HomeMy WebLinkAbout059847-CO2 - Construction-Related - Contract - S.J. Louis Construction of Texas, Ltd.FORT �CIRTN Cityof Fort Worth CSC No. 59847-CO2
Change Order Request
Project Name: Part 14 -Channel Segment C Sanitary Sewer Relocations City Sec No.: 59847
Project No.(s): 59847 / 104484 / 26680 / 061018052 DOE No. N/A City Proj. No.: 104484
Relocation and abandonments of sanitary sewer facilities to accommodate future Bypass Channel C by the United States, Army Corps of
Project Description: Engineering for the Fort Worth Central City project.
Contractor: S.J. Louis Construction of Texas, Ltd. Change Order # Date: 1 3/11/2026
City Project Mgr.1 Bijay Upreti, P.E. City Inspector: Stephen Martinez
Phone Number: 817-392-8909 Phone Number: 682-432-5485
Dept. i Sewer I Water
Totals I Contract Time
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
$34,824,041.30
$34,824,041.30
500
$244,271.03
$244,271.03
161
$0.00
$35,068,312.33
$35,068,312.33
661
Amount of Proposed Change Order
$3,526,707.28
$3,526,707.28
552
Revised Contract Amount $38,595,019.61
Original Funds Available for Change Orders $417,888.00
Remaining Funds Available for this CO $173,616.97
Additional Funding (if necessary) $3,353,090.31
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
$38,595,019.61
1.213
$417,888.00
$173,616.97
$3,353,090.31
10.83%
$43,530,051.63
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 2 is for the modifications described in CMR #4, PCM No. 2 and PCM No. 3. CMR No. 4 is for the
installation and removal of the concrete trail for the Cowtown marathon as requested by TRWD/Cowtown Marathon. PCM
No. 2 adjusts the sanitary sewer pipe alignment on the downstream end of the project to mitigate potential settlement
issued per CDM analysis for the additional fill area as necessitated by USACE revisions of the bypass channel design. The
additional fill area required a 164 linear feet pipe cradle to support the sanitary sewer pipe and pier foundations for siphon
structure B-1. PCM No. 2 also adds pier foundation for siphon structure C1 and C2 to accommodate poor soil conditions as
noted in RFI #14, which were identified during excavation. PCM No. 3 is for the recommended subgrade improvements for
Junction Structure A and Junction Structure D. Subgrade improvements are necessary due to the poor soils conditions
noted in RFI #14, which were identified during excavation. The cost of the work to perform all of the additional work as
described in CMR No. 4, PCM No. 2, and PCM No. 3 shall be included in the agreed cost of the change order. If there is not
a specific work item included in the change order and its required to execute the work for CMR No. 4, PCM No. 2 and PCM
No. 3 it shall be considered subsidiary to all other Work items. The change order also extends the contract time for the
project to be completed on December 15, 2026 per attached contract time determination schedule. Explanation of new line
items can be found in attachment.
Staff concurs with the contractor's request for an additional 552 calendar days on the project for delays resulting from the
above issue and to complete additional work.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Centractor's Gampany Name
-.Coht�:a%io(,f 6me [rritractor ;�
na ,.;
S.J. I r-A; Cans Cuclion 0 Te�cas-Lld. ..
—
Inspector
Clbrectof.(,NaterDept).
TS
03/26/2026
S�
i=-tan' City Attorney
104/09/2026
zs eiak a rz zoze iestao co
D9:° ' ern
04/02/2026Jesica McEaehern Dale 2026.04.0922,423ica9-OS'00'
M&C Number 26-0780
Council Action (If Required)
M&C Date Approved 3/10/2026
OFFICIAL RECORD
CITYSECRETARY
FT. WORTH, TX
Fa n-F W" RT»
City of Fort worth
Change Order Additions
Project Name Part 14 - Channel Segment C Sanitary Sewer Relocations City Sec No.: 59847
Project No.(s): 59847 / 104484 / 26680 / 061018052 1 DOE No. N/A City Proi. No.: 104484
Project
Description
Relocation and abandonments of sanitary sewer facilites to accommodate future Bypass Channel C by the United States,
Army Corps of Engineering for the Fort Worth Central City project.
