Loading...
HomeMy WebLinkAbout062807-CO4 - Construction-Related - Contract - Woody Contractors, Inc.CSC No. 62807-004 FORT V oRT" Change Order Request Project Name Sanitary Sewer Rehabilitation, Contract 103, Part 1 City Sec No. 162807 Project No.(s) 060043010700430102004311CO2723 DOE No. N/A City Pro. No.1 CO2723 Project Description Replacement of cast iron water and deteriorated sanitary sewer mains Contraclorl Woody Contractors, Inc. Change Order # Date: 3112/2026 City Project Mgr. I Dena Johnson, P.E. CityInspector L Richard Walden Phone Number:l (817) 392 7866 Dept. Original Contract Amount Extras to Dale Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Phone Number: (817)392-8306 Unit 1 - Water Unit 2A - Sanitary Sewer Unit 2B - Sanitary Sewer Unit 4 - TPW Totals Contract Time (CalandarDays) $1,774,350.35 $2,732.677.55 $628,912.00 $439,388.25 $5,515,328,15 500 $18,911.00 I $18,911,00 $1.774,350.35 $2,751.588.55 $628,912.00 $439,388.25 $5,594,239.15 500 Amount of Proposed Change Order $0.00 $44,310.40 $0.00 $0.00 $44,310,40 Revised Contract Amount $1.774,350.35 $2,795,898.95 $628,912.00 $439,388.25 Orig. Funds Available for Change Orders $88,718.00 $168,079.00 $43,939.00 Remaining Funds Available for this CO $88,718.00 $149,168.00 $43.939.00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT $5,638,549.55 500 $300,736.00 $281,825.00 1.13% $6,969,1fi0.19 JUSTIFICATION (REASONS) FOR CHANGE ORDER Change Order No. 4 provides for additonal pay item quantities of cement, cement stabilization and 4 feet of sidewalk adjacent to curb that are necessary on the project. r 0 uuudiatuUU dnu dyteeu mdt me acceptance or mis unange ureer Dy the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Contractor Name Jontfactor Signature Date Woody Contractors, Inc. Troy Woody Inspector Project Manacter Date 3/17 2 Director(Water Dept) Go ptf isor fTPW De t Sate CMsto her Harder Christopher Harder (Mar 19, 2026 16:38:39 COT) / Senior Assistant City_Attorney AssistaneC't M pat 03/25/2026 CounciCAcUon if re aired` _ M&C Number NIA M&C Date Approved L_ OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX F'o�� H City of Fort Worth Change Order Additions Project Name I Sanitary Sewer Rehabilitation, Contract 103, Part 1 City Sec No. 62807 Project No.(s) 060043010700430102004311CO2723 DOE No. N/A City Pro. No. CO2723 Project Description Replacement of cast iron water and deteriorated sanitary sewer mains Contractor I vvooay contractors, Inc. City Project Mgr, I Dena Johnson, P.E. A❑DI ❑r)NS Page 1 of 1 Change Order # ® Date: 3112/2026 City Inspector Richard Walden FORT WORTH City of Fort Worth Change Order Deletions Project Name Sanitary Sewer Rehabilitation, Contract 103, Part 1 City Sec No. F 62807 Project No.(s) 0600430/0700430/0200431/CO2723 DOE No. N/A City Pro. No. CO2723 Project Description Replacement of cast iron water and deteriorated sanitary sewer mains Contractor Woody Contractors, Inc. 77771 Change Order #® Date 3/1212026 City Project Mgr. Dena Johnson, P.E. City Inspector Richard Walden DELETIONS Page 1 of 1 .Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Dena 7oh4Sm Dena Johnson Name of Employee Project Manager Title vonnq p o� FORt�baa ATTEST: a" c9oo �o 11 OVo o�=d Ppa� nEXo5a44 Jannette Goodall City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH. City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: Woody Contractors, Inc. Subject of the Agreement: Sanitary Sewer Rehabilitation Contract 103, Partl M&C Approved by the Council? * Yes ❑ No 0 If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes ❑✓ No ❑ 62807-CO4 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes ❑✓ No ❑ If unsure, see back page for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No ❑✓ If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: 3/17/2026 If different from the approval date. Expiration Date: N/A If applicable. Is a 1295 Form required? * Yes ❑ No ❑✓ *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. CO2723 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes ❑✓ No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department.