HomeMy WebLinkAbout062766-CO5 - Construction-Related - Contract - McCarthy Building Companies, Inc.CSC No. 62766-005 DEVELOPER-AWARDED-PROJECT CHANGE ORDER PROJECT NAME: CONTRACT: CFA # CITY PROJECT # CITY SECRETARY CONTRACT # FID # X# FILE # INSPECTOR: PROJECT MANAGER: ORIGINAL CONTRACT DEVELOPER CONTINGENCY TO DATE AMENDMENTS TO DATE CREDITS TO DATE CONTRACTTO DATE AMOUNT OF PROP. DEVELOPER CONTWGENCY REVISED CONTRACT AMOUNT TOTAL REVISED CONTRACT AMOUNT PER UNIT REVISED COST SHARE TOTAL REVISED CONTRACT Revised:12-17-2018 Camp Bowie Improvements Montgomery to University 24-0132 � 104639 62766 30114-0200431-104639-E07685 X-28250 K-3288 CITY PARTICIPATION:I Roderick Baker Andrew Goodman WATER/SEWER Developer Cost City Cost $0.00 $3,729,616.00 $0.00 $46.97 $0.00 $285,500.00 $0.00 $0.00 $0.00 $4,015,162.97 $0.00 $0.00 $0.00 $4,015,162.97 $4,015,762.97 Dev. Cost: Phone No: Phone No: $0.00 $0.00 CONTRACT UNIT $0.00 City Cost: $13,613,875.93 YES 2143979308 8173926251 CHANGE ORDER No: 5 TPW Developer Cost City Cost $0.000 $9,169,041.00 $0.000 $144,171.97 $0.000 $285,500.00 $0.000 $0.00 $0.000 $9,598,712.97 $0.000 $0.00 $0.000 $9,598,712.97 $9,598,712.97 $13,613,875.93 WORKING DAYS 0 $0.00 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Page 1 You are directed to make the following changes in the contract documents: TPW PAY ITEM # WC #1 Earthwork 8 Demo M1 General Conditions M2 CCIP M3 M4 M5 WC#4 M1 M2 M3 M4 M5 W C #6 M1 M2 M3 M4 MS Asterisk (*) indicates New Pay Item REASONS FOR CHANGE ORDER CITY BID ITEM # NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA QUANTITY 0.00210 0.00003 0.00037 0.00041 0.00037 -0.0101 S 0.01050 0.00012 0.00170 0.00191 0.00173 -0.04721 0.16722 0.00033 0.00468 0.00526 0.00475 -0.12998 UNIT LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS ITEM DESCRIPTION Earthwork & Demo General Conditions CCIP Fee McCarthy Performance and PaymentBond Construction Contin9ency Electrical and Lighting General Conditions CCIP Fee McCarthy Performance and Payment Bond Construction Continpency Traffic Control General Conditions CCIP Fee McCarthy Performance and Payment Bond Construction Contingency CFW UnitPnce NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA TPW UNIT PRICE $ 1,452,399.00 $ 1,203,831.00 $ 168,428.00 $ soa,zss.00 $ 73,105.00 $ 336,621.00 $ 1,350,000.00 $ 1,203,831.00 $ 168,428.00 $ 608,259.00 $ 73,105.00 $ 336,621.00 $ 233,367.00 $ 1,203,831.00 $ 168,428.00 $ 608,259.00 $ 73,105.00 $ 336,621.00 Developer Cost $0.00 $0.00 $0.00 $o.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 City Cost $ 3,055.00 $ $ 31.16 $ $ 61.71 $ $ zso.zs � $ 27.19 $ $ (3,425.32) $ $ 14,175.00 $ $ 144.61 $ $ 286.34 $ $ 1,161.17 $ $ 126.14 $ $ (15,89326) $ $ 39,023.61 $ $ 398.12 $ $ 78828 $ $ 3,196.70 $ $ 347.25 $ $ (43,753.96) $ ao.00 TOTAL 3,055.00 31.16 61.71 25026 27.19 (3,425.32) 14,175.00 144.61 286.34 1,161.17 126.14 (15,89326) 39,023.61 398.12 788.28 3,196J0 347.25 (43,753.96) so.00 Revised: 12-17-2018 Page 2 RECOMMENDED: (Cons�dting Engineer) `� �= �01 /20/2026 Bv: j `�! �Vc� �I ;.'_Us�.� ��' ,- Date. Name: Madeline White PE T;t,e: Project Manager qpPROVAL RECOMAAENDED: CFW - �Nater Department Bv: s�� ✓�a P� Suby Varughese Name'. T;tie: Engineering Manager APPROVAL RECOMMENDED: TPW B�7� ,�� , , Name: Lauren Prieur T,t,e: Director, TPW APPROVED: APPROVED: • (Contractor) (Developer) � ��2 �/2026 Mark Valdez o,= `` s"' oate:l /2112026 Travis Rieff ; so,aaaoo Date: BY� By Mark Valdez . Name: TraVIS RI2� Name: VP - Development T�t�e: Proiect Manaaer Title: APPROVED: CFW - Assistanf City Manager r� 02/18/2026 Date. 02/06i2026 ey, ,"_���� `_ Date. Name: Jesica McEachern T�tie. Assistant City Manager �Fowr�°°aa o $o pooea000e!Yo9�ap a : �U' � d ATTEST °Qo*��o "'_ aa°a naoos4',� oate. 02�09I2026 � � -�Q-°s- Date: �2�18l2026 By: � Name: Jannette S. Goodall . Title'. City Secretar,� • NIA NlA M&C Number: M&C Date Approved: �n�:�' ��"�-`y Andrew Goodman IPRC Project Manager 02/03/2026 �FFIGIAL RECORD CITY SEGRETARY FT. WaRTH, TX Page 3 APPROVED AS TO FORM AND LEGALITY: CFW - Assistant City Attorney BY: Name: Richard McCracken T�tie: Sr. Asst. City Attorney Date: 02�12/2026 " Contract Gompfiance Manager (Project Manager): By signing I acknowledge that I am the person responsible for the monitoring and administratlon of thfs contrace ents. and ensuring all performance and reporting req There are NO City Funds associated with this Contract � There are City Funds associated with this Contract Revised: 12-17-2018 _ � McCarthy Building Companies Inc. 3400 North Central Expressway Suite 500 Richardson, Texas 75082 Phone: (972)991-5500 PCCO #013 Project: 002259.000 - Camp Bowie 3230 Camp Bowie Blvd, Fort Worth. Texas 76107 Prime Contract Change Order #013: CO 13 - Asphalt Crossover Demo TO: FROM: McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 DATE CREATED: 5/22/2025 CREATED BY: Mark Valdez (McCarthy Building Companies Inc) CONTRACT STATUS: Draft REVISION: 0 SCHEDULEIMPACT: CONTRACT FOR: 1:CAMP BOWIE BOULEVARD ROADWAY TOTAL AMOUNT: $0.00 IMPROVEMENTS (MONTGOMERY STREET TO UNIVERSITY DRIVE) INOTE: Asphalt removal was assumed to be completed DESCRIPTION: by Clt�/ CiUfIIICj a Sepafate IIl1pCOV2111211tS pC0�2Ct. CE #CO - 13 - CO 13 - Asqhalt Crossover Demo This Change Order covers additional labor, equipment, and materials to demo existing asphalt that was not completed "by others". Please reference sheet 20 of plan set (Sta. 10+00 - 11+00). ATTACHMENTS: POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # I Title 013 CE #CO - 13 - CO 13 - Asphalt Crossover Demo CHANGE ORDER LINE ITEMS: PCO # 013 : CE #CO - 13 - CO 13 - Asphalt Crossover Demo # Cost Code � 31000-31000.0000.00.00 - WC #1 - EW 8 yyC 1- Earthwork & Demo DEMO 2 01800-01800.0810.00.00 - COST OF RISK M2 - CCIP (GL) 01800-01800.0820.00.00 - BUILDER'S RISK 3 INSUR Builder's Risk 4 01900-01900.0910.00.00 - INITIAL MARKUP M3 - Fee 01700-01700.0730.00.00 - PERF & PAYMENT 5 BOND M4 - P& P Bond 6 01900-01900.0955.00.00 - CONTINGENCY MS - Contingency Schedule Impact Total: Description Type Subcontracts Material Material Fee Material The original (Contract Sum) Net change by previously authorized Change Orders The contract sum prior to this Change Order was The contract sum would be changed by this Change Order in the amount of The new contract sum including this Change Order will be The contract time will not be changed by this Change Order. Amount $0.00 $0.00 Amount $3,055.00 $61.71 $31.16 $250.26 $27.19 Material ($3,425.32) Subtotal: $0.00 Grand Total: $0.00 $12,898,656.00 $715,218.93 $13,613,874.93 $0.00 $13,613,874.93 McCarthy Building Companies Inc. page 1 of 2 Printed On: 5/22/2025 09:35 AM M�CARTHY Crescent Property Services LLC 3230 Camp Bowie Blvd, Suite 500 Fort Worth, TX 76107 oiqitally siqned by 7ravis Rieff DN.C=US E=Trie�1@crescentcom, Travis Rieff �e erlopment�CN Trav�iaRenOU=VP Date:2025.06 06 1623:08-05'00' SIGNATURE McCarthy Building Companies Inc. PCCO #013 DATE Treble0ak 4849 Greenville Avenue, Suite 100 Dallas, TX 75206 McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 Josh Goad, President Dlgitalty slgned by Mark Valdez � Treble0ak, LLC oN c=us, E=Mnvaidez@Mccanny.com, RecommendApproval Mark Valdezo=°Mocannye��id��ycomaP��es,i�c, q�v�/ � 6/6/25 CN=Mark Va�dez Da[e: 2025.0522 09:51:49-05'00' �IGNATURE DATE SIGNATURE DATE page 2 of 2 Printed On: 