HomeMy WebLinkAbout061920-FP2 - Construction-Related - Contract - Conatser Construction TX, L.P.-FP2
City Secretary
Contract No. 61920
FORT WORTH..,
Date Received 4/3/2026
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Northpointe West Phase 4
City Project No.: 104932
Improvement Type(s): ❑x Paving x❑ Drainage ❑ Street Lights ❑ Turn Lane
Original Contract Price:
$2,713,713.25
Amount of Approved Change Order(s):
Revised Contract Amount:
$2,713,713.25
Total Cost of Work Complete:
$2,713,713.25
-A.a
Arturo Sancen (Apr 3, 2026 12:46:13 CDT)
Contractor
Superintendent
Title
Conaster Construction TX, L.P.
Company Name
MioMol Sarron
Michael Barton (Aar 3. 2026 12:46:56 CDT)
Project Inspector
Raw Twan
Ram Twari (Aor 3. 2026 14:16:38 CDT)
Project Manager
11�
CFA Manager
Lauren Prieur (Apr 3, 2026 15:12:48 CDT)
TPW Director
04/03/2026
Date
04/03/2026
Date
04/03/2026
Date
04/03/2026
Date
04/03/2026
Date
OFFICIAL RECORD
CITY SECRETARY
Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Northpointe West Phase 4
City Project No.: 104932
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes x❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 220 WD Days Charged: 278 WD
Work Start Date: 10/1/2024 Work Complete Date: 3/12/2026
Completed number of Soil Lab Test: 1332
Completed number of Water Test: 41
Page 2 of 2
FoRTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name NORTHPOINTE WEST PHASE 4
Contract Limits
Project Type DRAINAGE & PAVING
City Project Numbers 104932
DOE Number 4932
Estimate Number 1 Payment Number 1 For Period Ending 3/12/2026
WD
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors M.GLOVER / M.BARRON
Contract Time 22WD
Days Charged to Date 278
Contract is 100.00 Complete
Thursday, March 12, 2026 Page 1 of 5
City Project Numbers 104932
Contract Name NORTHPOINTE WEST PHASE 4
Contract Limits
Project Type DRAINAGE & PAVING
Project Funding
UNIT III: DRAINAGE IMPROVEMENTS
DOE Number 4932
Estimate Number 1
Payment Number 1
For Period Ending 3/12/2026
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
- -
I
- - - - - - - - - - - - - -
REMOVE 4' DROP INLET
- - - - - - -
1 EA
- - -
$2,500.00
- - - -
$2,500.00
- - - -
1
- - - - -
$2,500.00
2
REMOVE 5' DROP INLET
1 EA
$3,500.00
$3,500.00
1
$3,500.00
3
LARGE STONE TYPE "A" DRY RIP RAP (12"
1268 SY
$125.00
$158,500.00
1268
$158,500.00
DEEP)
4
TRENCH SAFETY
2687 LF
$2.00
$5,374.00
2687
$5,374.00
5
4' STORM JUNCTION BOX
9 EA
$7,000.00
$63,000.00
9
$63,000.00
6
10' CURB INLET
10 EA
$3,800.00
$38,000.00
10
$38,000.00
7
15' CURB INLET
6 EA
$4,800.00
$28,800.00
6
$28,800.00
8
20' CURB INLET
6 EA
$5,800.00
$34,800.00
6
$34,800.00
9
4' DROP INLET
I EA
$5,000.00
$5,000.00
1
$5,000.00
10
12" HP PIPE
455 LF
$65.00
$29,575.00
455
$29,575.00
11
24" HP PIPE (CO#1)
0 LF
$80.00
$0.00
0
$0.00
12
30" HP PIPE(CO# 1)
0 LF
$100.00
$0.00
0
$0.00
13
36" HP PIPE(CO#1)
0 LF
$145.00
$0.00
0
$0.00
14
CONNECT TO EXISTING STORM LINE
6 EA
$2,500.00
$15,000.00
6
$15,000.00
15
4" CONCRETE CHANNEL
766 SY
$62.00
$47,492.00
766
$47,492.00
16
