HomeMy WebLinkAbout063487-CO1 - Construction-Related - Contract - Vernara, LLCCSC No. 63487-COI
FORTWORTH, City of Fort Worth
_—' Change Order Request
Project Name 2025 Concrete Restoration Contract 4 City Sec # 63487
Client Project #(s) 1106091
Project
Concrete pavement panel replacement at various locations
Contractor Vernara, LLC Change Order # 1 Date 3/10/2026
City Project Mgr. I Iretomiwa Otuyelu City Inspector Brandon Gibson
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
TPW
Totals
Contract Time
(CD)
$2,149,650.00
$2,149,650.00
180
$2,149,650.00
$2,149,650.00
180
Amount of Proposed Change Order
$387,650.00
$387,650.00
45
Revised Contract Amount $2,537,300.00
Original Funds Available for Change Orders $214,965.00
Remaining Funds Available for this CO $214,965.00
Additional Funding (if necessary) $172,685.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRA CT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
$2,537,300.00
225
$214,965.00
$214,965.00
$172,685.00
18.03%
$2,687,062.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
IN ACCORDANCE WITH THIS CHANGE ORDER REQUEST, THE CONTRACTOR SHALL: Furnish all labor and materials as outlined in proposed Change Order #1. This
change order increases the quantities of existing bid items required to complete the concrete panel removal and replacement on Gold Spike Drive and Railhead Road. During
construction, additional concrete panels deteriorated and failed due to the ongoing construction activities and sustained heavy semi -truck traffic serving the surrounding industrial
properties. As a result, the quantity of concrete pavement requiring removal and replacement has increased by approximately 5,600 square yards above the original estimated
amount.
Time: Staff supports the contractors request for an additional forty-five (45) calendar days to complete the expanded scope of work.
Cost: Part of this Change Order will be funded using the remaining construction allowance.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name
Contractor (Name)
Contract Signature
Vernara, LLC
Ashkan Beheshti
8-- `" — -
03/12/26
Inspector/Inspection Supervisor _
Date
Project and Contract Compliance Manager
Date
era'4"' C"Os 1h � Hwy
—I
03/12/26
.per
T
03/12/26
Program Manager _
Date
Senior Capital Project Officer
Date
ZmLb+�
03/19/26
M.jw -
03/20/26
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
03/25/26
d&._ 9
03/25/26
Assistant City Attorney
Date
Assistant City Manager
03/27/26�
0
03/27/26
Council Action (if required)
ATTEST: �o F A>"ke°apQ
Jannette Goodall, City Secretary
aaa,.... bra
M&C Number 1 26-0170 M&C Date Approved 3/10/2026
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FOxr WORTH City of Fort Worth
V-- Change Order Additions
Project Name 2025 Concrete Restoration Contract 4 City Sec # 63487
Client Project # 1 66091
Contractor Vernara, LLC PM Iretomiwa Otuyelu Inspector Brandon Gibson
Change Order Submittal # Date 3/10/2026
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
1 00 Remove Conc Pvmt
4.
,4 .