5/22/2025 09:35 AM _ � McCarthy Building Companies Inc. 3400 North Central Expressway Suite 500 Richardson, Texas 75082 Phone: (972)991-5500 PCCO #014 Project: 002259.000 - Camp Bowie 3230 Camp Bowie Blvd, Fort Worth. Texas 76107 Prime Contract Change Order #014: CO 14 - Phase 1 Conduit Boring TO: FROM: McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 DATE CREATED: 5/22/2025 CREATED BY: Mark Valdez (McCarthy Building Companies Inc) CONTRACT STATUS: Draft REVISION: 0 SCHEDULEIMPACT: CONTRACT FOR: 1:CAMP BOWIE BOULEVARD ROADWAY TOTAL AMOUNT: $0.00 IMPROVEMENTS (MONTGOMERY STREET TO UNIVERSITY DRIVE) DESCRIPTION: CE #CO - 14 - CO 14 - Phase 1 Conduit Borinq In order to minimize project impacts, McCarthy proposes to bore phase 1 conduit in lieu of trenching to eliminate the need for additional demo and restoration. ATTACHMENTS: Mark Ups - Conduit Conflicts.pdf POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # I Title 014 CO 14 - Phase 1 Conduit Boring Schedule Impact Amount Total: Description Type Subcontracts Material Material Labor & Burden $0.00 $0.00 Amount $14,175.00 $286.34 $144.61 $1,161.17 CHANGE ORDER LINE ITEMS: PCO # 014 : CO 14 - Phase 1 Conduit Boring # Cost Code 26000-26000.0000.00.00 - WC #4 - ELEC & � LIGHT W4 - Electrical and Lighting 2 01800-01800.0810.00.00 - COST OF RISK M2 - CCIP (GL) 3 01800-01800.0820.00.00 - BUILDER'S RISK guilder's Risk INSUR 01000-01000.0001.00.00 - PROJECT 4 MANAGEMENT M3-Fee 5 01700-01700.0730.00.00 - PERF & PAYMENT M4 - P& P Bond BOND 6 01900-01900.0955.00.00 - CONTINGENCY MS - Contingency The original (Contract Sum) Net change by previously authorized Change Orders The contract sum prior to this Change Order was The contract sum would be changed by this Change Order in the amount of The new contract sum including this Change Order will be The contract time will not be changed by this Change Order. Material $126.14 Material ($15,893.26) Subtotal: $0.00 Grand Total: $0.00 $12,898,656.00 $715,218.93 $13,613,874.93 $0.00 $13,613,874.93 McCarthy Building Companies Inc. page 1 of 2 Printed On: 5/22/2025 10:31 AM M�CARTHY Crescent Property Services LLC 3230 Camp Bowie Blvd, Suite 500 Fort Worth, TX 76107 SIGNATURE McCarthy Building Companies Inc. PCCO #014 DATE Treble0ak 4849 Greenville Avenue, Suite 100 Dallas, TX 75206 McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 Josh Goad, President � Treble0ak, LLC Recommend Approval � 6/9/25 S NATURE DATE SIGNATURE DATE page 2 of 2 Printed On: 5/22/2025 10:31 AM _ � McCarthy Building Companies Inc. 3400 North Central Expressway Suite 500 Richardson, Texas 75082 Phone: (972)991-5500 Description Prime Contract Change Order #015: CE #CO -15 - CO 15 - 36" Line Removal TO: FROM: McCarthy Building Companies Inc DATE CREATED: CONTRACT STATUS: SCHEDULE IMPACT: CONTRACT FOR: 5/30/2025 Draft 12851 Manchester Rd Saint Louis, Missouri 63131-1802 CREATED BY: Mark Valdez (McCarthy Building Companies Inc) REVISION: 0 1:CAMP BOWIE BOULEVARD ROADWAY TOTAL AMOUNT: $0.00 IMPROVEMENTS (MONTGOMERY STREET TO UNIVERSITY DRIVE) DESCRIPTION: CE #CO - 15 - CO 15 - 36" Line Removal This Change Order covers additional labor, equipment, and materials to demo abandoned 36" water line and cap ends. CMAR to utilize savings to cover all costs. Reference shared savings table. ATTACHMENTS: POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # I Title 015 CE #CO - 15 - CO 15 - 36" Line Removal Schedule Impact Total: CHANGE ORDER LINE ITEMS: PCO # 015 : CE #CO - 15 - CO 15 - 36" Line Removal # Cost Code � 3300033000.0000.00.00 - WC #8 - yyC 8- Underground Utilities UNDRGND UTIL 01800-01800.0810.00.00 - COST OF RISK 2 (GL) M1 - CCIP 01800-01800.0820.00.00 - BUILDER'S