36" 4:1 SLOPED END HEADWALL
1 EA
$6,000.00
$6,000.00
1
$6,000.00
17
INLET PROTECTION
23 EA
$250.00
$5,750.00
23
$5,750.00
18
24" RCP, CLASS III (CO#1)
645 EA
$80.00
$51,600.00
645
$51,600.00
19
30" RCP,CLASS III(CO#1)
1334 EA
$100.00
$133,400.00
1334
$133,400.00
20
36" RCP, CLASS HI(CO#1)
253 EA
$145.00
$36,685.00
253
$36,685.00
Sub -Total of Previous Unit
$664,976.00
$664,976.00
UNrr IV: PAVING IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
---------------------------------------
1
HYDRATED LIME (30 LBS/SY)
519 TN
$250.00
$129,750.00
519
$129,750.00
2
6" LIME TREATMENT
34601 SY
$3.25
$112,453.25
34601
$112,453.25
3
6" CONC PVMT
32492 SY
$51.50
673,338.00
32492 1,673,338.00
4
4" CONC SIDEWALK
7781 SF
$4.00
$31,124.00
7781
$31,124.00
5
BARRIER FREE RAMP, TYPE P-1
14 EA
$2,000.00
$28,000.00
14
$28,000.00
Thursday, March 12, 2026 Page 2 of 5
City Project Numbers 104932
DOE Number
4932
Contract Name NORTHPOINTE WEST PHASE 4
Estimate Number
I
Contract Limits
Payment Number
1
Project Type DRAINAGE & PAVING
For Period Ending
3/12/2026
Project Funding
6 BARRIER FREE RAMP, TYPE R-1
20 EA
$2,000.00
$40,000.00 20
$40,000.00
7 TOPSOIL
151 CY
$28.00
$4,228.00 151
$4,228.00
8 BLOCK SOD PLACEMENT
903 SY
$8.00
$7,224.00 903
$7,224.00
9 REMOVE BARRICADE & CONNECT TO
6 EA
$500.00
$3,000.00 6
$3,000.00
EXISTING PAVEMENT HEADER
10 CONSTR BARRICADE
1 EA
$850.00
$850.00 1
$850.00
11 CONSTRUCT STD. PVMT. HEADER
29 LF
$30.00
$870.00 29
$870.00
12 STOP SIGNS
18 EA
$450.00
$8,100.00 18
$8,100.00
13 STREET NAME BLADE PAIR
14 EA
$350.00
$4,900.00 14
$4,900.00
14 STREET SIGN POLE
--------------------------------------
14 EA
$350.00
$4,900.00 14
$4,900.00
Sub-Total of Previous Unit
$2,048,737.25 $2,048,737.25
Thursday, March 12, 2026 Page 3 of 5
City Project Numbers 104932
Contract Name NORTHPOINTE WEST PHASE 4
Contract Limits
Project Type DRAINAGE & PAVING
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 1
DOE Number 4932
Estimate Number 1
Payment Number 1
For Period Ending 3/12/2026
$2,713,713.25
$0.00
Total Contract Price $2,713,713.25
Total Cost of Work Completed $2,713,713.25
Less % Retained $0.00
Net Earned $2,713,713.25
Earned This Period $2,713,713.25
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$2,713,713.25
Thursday, March 12, 2026 Page 4 of 5
City Project Numbers 104932 DOE Number 4932
Contract Name NORTHPOINTE WEST PHASE 4 Estimate Number I
Contract Limits Payment Number 1
Project Type DRAINAGE & PAVING For Period Ending 3/12/2026
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors M.GLOVER / M.BARRON Contract Date
Contractor CONATSER CONSTRUCTION TxLP Contract Time 220 WD
5327 WICHITA ST Days Charged to Date 278 WD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $2,713,713.25
Less % Retained $0.00
Net Earned $2,713,713.25
Earned This Period $2,713,713.25
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$2,713,713.25
Thursday, March 12, 2026 Page 5 of 5
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
March 12, 2026
Conatser Construction, Tx. L.P.
