Change Order Request
Project Name Water and Sanitary Sewer Replacements Contract 2020, WSM-L City Sec No. 163510
Project No.(s) 56002/0600430/0700430/0200431/5740010 M&C 25 0397 City Pro. No. 1103362
Project Description Water and Sanitary Sewer Replacements Contract 2020, WSM-L - Part 1
Contractor 2R Construction services, LLC Change Order # 4--.- 2 Date: 211912026
City Project Mgr. Clayton Torrance City Inspector I Nakia McCain
Phone Number: 817-392-8528 Phone Number:[ 682-319-6130
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Water Unit 1
Sewer Unit 2
Paving Unit 3
Totals
Contract Time
(Calandar Days)
$3,831,116.34
$2,935,486.50
$1,870,904.20
$8,637,507.04
500
$0 00
$0 00
$0 00
2
$3,831,116.34
$2,935,486.50
$1,870,904.20
$8,637,507.04
502
Amount of Proposed Change Order
$0.00
$0.00
$0.00
$0.00
05
Revised Contract Amount $3,831,116.34 $2,935,486.50 $1,878,90420
Orig. Funds Available for Change Orders $212,188 00 $160,479.00 $0 00
Remaining Funds Available for this CO $212,188.00 $160,479.00 $0.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
$8,637,507.04
$372,667.00
0.00%
$9,930,895.6-
507
JUSTIFICATION (REASONS) FOR CHANGE ORDER I
Change Order No. 2 provides for the removal and replacement of a leaking existing 8" gate valve that was
encounter during construction on North Bailey Avenue and Wildwood Road.
The change order also provides for the removal of a tree that was located within the bore pit of a project sewer
line.
Staff agrees with the contractor requested S additional days.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Chanae Order by the contractor constitutes an accord and satisfaction and represents navment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractors Company. . Name
Contactor Name
Contractor Signature
Date
2R Construction Services, LLC
Raul Canales
,Raul eU44-d
1 2/19/26
Irise ictqf
Project Manager
Date
k- �"
��
2/19/26
&recto[ , star Dept).
Cops n Su ervisor Wate e t
Date
Christopher Rcirder TS
for ssistat CinAttorne
P
Assistant P Manager
Da e
ouglas Black Mar 12. 202620.06.02 CDT
`—\\� 11�" /
03/1 ! /202
Council Action if required)_
M&C Number NIA
M&C Date Approved
FORT WORTH
City of Fort Worth
Change Order Additions
Project Name Water and Sanitary Sewer Replacements Contract 2020, WSM-L City Sec No. 63510
Project No.(s) 56002/060043010700430/0200431/5740010 DOE No. 25-03 City Pro. No. 103362
Project
Description
Water and Sanitary Sewer Replacements Contract 2020, WSM-L - Part 1
Contractor 2R Construction Services, LLC Change Order # F--2—] Date: 2/19/2026
City Project Mgr. Clayton Torrance City Inspector Nakia McCain
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
7
8" Gate Valve w/ Concrete Collar
Water Unit 1
1.0
EA
2,320.00
2,320.00
10
Remove and Salvage 8" Water Valve
Water Unit 1
1.0
EA
$250.00
$250.00
48
6"-12" Tree Removal
Sewer Unit 2
1.0
EA
$1,500.00
$1,500.00
Water Unit 1
$2,570.00
Sewer Unit 2
$1,500.00
Paving Unit 3
Additions Sub Total
$4,070.00
Page 1 of 1
Fo Rr WO P,-F H City of Fort Worth
Change Order Deletions
Project Name Water and Sanitary Sewer Replacements Contract 2020, WSM-L City Sec No. 63510
Project No.(s) 56002/0600430/0700430/0200431/5740010 DOE No. 25-0397 City Pro. No. 1 103362
Project Description Water and Sanitary Sewer Replacements Contract 2020, WSM-L - Part 1
Contractor 2R Construction Services, LLC Change Order #0 Date 2/19/2026
City Project Mgr. Clayton Torrance City Inspector Nakia McCain
DELETIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
59
Sewer Construction Allowance
Sewer Unit 2
0.018750
LS
$80,000.00
$1,500.00
60
Water Construction Allowance
Water Unit 1
0.0257
LS
$100,000.00
$2,570.00
Water Unit 1
$2,570.00
Sewer Unit 2
$1,500.00
Paving Unit 3
Deletions Sub Total
$4,070.00
Page 1 of 1
02/23/2026
Water and Sanitary Sewer Replacements Contract 2020, WSM-L
CSC: 63510
CPN:103362
Chanee Order 2 Notes
Staff has reviewed the requested days and considers them to be fair and reasonable.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Clayton M. Torrance, P.E.
Name of Employee
Professional Engineer