HomeMy WebLinkAbout28059-10-2025 - City Council - OrdinanceOrdinance No.28059-10-2025
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $109,697.00, FROM
AVAILABLE PAYGO RESIDUALS IN THE WATER AND SEWER CAPITAL PROJECTS FUND,
FOR THE PURPOSE OF FUNDING THE 16 INCH TO 24 INCH CAST
IRON WATER MAIN REPLACEMENTS FOR EASTWOOD AND TIMBERLINE ELEVATED STORAGE
TANKS PROJECT (CITY PROJECT NO. 105070); PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING
ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance
27979-09-2025, as amended, is hereby further amended to make the following adjustments by
increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund in the
amount of $109,697.00, from available PayGo Residuals in the Water and Sewer Capital Projects Fund,
for the purpose of funding the 16 inch to 24 inch Cast Iron Water Main Replacements for Eastwood and
Timberline Elevated Storage Tanks project (City Project No. 105070).
[--1 *0 1 IQ ki I PJ
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no
way impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27979-09-2025 and all other ordinances
and appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said conflicting
provisions of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROV D AS TO FORM AND LEGALITY:
Douglas Black (Oct 31, 202516:17:13 CDT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: October 27, 2025
[a]IC&I x810:1IF0 Will
Jannette S. Goodall
City Secretary ��da����
moo'* 00 0 �aa�
�.o00 0•1 d
000 �_0
0 Id
000000 a�a� nEXAS.oAp
MAYOR AND COUNCIL COMMUNICATION MAP
60SECIWM REPLAI-AECOM
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 10/21/25 M&C FILE NUMBER: M&C 25-0965
LOG NAME: 60SECIWMREPLAl-AECOM
SUBJECT
(CD 5 and CD 11) Authorize Execution of Amendment No. 1 in the Amount of $109,697.00 to an Engineering Agreement with AECOM Technical
Services, Inc. for the 16 Inch to 24 Inch Cast Iron Water Main Replacements for Eastwood and Timberline Elevated Storage Tanks Project, and
Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-2030 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Amendment No. 1 in the amount of $109,697.00, to City Secretary Contract No. 61678, an engineering agreement
with AECOM Technical Services Inc. for the 16 inch to 24 inch Cast Iron Water Main Replacements for Eastwood and Timberline Elevated
Storage Tanks project for a revised contract amount of $1,392,318.00; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $109,697.00, from available PayGo residuals, for the purpose of funding the 16 inch to 24 inch Cast Iron Water Main
Replacements for Eastwood and Timberline Elevated Storage Tanks project (City Project No. 105070) and to effect a portion of Water's
contribution to the Fiscal Years 2026-2030 Capital Improvement Program.
On June 11, 2024, Mayor and Council Communication (M&C) 24-0514, the City Council authorized an engineering agreement in the amount of
$1,282,621.00 with AECOM Technical Services, Inc. (City Secretary Contract No. 61678) for the 16 inch to 24 inch Cast Iron Water Main
Replacements for Eastwood and Timberline Elevated Storage Tanks project.
Amendment No. 1 will provide for additional survey and design for the replacement of 2,800 linear feet of existing 20-inch cast iron water
transmission main as well as the installation of 2,800 linear feet of water distribution lines and the replacement of existing deteriorated 6-inch
sanitary sewer mains on Miller Avenue and sanitary main replacement on Eastland Street in order to eliminate several storm drain conflicts on
Miller Avenue as follows:
Street ' From To
Miller Forbes Avenue N
Avenue Street
Miller Forbes Avenue N
Avenue Street
Scope
Water; 20-inch cast iron 2,800 linear
feet, Replace
Water; 8-inch PVC 2,800 feet, Install
Miller Forbes Fitzhugh Sewer; 8-inch PVC 425 feet,
Avenue Street Avenue Replace
Miller Miller Avenue N Sewer; 8-inch PVC 425 feet,
Avenue lAvenue Replace
Eastland Miller East 2,000 Sewer; 15-18 inch, Replace
Street Avenue feet
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance,
as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds
in support of the Water's portion of the City of Fort Worth's Fiscal Years 2026-2030 Capital Improvement Program.
Funding is budgeted in the Unspecified All -Funds project within the Water and Sewer Capital Projects Fund for the purpose of funding the 16 inch
to 24 inch Cast Iron Water Main Replacements for Eastwood and Timberline Elevated Storage Tanks project.
Appropriations for 16 inch to 24 inch Cast Iron Water Main Replacements for Eastwood and Timberline Elevated Storage Tanks project are as
depicted below:
Fund Existing Additional Project Total*
Appropriations Appropriations
W&S Capital
Projects - Fund $1,594,629.00 $109,697.00 $1,704,326.00
56002
Project Total $1,594,629.00 $109,697.00 $1,704,326.00
*Numbers rounded for presentation purposes.
This project is located in COUNCIL DISTRICTS 5 AND 11.
A Form 1295 is not required because: This contract will be with a publicly -traded business entity or a wholly -owned subsidiary of a publicly -traded
business entity: AECOM Technical Services, Inc.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified All -Funds project within the W&S Capital Projects Fund and
upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital
Projects Fund for the 16-24in Cl WM Repl. EW & TL EST project. Prior to any expenditure being incurred, the Water Department has the
responsibility to validate the availability of funds.
Submitted for Citv Manaaer's Office bv: Jesica McEachern 5804
Oriainatina Business Unit Head: Chris Harder 5020
Additional Information Contact: Dena Johnson 7866