RISK 3 INSUR Builder's Risk 4 01900-01900.0910.00.00 - INITIAL MARKUP M3 - Fee 5 01700-01700.0730.00.00 - PERF & PAYMENT M4 - P& Bond BOND P The original (Contract Sum) Net change by previously authorized Change Orders The contract sum prior to this Change Order was The contract sum would be changed by this Change Order in the amount of The new contract sum including this Change Order will be The contract time will not be changed by this Change Order. PCCO #015 Project: 002259.000 - Camp Bowie 3230 Camp Bowie Blvd, Fort Worth. Texas 76107 Type Subcontracts Amount Material $0.00 Material $0.00 Fee $0.00 Material $0.00 Subtotal: $0.00 Grand Total: $0.00 $12,898,656.00 $715,218.93 $13,613,874.93 $0.00 $13,613,874.93 $0.00 $0.00 Amount $0.00 McCarthy Building Companies Inc. page 1 of 2 Printed On: 6/16/2025 03:25 PM MGCARTHY Crescent Property Services LLC 3230 Camp Bowie Blvd, Suite 500 Fort Worth, TX 76107 SIGNATURE McCarthy Building Companies Inc. PCCO #015 DATE Treble0ak 4849 Greenville Avenue, Suite 100 Dallas, TX 75206 McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 Josh Goad, President � Treble0ak, LLC Recommend Approval 6/20/25 S NATURE DATE SIGNATURE DATE page 2 of 2 Printed On: 6/16/2025 03:25 PM NOIE: CONIRACTOR TO SALVAGE HISTORIC BRICK REMOVE O� PROiECT EXISPNG RAMPA LOT 11R2, BLOCK 3R rvo unuzE roaq�rYutt iii sF or /� (4 VAN ZANDT HILLSIDE ADOITION iRENCH REPAIR. E%CESS CONCRETE (t � @ -REMOVE & SALVAGE �;�, HISTORIC BRICK N1LL BE si�Ewn�K � Q t' (CAB. A. $LIDE 8109� .. COOROINATEO WITH COFW v p E%ISTING LIGHT POLE, �� OuO�VEn EXSiNG FOR STORAGE. G /� 3 F P�N � UNIVERSITV OF NORiH tEXAS SYStEA1 REMOVE & SALVAGE �l (NO RECORD INFORMnrOry �OUND) EXISTING LIGHT POLE, REMOVE 24 LF OF CON�llli NOTE: CURB AND GUTTER FOU �ATONS&NC 1. CONTRACTOR AND CITY REMOVE & SALVAGE STOP / CONpUIt INSPECTOR TO CONiACT THE SIGN iH SiREEt NAME / -- CITV'S WATER FIELD , AN� NO PARKING FOR . �/ � I c f 4 /�j 4 Y OPERAlIONS PRIOR t0 ALL ; RELOCAlION '� �--t � �j IiEMS BEING REMOVED OR - "' � SALVAGED. ��I� S . . z coNrencroe stin� -- i PRONDE DOWMENTS TO CITY G ll �*T\*� . ....... .. . x . -� O NSPECTOR FOR ALL REMS II A /tREMOVE & PROTECT 0 REMOVE� ANO SALVAGED TO � / � ��40 SY OG BRICK rREMOVE & SALVAGE EX pROIECT + iHE CITY S FlELO WATER + � LADJUST VALVES TO PA�ERS PER COFW / LIGHT POLE, REMOVE EX E%ISTING CIIRB a o / GRA�E PER 33 OS 14 � SPEC 32 14 i6 REMOVE 3�35 SF OF FOUNDAiION & CONDUIi OPERAlI0N5. REMOVE 609 LF Of & GUT'IER '�� '�' r 3. CONTACT WAREHOlISE r L � REMOVE }00 SY OF CONCRETE SIDEWALK A CURB ANO GUTIER SIIPERVI50R, JESUS RAMIREZ REMOVE 93 SY OF � ASPHALT PAVEMENT � �AHPROX. LOCATION OF EXISTING 30 N2 FOUND IN a AT (81]) 392-502J OR Q . CONCRETE PAVEMENT f� � � E FIELO CONTRACTOR TO CIIT E% ST NG LINE F SALVAGED IAAiERIALS i0 W �� � �� �� ,� _ O �KPZ 062JCONTRACi + WRB �HAT CONFLCiS WiTH W TRENCH AN� ABANDON (� WATER SYSlEMS SUPERNSOR ,' MATIHEW �AVIS Ai (81]J y ;; REMOVE AND REPLACE S NITARY REMAINING 11NE PER 01 41 14 944-82JJ. DELIVER ALL � � MANHOLE (SEE SHEET 14) 11+00 12+00 VE & RE L 14- ' CITY OF FORT WORiH FlELD �� REMOVE k SALVAGE IX � � __ t _ AND GUiiARE�� � Z OPERAlI0N5 LOCAiEO Ht Z � E t1 " � �.LICHT POLE, REMOVE EX . . E�- --�------F-�—�` -`-'-�- �-Ei---�_t - WHERE MINIMUM WRB Ei---- �• 1fi08 11iH AVE. FORi WORiH �-� � �, WNDAlION & CONDUIi " .�=� � DEPTH OF 12" IS J TX )6102 J ::....�.... � "Oi MET .._. ..