HomeMy WebLinkAbout064425-CO1 - Construction-Related - Contract - Woody Contractors, Inc.CSC No. 64425-COl
FORT WORTH: City of Fort Worth
~' Change Order Request
Project Name Citywide Storm Drain Improvements
City Sec # 64425
Client Project #(s) Citywide Various Projects
Project Description Replacement, extension andd/or omprovement of existing City drainage infrastructure on an on -call basis
Contractor Woody Contractors, Inc. Change Order # 1 Date 2/25/2026
City Project Mgr. Benjamin Thompson City Inspector N/A
Dept. TPW Contract Time
Totals (CD)
Original Contract Amount $2,000,000.00 $2,000,000.00
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $2,000,000.00 $2,000,000.00
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 255(o) $2,500,000.00
STIFICATION (REASONS) FOR CHANGE ORDER
Additional bid items are needed but were not included in the original unit price contract. The items being added are needed for the construction of the storm drain
improvements at 1250 Green Oak St (CPN 106723) are Modular Block wall and connecting the proposed improvement with existing wall and at 2975 Loving Avenue
(CPN C00626) are removing and installing <200 SY Articulated Block .The proposed unit costs have been compared to the recent drainage improvement Reactive
Contract Unit Price and are similar.The City finds that the contractor's proposed installation price is fair and reasonable .
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
Contractor's Contra'
Woody Contractors, Inc. Troy Woody
Date
Feb 26, 2026
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
o€
Feb 26, 2026
�j/` _
�r
Feb 26, 2026
Program Manager
Date
Senior Capital Project Officer
Date
_ eW�
Feb 26, 2026
J, . -„f
Feb 26, 2026
nt Director (Dept)
Date
Director, Contracting Department (Dept)
Date
Pam�;aL „,�,_1, �,- ,,
Mar2,2026
emsUSW2;;
Mar2,2026
Assistant City Attorney
Date
Assistant City Manager M
Date
Feb 26, 2026
Mar 11, 2026
Council Action (if required)
M&C Number I NA M&C Date Approved NA
ATTEST: F ;i4,
�Odpd
e=O-
Jannette Goodall, City Secretary °0oQ°aana� e>
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Foirr WoH i City of Fort Worth
'r-' Change Order Additions
Project Name Citywide Storm Drain Improvements City Sec # 64425
Client Project # Citywide Various Projects
Contractorl Woody Contractors, Inc. PMJ Benjamin Thompson Inspector NIA
Change Order Submittal # Date 51712025
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
406
Modular Block Wall
TPW
0
SF
200.00
$0.00
407
Connect to Ex. Wall
TPW
0
EA
$5,000.00
0.00
408
Install Articulated Block <200 SY
TPW
0
SY
$1,375.00
0.00
409
Remove Articulated Block
TPW
0
SY
$260.00
0.00
TPW
$0.00
Sub Total Additions
$0.00
Change Order Additions Page 1 of 1
rt RU> ORTH City of Fort Worth
Change Order Deletions
Project Name Citywide Storm Drain Improvements City Sec # 64425
Client Project # Citywide Various Projects
Contractor Woody Contractors, Inc. PM Benjamin Thompson Inspector NIA
Change Order Submittal # =1 Date 2/2412026
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit I Unit Cost Total
TPW S0.00
Sub Total Deletions S0.00
Change Order Deletions Page 1 of 2
M/SBE for this Change Order
M/SBE Sub
Type of Service
Amount for this CO
N/A
Total
$0.00
Previous Change Orders
co # DATE AMOUNT
Total $0.00
2/11 /26, 1:56 PM
M&C Review
CITY COUNCIL AGENDA
Create New From This M&C
Official site of the City of Fort Worth, Texas
}R
REFERENCE **M&C 25- 20SWM CITYWIDE
DATE: 11/11/2025 NO.: 1042 LOG NAME: STORMDRAIN
IMPROVEMENTS 2025
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: (ALL) Authorize Execution of a Contract with Woody Contractors, Inc. in the Amount of
$2,000,000.00 for the Citywide Storm Drain Improvements Project, with a One Year
Renewal Option
RECOMMENDATION:
It is recommended that the City Council authorize execution of a contract with Woody Contractors, Inc.
in the amount of $2,000,000.00 for the Citywide Storm Drain Improvements project (City Project No.
100092), with one renewal option.
DISCUSSION:
This Mayor and Council Communication (M&C) will authorize execution of a construction contract with
Woody Contractors, Inc. in the amount of $2,000,000.00 for the extension, replacement, and/or
improvement of existing City drainage infrastructure on an on -call basis. Work on individual locations
will be authorized by work orders. The cost of each work order will be based on the unit prices bid by
the contractor for the work items in the solicitation. The maximum cumulative amount for all work
orders under this contract is $2,000,000.00. While the total bid amount is $24,199,785.00, the actual
contract amount will be $2,000,000.00, which represents the budgeted limit for the on -call services.