Contractor S.J. Louis Construction of Texas, Ltd. I Change Order:= Date: 3/11/2026
City Project Mgr. Bijay Upreti, P.E. City Inspector Stephen Martinez
ADDITIONS
DEPT
QtY
RaitL
Unit Cost
Total
3
3331,4723 66" Fiberglass Sewer Pipe, Deep Trench Backfill
Sewer
74.00
LF
$1,346.00
$99,604.00
57
3201.0113 6' Wide Asphalt Pvmt Repair, Residential
Sewer
60.00
LF
$83.00
$4,980.00
58
3201.0203 Asphalt Pvmt Repair Beyond Defined Width, Industrial
Sewer
300.00
SY
$129.00
$38,700.00
62
3216.0101 6" Conc Curb and Gutter
Sewer
120.00
LF
$45.00
$5,400.00
63
3231.0124 8' Chain Link, Aluminum
Sewer
180.00
LF
$50.00
$9,000.00
64
3291.0100 Topsoil
Sewer
528.00
CY
$19.00
$10,032.00
65
3292.0400 Seeding, Hydromulch
Sewer
9,500.00
SY
1$0.80
$7,600.00
67
13301.0002 Post -CCTV Inspection
Sewer
74.00
LF
$1.50
$111.00
71
3305.0109 Trench Safety
Sewer
74.00
LF
$1.00
$74.00
73
3471.0001 Traffic Control
Sewer
8.00
MO
$3,000.00
$24,000.00
76
Install Concrete Trail Detour (Cowtown Marathon)
Sewer
1.00
LS
$51,222.72
$51,222.72
77
Remove Concrete Trail Detour (Cowtown Marathon)
Sewer
1.00
LS
1$10,000.00
$10,000.00
78
66" Fiberglass Sewer Pipe, Pipe Support Cradle (PCM No. 2)
Sewer
164.00
LF
$8,929.88
$1,464,500.32
79
66" Fiberglass Sewer Pipe, Deep Trench Backfill (Excavation and Backfill Onl
Sewer
1.00
LS
$404,000.00
$404,000.00
80
Additional Exploratory Excavation for PCM No.2
Sewer
1.00
LS
$7,575.00
$7,575.00
81
Additional Construction Staking for PCM No. 2 and PCM No. 3
Sewer
1.00
LS
$25,250,00
$25,250.00
82
Additional Erosion Control Devices for PCM No.2 and PCM No.3
Sewer
1.00
LS
$5,050.00
$5,050.00
83
30" Drilled Concrete Pier (Pipe Support Cradle)
Sewer
387.00
VF
$471.18
$182,346,66
84
30" Drilled Concrete Pier (Siphon Structure B-1)
Sewer
332.00
VF
$471.18
$156,431.76
85
30" Drilled Concrete Pier (Siphon Structure C-1)
Sewer
312.00
VF
$471.18
$147,008.16
86
30" Drilled Concrete Pier (Siphon Structure C-2)
Sewer
298.00
VF
$471.18
$140,411.64
87
Additional Dewatering, Site Preparation for Siphon Structure C1 and C2
Sewer
1.00
LS
$146,450.00
$146,450.00
88
Additional Special Shoring for Siphon Structure C-1
Sewer
1.00
LS
$101,000.00
$101,000.00
89
3305.0203 Imported Embedment/Backfill, CLSM
Sewer
1,000.00
CY
$160.00
$160,000.00
90
Junction Structure A (Subgrade Stabilization per PCM No.3)
Sewer
1.00
LS
$30,300.02
$30,300.02
91
Junction Structure D (Subgrade Stabilization per PCM No. 3)
Sewer
1.00
LS
$404,000.00
$404,000.00
Page 2 of 4
Sewer
$3,635,047.28
Water
Additions Sub Total
$3,635,047.28
Fn lEz.T W[l lEz.T H City of Fort Worth
Change Order Deletions
Project Name Part 14 - Channel Segment C Sanitary Sewer Relocations City Sec No.: 59847
Project No.(s): 59847 / 104484 / 26680 / 061018052 DOE No. N/A City Proj. No.: 104484
Project Description
Relocation and abandonments of sanitary sewer facilites to accommodate future Bypass Channel C by the United
States, Army Corps of Engineering for the Fort Worth Central City project.
Contractor I S.J. Louis Construction of Texas, Ltd. Change Order: E�:] Date 1 3/11/2026
City Project Mgr. Bijay Upreti, P.E. City Inspector: Stephen Martinez
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
1 3331.4721 66" Fiberglass Sewer Pipe Sewer 82.00 LF $1,284.00 $105,288.00
28 3339.1103 5' Extra Depth Manhole Sewer 4.00 VF $263.00 $1,052.00
37 3339.0001 Epoxv Manhole Liner Sewer 4.00 VF $500.00 $2,000.00
r 1$108,340.00
Deletions Sub Total 1$108,340.00 1
Page 3 of 4
Kimley>Morn REQUEST FOR INFORMATION
Project:
RFI #: 014
FWCC Part 14 — Channel Segment C Sanitary
Sewer Relocations
Project No.: City Project No. 104484
Date Initiated: 11/17/2025
KHA No. 061018052
Sender: S.J. Louis Construction of Texas
Receiver: Kimley-Horn and Associates, Inc.
Copies To:
Subject: Existing Soil Conditions at Structures C1 and C2
Request:
See attached RFI
Sender's Proposed Answer/Solution:
N/A
THE PROPOSED ANSWER/SOLUTION❑ IS, ® IS NOT, INCLUDED IN THE CONTRACT.
Receiver's Response:
Further evaluation has been performed along the entire pipeline alignment and the following
approach should be taken by the Contractor. Engineer will follow up with a proposed
contract modification and request a change order proposal from the Contractor for the
additional scope of work required:
o Junction Structure A (12' Diameter Polymer Concrete Manhole):
■ Remove underlying soils to a minimum of 4-feet below proposed manhole
bottom extending outward beyond proposed manhole footing (15.2-feet) a
minimum of 2-feet, replace with compacted ASTM No. 57 stone (-80 CY).
o Siphon Structure C-1:
■ Install drilled piers below proposed structure as indicted in revised drawings
in PCM-02.
o Siphon Structure C-2:
■ Install drilled piers below proposed structure as indicted in revised drawings
in PCM-02.
o Junction Structure D (12' Diameter Polymer Concrete Manhole):
• Remove underlying soils to a minimum of 13-feet below proposed manhole
bottom extending outward beyond proposed manhole footing (15.2-feet) a
minimum of 6-feet, replace with compacted ASTM No. 57 stone (~360 CY).
Response By: Company: Date:
Josh Kercho, P.E. Kimley-Horn and Associates, Inc. 12/19/2025
DISTRIBUTION:
S.J. Louis Construction of Texas Ltd. (Ronald Etter, Adam Lunsford)
City of Fort Worth Water Department (Bijay Upreti, Stephen Martinez)
Kimley-Horn Project File
kimley-horn.com
18 RFI (RFI) - 4
Project: 104484-14 - W&SS Relocations
for the FWCC Project - Part 14
-Channel Segment C SSr Reloc
Process
RFI - 4
Document:
Current Workflow
Consultant Review/Revise
Step:
Subject:
Existing Soil Conditions at
Structures C1 and C2
Status:
Received
General Information
Question:
Priority:
RT WORTHO
Project Number: 104484-14
Overall Due Date: 11.17.2025 OS:OOPM
Step Due Date:
While excavating down for structure C-2 the subgrade for this structure is very unstable
and doesn't appear suitable to construct the C-2 structure as shown in plans unless some
additional measures are taken to prevent settlement of the structure. Can the FOR and
the GeotechnicaI Engineer review the existing ground conditions in this area and provide
clarification on what is needed to support the structure? Please review structure C-1 as
well as it is in the same area.
High
Is there a Potential
Cost Impact?: Yes
Estimated Cost ($): If yes was selected, please indicate the estimated cost by entering a whole
number.
1
Is there a Potential
Schedule Impact?:
Yes
Estimated
If yes was selected, please indicate the estimated number of days.
Schedule Impact:
1
Plan Sheet
Number:
18A and 19A
Specification
Section:
Proposed Solution:
Need direction from Engineer or Geotech on what might be required to support the
structures. Possibly drilled piers similar to what was added downstream.
Date Submitted:
11.12.2025
Final Response
Final Response:
Updated Plan
Sheet:
Initiate Change «Change Order Request>>
Order Request?:
Comments
Josh Kercho, KIMLEY HORN AND ASSOCIATES INC, 11.18.2025 9:41 PM
Requested comment on step Consultant Review/Revise from Carl DeZee (KIMLEY HORN
AND ASSOCIATES INC), Collin McGovern (IUMLEY HORN AND ASSOCIATES INC),
Ivan Rocha (KIMLEY HORN AND ASSOCIATES INC).
can yall respond with a formal RFI?
Bijay Upreti, Fort Worth Water, 11.13.2025 2:35 PM
Please review and respond.
