HomeMy WebLinkAbout025078 - Construction-Related - Contract - Bauer Sport FloorsCITY COSECRETARY
NTRACT NCB
THE CITY OF FORT WORTH, TEXAS
BERTHA COLLINS
COMMUNITY CENTER
GYMNASIUM FLOOR REPLACEMENT
F0RJWORTH
KENNETH BARR BOB TERRELL
MAYOR ,4ITY MANAGER
21ccinoryh7SECH"
CifKt
CTOrs BONDING.:s.
____ CITY MANACfn Off
- ENGlNEtNG DIV.
TIM - NU COPY
HUGO MALANGA, Director
Department of Transportation and Public Works
1999
It
Apr 16 99 02:57p TPW 817-871-8488
}
CITY OF FORT WORTH
TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
ADDENDUM NO.2
April 7, 1999
LI REPLACEMENT OF GYMNASIUM WOOD FLOOR
BERTHA COLLINS COMMUNITY CENTER
0 Bid Opening Date: April 22, 1999
0
0
'l
I
I
0
C
0
a
0
0
The Contract Documents and Specifications for the above referenced project are hereby revised and
amended as follows:
Specifications:
Division 09590, Page 1, Change Project Scope to read:
"Remove existing flooring and plywood to existing clip -mounted sleepers. Remove shoe mold, wood
base, and expansion joint covers at entrance doors, exit doors, and doors to adjacent areas. Install
new expansion joint covers around floor and at all doors opening into gymnasium. Uneven settlement
of portions of the concrete sub -floor will require re -leveling of sleepers to make entire area level and
match existing wood floor in remainder of center. See limits of work required. Replace rotted
sleepers as required by negotiated change order."
Delete 2.01 in its entirety.
Revise 2.02 A.1 to read
1. Grade: No. 2 or better
Revise 2.02 E to read: "Thickness 25/32""
Delete 2.03A and B
Add 2.03.C Wood Sleepers
1. Reuse existing, remount on clips to level as required provide panto Dipped
2. Delete requirement for fire retardant treated sub -floor materials, p ply
sleepers where replacing existing.
3. Replace rotted or otherwise unacceptable sleepers as required by negotiated change order
Delete Section D. Rubber mounts
Add 2.03.J. Subfloor to be single layer 3/4" CDX plywood laid on sleepers at 45 degrees to
longitudinal dimension of floor.
Delete 3.03 A and B. Revise 3.03 C to read
C. CDX�" thick plywood
Drawings
Page 2 of 2
Addendum 2 Page 1 of 2
p.8
0
Apr 16 99 02:57p TPW
817-871-8488 p.9
I
I
I
I
e
I
I
I
0
Page 2 of 2
Details 1, 3.5. and 6: Change thickness of floor from 33/32" to 25/32".
Notes by symbol, Revise and add following notes to read 2 Level sleepers with hand held instruments, adjust sleepers as necessary
24 Reuse existing sleepers, shim to level
25 Delete in its entirety
27 Modify threshold to work floor height
28 Modify expansion joint covers at doors to provide smooth transition
31 secure surface mounted expansion joint cover plates along one side only.
Acknowledge the receipt of this addendum on your Proposal.
H. A. MALANGA, P.E.
DIRECTOR OF SPORT TIO PUBLIC WORKS
By:
Bob Wood, R. A., Architectural SerkoS
RELEASE DATE: April 7, 1999
Addendum2 Page 2 of 2
Apr 16 99 02:54p TPW 817-871-8488 p.2
9:
CITY OF FORT WORTH
[] TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
ADDENDUM NO.1
9 REPLACEMENT OF GYMNASIUM WOOD FLOOR
BERTHA COLLINS COMMUNITY CENTER
[I Bid Opening Date: April 22, 1999 (Delayed two weeks)
The Contract Documents and Specifications for the above referenced project are hereby revised and
amended as follows:
Revised Notice to Bidders is attached
0 Bid Date is changed
Prebid Conference is changed to 10:00 AM, Tuesday, April 6, 1999
Revised Proposal is attached. •.
