HomeMy WebLinkAbout28308-02-2026 - City Council - OrdinanceOrdinance No. 28308-02-2026
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN
THE WATER AND SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF
$9,774,623.00, FROM AVAILABLE PAYGO RESIDUALS IN THE WATER AND SEWER
CAPITAL PROJECTS FUND, FOR THE PURPOSE OF FUNDING THE WATER AND
SANITARY SEWER REPLACEMENT CONTRACT 2019 WSM-L PROJECT (CITY
PROJECT NO. 103380); PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance 27979-09-2025, as
amended, is hereby further amended to make the following adjustments by increasing estimated receipts and
appropriations in the Water and Sewer Capital Projects Fund in the amount of $9,774,623.00, from available PayGo
Residuals in the Water and Sewer Capital Projects Fund, for the purpose of funding the Water and Sanitary Sewer
Replacement Contract 2019 WSM-L project (City Project No. 103380).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any
reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining
portions, sections, or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force
and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27979-09-2025 and all other ordinances and appropriations
amending the same except in those instances where the provisions of this ordinance are in direct conflict with such other
ordinances and appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations
are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Apr 27, 2026 10:42:21 CDT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: February 10, 2026
CITY SECRETARY
Jannette S. Goodall
City Secretary o C
Q**00004C
°°Rra�
.�. �000
o
o
00000000 �4� �EXASo�p
MC CART AVE
7O
O
WAYSIDE AVE
FRAZIER AVE
O
z
0
�.
TOWNSEND DR
GORDON AVE '
RYAN AVE
BALDWIN ST
LIVINGSTON AVE
FOREST PARK BLVD_ 'Ji _
a�aarr
Q
m
V)70
c•
C i ,t_a , "3• GORDON AVE
poop
..dmrr�
a -41C CART AVE
' WAYSIDE AVE �•E_ a
�. FRAZIER AVE ,
v _
z TOWNSEND DR
cn
LIVINGSTON AVE
STANLEY AVE mm i •.
v JAMESAVE_
v R
(n
O
z cn
N D _ �'�_�L� �-.• ... � 8TH -AVE. �.�.1.yT,•�.�,:a.�.�`
RYAN AVE
WILLING AVEs.. WILLING
O m� v
-- Q �I
v 0
x m ;
p -cn1 5TH AVE W
m
mo �
Ry
q
R N'O<qCF
cn
Z
v
0
Z
0
r
0
um
1 ig
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 02/10/26
LOG NAME: 60WSSC19WSMLPl-GRATEX
SUBJECT
M&C FILE NUMBER: M&C 26-0114
(CD 9 and CD 11) Authorize Execution of a Contract with Gra-Tex Utilities, Inc., in the Amount of $8,949,903.00 for Water and Sanitary Sewer
Replacement Contract 2019 WSM-L Project Part-1 and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal
Years 2026-2030 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with Gra-Tex Utilities, Inc., in the amount of $8,949,903.00 for Water and Sanitary Sewer Replacement
Contract 2019, WSM-L project Part-1; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $9,774,623.00, from available PayGo residuals, for the purpose of funding the Water and Sanitary Sewer Replacement
Contract 2019 WSM-L project (City Project No. 103380) and to effect a portion of Water's contribution to the Fiscal Years 2026-2030 Capital
Improvement Program.
DISCUSSION:
This Mayor & Council Communication (M&C) is to authorize execution of a construction contract with Gra-Tex Utilities, Inc., in the amount of
$8,949,903.00 for the replacement of cast iron water and/or deteriorated sanitary sewer mains as indicated on the following streets and alleys:
Scope
COUNCIL
Street
From
To
of
DISTRICT
Work
Livingston Avenue
Cleburne
W. Biddison
Water/
9 and 11
Road
Street
Sewer
Cleburne Road
Livingston
W. Cantey
Water/
9
Avenue
Street
Sewer
Stanley Avenue
Cleburne
W Berry
Water
9
Road
Street
W. Berry Street
Livingston
James
Water/
9
Avenue
Avenue
Sewer
Alley between
Cleburne
W. Devitt
Livingston Avenue
Road
Street
Sewer
9
and Stanley Avenue
Alley between Stanley 200 feet
225 feet
Avenue and James
south of W.
south of W.
Sewer
9
Ave
Berry Street
Devitt Street
Additionally, asphalt pavement rehabilitation will be conducted on all the roadways curb to curb subsequent to the water and sanitary sewer main
replacement.
The project was advertised for bids on November 12, and November 19, 2025, in the Fort Worth Star -Telegram. On December 18, 2025, the
following bids were received:
Bidder
Gra-Tex Utilities, Inc.
SYB Construction, Inc
William J. Schultz, Inc. dba Circle C
Construction Company
Woody Contractors, Inc.
Amount Time of
Completion
650
$8,949,903.00 Calendar
Days
$9,286,740.76
$9,786,194.00
$11,535,831.00
Western Municipal Construction of $13,607,657.00
Texas, LLC
Small Business ( SB) Goal - Gra-Tex Utilities, Inc is in compliance with the small business goal.
In addition to the contract amount, $511,473.00 (Water: $383,533.00, Sewer: $127,940.00) is required for project management, material testing,
and inspection. Project contingencies are provided in the amount of $313,247.00 (Water: $234,584.00; Sewer: $78,663.00).
This project will have no impact on the Water Department's operating budget when completed. The sanitary sewer component of this project is part
of the Sanitary Sewer Overflow Initiative Program of the Water Department. Approximately 10,620 linear feet of cast iron water pipe and 4,150
linear feet of sanitary sewer pipe will be removed and replaced as part of this project.
It is the practice of the Water Department to appropriate its Capital Improvement Program (CIP) plan throughout the Fiscal Year, instead of within
the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants.
Funding is budgeted in the Unspecified -All Funds project within the Water and Sewer Capital Projects Fund for the purpose of funding the W/SS
Contract 2019 WSM-L project.
Appropriations for the Water and Sanitary Sewer Replacement Contract 2019 WSM-L project are as depicted below:
Fund Existing Additional project Total*
Appropriations Appropriations
W&S Capital
Projects - Fund $1,181,787.00 $9,774,623.00 $10,956,410.00
56002
IlProject Total $1,181,787.00 $9,774,623.001$10,956,410.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICTS 9 and 11.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified -All Funds project within the W&S Capital Project Fund, and
upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital
Projects for the W&SS Contract 2019 WSM-L project to support the execution of the construction contract. Prior to an expenditure being incurred,
the Water Department has the responsibility of verifying the availability of funds.
Submitted for Citv Manaaer's Office bv: Jesica McEachern 5804
Oriainatina Business Unit Head: Chris Harder 5020
Additional Information Contact: Jaikson Jacob 7866