��,,,,., , , „ 4. ALL SALVACEO EXISTING 30� WATER � / MATERIALS MUST BE r. LINE TO BE REPLACED I LpEMOVED Bv /�/ � SnLVAGE VnLVES = DELIVERED i0 CITT OF FIXiT (, BV OiHERS I SEPARATE CONIRACT CAMP BOYV/E BOULEVARY / V WORiH FIELO OPERATIONS F (X-28062) (%-28062) Mw[ -rq j � Q WITHIN IN 5 CALEN�AR DAYS. CPN' 1�5062 � aC REMOVE 14 SY OF I 154 - �-, -, - -. I-"� Zz• � CONCRETE P�AVEMEN oo m � � tpROTECT �INSTALLA1lON SY OF B� � G.... ..... , o : .q,. .,.,,_. . . ... . . i � .,. ,.. _ ' ,♦ a `REMOVE, PROTECT AN� REMOVE 222 SF OF -�� �` ° CK CONCREIE SIDEWALK � PAVERS PER COFW SPEC 32 5 GE GRATE o � /�14 16 AFTER WATER LI E -- , �yq�yE REMOVE 34 Li OF � � REMOVE 232 SF OF CURB AN� GUTIER &%ISu H��CIIRB CONCRETE SIDEWALK C REMOVE & DISPOSE OF REMOVE 39 LF OF REMOVE fi09 SF OF EX BUS STOP. TRASH E CURB ANO GUTiER �aNCRETE DRIVEWAY � GROUT. ABANDON, AND REPLACE 400 LF OF E%ISTING 12� CAN & BENCHES CAST IRON WATER MAIN -$EE WAIER SH. 6-8 _ att or roRr woRrH (VOL 1281, PG. 499) LOT 11R2, BLOCK 3R vq�vE no�usrniEN1- VAN ZANDT HILLSIDE ADDI710N REMovE �e sr oF (CAB. A, SLIDE 8109) coucaEr anvEMENr REMOVE & SALVAGE EX REMOVE 825 lERSITY OF NORiH iEXAS SYSIEM REMOVE & SALVAGE LIGHT POLE; REMOVE EX Sf OF CONCREIE 0 RECOR� INFORMAiION FOUND) EX SiOP SIGN WITH rouNonnoN � coNouir sioEwa�K smEEr NaME nNo acNov[ asa sF oF rvo anRrciNc roR ErE sioEwn�K reE�ocnnon ` REMOVE 43 LF OF PROTECT EXIST.—�� 9� PVMT MARKINC HSC SIGN— � � � � R�nove caosswnucR ` �N�X�� \k%� ,;;; ;; �� � GRO . . . _._... _ � _ _ _ . ...... .. �' + �6'Xfi' SI�EWALK � a ACEMENT FOR � ur�o aox REMO�E 36 LF �F A�JUS MANHOLE TO GRA�E REMOVE & SALVAGE REMOVE fi1 LF Q �CURB AND GUTIER �CONTRACTOR TO COOR�INAiE WITH E% PEDESIRIAN C R9 & GUTTER F �� FR CHISE TI T CO P NY SIGNS N- � �'( ��.fE� � REMOVE 8 LF OF CURB � -REMOVE ME�IAN - � � AN� GUTIER� W �0 � , 15+ 0 cuRe � curra _� 16+00 ; �� �� Z ' �,�,,,,, (ieo�F) + -, . � Ea E7 €a . . �� ',;,'„',',;;;;;;;;, . . � „ , .;;,,;,;,,,,,,,,,,,, ,, ,,,,,,,,,,,,,,,,,,,,, , � � REMOVE 250 SY OF \r FEMOVE 36 ABANDONED F� coHcae�e PnveMENr AMP BOwIE BOULEVAR� IwnrEa uNE. nenNoaN ExisnN �����_Mh REMOVE & SALVAGE E% ILINE O11T51DE OF WATER LINE � � Y a� d� Rt,VlS10NS O O m PD�ENDUM 1 C�N DFswivnoN ��29/2029 s��;aMP eowiE R wn1ER LirvE SNiFT & nBnrvDaNMErvi 2/24�202� a� �ecrreica� - ouir eury ez-ae (aHase �) ��in /zoss a � �o �25 )�1/2025 5 Q CC012,13,15.1) /28/202: 5 Q�FI 56 & XoxzoHrq E N�r ^/19��025 � REMOVE CONCRETE PAYEAIENT RENOVE CONCREIE LUS1]�' _______ CURB AND GUTTER REMOVE ASPHALT LIMITS OF SAWCUT PAVEMENT � aEuovE & � Ex taEE To eE ROtECT BRICK REMOVE� R PAVERS TO LFNDSCNPE PLRNS �REMOVE �RIYEWRY PA�EMENT '. HISTORIC BRICN � 1RENCH REPAIR REMOVE CONCREIE 9��E0, }�� F SI�EWALK gjr{`�� \� TREE PROTECIION i'-•�`��1C 111 5 W ftE LRN�SCAPE q � DETAILS 7. F(�.t.x�.,OGtW �,�9 �����b�w�i` _ REFERENCE LANDSCAPE II PLANS FOR TREE REMOVAL II TM` �go a ANO PROTECiION >>j��/m25yPw � GROUT. A9ANDON, AN� REPLACE 144 LF OF EXISPNG 4" CAST IRON WATER MAIN - SEE WAIER SH. 10 -MINOR A�JUSIMENT DMAC ON THE BRIX, LLC TO EXISTING STORM (INST, N0. D20J30405}) �0��,���,� Ma��o�E w�r� / O CONCRETE COLLAR REMOVE 91 SF OF � 66 PER SPEC 33 OS 14 CONCRETE �RIVEWAY �p �REIAOVE & REPLACE E% 1 d s��Ns 1 / � � ��SALVAGE WATER METER � I-�-REMOVE 103 Lf OF GURB AND \ � curre � REMOVE 64 SF OF O CONNEA EST�JONATK \ � - -------'_— �recMovcazaRolcc?\\\ � � 17+00 y e�PA�ERS PER COFW SPEO 32 14 16 8 Q � �_� f k reeMove MeonH � N reE vE 3 C11R9 & GUTIER CONCREiE PAVEMENI (251LF) W — REMOVE & SALVAGE � - E% STNG LIGHt POLE REMOVE & PROIECT 42fi � \ 7. � SY OF BRICK PAVERS PER J SALVAGE VALVES �CO:W SPEC 32 16 i6 Q ` � LIGHT POLE-, REMOVE Er REMOVE 300 SY OG r' �� �� SALVAGE VALVES� � R FOUNDAiION & CONDU ASPHALT PAVEMENT ,\ \ \\ F �. ^ � _ \ - X TRENCH PER 02 1 14. ` \ .