5327 Wichita Street
Fort Worth, TX 76119
RE: Acceptance Letter
Project Name: Northpointe West Phase 4
Project Type: Paving, Drainage
City Project No.: 104932
To Whom It May Concern:
On March 9, 2026 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on March 11, 2026. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on March 11, 2026, which is the date of
the punch list completion and will extend of two (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2237.
Sincerely,
& iiwai-r
Fain llwevi BARrCS,1112E 1 l 16 Ili 0) r,
Ram Tiwari, Project Manager
Cc: Michael Barron, Inspector
Mike Glover, Inspection Supervisor
Randy Horton, Senior Inspector
Andrew Goodman, Program Manager
UA Engineering, Consultant
Conatser Construction, Contractor
Lennar Homes, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
AFFIDAVIT
STATE OFTEXAS
COUNTY OF TARRANT
Before me, the Lindersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Group, Inc.,
general partner of Conatser Cons ti TX LP, known to me to b+c a credible person, who
being, by me duly sworn, upon his oath deposed and said:
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full,
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property darnaigcs;
On Contract described as:
NORTI IPOIIVTE VEST PH. 4
WATER, SANITARY SEWER, DRAINAGE,
PAVING, & STREET LIGHT IMPROVEMENTS
CFA PRJ ## 24-0053
CITY PROJECT # 104932
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX, LP
Subscribed and sworn to before me this aid day of April, 2026.
J � - - - -
KATHERINE ROSE
mutmA max,` oe(0ism Notary Public in Tarrant Cotinty, Tcxas
Qr 1334,47033
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conlornne wwhh the American InstiT a of
Architects, AtA Document G707
PROJECT:
Iname, addreSSjNorthpomleWWesL Prisse4
Fort NWorth. TX
TO IlOwvner)
OWNER
0
ARCHITECT
CONTRACTOR
SURETY
0
OTHER
Bored No 0280251
CITY OF FORT WORTH AND LENNM HOWS OF __j ARCHITECT' S PROJECT NO: CFA74-0053
TEXAS LAND AND CONSTRUCTION. LTD. CONTRACT FOR:
1707 M81$M Plroe E WT. "te 100 t~y(]mipcinle VftV. Phase 4 -VOW and Sss4 a y Sa w4i Improvernanlis
LrWV TX 7%63 J CONTRACT DATE:
CONTRACTOR: CONATSER CONSTRUCTION TX. L 'P'
In accordenee with the praviskms of the Contract betwcen the Owner and the Cranuwtor as indicated above, the
fhoes neon n* mo and addrew of SywwW Co-o"vh
BERKLE`i INSURANCE COMPANY
475 S,eamboa', Road
Greenw Lcri CT 46830 . SURETY COMPANY
on bond of Ihwe wtm t norm end a04r"a or Conveotat
CONATSER CONSTRUCTION TX, L P
5327Wichita 5t
I-crt wom TX 7611 35
r CONTRACTOR,
hereby approveR of the final payment to the Contractor. and agrees that fined payment to the Contractor shall not relieve
the Surety Company of any of its Obligations to owe~ Irmo ww ■dmn= oI' o~»,F
CITY OF FORT WORTH AND LEailrl►aR HOMES OF TEXAS LAND AND CONSTRUCTION h_TI)
1707 MarMlflt PMaoe Blvd., Suite 100
Irving Tx 715M , OWNER,
ss set forth in the said Surety Cwnpany's bond.
IN WITNESS, WHEREOF.
the Surety Company has hereunto set its hand this
i16 ttebt:
2nd day of April. 2026
BERKLEY iNSt RANCE COMPANY
Surety Compa"
Signature of Authorized Representative
RaLDILl"'i W... a Attorney -in -Fact
Title
NOTE Thk form is to 04 Md M a 69 W-111 dnUWMK to A" DMUMlEN7 0706. CONTRACTOR'S AFFIDAVIT' QF PAYMENT OF DEBTS AND CLAIMS,
ONE PAGE