7
3213.0104 9" Concrete Pavement
TPW
5,600.00000000
SY
95 0
532,000.00
8
3123.0102 Unclassified Excavation by Survey
TPW
1,000.00000000
CY
30.00
35
3471.0001 Traffic Control
TPW
1.00000000
MO
3,500.00
3,500.00
TPW
$699,900.00
Sub Total Additions
$699,900.00
Change Order Additions Page 2 of 3
FowrWoRr" City of Fort Worth
�'*`--- Change Order Deletions
Project Name 2025 Concrete Restoration Contract 4 City Sec # 63487
Client Project # 106091
Contractor Vernara, LLC PM Iretomiwa Otuyelu Inspector Brandon Gibson
Change Order Submittal # Date 3/10/2026
DELETIONS
ITEM
DESCRIPTION
DEPT
QtY
Unit
Unit Cost
Total
7-
0170.0101 Specified emo ization
TPW
5 , 0
4
0241.0401 Remove Concrete Drive
TPW
1,500.00000000
SF
2.00
3,000.00
5
3213.0401 6" Concrete Driveway
TPW
1,500.00000000
SF
8.00
9
9999.0003 Flexible Base, Type A, GR-s
TPW
500.00000000
CY
50.00
25,000.00
10
9999.0004 Geogrid Tensar(TRIAX 140-475) or Approved Equal
TPW
3,900.00000000
SY
$2.00
12
13292.0100 Block Sod Replacement
TPW
2,000.00000000
SY
$15.00
$30,000.00
13
3291.0100 Topsoil
TPW
150.00000000
CY
$43.00
15
0241.0300 Remove ADA Ramp
TPW
4.00000000
EA
500.00
000.00
16
3213.0506 Barrier Free Ramp, Type P-1
TPW
4.00000000
EA
2,000.00
17
0241.0100 Remove Sidewalk
TPW
300.00000000
SF
2.00
6 .00
18
3213.03014" Cone Sidewalk
TPW
300.00000000
SF
8.00
34
3305.0105 Inlet Adjustment
TPW
3.00000000
EA
$4,000.00
$12,000.00
36
3346.0007 4" Pipe Underdrain, Type 7
TPW
100.00000000
LF
50.00
37
9999.0001 Irrigation Adjustment & Landscape Repair Allowance (Irrigation)
TPW
0.80000000
LS
35,000.00
28,000.00
38
9999.0002 Construction Allowance
TPW
0.80000000
LS
150,000.00
TPW
$312,250.00
Sub Total Deletions
$312,250.00
Change Order Deletions Page 3 of 3
City of Fort Worth,
Mayor and
Texas
Council Communication
DATE: 03/10/26 M&C FILE NUMBER: M&C 26-0170
LOG NAME: 202025 CONCRETE RESTORATION CONTRACT 4 — C01
SUBJECT
(CD 2) Authorize Execution of Change Order No. 1, in the Amount of $387,650.00, and the Addition of 45 Calendar Days to the Construction
Contract with Vernara LLC, for the 2025 Concrete Restoration Contract 4 Project for a Revised Contract Amount of $2,537,300.00
RECOMMENDATION:
It is recommended that the City Council authorize execution of Change Order No. 1, in the amount of $387,650.00, and the addition of 45 calendar
days to the City Secretary Contract No. 63487 with Vernara LLC, for the construction of the 2025 Concrete Restoration Contract 4 project (City
Project No. 106091) for a revised contract amount of $2,537,300.00.
DISCUSSION:
On June 10, 2025, Mayor & Council Communication (M&C) 25-0530, awarded the City Secretary Contract No. 63487 with Vernara LLC, in the
amount of $2,149,650.00 for the construction of the 2025 Concrete Restoration Contract 4 project (City Project No. 106091) at Gold Spike Drive
from Meacham Boulevard to Railhead Road, Railhead Road from Northeast Loop 820 Service Road Eastbound to Blue Mound Road, and Robert
W. Downing Drive from Western Center Boulevard to Cedar Tree Drive.
During construction, additional concrete panels on Gold Spike Drive and Railhead Road deteriorated and failed due to the ongoing construction
activities and sustained heavy semi -truck traffic serving the surrounding industrial properties. As a result, the quantity of concrete pavement
requiring removal and replacement has increased by approximately 5,600 square yards above the original estimated amount. Change Order No. 1
is necessary to add additional concrete panel replacement quantities to restore the pavement to a safe and serviceable condition and to ensure
the roadway can adequately support existing heavy vehicle traffic.
Staff has reviewed and verified the quantities for the additional work under this Change Order No. 1. In addition, to complete this work, staff
recommends extending the contract time by 45 calendar days.
The following table summarizes previous contract action and change orders:
Construction Contract
Date
Amount
Original Contract Amount (M&C 25-06/10/2025
0530)
$2,149,650.00
Change Order No. 1
This M&C
$387,650.00
Revised Contract Amount
$2,537,300.00
This change order will have no impact on the Transportation and Public Works Department's annual operating budget. Funding is budgeted in the
General Capital Projects Fund for the Transportation and Public Works Department for the purpose of funding the 2025 Concrete Restoration 4
project, as appropriated.