0 City of Fort Worth Standard Wage Rates are attached.to replace Federal. Wage Rates.
U. Acknowledge the receipt of this addendum on your Proposal.
H. A. MALANG P.E.
DIRECTO F SPPO A D BLIC WORKS U . By.
ob Wood, X. Architectural ervlces
9 RELEASE DATE: March 19, 1999
U
0
0
U
a
aAddendum I Page 1 of 6
El
El
Apr 16 99 02:54p TPW 817-871-8488 p.3
U,
J
J
0
0
J
J
0
0
0
[I
0
C
0
NOTICE TO BIDDERS
Revised 3119199
Sealed bids for the replacement of gymnasium wood floor at the Bertha Collins Community Center,
1501 Martin Luther King Freeway, North, Fort worth, will be received at the Purchasing
hasApril g2,1 Office, City of
Fort Worth, 1000 Throckmorton, Fort Worth�fi�7�,yu�iNriy7'.30 P�M-,es IThuater 'rsdn he'Council Chambers.
will be opened and publicly read aloud app
A Pre -Bid Conference will be held at 10:00 AM, Tuesday, April 6,1999, at the Bertha Collins
Community Center, MAPSCO 77B.
The Project consists of replacing the existing wood gymnasium floor. Including rubber base, leveling
shims, metal expansion threshold, striping and finish.
The MWBE Goal for this project is 10%. Contact the MWBE office (871-6104) to obtain lists of
certified subcontractors and suppliers.
Contractors will be required to post a Payment Bond and provide Contractors General Liability and
Statutory Workers Compensation Coverage.
Copies of the Project Manual and plans for this project may be obtained at the Department of
Engineering Plans Desk, City Hall, 1000 Throckmorton Street (817-871-7910) In return for a $50
deposit for each set. For additional information contact Bob Wood, 871-8088.
Advertisement: March 25, 1999
April 1, 1999
Addendum 1 Page 2 of 6
I
Apr 16 99 02:55p TPW 817-871-8488 p.4
IJ'
U.
PROPOSAL
TO: MR. BOB TERRELL
CITY MANAGER
CITY OF FORT WORTH, TEXAS
FOR: REPLACEMENT OF GYMNASIUM WOOD FLOOR
BERTHA COLLINS COMMUNITY CENTER,
1501 MARTIN LUTHER KING FREEWAY, NORTH
FORT WORTH, TEXAS
Pursuant to the foregoing "Notice to Bidders," the undersigned has thoroughly examined the plans,
specifications and the site, understands the amount of work to be done, and hereby proposes to do all
the work and furnish all labor, equipment and materials necessary to fully complete all the work as
provided in the plans and specifications, and subject to the Inspection and approval of the Director of
[J Transportation and Public Works of the City of Fort Worth.
Upon acceptance of this Proposal by the City Council, the bidder is bound to execute a contract and, if
[J the contract amount exceeds $25,000.00, furnish Performance and/or Payment Bonds approved by
the City of Fort Worth for performing and completing the Work within the time stated and for the
following sum, to. wit:
j DESCRIPTION OF ITEMS
u Base Bid: Entire Project
The undersigned agrees to complete the Work within calendar days after the date of
Notice to Proceed.
I] The City reserves the right to accept or reject any and all bids or any combination thereof proposed for
the above work.
fl The undersigned assures that its employees and applicants for employment and those of any labor
organization, subcontractors or employment agency in either furnishing or referring employee
applicants to the undersigned are not discriminated against as prohibited by the terms of City
Ordinance 7278 as amended by City Ordinance 7400 (Fort Worth City Code Section 13A-21 through
a13A-29).
Residency of Bidders: The 1985 Session of the Texas Legislature passed house Bill 620 relative to
the award of contracts to non-resident bidders. The law provides that, in order to be awarded a
contract as low bidder, non-resident bidders (out of state contractors whose corporate offices or
principal place of business are outside of the State of Texas) that bid projects for construction,
improvements, supplies or services in Texas at an amount lower than the lowest Texas resident
bidder by the same amount that Texas resident bidder would be required to underbid a non-resident
bidder In order to obtain a comparable contract in the state In which the non-resident's principal place
of business is located. The appropriate blanks in Section A must be filled out by all non-resident
bidders in order for your bid to meet specifications. The failure of out of state or non-resident bidders
Failure to complete the forms may disqualify that bidder. Resident bidders must check the box in
Section B.
ElAddendum 1 Page 3 of 6
0
it
Apr 16 99 02:55p TPW 817-871-8488
U,
p.5
II.
A. 1_i Non-resident vendors in (give state), our principal
place of business, are required to be percent lower than resident
bidders by state law.
1J Non-resident vendors in (give state), are not required to
a
underbid resident bidders.
B. I J Our principal place of business or corporate offices are In the State of
Texas.
Within ten (10) days of receipt of notice of acceptance of this bid, the successful bidder will execute
Surety Bond for the faithful performance of this
the formal contract and will deliver an approved
The deposit check in the sum of Dollars ($______ is to become the
contact. attached et
property of the City of Fort Worth, Texas, or the attached Bidder's Bond is to be forfeited in the an
the time set forth, as liquidated damagesdelayd
the contract and bond are not executed within
additional work caused thereby.
aMINORITY/WOMENS
BUSINESS ENTERPRISE (MANSE): (For bids in excess of $25,000)
• I am aware that I must submit information the Director, Transportation and Public Works,
FIVE BUSINESS DAYS of submittal of this Proposal in
a
concerning the M/ BE participation within
order to be RESPONSIVE.
QRespectfully
submitted,
Company Name
By:
Signature
Printed Name of Principal Title
Address:
Street
El
0
L
I
u
0
City
Phone: Fax:
Receipt Is acknowledged of the following addenda:
Addendum No. 1: Addendum No. 3:
Addendum No. 2: Addendum No. 4:
Addendum 1 Page 4 of 6
Zip
G
Apr 16 99 02:55p TPW 817-871-8488 p.6
El
1994
BUILDING & CONSTRUCTION TRADES
STANDARD WAGE RATES
FOR TARRANT COUNTY
DCLASSIFICATION
HOURLY RATE
BUILDING TRADES
AIR CONDITIONER MECHANIC
13.86
_
CONDITIONER MECHANIC HELPER
6.64
aAIR
BRICKLAYER/STONE MASON
13.56
BRICKLAYER/STONE MASON HELPER
8.29
CARPENTER
10.68
8.52
CARPENTER HELPER
CONCRETE FINISHER
11.51
CONCRETE FINISHER HELPER
8.38
CONCRETE FORM BUILDER
10.36
CONCRETE FORM BUILDER HELPER
7.58
DRYWALL INSTALLER
11.93
DRYWALL INSTALLER HELPER ,
7.55
DRYWALL TAPER
10.29
ELECTRICIAN (JOURNEY)
13.60
ELECTRICIAN HELPER
8.22
ELECTRONIC TECHNICIAN
8.75
FLOOR LAYER (RESILIENT)
13.17
FLOOR LAYER (CARPET)
13,17
FLOOR LAYER HELPER
6.44
GLAZIER
12.10
Li
GLAZIER HELPER
7.26
INSULATOR
10.83
a
INSULATOR HELPER
8.70
LATHER
15.83
METAL BUILDING ASSEMBLER
9.06
ri
METAL BUILDING ASSEMBLER HELPER
7.22
PAINTER
10.20
6.52
PAINTER HELPER
PLASTERER
15.48
PLASTERER HELPER
9.00
PLUMBER/ PIPE FITTER .