�.. _ � . � .. .., .. Q Q� Q Q� 0 �`REMOVE, PROTECT AND� � � c � REPLACE SJJ SY OF BRICK PROTECT SALVPGE VALVES PFVERS PER COFW SPEC 32 EXISiING ClIR9 4 ifi AFTER WAiER LINE & GUTiER LOT 1 i'NSTn��nnoN � REMovE CRosSwn�rc THE KIMBELL , � sroa ena avMr INST. NO. D210282133) ��l MARKINC CITY Of fORi WORiH PRatECt � (INSi. N0. �200026685) CROl1T, ABANDON. ANO REPLACE 400 LF OF EXISIING 12" E�XIStING C�R9 � � �{ � CAST IRON WAiER MAIN - SEE WATER SH. 6-B � � GU?iER 1�vG�e?�jp • �0 e� REVIEWED By AntlrewGootlman af 2:18 pm, Dec 18.TOI5 Westwood ,'�eesuwverxcnrsm�s�=oa,�a, . a.,o�� sx.�. eOs . oRLL o��e«5 �a o s�. �p aE s �x�ss oMEAmsE _ _ e e o�B�])Fei1n a1WRAnoxs (e1)) .lsx-axse hvWc�m� c tsa.�aa � ui�s sn. nu o � ( � ' � 900-o i�lEss. ��a� IIORIZONTAL & VERTICAL COn'CROL �w:` r"�€°cSo"�€ � �W ,�c"q£R`�F' ::wx;� E�SF:�,�aoBS:°�" Rx§��a �§9 9i3i� E� 9��6 os s, @�$�cut rv�c i@ P@��*��N�XE� 9MR '�u i wcai ��rt �,�v�i�%��eLw nxo I�Lw�����'�acu VFN wnmYE �Lw�s�6��a�g,*r�,^rPr�sm�^EEi CI]Y PROJECT NO. 105654 � X-28250 IPRC IPRC24-0119 MAPSCO N0. TAR-0]6A FlO 30114-020043331-105654-EO]685 TAO MAP NO. 2036-39T ciry or r-oKT woxrx, Tr_x.as CAMP BOWiE BOULEVARD ROADWAYIMPROVEMENTS DEMOLiTiON PLAN STA 10+00 To sra �s+oo DESIGNE�:CTL/MKB PN JOB NO DATE- SHEET DRAWN: CSC/MKB 5085-22.692 JUL 2024 20 OF 92 � .-1 � � 3 0 m � Q CJ _ � McCarthy Building Companies Inc. 3400 North Central Expressway Suite 500 Richardson, Texas 75082 Phone: (972)991-5500 TO: DATE CREATED: PCCO #016 Project: 002259.000 - Camp Bowie 3230 Camp Bowie Blvd, Fort Worth. Texas 76107 Prime Contract Change Order #016: CO 16 - PH 1.5 TCP FROM: McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 6/06/2025 CREATED BY: Mark Valdez (McCarthy Building Companies Inc) CONTRACT STATUS: Draft REVISION: 0 SCHEDULEIMPACT: CONTRACT FOR: 1:CAMP BOWIE BOULEVARD ROADWAY TOTAL AMOUNT: $0.00 IMPROVEMENTS (MONTGOMERY STREET TO UNIVERSITY DRIVE) DESCRIPTION: CE#CO-16-0016-PH 1.5TCP This Change Order covers additional labor, and equipment to add phase 1.5 TCP into project sequencing. Scope of work will require additional grading, asphalt, barricades, and removals. ATTACHMENTS: POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # I Title 016 CO 16 - PH 1.5 TCP CHANGE ORDER LINE ITEMS: PCO#016: CO 16-PH 1.5TCP # Cost Code 34044-34044.0050.00.00 - WC #6 - TRAF � CNTRL WC 6- Traffic Control 2 01800-01800.0810.00.00 - COST OF RISK CCIP (GL) 01800-01800.0820.00.00 - BUILDER'S RISK 3 INSUR Builder's Risk 4 01900-01900.0910.00.00 - INITIAL MARKUP Fee 5 01700-01700.0730.00.00 - PERF & PAYMENT P& gond BOND P 6 01900-01900.0955.00.00-CONTINGENCY Contingency Schedule Impact Amount Total: Description Type Subcontracts Material The original (Contract Sum) Net change by previously authorized Change Orders The contract sum prior to this Change Order was The contract sum would be changed by this Change Order in the amount of The new contract sum including this Change Order will be The contract time will not be changed by this Change Order. $0.00 $0.00 Amount $39,023.61 $78828 Material $298�Yt g3ss�2 Fee $3,19670 +J V ` Material $34725 Material ���5) �gaa,�ss ss) Subtotal: $0.00 "".,. � _ Grand Total: $0.00 $12,898,656.00 $715,218.93 $13,613,874.93 $0.00 $13,613,874.93 McCarthy Building Companies Inc. page 1 of 2 Printed On: 6/6/2025 03:30 PM . � Crescent Property Services LLC 3230 Camp Bowie Blvd, Suite 500 Fort Worth, TX 76107 SIGNATURE DATE Treble0ak 4849 Greenville Avenue, Suite 100 Dallas, TX 75206 SIGNATURE PCCO #016 McCarthy Building Companies Inc 12851 Manchester Rd Saint Louis, Missouri 63131-1802 DATE SIGNATURE DATE McCarthy Building Companies Inc. page 2 of 2 Printed On: 6/6/2025 03:30 PM iusrn� cwzo-io � Rk.VLS10NS aE oreE creosswwc �� ✓ / / / / � 4 i �, / � r�o orscvirnor� oarz �� � / i � i i � nai��i�oo= FRRFrc PP Asc U� nopD � / , // �/VAN ZANDT HLLSIDE ADDI ON // �/ i Q TRaFFic�coNmo�C�no�rvricurennoN r.finAi�n.; I TEMPORARY r—CW20-iD R3_2 .