City of Fort Worth, Texas
Mayor and Council Communication
DATE: Tuesday, March 10, 2026 REFERENCE NO.: **M&C 26-0180
LOG NAME: 60FWCCP14SSRCO2-SJLOUIS
SUBJECT:
(CD 2 and CD 9) Authorize Execution of Change Order No. 2 in the Amount of $3,526,707.28 to a Contract
with S.J. Louis Construction of Texas, Ltd., for the Fort Worth Central City Part 14 - Channel Segment C,
Sanitary Sewer Relocation, Adopt a Resolution Expressing Official Intent to Reimburse Expenditures with
Proceeds of Future Debt, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to
the Fiscal Years 2026-2030 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No. 2 in the amount of $3,526,707.28 to City Secretary No.
59847 a contract with S.J. Louis Construction of Texas, Ltd. for the Fort Worth Central City Part 14 -
Channel Segment C, Sanitary Sewer Relocation for a revised contract amount of $38,595,019.61;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds
from future debt and/or annual payments from the Tarrant Regional Water District for the Fort Worth
Central City Water and Sewer Relocations project; and
3. Adopt the attached appropriation ordinance adjusting appropriations in the Water and Sewer
Commercial Paper Fund by increasing appropriations in the Fort Worth Central City Water and
Sanitary Sewer Relocations project (City Project No. 104484) in the amount of $3,526,708.00 and
decreasing appropriations in the W&S Commercial Paper project (City Project No. UCMLPR) by the
same amount to effect a portion of Water's contribution to the Fiscal Years 2026-2030 Capital
Improvement Program.
DISCUSSION:
On June 27, 2023 by Mayor and Council Communication (M&C) 23-0542, the City Council authorized a
construction contract with S.J. Louis Construction of Texas, Ltd. in the amount of $34,824,041.30 for Fort
Worth Central City Part 14 - Channel Segment C, Sanitary Sewer project. The contract was subsequently
revised by Change Order No. 1 in the amount of $244,271.03 authorized by the City Council on March 25,
2025 (M&C 25-0268) that provided for sanitary sewer main and manhole rim elevation adjustments
between stations 1+00 and 7+00 to accommodate future Channel grading by the United States Army
Corps of Engineers (USACE).
Change Order No. 2 primarily provides for the following: Adjustments to the sanitary sewer pipe alignment
on the downstream end of the project to mitigate potential future settlement (from any analysis conducted
by the consultant USACE for additional fill area due to the USACE's revisions to its bypass channel
design; A 164 foot 30-inch pipe cradle to support the sanitary sewer pipe and 30-inch pier for siphon
structure B-1 due to the additional fill; Pier foundations for siphon structures C1 and C2 to accommodate
unstable and unusable soil material that was encountered during excavation; Additional dewatering, site
preparation and shoring for the installation of siphon structures C1 and C2 due to unstable and unusable
soil material that was encountered during construction; Additional subgrade stabilization for junction
structures A and D due to unstable and unusable soil material that was encountered during excavation;
Flowable fill material to replace unstable material that is encountered during construction and installation
and removal of the concrete sidewalk detour requested by the Cowtown Marathon.
This project is anticipated to be repaid from a series of annual reimbursements from the Tarrant Regional
Water District (TRWD) as part of the Fort Worth Central City (FWCC) Water & Sewer Relocations project.
In the event any bond -eligible costs are not fully reimbursed by TRWD, those costs would be anticipated
to be included in a future revenue bond issue for the Water & Sewer Fund. Available cash within the Water
and Sewer portfolio and the City's portfolio along with the appropriation authority authorized under the
Callable Commercial Paper Program (CP) will be used to provide interim financing for this project until the
debt is issued. Once payment is received from TRWD and/or debt associated with the unreimbursed
portions of this project is sold, those funds will be used to reimburse the Water and Sewer portfolio and the
City's portfolio in accordance with the attached reimbursement resolution. Under federal law, debt must be
issued within approximately three years in order for these expenses to be reimbursable. Adoption of the
attached resolution does not obligate the City to sell bonds but preserves the ability of the City to
reimburse itself from tax-exempt bond proceeds.
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY),
instead of within the annual budget ordinance, as projects commence, additional funding needs are
identified, and to comply with bond covenants.