12.18
PLUMBER/ PIPE FITTER HELPER
8.57
REINFORCING STEEL SETTER
9.77
aAddendum
1 Page 5 of 6
In
I
Apr 16 99 02:56p
TPW
817-871-8488 p.7
REINFORCING STEEL SETTER HELPER
6.98
ROOFER
10.49
ROOFER HELPER
7.95
SHEET METAL WORKER
10.47
SHEET METAL WORKER HELPER
7.34
SPRINKLER SYSTEM INSTALLER
9.72
STEEL WORKER STRUCTURAL
13.24
STEEL WORKER STRUCTURAL HELPER
8.40
LABORER SKILLED
7.65
LABORER COMMON
6.47
EQUIPMENT OPERATORS
CRANE, CLAMSHELL, BACK HOE
10.20
DERRICK, DRAG LINE, SHOVEL
10.20
9.27
FORKLIFT -
FOUNDATION DRILL OPERATOR
10.53
FRONT END LOADER
9.89
806
TRUCK DRIVER
11.83
WELDER
8.59
WELDER HELPER
Addendum I Page 6 of 6
0
�_4
ElNOTICE TO BIDDERS
fl Sealed bids for the replacement of gymnasium wood floor at Bertha Collins Community
U Center, 1501 M.L.K. Frwy N., Fort Worth, will be received at the Purchasing Office, City
of Fort Worth, 1000 Throckmorton, Fort Worth, 76102, until 1:30 P.M., April 8, 1999,
and will be opened and publicly read aloud approximately thirty minutes later in the
Council Chambers.
£
0
0
I
0
0
I
I
ci
0
0
[I]
0
I
A Pre -Bid Conference will be held at 10:00 A.M., Tuesday, March 23, 1999, at the
Bertha Collins Community Center. MAPSCO 63X and 77B.
The Project consists replacing the wood gymnasium floor, wood base to rubber.
Level new floor. Furnish and install metal expansion thresholds. Stripe and paint floor
as specified. �J
The MWBE Goal for this project is,O!v. Contact the MWBE office (871-6104) to obtain
lists of certified subcontractors and suppliers.
Contractors will be required to post Payment Bond for projects .over $25,000 and
Performance Bonds for projects over $100,000. Contractors and sub -Contractors must
provide Contractors General Liability and Statutory Workers Compensation coverage.
Up to two sets of specifications and plans for this project may be obtained at the
Department of Engineering Plans Desk, 871-7910, City Hall, 1000 Throckmorton Street,
in return for a $50 deposit each. For additional information, contact Bob Wood,
871-8088.
Advertisement: March 11, 1999
March 18, 1999
NTB - 1
D
TABLE OF CONTENTS
NOTICE TO BIDDERS
NTB-1
TABLE OF CONTENTS
TOC-1
INSTRUCTIONS TO BIDDERS
ITB-1 to ITB-4
SPECIAL INSTRUCTION FOR BIDDERS (MWBE)
MWBE —Ito 7
PROPOSAL
P-1 to P-2
GENERAL CONDITIONS
GC -1 to GC -21
WAGE RATES
WEATHER TABLE
WT -1
TECHNICAL SPECIFICATIONS
09590-1 to 6
FORM OF CONTRACT
C-1 to C-2
PERFORMANCE BOND
PAYMENT BOND
CONTRACTOR COMPLIANCE WITH WORKERS
COMPENSATION LAW
DRAWINGS:
PLAN
SHEET 1 OF 2
DETAILS
SHEET 2 OF 2
TOC-1
0
INSTRUCTIONS TO BIDDERS
a
ci
0
0
0
0
0
r
J
L
LI
1. PROPOSAL REQUIREMENTS: The following requirements are considered in judging
the responsiveness of a Proposal:
• Use the Proposal Form provided in the Project Manual.
• Entries on the Proposal Form may be handwritten or typed
• Write in contract duration if not specified
• Acknowledge all Addendums on the Proposal Form
• Have a Principal sign the Proposal
• Enclose a bid deposit of 5%. This can be in the form of a cashiers check or
standard bid bond. Personal checks are not acceptable. Note Project Name on
the check or bid bond
Following the bid date, you have five City business days to prepare and submit your M/WBE Plan.