//.. // // ......� (va. zoa� rc. a) �oT 3 �/ / xareaoH.a�s�ucw�, �. � � I � �� sroP �� � �, , , � �rN=r No � �� � 0 iR � BLOCK 5 Ri-� / LOT 8 aeqicnoc D206345295) ` E � E ti o � VAN ZANDT'S HILLSIDE ADDITION ii M � Gair Co / � a / � LOT 4; / / (INST. NO D221271821) ��u�T uc � LOT ; � LOT 6 / LOT 5 ' �� � � LOT 2 / LOT 1 � � �,,. coNsmucnoN mNE � �F F , p � �� oevzem�a] '� / / � �� �,(o i / iz9o�ia)/ ,. �� v. ... ans) � ��_ _ _ - _ � � urve c�osuee - E �� � T �_ Q ex eow � � � / - p � rroe ni enaaienoe '_____�� � � �� __ ^� �-� ' ' . � �. . '� + ________L__"_ ___ o_______"� � � �MaoenertenFFic , � � � .. . � o � N _---_ ���tieuzws oevices -00 21+00 • � ��. � , e: +0 23+00 24+00 ` � � , , Q (�ERPCAL PANELS) _ � �_________ _ _ _' � , y • � � � � • CHANNELI2ING �ENCES - _ _�- ---- (�RUMS) • �' � �� � � iFAFfIC FtOW � � � �� �������` ��� � OIREClION � ___ _ � W - - - — - �- �'� � , , � � �Iv� J N�.�C�ONiRACTOR SHALL SHIGT SICNAL HEA05 AS NEEDED � ��,�Y� x tow a �1 r A V CAMP BOWIE BOULEVARD�CRM SXOVERLT F�� _� Ex R�w // = MORCE�ACH TRAFFlC CONTROL PLAry qrvD ENSURE SiCNnL ��'� y���y HEAD PLACEMENT IS IN COMPLIANCE VAIH iHE iE%PS / � �� 1 TR.CTIO� �����-�» . � V 2 CONiRACTOR TO PROTECT ALL EXISTINC iRAFFlC SIGNAL � �1- f LOi 1 �/ ' O � , �. � NFRASTRUCTURE �URINC CONSIRUCTION, INCWDING BUT �� t' .�"f NOT LIMITE� TO SIGNAL POLES. CONDUIi, SICNAL HEADS, �1 �"�- THE KIMBELL �/ � � � LOP�D a SIGNNGE. ETC. �� � (INST. N0. D210262133) _ . � �� � � O TEMaoaaav � � . \ CHnNN`uZING DEVICES LOT 1, BLOCK 1 CTv oF FortT WoreTH enRAcno[ ,� / /� R9-9 M.M.A. AODITION T�Mao nFFiC owsj% (iNsr No o2oao2s as) ��E ' (CAB. A, SLIDE 5215) P�^sEreA Hoea TMe icx.s � . / � � /,� / cr+axecaixc wx�encc ncr. � / � . � MPA GOIINDATiON eaamcno[ _ (VOL 2440, PG 0�2) i r'�NSTA�� R„-a s�c� Rono c�oseo � REVIEWED AT INTERSECTION Of TD vnn� cuauaN wnr e< THRUTRAFFIG eyanarewGooamanats:szam,✓unz�,wu oaaNE�� sraEE1 Rit-a � I StALL CW20-ID o INSIALL CW20-�D O ���� seoo .eso / TEMPORARY SIGJ 600 LF SIGN 400 LF � niMe H�MAINDER OF CHANNEIJZiNG DEViCES SGNA400 LF20 D ��BEFORE CROSSWALu BEFOFE CFO 'n�G�'suvverix�'rirsmisnoa�asai / �o ee useo voe D � cwzo-m cwzo-io AHEno �oi B ��\ 7E�poRqRv 7 eEFoaE caosswnu� �� CONSTRUCTIOn \OTI:S � LOT AR, BLOCK 5 PHASE CW20-1D 1 fTj I ' ;� NOTES: m�s �Hccs xcr�H �s nHo PHVX, LTD � j i, 3. COrviRnciDR Sh'nL� utiuzE ExiSPNG SPnRES nvniLnBLE nT lNE r rt�o sxui ec is �rvo �u oavewr.r Ano srv�u eE a urv�css omrnmsE (iu51 No VAN ZANDT HILLSIDE O � � BASE OF iHE SIGNAL POLE WHERE POSSIBLE. CONiRACTOR MAY PULL sxu� x � n x x x x * E ar areoaosEo r+a�t AD�ITION � �'�'� :� NEW CABLE TO CABINET IF NEE�ED. AS-BUILT DOCUMENTATION WAS D206345295) ` \ - %T � D '�' UNAVAILABLE TO DETERlAINE E%ISTNG WIRING AND CABLE /(INST. N0. D209012232� �q.. /h/ y< � I TERAIINATIONS. CONTRACTOR MAY INSTALL NEW CABLE W1iHIN POLE IS ���p 58 n*E vu�rts Mun eE arsmuxm vm caw wartv ocvnaiucHr oEsa� \ iwE \ T4 T ♦ n�u cu nrnxvs uus* a[ Acsmn xco wTM noqna+n� couca[�[ � 6ARNEY HO LAN9 OL COMPNAY Ip* S (� y , �, � MORE CONpUCTORS ARE NEEDED. ' ( �Si `.� C2C63�s2q5� � ' I" 6. CONTRACTOR TO ENSURE LANE SHIFT TAPER IS A MINIMUM 0: 100 q�c Ni�ci N[ rouomxc n* �us* ae xwRs vvort m[xcnvpnxc ni / ' �/� FEET LONG PER MIITC� SECiION 3B.02.16 IF LANE SHIFT TAPER : � �i 19DEwnLK CAMP BOWIE BOULEVAl7� Ex�aow��E � I i� coNrRi,croa ro / ReouiaeMer�rs cnr�No� ee Mer, nooinoNn� novnNceo wnRwuc p,k„ a o a�e e�„ � "0y�., F ��qpR�_py� �.COORDNAiE W iY ::IiT SIGNS INOICAiING A SPEED REDIICTION AND LANE SHIFi SHOULD BE �p o () � -� I Re 9 � � SGNnL ENGNEF't '0 USED TO APPROPRIATELY WARN DRIVERS PRIOR TO iHE LANE SHIFT. �oAr waATM wE oveRaoxs ai� �sz-az� roAr waAm rsvw (ei� ei1 aiao �n - � - — - n�os crvcxcr (eii� zi�a.