HomeMy WebLinkAbout061728-CO1 - Construction-Related - Contract - Willco Underground, LLCFt? RT WORTH City of Fort Worth
CSC No. 61728-COl
Change Order Request
Project Name: Benbrook Water Authority Connection CitySec No.: 61728
Project No.(s): 56016/0600430/5740010/105248 DOE No. N/A City Proj, No.: 105248
Project Description: Emergency water connection between Benbrook Water Authority and City of Fort Worth
Contractor: Willco Underground, LLC Change Order # Date: 1 12/3/2025
CityProject Mgr. Russell Redder, P.E. City Inspector:
Nick Momo
Phone Number: 1 817-392-4970 Phone Number: (682)309-3743
Dept. Water
Totals Contract Time
(Calender days)
Original Contract Amount $1,054,059.00
$1,054,059.00 150
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1,054,059.00
$1,054,059.00 150
Amount of Proposed Change Order
$22,271.54
$22,271.54
263
Revised Contract Amount $1,076,330.54
$1,076,330.54
413
Original Funds Available for Change Orders $52,703.00
$52,703.00
$52,703.00
Remaining Funds Available for this CO $52,703.00
Additional Funding (if necessary)
2,11 %
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
$1,317,573.75
MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change order No. 1 provides for additional time, effort, and materials required by the contractor due to extended
redesigns of the structure due to unknown site conditions that were encountered construction and the need to
demobilize and remobilize on site. The change of design necessitated resubmission of documents by the
contractor and use of additional materials in constructing the vault.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Corp. pany Name
Contractor Name
Contractor � ature
Date
Willco Underground, LLC
Josh Molina, P.E.
��
02/18/2026
Date
Project Mana er
Date
—Inspector
ru.G 1-yLd
03/11 /2026
LiZ3 ► 2oz,.
Director Water Dept)
Date
Construction Supervisor
Date
Chris- opher I+ardor %5.
03/17/2026
03/1 1 /26
Assistant City Attorney
Date
I AssistantQty Manager
Date
03/18/2026
'
03/19/2026
Council Action (If Required)
M&C Number n/a M&C Date Approved n a
F_ "RT WC) RT H City of Fort Worth
Change Order Additions
Project Name Benbrook Water Authority Connection City Sec No.: 61728
Project No.(s): 56016/0600430/5740010/105248 DOE No. N/A City Proj. No.: 1 105248
Project
Description
Emergency water connection between Benbrook Water Authority and City of Fort Worth
Contractor Willco Underground, LLC I Change Order:= Date: 12/3/2025
City Project Mgr. Russell Redder, P.E. City Inspector Nick Momo
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
32
Demobilization/Remobilization
Water
2.00
EA
$5,000.00
$10,000.00
33
Flowable Fill
Water
1.00
LS
$7,590.00
$7,590.00
34
Pipe line adjustments inside and outside the vault
Water
1.00
LS
$4,681.54
$4,681.54
Page 1 of 1
Water
$22,271.54
Additions Sub Total
1$22,271.54
F"RT W(7RTH City of Fort Worth
Change Order Deletions
Project Name Benbrook Water Authority Connection City Sec No.: I 61728 _ _
Project No.(s): 56016/0600430/5740010/105248 DOE No. LN/A City Proj. No.: 105248
Project Description
Emergency water connection between Benbrook Water Authority and City of Fort Worth
Contractor
Willco Underground, LLC
Change Order: F, I
Date 12/3/2025
City Project Mgr.
Russell Redder, P.E.
City Inspector:
Nick Momo
DELETIONS
ITEM IDESCRIPTION I DEPT I Qty JUnit I Unit Cost JTotal
Water
Page 1 of 1 (Deletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub I Type of Service Amount for this CO
Same as original Contract i Miscellaneous $22,271.54
Total 1 $22,271.54
Previous Change Orders
Co # DATE AMOUNT
Total $0.00
Page 1 of 1
Mr. Molina,
With respect to the time extension requested in your proposed Change Order #1, 1 have the following
comments:
• In the period between NTP on November 4, 2024 and February 21, 2025 when the unknown
ductbank was discovered interfering with the construction, Willco Underground claims 40 days
of delay for submittal replies. These 40 days will be accepted.
• From February 21, 2025 until July 22, 2025, the structure and associated pipeline connections
were redesigned twice to account for the ductbank and then to move the vault farther from the
24" water main to the west. This took a total of 151 days, which the City accepts as out of Willco
Underground's control. These days encompass both RFI-06 and the Field Conflict with the 24"
Tee.
• The 155 days claimed for the delayed response to Submittal 011-Graphic Screen Design
Submittal cannot be accepted, as this submittal was non -reviewable record data and was
marked "For Your Use". No response was required from the City.
• The 50-day delay claimed for the review of Submittal 006-Concrete Vault Submittal Rev 2
(August 5, 2025) cannot be accepted as the Engineer's response was uploaded to Trimble Unity
Construct on August 25, 2025, as verified by that system.
• Following the issuance of new plans on July 22, 2025, Willco Underground initially submitted a
schedule showing a return to work on August 11, 2025. However, your remobilization was
delayed until October 2, 2025 - 72 days after the plans were available. We accept this change.
As explained above, the City proposes to add 263 days to this contract in Change Order 1. This will
change the completion date to December 22, 2025.
With respect to the monetary changes, the mobil ization/remobilizations can be paid at $5,000 apiece
for a total of $10,000. Other charges are accepted as submitted. Flowable fill will be paid based upon
the quantity installed, and must be backed up with manifests/loading tickets to determine the total
amount. If it matches your proposal, then the total monetary increase will be $22,271.54.
Russell Redder, P.E.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Russell Redder, P.E.
Name of Employee
Project Manager
Title
o�
ATTEST: o �F..... �d
�� l� �ann�nezAs4b
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX