen Road, the need to improve long-term pavement performance and durability, while allowing stabilization operations to proceed without
further delay. In addition, this Change Order includes a new bid item to replace damaged historic curb markers along Rivercrest Drive that are beyond repair, including associated curb and
gutter work, to preserve the historic features and restore functionality.
Time: The contractor has requested a total time extension of 170 calendar days due to the following impacts: 1- CEM-LIME material shortages: Limited availability and inconsistent supply of
CEM-LIME delayed subgrade stabilization operations, resulting in a 90 calendar-day impact to the project schedule. 2- Historic Curb Marker: Replacement of 3 historic curb markers and the
adjacent curb and gutter requires an atltlitional 15 calendar days to complete the specialized work. 3- Unanticipated shallow water main conflict: A shallow water main encountered along the
2000 block of Clinton Avenue preventetl the pulverization and subgrade work due to the risk of damaging the water main, impacting the project for 30 calendar days (October 23, 2025,
through November 24, 2025), until the water department lowered this water line. 4- Increased asphalt pavement thickness on Deen Road: The increased pavement section requires 20
calendar days for procurement of the additional materials and completion of pulverization and material removal, as well as 15 calendar days to install the two additional asphalt liks. Based on
these cumulative impacts, staff support the Contractor's request for an additional 170 calendar days to complete the work.
Cost: Staff have reviewed the contractor's proposed unit prices and compared them with pricing from recent, comparable projects. Based on this evaluation, the proposetl pricing is deemed
fair antl reasonable. Part of this Change Order will be funded using the remaining construction allowance.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
Contractor's Companv Name Contractor (Namel Contract Siqnature Date
Peachtree Construction Ltd
Inspector/lnspection Supervisor
�>a�, �.,.�,� a.r,i
Assistant Director (Dept)
k�,r,a,:.�� ( � (�!�q°�.1,�/ �.
J Barry Clark i ' _ __
Date Pro'ect and Contract Com liance Manac
02/02/2026 ��
02/09/2026 �'1'""
Date Director, Coni
02/10/2026 -�,; ��;�r
02/02/2026
Date
02/09/2026
Date
02/10/2026
t� �oz/ii/zoz6 ���;;,�; �oz/is/zozs �
Council Action if re uired
�9 nann M&C Number I NA � M&C Date Approved I NA I
ATTEST(
Jannette Goodall, City Secretary
poF Fo►tT�aa
v�'° �9pd
FF'o o�1d
OV8 o=C
pPp'f °oo ���`�
a�an nezpsbaa
�FFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT W(IRTH
-.�,_.�
Project Name � 2025 Asphalt Resurfacing Contract 3
ClientProject# � 105639
Contracrorl Peachtree Construction, Ltd
I I tM Ut5(:Klf' I IUN
4;i ;t4/1.UUU1 Irattic(;ontrol
49 0241.1700 Pavement Pulverization 12"
50 9999.0002 1.5" Asphalt Pvmt Superpave SP-D
51 9999.0003 2.5" Asphalt Pvmt Type B SDG-B)
52 9999.0004 Replace Historical Gurb Markers
53 3211.0600 Gement L 26 LBS/SY
City of Fort Worth
Change Order Additions
� City Sec # � 62398 �
�
IPMI Iretomiwa Otuyelu I Inspectorl Stephen Barnard I
Change Order Submittal #�2 Date � 1/26/2026 �
ADDITIONS
Utf' I
I f' W
TPW
TPW
TPW
TPW
TPW
U�t� Unrt Unrt Gost
9.UUUUUUUU MU $14,UUU.UU
16,500.000OOOOG SY $10.55
16,500.000OOOOC SY $14.55
16,500.0000000( SY $23.2U
3.0000000( EA $4,250.OU
215.0000000( TN $349.5U
