HomeMy WebLinkAbout061681-CO3 - Construction-Related - Contract - Gibson and Associates, Inc.CSC No. 61681-CO3
FORT WORTH., City of Fort Worth
Change Order Request
Project Name 2024 Bridge Rehabilitation Contract 1 City Sec # 61681
Client Project #(s) 105238
Project Description Bridge Rehabilitation at 14 Locations
Contractor Gibson and Associates, Inc. Change Order # 3 Date 2/16/2026
City Project Mgr. Tariqul Islam City Inspector Henry Tristan
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
TPW
Totals
Contract Time
CD
$702,890.50
$702,890.50
210
20
$702.890.50
$702,890.50
230
Amount of Proposed Change Order
$0.00
30
Revised Contract Amount $702,890.50
Original Funds Available for Change Orders $105,434.00
Remaining Funds Available for this CO $105,434.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$702,890.50
260
$105,434.00
$105,434.00
0.00%
$878,613.13
JUSTIFICATION (REASONS) FOR CHANGE ORDER
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: Furnish all labor and materials as specified in Change Order #3. This change order will add a
new pay item for steel railing repairs on a new location- Academy Boulevard Bridge- necessitated by damage from a recent traffic incident. The traffic incident compromised
portions of the existing steel railing system, requiring the removal and replacement of damaged components to restore the bridge's railing structural integrity and safety. In
addition, field inspection determined that the remaining steel railing exhibits advanced surface deterioration, including corrosion and coating failure. To ensure long-term
performance and prevent further degradation, a new bid item for surface preparation and repainting of the affected railing segments is required as part of this change order. The
net change order amount is $0.00, as the cost of the added work will be fully offset through the deletion of unused quantities from the original contract. No additional project
funding is required.
Time: Staff supports the Contractor's request for an additional 30 calendar days to complete the expanded scope of work. This includes the internal review time and
coordination, and procurement of the materials.
Cost: The City reviewed the Contractor's proposed unit prices and compared them with recent TxDOT average bid prices for similar steel fence repairs and steel railing painting.
While TxDOT does not have directly comparable bid prices for this specific work, the Contractor provided a detailed cost breakdown for the steel railing repairs. Based on this
evaluation, the proposed pricing is deemed fair and reasonable.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
ntractor's Company Namew EContractor Nam
Gibson and Associates, Inc. Trey Meador
Contract Si natur
e Meadr(F.b17,2026153423CST)
Date
02/17/2026
Inspector/Inspection Su ervi
o� A
Date
02/18/2026
Project and Contract Compliance Uana
'Mar
Date
02/23/2026
Program Manager
Date
Senior Capital Project Officer
Date
Z.NaAq*�--
02/24/2026
'�
02/27/2026
Assistant Director (Dept)
i,',2 c-T,
Date
03/02/2026
Director, Contractn "
..21+w�
Date
03/02/2026
Assistant City Attorney
Date
lAssistant City Manager
Date
001e�
03/05/2026
1
03/16/2026
Council Action if required)
M&C Number N/A
M&C Date Approved N/A
A4g4
ATTEST: p F FOR
°°°° t
Oo°° °°o4;0+IdO
pFe o9�d
Jannette Goodall, City Secretary dv8 0=0
OFFICIAL RECORD
daII4 aEXog4pb
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
v---- Change Order Additions
Project Name 2024 Bride Rehabilitation Contract 1 City Sec # 61681
Client Project # 105238
Contractor Gibson and Associates, Inc. PM Tariqul Islam InspectorF Henry Tristan
Change Order Submittal # 0 Date 2116/2026
ADDITIONS
ITEM
DESCRIPTION
UEP I
uty
Unit
Unit Cost
Total
ew-
teeRail epair-Academy v ri ge
TPW
21.00000000
LF
525.00
1175.00
New - 37
Clean and Paint Metal Rail -Academy Blvd (EB & WB)
TPW
1.00000000
LS
$6,000.06
New - 38
Traffic Control - Academy Blvd
TPW
1.00000000
LS
1,550.00
550.00
TPW
$18,575.00
Sub Total Additions
$18,575.00
Change Order Additions Page 2 of 3
FOR_ r1 WCity of Fort Worth
Change Order Deletions
Project Name 2024 Bride Rehabilitation Contract 1 City Sec # 61681
Client Project # 105238
Contractor Gibson and Associates, Inc. PM Tariqul Islam Inspector Henry Tristan
Change Order Submittal # 0 Date 2/16/2026
DELETIONS
Change Order Deletions Page 3 of 3
FORT WORTH.
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: 2024 Bridge Rehabilitation Contract 1, CO 3
M&C
CPN 1-0523R CSO # 61681
DOC#
DATE:
INITIALS
DATE OUT
To: 1. Seidi Tovar (Business Support)
ST
ST
02/23/2026
2. Gibson & Associates, Inc.- Trey
Meador
TM
02/17/2026
s. Henry Tristan (Inspector)
f�enYy TTnkv
02/18/2026
4. Oscar Aguillon (Sr. Inspector)
-2A
OA
02/24/2026
5.Tariqul Islam (PM)
7.'
Tariqul Islam
02/23/2026
6. Zelalem Arega (PGM)
Z-A
Zelalem Arega
02 24 2026
7. Mary Hanna (SCPO)
W'
02/27/2026
8. Patricia Wadsack (AD)
PLW
03/02/2026
9. Lauren Prieur (Director)
LauurrrenPrleur
03/02/2026
10. Doug Black (ACA)
-W—
Douglas Black
03/05/2026
11. Jesica McEachern (ACM)
03/16/2026
12. Jannette Goodall (CS)
Ja nett
16 03 2026
/ /
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review
and take the next steps.
NEEDS TO BE NOTARIZED: U Yes❑✓ No
RUSH: ❑ Yes ❑✓ No SAME DAY: ❑ Yes ❑✓ No NEXT DAY: [:]Yes ❑✓ No
ROUTING TO CSO: ❑✓ Yes ❑No
Action Required:
❑ As Requested ❑ Attach Signature, Initial and NotaryTa
■ Signature/Routing and or Recording
❑ Comment
❑ File
Return to: Please call at ext. for pick up when completed. Thank you.
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Gibson and Associates, Inc.
Subject of the Agreement: Change Order No. 3 to CSC No. 61681, a Contract for the 2024 Bridge Rehabilitation Contract 1 Project
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 105238
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.