Funding for the Fort Worth Central City Part 14 - Channel Segment C, Sanitary Sewer Relocations in the
FWCC Water and Sewer Relocations Project is depicted below:
Fund
Existing
Appropriations
Additional
Appropriations
Project Total*
W&S
Commercial
Paper— Fund
$28,420,939.77
$3,526,708.00
$31,947,647.77
56026
W&S Capital
_
Projects — Fund
$28,017,620.49
$0.00
$28,017,620.49
56002
Project Total
$56,438,560.26
$3,526,708.00
$59,965,268.26
Note: This table includes the actions considered in M&C 26-0112 on the February 10, 2026 City Council
Agenda.
The sanitary sewer $3,526,707.28 amount of this Change Order is considered Trinity River Vision
Authority (TRVA)-relocated work, which are eligible for funding from Tax Increment Reinvestment Zone
No. 9 pursuant to the TRVA Project Plan. Having met its $26.6 million commitment to the TRVA project,
the City will be reimbursed the sanitary sewer amount of $3,526,707.28 by TRWD, in accordance with
provisions of the executed Interlocal Agreement between the City and the TRWD (City Secretary Contract
No. 43425 as amended). The TRVA Program Manager in the FW Lab Department will be responsible for
collecting the full reimbursement from TRWD at the end of each fiscal year.
Funding is available within the W&S Commercial Paper Fund for the Water Department for the purpose of
funding the FWCC Water & Sewer Relocations project.
This project is located in COUNCIL DISTRICTS 2 and 9.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Commercial Paper project within
the W&S Commercial Paper Fund and upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the W&S Commercial Paper Fund for the
FWCC Water & Sewer Relocations project to support execution of the change order. Prior to any
expenditure being incurred, the Water Department has the responsibility to validate the availability of
funds.
FUND IDENTIFIERS (FIDs):
TO
and Department �ccoun Project frog
ID ID
Budget Reference #
Year (Chartfield 2'
FROM
Fund
Department
Accoun
Project
Program
ctivity
Budget
Reference # mount
ID
ID
Year
(Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by_ Jesica McEachern (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Bijay Upreti (8909)
ATTACHMENTS
1. 60FWCCP14SSRCO2-SJLOUIS FID Table (WCF 02.03.26).xlsx (CFW Internal)
2.60FWCCP14SSRCO2-SJLOUIS.pdf (Public)
3. 60FWCCP14SSRCO2-SJLOUIS FundsAvail.docx (CFW Internal)
4. Commercial Paper as of 02.03.26.xlsx (CFW Internal)
5. Form 1295.pdf (CFW Internal)
6. ORD.APP 60FWCCP14SSRCO2-SJLOUIS 56026 A026(R3) - JLM.docx (Public)
7. PBS CPN 104484.pdf (CFW Internal)
8. Res.60FWCCP14SSRCO2-SJLOUIS (Rev2.19.26).docx (Public)
X „ X
H YI YI
O O O
a a a
L L L
3 3 3
a a a
N
c
c c
E
E I- E
I-
a
a =a
W
J
L
0
d
M _
M Y m
Y
cn
O
a u
O O
a Z a
7
111
'1
H
V H
V u
H
LL
LL
Z
W
a
a X d
to ba
m
m L m Y
0
W
m
Z
a+
LU
++
a
a Lua
a
oil
a C d
0
o
0 'o
LL
a`
a` a`
c
3
c c
3 3
O
U
O O
U U
U
a
U U
a a
oil
11
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
DigifellVsignad by Bijay Upreb
DNGUS,
Bijay Upreti 'N°°e;;av�pr@fe
Gale: 2025.04.11 14:18:-5-
Signature
Bijay Upreti, P.E.
Name of Employee
Sr. Professional Engineer
Title
anpq
AoFFOR*waa
J a n n ette S. Digitally signed by
ATTEST: Jannette S. Goodall
$a♦o, a,>,tl
Goodall Date:2026.04.10
aaQnnX6saa
08:31:30-05'00'
Jannette S. Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: S.J. Louis Construction of Texas, Ltd.
Subject of the Agreement:
Part 14 - Channel Segment C Sanitary Sewer Relocations
M&C Approved by the Council? * Yes ❑ No 0
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑✓ No ❑
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see back page for permanent contract listing.
59847-CO2
Is this entire contract Confidential? *Yes ❑ No ❑✓ If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 3/10/26
If different from the approval date.
Expiration Date:
N/A
If applicable.
Is a 1295 Form required? * Yes 0 No ❑
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 104484
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ❑✓ No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.