TF'W
Sub Total Addihons
lotal �
$/U,UUU.UU�
$174,075.00�
$24Q075.00�
$382,800.00�
$12,750.00�
$75,142.50�
�
�
�
�
�
�
$954,842.50�
�
�
�
$954,842.50�
Change Order Additions Page 2 of 3
FoR�
Project Name � 2025 Asphalt Resurfacing Contract 3
Client Project # I 105639
Contractorl Peachtree Construction, Ltd
crty ot Fon wortn
Change Order Deletions
� City Sec # � 62398 �
�
� PMI Iretomiwa Otuyelu � Inspectorl Stephen Barnard �
Change Order Submittal # �2 Date � 1/26/2026 �
UtLt I IVNS
I I tM UtSI:FiIF' I IUN UtF' I
�5 yyyy.uuut Nspnan Navement tsase rtepair i Nvv
16 3Z1ZA900 Asphalt Grack Sealant I F'W
22 U241.1 /UU F'evertlent F'ulve�rzati0n 11" I F'W
24A 9999.100L 3" Asphalt F'vmt Superpave SF'-U I F'W
LS 5111.U1iU1 (:tMLIMt Cil SLLCSISY I F'W
45 9999.1000 Irrigation djustment & Lantlscape Ftepair Allowance I F'W
4fi yyyy.1UUS F'eving (;OnStfuCtiOn AllOwenCO I F'W
ury unrt umt cost
4UU.UUUUUUUU l:Y y44U.UU
100AOOOOOOU GA $4UAU
16,UUU.UUUUUUUU SY $tl.2b
16,000.000OOOOU SY $27.24
11U.UUUUUUUU IN $4;iU.UU
0.5000000U LS $5U,UUUAU
U.SUUUUUUU LS $1bU,UUU.UU
r�w
Sub I Ot91 Ue10ti0nS
i otai �
y1 /b,UUU.UU�
$4,UUU.UU�
$1;i2,UUU.UU�
$435,84U.UU�
$yU,:iUU.UU�
$25,ODU.UU�
$4b,UUU.UU�
�
�
�
1
I
$908,140.00�
�
�
�
$yUFi,14U.UU�
Change Order Deletions Page 3 of 3
FaRTVV�RTH�
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 2025 ASPHALT RESURFACING CONTRACT 3— CO 2
M&C:
Date:
To:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
11
12
13
CPN: 105639
Name
Lizbeth Medina
Peachtree Construction Ltd
Stephen Barnard
Daniel Roy
Iretomiwa Otuyelu
Zelalem Arega
Mary Hanna
Patricia Wadsack
Lauren Prieur
Doug Black
Jesica McEachern
Jannette Goodall
TPW Contracts
CSO: 62398—0O2
Department Initials
Bus-Sppt ��,';"t
Vendor JBc
,o�
TPW - Inspector �,
s,.�,� �w,�,�.�
TPW — Sr.Inspector ���, y
TPW � �
TPW Z� „
TPW hl�
TPW AD p(,'�/'
TPW Director xxv
Legal �
CMO �
CSO �
TPW
DOC#: 2
Date Out
02/09/2026
02/02/2026
02/02/2026
02/09/2026
02/09/2026
02/09/2026
02/10/2026
02/10/2026
02/10/2026
02/11/2026
02/16/2026
02/17/2026
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
L�LS� L1Si: - Bus Sppt: Lizbeth Medina; Prg Mgr.: Zelalem AreQa; Sr CPO — Mary Hanna
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and
take the next steps.
NEEDS TO BE NOTARIZED: ❑YES �No
RUSH: ❑YES �No SAME DAY: ❑YES ❑No
ROUTING TO CSO: �YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
� Signature/Routing and or Recording
❑ Comment
❑ File
NEXT DAY: ❑YES ❑No
❑ Attach Signature, Initial and Notary Tabs
Return To: Please notify TPWContracts(�a,fortworthtexas.�ov for pickup when complete. Call ext. 7233 or ext.
8363 with questions. Thank you!
FORT ��RTH�
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Peachtree Construction, Ltd.
Subject of the Agreement: Change Order No. 2 to CSC No. 62398, a Contract for the 2025
Asphalt ResurFacing Contract 3 Project
M&C Approved by the Council? * Yes ❑ No 8
If �so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "PermanenY'? *Yes 8 No ❑
If �unsure, see back page for pernianent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: Expiration Date:
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No 8
*If �so, please ensure it is attached to the approving M&C or attached to the contract.
Proj ect Number: If applicable. 105639
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processin� in the followin� order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.