HomeMy WebLinkAbout27560-03-2025 - City Council - OrdinanceOrdinance No. 27560-03-2025
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $49,129.00, TRANSFERRED FROM AVAILABLE PAYGO
FUNDS IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING
THE WESTSIDE TREATMENT PLANT III 30" WATER TRANSMISSION MAIN
PROJECT (CITY PROJECT NO. 102688); PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2024-2025 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of $49,129.00, transferred from available PayGO funds in the
Water and Sewer Fund, for the purpose of funding the Westside Treatment Plant III 30" Water Transmission
Main project (City Project No. 102688).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shal I in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27107-09-2024 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
1J ox
Douglas W. Black Jannette S. Goodall
Senior Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE: March 25, 2025
0
o=
0
o
0
°
0
0
�!X G-
00000�0 A'
MAYOR AND COUNCIL COMMUNICATION MAP
60WESTSIDE III WATERMAINPI CO3-THALLE
N I WESTPOINT BLVD
I
Westside Water
ti Treatment Plant
I I
1; Phase 1
Under Construction a
al I \ U
--� �Illi'11111F11 11,1111"
- a
I
Proposed Phase 2 Water 0
Transmission MainFA
J
�L"JU I.SU U
I� I
E OR
,wqF7 !r- -
- T I�
O Phase 1 = OA,
%')`Innd%C'ilr Under Construction 1
I-
Water Ground — — — — —
Storage Tank Site
FORTWORTH® g
0
A
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 03/25/25 M&C FILE NUMBER: M&C 25-0271
LOG NAME: 60WESTSIDE III WATERMAINPICO3-THALLE
SUBJECT
(CD 3 and CD 7) Authorize Execution of Change Order No. 3 in the Amount of $49,128.51 to a Contract with Thalle Construction Company, Inc.,
for the Westside Treatment Plant 111 30" Water Transmission Main Project and Adopt Appropriation Ordinance to Effect a Portion of Water's
Contribution to the Fiscal Years 2025-2029 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
Authorize execution of Change Order No. 3 in the amount of $49,128.51 and the addition of 60 calendar days to City Secretary No.59067 a
contract with Thalle Construction Company, Inc., for the Westside Treatment Plant III 30" Water Transmission Main project for a revised
contract amount of $20,022,846.31; and
Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $49,129.00, transferred from available PayGo funds within the Water and Sewer Fund, for the purpose of funding the
Westside Treatment Plant III 30" Water Transmission Main project (City Project No. 102688) to effect a portion of Water's contribution to the
Fiscal Years 2025-2029 Capital Improvement Program.
DISCUSSION:
On February 28, 2023, by Mayor and Council Communication (M&C) 23-0184, the City Council authorized a construction contract with Thalle
Construction Company, Inc. in the amount of $19,873,823.75 for the Westside Treatment Plant III 30" Water Transmission Main project. The
contract was subsequently revised by Change Order No. 1 in the amount of $14,981.85 after deducts administratively authorized June 10, 2024,
that primarily provided for tunneling to cross beneath a 24 inch dia. gas transmission main, and by Change Order No. 2 in the amount of
$84,912.20 after deducts administratively authorized on August 28, 2024 that provided for pulverization and overlay (POL) on Old Weatherford
Road and the addition of flexbase on Chapin School Road (County Road) in lieu of permanent pavement repair.
Change Order No. 3 will provide for additional pulverization and overlay (POL) on Old Weatherford Road and additional flexbase subgrade on
Chapin Road (County Road).
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance,
as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds
in support of the Water's portion of the City of Fort Worth's Fiscal Years 2025-2029 Capital Improvement Program, as follows:
60WESTSIDE III WATERMAINP1CO3-THALLE
Capital
Project
Revised
FY2025 CIP Budget
Fund
Name
Appropriations Authority Adjustment FY2025
Name
Budget
W&S
102688 -
Capital
WS
Projects— Treatment
$0.00 This M&C $49,129.00 $49,129.00
Fund
Plant III
56002
30" WTM
Funding is available in the Transfer to Water/Sewer account of the Water and Sewer Fund for the purpose of funding the Westside Treatment Plant
III 30" Water Transmission Main project within the W&S Capital Projects Fund.
FY2025 — Water PAYGO Appropriations per City Ordinance 27107-09-2024
FY2025
Amended
FY2025
PayGo
Original
(includes any
Adopted
council
PayGo
actions
subsequentto
budget
YTD PayGo
FY2025
Approved This MSC
Remaining
for/Moved to
PayGo
Capital Projects
Balance
adoption)
$92,597,771.00 $92,597,771.00 ($38,627,523.00) ($49,129.00) $53,921,119.00
Note: There may be other pending actions or recently approved actions that are not reflected in the table due to timing.
Appropriations for the Westside Treatment Plant III 30" Water Transmission Main project are as depicted below:
Fund Existing Additional Project Total*
Appropriations Appropriations
W&S Rev Bonds $2,845,105.00
Series 2021 - Fund
56019
W&S Rev Bonds
Series 2023 — Fund $21,125,743.00
56021
Project Total $23,970,848.00
$49,129.00 $2,894,234.00
$0.00 $21,125,743.00
$49,129.00 $24,019,977.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICT 3 and 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the Water & Sewer Fund, and upon approval of the above recommendations and
adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the WS Treatment Plant III 30 WTM
project to support the above recommendations and change order. Prior to any expenditure being incurred, the Water Department has the
responsibility of verifying the availability of funds.
Submitted for Citv Manaaer's Office bv: Jesica McEachern 5804
Oriainatina Business Unit Head: Chris Harder 5020
Additional Information Contact: Walter Norwood 5026