Early submittal is encouraged. Be aware that if you elect to provide documentation of a Good
Faith Effort you will have to accomplish each and every action in the Special Instructions to
Bidders, Minority and Women Business Enterprises Specifications, included in this Project
Manual. In order to meet all the requirements for a Good Faith Effort you will have to start at
least two weeks before the Bid date.
2. BID SECURITY: Cashier's check or an acceptable bidder's bond payable to the City of
Fort Worth, in an amount of five (5) per cent of the bid submitted. The Bid Security must
accompany the bid and is subject to forfeit fin the event the successful bidder fails to execute the
contract documents within ten (10) days after the contract has been awarded. The Bid Security
shall be included in the envelope containing the bid proposal. Failure to submit the Bid Security
will result in the proposal not being considered for this project. Bidder's bond will be returned if
the City fails to award the contract within 49 calendar days of receipt of bids, unless an extension
is agreed to by the Bidder.
3. PAYMENT BOND AND PERFORMANCE BOND: The successful bidder entering into a
contract for the work will be required to give the City surety in a sum equal to the amount of the
contract awarded. The form of the bond shall be as herein provided and the surety shall be
acceptable to the City. All bonds furnished hereunder shall meet the requirements of Article 5160
of the Revised Civil Statutes of Texas, as amended.
ci In order for a surety to be acceptable to the City, (1) the name of the surety shall be included on
the current U. S. Treasury List of Acceptable Sureties (Circular 870), or (2)• the surety must have
capital and surplus equal to ten times the amount of the bond. The surety must be licensed to do
D business in the state of Texas. The amount of the bond shall not exceed the amount shown on
the Treasury list or one -tenth of the total capital and surplus. If reinsurance is required, the
company writing the reinsurance must be authorized, accredited or trusteed to do business in
Texas.
No sureties will be accepted by the City which are at the time in default or delinquent on any
Y
bonds or which are interested in any litigation against the City. Should any surety on the contract
L U be determined unsatisfactory at any time by the City, notice will be given to the Contractor to that
effect and the contractor shall immediately provide a new surety to the City.
I
Eli
ITB- l
08/ 10/98
0
If the total contract price is $25,000 or less, payment to the contractor shall be made in one lump
sum. Payment shall not be made for a period of 45 calendar days from the date the work has
been competed and accepted by the City.
[� If the contract is in excess of $25,000, a Payment Bond shall be executed, in the amount of the
a contract, solely for the protection of all claimants supplying labor and materials in the prosecution
of the work.
If the contract amount is in excess of $100,000, a Performance Bond shall also be provided, in the
amount of the contract, conditioned on the faithful performance of the work in accordance with the
plans, specification, and contract documents. Said bond shall be solely for the protection of the
City of Fort Worth.
lii4. BOND SURETY: Preferred sureties for bonds required for the project are included on the
current U. S. Department of the Treasury - Fiscal Service list of companies holding certificates of
authority as acceptable sureties on federal bonds and as acceptable reinsuring companies
U' (Circular 570); and, the limit of a bond written by any one acceptable company shall not exceed
the amount shown on the Treasury list for that company.
Surety must be admitted to do business in the state and have capital and surplus equal to ten
times the limit of the bond or any amount in excess of the ten percent limit must be reinsured by a
company or companies duly authorized, accredited or trusteed to do business in this state.
Should any surety for the contracted project be determined unsatisfactory at any time during
Project. The Contractor shall immediately provide a new surety bond satisfactory to the City.
0
0
0
0
0
El
11-
0
ID
No sureties will be accepted by the Owner which are at the time in default or delinquent on any
bonds or which are interested in any litigation against the owner. All bonds shall be made on the
forms furnished by the Owner, and shall be executed by an approved surety company doing
business in the City of Fort Worth, Texas, and which is acceptable to the owner. Each bond
shall be properly executed by both the Contractor and Surety Company.