The bid amounts cited in the solicitation were based on hypothetical quantities for the purpose of
establishing unit prices for each work item. Payment for each work order will be made based on actual
quantities measured at those bid prices. Funding will be verified individually for each work order prior to
its execution.
The project was advertised for bid in the Fort Worth Star -Telegram on August 27, 2025, and September
3, 2025. On September 18, 2025, one bid was received:
Bidder Amount
Woody Contractors, Inc $24,199,785.00
The term of the contract will be until the work is completed or funds are expended, whichever occurs
first. The contract may be renewed one (1) time, with the same terms, conditions, and unit prices, at
the City's discretion.
An additional $292,000.00 is needed for contingencies, construction management, surveying,
inspection, materials testing, and GIS/project controls.
Project Cost Description
Amount
Woody Contractors, Inc.
$2,000,000.00
Contingencies, Construction Management,
Surveying, Inspection, Material Testing
$292,000.00
Total Project Budget
$2,292.000.00
apps.cfw net.org/council_packet/mc_review.asp?ID=33905&councildate=11 /11 /2025 112
2/11 /26, 1:56 PM
M&C Review
These projects are not currently defined, and the impacts on Operations Budgets are unknown.
Projects that replace or improve existing infrastructure should not have an impact on the operational
budget, as the City already maintains infrastructure in these locations. However, extensions, such as
additional storm drainpipes or inlets, would increase future maintenance responsibilities.
Funding is budgeted in the Drainage Improvement Projects programmable project (City Project No.
P00043) within the Stormwater Capital Projects Fund for the purpose of funding various work order
projects, as appropriated.
The projects are located in ALL COUNCIL DISTRICTS.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously
appropriated, in the Stormwater Capital Projects Fund for the Drainage Improvements Projects
programmable project to support the approval of the above recommendation and execution of the
contract. Prior to any expenditure being incurred, the Transportation and Public Works Department
has the responsibility to validate the availability of funds.
TO
Fund
Department
Account
Project
Program
Activity
Budget
Reference #
Amount
ID
ID
Year
(Chartfield 2)
FROM
Fund
Department
Account
Project
Program
Activity
Budget
Reference #
Amount
ID
ID
Year
(Chartfield 2)
Submitted for City Manager's Office by;
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
Jesica McEachern (5804)
Lauren Prieur (6035)
Thanaa Maksimos (2485)
1295 Form.pdf (CFW Internal)
20SWM CITYWIDE STORM DRAIN IMPROVEMENTS 2025 funds avai1.docx (CFW Internal)
20SWM CITYWIDE STORM DRAIN PROJECT FID TABLE.xlsx (CFW Internal)
Citywide Bid Tabulation.pdf (CFW Internal)
SAMS Search 2025.10.7.pdf (CFW Internal)
Signature: Cnk ah Chavez,
Crlstlan Chavez (Mar 11, 202614. 18. 44 CDT)
Email: cristian.chavez@fortworthtexas.gov
Signature:5„v�QA
Email: allison.tidwell@fortworthtexas.gov
apps.cfw net.org/council_packet/mc_review.asp?ID=33905&councildate=11 /11 /2025 2/2
FORT WORTH.,
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: Citvwide Storm Drain Imorovements Proiect Construction Contract
M&C: 25-1042 CPN: 100092 CSO: CS58111 DOC#:
Date:
To:
Name
Department
Initials
Date Out
1
Troy Woody
Contractor
a
Troy Woody
Feb 26, 2026
2.
Mike Glover
TPW - Inspector
M he�OeY
Feb 26, 2026
3.
Ben Thompson
TPW - Project Manager
a—
Feb 26, 2026
4.
Thanaa Maksimos
TPW — Program Manager
TM
TM
Feb 26, 2026
5.
Lissette Acevedo
TPW — Interim Sr. CPO
CJ
Feb 26, 2026
6.
Patricia Wadsack
TPW —Assistant Director
PLW
Mar 2, 2026
7.
Lauren Prieur
TPW - Director
L(a�x�I/flP„e1
Mar 2, 2026
8.
Doug Black
Legal - Assistant City Attorney
Douglas e--�as8lack
Mar 2, 2026
9.
Jesica McEachern
CMO —Assistant City Manager
CKMar
11, 2026
10.
Katherine Cenicola
CSO — City Secretary
cccc
Mar 11, 2026
11.
Jannette Goodall
CSO — City Secretaryc
Mar 11, 2026
12.
Allison Tidwell
CSO — City Secretary
All,— rdWe1
Mar 13, 2026
13.
Tpw—SW—Contract
TPW Stormwater
NEEDS TO BE NOTARIZED: ❑YES MNo
RUSH: OYES ®No SAME DAY
ROUTING TO CSO: ZYES LINO
Action Required:
❑ YES ❑No NEXT DAY: ❑YES []No
E, Signature/Routing and or Recording