This project is located in COUNCIL DISTRICT 2.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously appropriated, in the General Capital
Projects Fund for the 2025 Concrete Restoration 4 project to support the approval of the above recommendation and the execution of the change
order. Prior to any expenditure being incurred, the Transportation and Public Works Department has the responsibility to validate the availability of
funds.
Submitted for City Manager's Office by- Jesica McEachern 5804
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662
CERTIFICATE OF INTERESTED PARTIES
FORM 1295
1 of 1
Complete Nos. 1- 4 and 6 if there are interested parties.
Complete Nos. 1, 2, 3, 5, and 6 if there are no interested parties.
OFFICE USE ONLY
CERTIFICATION OF FILING
Certificate Number:
2026-1411335
Date Filed:
01/21/2026
Date Acknowledged:
1
Name of business entity filing form, and the city, state and country of the business entity's place
of business.
VERNARA LLC
DALLAS, TX United States
2
Name of governmental entity or state agency that is a party to the contract for which the form is
being filed.
CITY OF FORT WORTH
3
Provide the identification number used by the governmental entity or state agency to track or identify the contract, and provide a
description of the services, goods, or other property to be provided under the contract.
106091
2025 Concrete Restoration Contract 4 - Change Order No. 1
4
Name of Interested Party
City, State, Country (place of business)
Nature of interest
(check applicable)
Controlling
intermediary
5
Check only if there is NO Interested Party. ❑
X
6
UNSWORN DECLARATION
My name is Ashkan Beheshti and my date of birth is
My address is 17250 Dallas Pkwy Dallas Tx 75248 USA
(city) (state) (zip code) (country)
I declare under penalty of perjury that the foregoing is true and correct.
Executed in Dallas County, State of TX on the 21 day of 01 2026
I_: (month) (year)
Signature of authorized agent of contracting business entity
(Declarant)
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V4.1.0.22701b2a
FORT WORTH,,
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 2025 CONCRETE RESTORATION CONTRACT 4 — CO 1
M&C: 26-0170
CPN: 106091 CSO: 63487 DOC#:1
Date:
To:
Name
Department
Initials
Date Out
1.
Lizbeth Medina
Bus-Sppt
MM
03/12/26
2.
Vemara, LLC
Vendor
AB 8
03/12/26
3.
Brandon Gibson
TPW - Inspector
sG
03/12/26
4.
Randall Horton
TPW — Sr.Inspector
7vjj-
03/12/26
5.
1 Iretomiwa Otuyelu
TPW
1 0
03/12/26
6.
Zelalem Arega
TPW
Z 41
03/19/26
7.
Mary Hanna
TPW
✓
03/20/26
8.
Patricia Wadsack
TPW AD
03/25/26
9.
Lauren Prieur
TPW Directory
°
03/25/26
10.
Doug Black
Legal
0
Douglas Black
03/27/26
11.
Jesica McEachern
CMO
03/27/26
12.
Jannette Goodall
CSO
03/30/26
13.
TPW Contracts
TPW
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
ALSO List: - Bus Sppt: Lizbeth Medina • Prg Mgr.: Zelalem Arega; Sr CPO — Mary Hanna
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and
take the next steps.
NEEDS TO BE NOTARIZED: []YES ®No
RUSH: ❑YES ❑No
ROUTING TO CSO
SAME DAY: ❑YES ❑No
❑YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
❑ Signature/Routing and or Recording
❑ Comment
❑ File
NEXT DAY: ❑YES []No
❑ Attach Signature, Initial and Notary Tabs
Return To: Please notify TPWContracts(afortworthtexas.gov for pickup when complete. Call ext. 7233 or ext.
8363 with questions. Thank you!
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Vernara, LLC
Subject of the Agreement: Change Order No. 1 to CSC No. 63487, a Contract for the 2025
Concrete Restoration Contract 4 Project at Various Locations
M&C Approved by the Council? * Yes 8 No ❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
1295 Form - page 8
Effective Date:
Expiration Date:
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes 8 No ❑
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 106091
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)