HomeMy WebLinkAbout061303-FP2 - Construction-Related - Contract - Acadia Services LLCFORT WORTH,"
-FP2
City Secretary
Contract No. 61303
Date Received 4/3/2026
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Laprelle Wagley Robertson Phase 1A
City Project No.: 105163
Improvement Type(s): ❑ Paving ❑x Drainage ❑ Street Lights ❑ Traffic Signal
Original Contract Price:
$22,300.00
Amount of Approved Change Order(s):
$0.00
Revised Contract Amount:
$0.00
Total Cost of Work Complete:
1$22,300.00
Will Collins
Aln Collins lA,, 1 2026 14:123o COT
Contractor
Senior Project Manager
Title
Acadia Services LLC
Company Name
Y1161 A?-
Project Inspector
e
Project Manager
CFA Manager
de.....7,.:.r,,.
Lauren Prieur (Apr 3, 2026 11:38:00 CDT)
TPW Director
04/01/2026
Date
04/01 /2026
Date
04/02/2026
Date
04/03/2026
Date
04/03/2026
Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name: Laprelle Wagley Robertson Phase 1A
City Project No.: 105163
City's Attachments
Final Pay Estimate M
Change Order(s): ❑ Yes 0 N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety ..
Statement of Contract Time
Contract Time: 120 WD Days Charged: 111 WD
Work Start Date: 9/2/2025 Work Complete Date: 2/20/2026
Completed number of Soil Lab Test: 87
Completed number of Water Test: 0
Page 2 of 2
FoRTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name LAPRELLE WAGLEY ROBERTSON PHASE I
Contract Limits
Project Type DRAINAGE
City Project Numbers 105163
DOE Number 5163
Estimate Number 1 Payment Number 1 For Period Ending 2/20/2026
WD
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor ACADIA SERVICES
1510 7ELMAK ST
GRAND PRAIRIE, TX 75050
Inspectors A. DUARTE / H. TAEZAZ
Contract Time 120 WD
Days Charged to Date Ill
Contract is 100.00 Complete
Wednesday, March 25, 2026 Page I of 4
City Project Numbers 105163
Contract Name LAPRELLE WAGLEY ROBERTSON PHASE I
Contract Limits
Project Type DRAINAGE
Project Funding
UNIT III: DRAINAGE IMPROVEMENTS
Item
Description of Items
Estimated
Unit
No.
Quanity
- -
1
- - - - - - - - - - - - - -
10' CURB INLET
- - - -
1
- -
EA
2
15' CURB INLET
1
EA
3
REMOVE PLUG CONNCT TO EXISTING 24"
1
EA
STORM
4
REMOVE PLUG CONNCT TO EXISTING 21"
1
EA
STORM
Sub -Total of Previous Unit
DOE Number 5163
Estimate Number 1
Payment Number 1
For Period Ending 2/20/2026
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
-----------------
$6,000.00
$6,000.00
1
$6,000.00
$8,000.00
$8,000.00
1
$8,000.00
$4,900.00
$4,900.00
1
$4,900.00
$3,400.00
$3,400.00
1
$3,400.00
$22,300.00
$22,300.00
Wednesday, March 25, 2026 Page 2 of 4
City Project Numbers 105163
Contract Name LAPRELLE WAGLEY ROBERTSON PHASE I
Contract Limits
Project Type DRAINAGE
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Total Contract Price
DOE Number 5163
Estimate Number 1
Payment Number 1
For Period Ending 2/20/2026
$22,300.00
$22,300.00
Total Cost of Work Completed
$22,300.00
Less % Retained
$0.00
Net Earned
$22,300.00
Earned This Period $22,300.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$22,300.00
Wednesday, March 25, 2026 Page 3 of 4
City Project Numbers 105163
Contract Name LAPRELLE WAGLEY ROBERTSON PHASE I
Contract Limits
Project Type DRAINAGE
Project Funding
Project Manager NA
Inspectors A. DUARTE / H. TAEZAZ
Contractor ACADIA SERVICES
1510 JELMAK ST
GRAND PRAIRIE, TX 75050
DOE Number 5163
Estimate Number 1
Payment Number 1
For Period Ending 2/20/2026
City Secretary Contract Number
Contract Date
Contract Time 120 WD
Days Charged to Date III WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $22,300.00
Less % Retained $0.00
Net Earned $22,300.00
Earned This Period $22,300.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$22,300.00
Wednesday, March 25, 2026 Page 4 of 4
FORT WORTH.
TRANSPORTATION AND PUBLIC WORKS
March 20, 2026
Acadia Services,LLC
351 W. Southlake Blvd.
Southlake,Tx 76092
RE: Acceptance Letter
Project Name: LaPrelle Wagley Robertson Phase 1A
Project Type: Drainage
City Project No.: 105163
To Whom It May Concern:
On February 24, 2026 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on March 19, 2026. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on March 19, 2026, which is the date of
the punch list completion and will extend of two (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-8424.