�aa � � . ��— �( � UPOAiE SC�A ADVANCED SIGNAGE PLACEIAENT SHOULD BE IN COMPLIANCE VAIH orvcoa cas k iccmZ �aii) zis 'PHASING AV� N �G 1MUTCD REQUIREMEMS. � -� � ^ � y` PFOP 1EMP PVMT MARKNGS nuolrvEPfniu�Es�i}SBoo-oG�lEss��a� � � � / � �� reMvoaner �F7 1uaN � � �� 7IORIZONTAL & VERTICAL COn'CROL � _ � ; ' naeowavMlMneKinc ��w; �tcu� .�xh`asE = r � ���/� cws a ."�€°c.o"a€ `e"W "'F"'c"„" `0�' o �SF:��ao B5.'�" v 3 o ___�_�_�___ F .a.2� e,. oss, - r � --- -- - - �� _ 3z+oo �3 ��"§��a°ad"'z � §99i3i� � i��s4da�43 -- � ___ F � a�E�,,,_K �-------- 3 -- ; Z �—_�`----� . �---�TT� �_�� �'� � _�� g —�. ��► � � 3+00 � %i @ xcaMv"`qov°fnE e"w� x"o°X @ a@ � �qH w�E u°w""sccpox or eAr smee. � m \ — / � � R9 9 v�i �rt � i'�ae� _������_ � � ..� Ibr_ T S �: ��i�%��� c �: �e�l����a eeM 0 �iEN�e�l�s'.�3a�3}�cn"v�m� _ �� � E � N � e�Now\ �A " rwE v�a� 1 � i•''����� '___ .���.�� /��' , �l' ��'�ar �F Ro"� cinvaoeecrHa. rasesa x zaeeo .. � � \ � � � VNrI�NAHOWG �� 0��... � ,iENPORARY /���....... V3va OVERHEA� ` \..\... �IN �� wORK IPRC IPRC24 0119 MAPSCO NO TAR 0]6A N � � PVIAiOMARKING ,— 1 MTP RACYst� U�� \\ B» a �M FlO 30114 020043331-105654-EO]685 TAO MAP NO. 2036 39T a � � � N . � � � _ sc E o cusTOM � � sra�� cw2o io cweo i❑ � }� rv�vorv�van�r � sEroee�eo�swnuc �, �, ry qwzow ; � CITY Ot FORT WOK'rH, TY_X.4S Q � � aa ee I T f vo e o e oun� � i% TEua LOT 1, BLOCK 1 " I � � � // � — �EFT TURN �nNEs ' � � �� �] � M M.A. ADDITION ' �/� ��~ sicN ovEaHEno oN � � Gp � soNn� aa� FOR � (cne. n, suoe szts) � i � � /�V� " / wEs,aooNo �,H sr � �'"E"^P0 E �'R" � ' CAMP BOWTE BOULEVARD W N / ' / -� ARROW P i RKING MPn FouNOArioN / /'�_1 Q o� rureNNc �Fr ro �� ,r�� � ROADWAY IMPROVEMENTS (VOL 124a0 PG '.0�2) �.( `� UN VERSItt DR VE �� O /.-'S��,,� N�,A��,EMPoa�ar � ��� �J�� '°� � � �' �� s�� ��� " �� �� TRAFFIC CONTROL PHASE lA � eeFoae caosswn�K � p� "� ��j� � Nsrng� cwzo io �E� ad�raN�v m � '� scry oa �r ��� // / BEFORE CROSSWALK R3-HN � DESIGNE�:CTL/MKB PN JOB NO DATE- � SHEET Q 'gF CW20-iD DRAWN: CSC/MKBI5085-22.692I JUL2024 I43AOF92 U ����c�7 � � ���� ��l�e � S Se�reta�'� �� s�itta 1ip � Routing & T ontr � G���6 deka�As• G ore �es Oo,�3 thr a h�e��s �or m h`1 gu�\d�n9 G°mpa� C G �'• MGGa� OCde� #5 \���s da�a GP Se e a t t ��� S�ia� C�ar9e �,�d utid�t�e COn��a�t �ee�ent'. \ U�deC ro t�� t�e Ag a�d eAe�tr`�� , s�b�e� Go�du\� boc�n • 2�66,p,1,62�66 P� in�\udes ��� es Q�� 62766, 6 Coun�'� � t �° � �dby tb� t� the �ortit���� ' e� � �p b� �ttctch�c� �ontraCti'�� dywent �`�ti�nti�e��. v �&C Ap &� ,,�ust �Xnstiz�g ��d th� � . If� so, the N� �nd�enti�t� a�a�t iam�e' �o � i�f ��,�'ation i� �g t1�15 �,id� e �����'� ���>>� �� � �����t lis�n�" ��. o�ly s�e�t ��� lo�pt��� If� so, I�� `�� <<�'erri�an erman�'��t ��o � d the pa�� Ig the G�ne� �,a�k pa�� f�'r � ����al� �:���s f�de�t�c�l �n C°��a Z �251�p27 �uy e, t �1�t��,n �s �f un i�e �����a�t wh�t inf�''� ate� bl�� I����s en �c�s�- ll� �xpirationS� 1 f applic� ��entiul, Pl�' � � c� t� th� �°ritr'�et. ,o vul `�at�� h� �tl�� �ate' t ro��1 the app Q�°•,ing N1&� "r ��tta� o�traCt �CS��I ���e � f di. ffe,,en f ��d� ;� � es t�ti� �pp� �,�y C ��5 F p� re�� ti� atta�h�`� �639 d tbe Ci�' �e��e Is a 1 ens�� �o to ad � 1� so, ple`��� I f� app�i���l� tbe G����a�� in o�de� : be��' a��Xti .�leld �n �� �n tihe fol�ow Pr°�e�t��m e � id y°'�'���s � �° � r Csp �����s ��b��� �� to be routed f� roveri ontra�t� ���a e Ceni�°�alAs gne�� � 1 �atlle�� S Goo�a�o��ille�� �illbe ,� �anne� �1dwe11 � the �0�tr c��t lli5on . � �� not pro�tid�d, 3 , �' � � the tin forrr�ati° � C� tic 1 is requir�- d o,rritiat�Qn � Ind ��ptes th� l���epar�rney��. retur'�e d to th