Sincerely,
Sandip Adhikari , Project Manager
Cc: John Rogers, Inspector
Troy Gardner, Inspection Supervisor
Charles Hayes, Senior Inspector
Andrew Goodman, Program Manager
BGE, Inc., Consultant
Acadia Services, LLC, Contractor
TPHMI DFW 4047, LLC, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Will Collins, Senior
Project Manager Of Acadia Services, known to me to be a credible person,
who being by me duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
CPN 105163 LaPrelle Wagley Robertson Ph. lA r 'nage Improvements
BY
Vv i 1 Collins - Senior Project Manager
Subscribed and sworn before me on this date 1st of April, 2026.
l�
Notary Public
Tarrant, TX
Guillermo Barron
My Commission Expires
016/2027
Notary ID134594465
CONSENT OF
OWNER
ARCHITECT I
SURETY COMPANY
CONTRACTOR
TO FINAL PAYMENT
SURETY
OTHER I_,
AIA DOCUMENT G707
Bond No. 4408822
PROJECT: LaPrelle Phase 1A (Wagley Robertson Rd)
(name, address) 303 Blue Mound Road West Haslet TX
TO (Owner)
F ARCHITECT'S PROJECT NO: City Project No. 105163
TPHMI DFW 4047, LLC CONTRACT FOR: Drainage Improvements
6201 W. Plano Pkway, Suite 150
Plano, TX 75093
I CONTRACT DATE: 4/4/2024
L__.. J
CONTRACTOR: Acadia Services, LLC
351 W. Southlake Blvd. Southlake, TX 76092
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(here insert name and address of Surety Company)
FCCI Insurance Company
6300 University Parkway , Sarasota, FL 34240 SURETY COMPANY,
On bond Of (here Insert name and address of Conlractor)
Acadia Services, LLC
351 W. Southlake Blvd. Southlake, TX 76092 CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not
relieve the Surety Company of any of its obligations to (here insert name and address of owner)
TPHMI DFW 4047, LLC
6201 W. Plano Pkway, Suite 150 Plano, TX 75093 OWNERS,
as set forth in the said Surety Company's bond.
IN WITNESS WHEREOF,
the Surety Company has hereunto set its hand this 15th day of December, 2025
FCCI Insurance Company ,���N....
Surety Compa A"0 ' 7
=LL' SrAL =<_
1"4 a
'' • ignatu f Auth epresentative
Attest: !'_2�t`,�l�l :...
(Seal): BaiLee Islas, Surety Witness enni er U A orne -in-Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND
CLAIMS, Current Edition
AIA DOCUMENT G707 • CONSENT OF SURETY COMPANY TO FINAL PAYMENT • APRIL 1970 EDITION • AIA® ONE PAGE
Q 1970 • THE AMERICAN INSTITUTE OF ARCHITECTS. 1735 NEW YORK AVE.. NW. WASHINGTON, D.C. 20006
FCcrINSUL,RANCE
r,Ror
GENERAL POWER OF ATTORNEY
Know all men by these presents: That the FCCI Insurance Company, a Corporation organized and existing under
the laws of the State of Florida (the "Corporation") does make, constitute and appoint:
Jennifer Upton
Each, its true and lawful Attorney -In -Fact, to make, execute, seal and deliver, for and on its behalf as surety, and
as its act and deed in all bonds and undertakings provided that no bond or undertaking or contract of suretyship executed
under this authority shall exceed the sum of (not to exceed $20,000,000.00): $20,000,000.00
Surety Bond No.: 4408822
Principal: Acadia Services, LLC
Obligee: TPHMI DFW 4047, LLC
This Power of Attorney is made and executed by authority of a Resolution adopted by the Board of Directors. That
resolution also authorized any further action by the officers of the Company necessary to effect such transaction.
The signatures below and the seal of the Corporation may be affixed by facsimile, and any such facsimile
signatures or facsimile seal shall be binding upon the Corporation when so affixed and in the future with regard to any
bond, undertaking or contract of surety to which it is attached.
In witness whereof, the FCCI Insurance Company has caused these presents to be signed by its duly authorized
officers and its corporate Seal to be hereunto affixed, this 23rd day of July 2020.
e �,/� • : SVFtANCE co,•
Attest: pPo �`�• �'-
Christina D. Welch, President LL ` SEAL 9< Christopher Shoucair,
FCCI Insurance Company ,,„,,, EVP, CFO, Treasurer, Secretary
'-�oa1oV. ' ;' FCCI Insurance Company
State of Florida
County of Sarasota
Before me this day personally appeared Christina D. Welch, who
is personally known to me and who executed
the foregoing document for the purposes expressed therein.
My commission expires: 2/27/2027 rewym w
\ d1 �s1.)
• CWWWoni�x UM
Notary Public
tea•
�ja^I' Yn.2W
State of Florida
County of Sarasota
Before me this day personally appeared Christopher Shoucair, who is personally known to me and who executed
the foregoing document for the purposes expressed therein.
! `, „_NH
My commission expires: 2/27/2027 C*nmkW
'► of ", E*Wftb W ,20Z/
c
Notary Public
CERTIFICATE
I, the undersigned Secretary of FCCI Insurance Company, a Florida Corporation, DO HEREBY CERTIFY that the
foregoing Power of Attorney remains in full force and has not been revoked; and furthermore that the February 27, 2020
Resolution of the Board of Directors, referenced in said Power of Attorney, is now in force.
,y�FAricF� Dated this 15th day of December 2025
;1a; •aver ••..�.�°.
SEA
199; Christopher Shoucair, EVP, CFO, Treasurer, Secretary Shoucair, EVP, CFO, Treasurer, Secretary
�1GRCd FCCI Insurance Company
1-IONA-3592-NA-04, 7/2021