5. PRE -BID SITE INVESTIGATION: Prior to filing a bid, the bidder shall examine the site(s)
of the work and the details of the requirements set out in these specifications to satisfy himself as
to the conditions which will be encountered relating to the character, quality, and quantity of the
work to be performed and materials and equipment required. The filing of a bid by the bidder shall
be considered evidence that he has complied with these requirements.
6. AMBIGUITY: In case of ambiguity or lack of clearness in stating prices in the proposal,
the City reserves the right to adopt the most advantageous construction thereof to the City or to
reject the proposal.
7. WAGE RATES: Not less than the prevailing wage rates established by the City of Fort
Worth, Texas, and set forth in Contract Documents, must be paid on this project.
8. POST BID - PREAWARD SUBMITTALS: Bidders will be required to submit the following
information to the Project Manager within five business days subsequent to bid opening (Normally
Thursday following a Thursday bid opening) in order to assist City staff in determining the
Contractor's capability of performing the work and in meeting City contract requirements:
08/10/98
Minority/Women's Business Documentation
Contractors Qualification Statement (AIA Form A305)
Proposed Subcontractors
Assurance of Insurability for Workers Compensation Insurance
ITB - 2
0
9. PROPOSED SUBCONTRACTORS: Acceptance
p e of the bid in no way requires the City to
accept the qualifications of the subcontractors. The Subcontractor lists are for use by the City in
preparing recommendations for award of the contract. The Contractor must provide and use
�J subcontractors listed unless requested or allowed to substitute by the City.
10. DISCREPANCIES AND ADDENDA:
Should a bidder find any discrepancies in the drawings and specifications, or should he be in
doubt as to their meaning, he shall notify the City at once and, if required, the City will then
prepare a written addendum which will be available to all Bidders at the Plans Desk or place
designated for distribution of Bid Documents by the Notice to Bidders. The Contractor is
responsible for determining if addendums are available and for securing copies prior to submitting
a proposal. Oral instructions or decisions unless confirmed by addenda will not be considered
valid, legal or binding. No extras will be authorized because of failure of the contractor to include
work called for in the addenda.
ElBidder must acknowledge addenda in the Proposal. Failure to acknowledge addenda may cause
Proposal to be ruled non -responsive.
11. MINORITY/WOMENS BUSINESS ENTERPRISE (M/WBE):
The lowest responsive, responsible, bidder meeting the M/WBE requirements will be
recommended for award. Information concerning participation of Minority and Women's Business
Enterprises is not required for Projects less than $25,000. All purchases from M/WBE suppliers,
second tier subcontractors and second tier suppliers may be included in M/WBE contribution
toward meeting the goal.
The Bidder shall submit the M/WBE UTILIZATION FORM, PRIME CONTRACTOR WAIVER
FORM and/or the GOOD FAITH EFFORT FORM ("Documentation") as appropriate. The
fl Documentation must be received no later than 5:00 P.M. five (5) City business days after the bid
opening date. The Bidder shall obtain a receipt from the appropriate employee of the managing
department to whom delivery was made. Such receipt shall be evidence that the Documentation
was received by the City.
Successful Bidder will be required to submit co-signed letters of intent or executed agreements
Dwith all M/WBE subcontractors and suppliers prior to receiving a Notice to Proceed.
12. WORKERS COMPENSATION INSURANCE: Bidders will be required to demonstrate
that coverage is in effect at time of Award of Contract. Sample Certificate of Insurance, or other
fl proof that Workers Compensation Insurance will be obtained, must be submitted within five
working days of bid opening.
13. TAXES: Equipment and materials not consumed by or incorporated into the work are
u subject to State sales taxes under House Bill 11, enacted August 15, 1991.
14. PERMITS: Contractor shall apply for all City of Fort Worth Permits and for any other
permits required by this project. City of Fort Worth Permit fees are waived. Separate permits
may be required for each work location.
fl Q 15. CONTRACT DURATION: Time is of the essence. City will evaluate the bids based upon
construction cost and stated bid period of time for construction. Where time is proposed by the
Bidder, the City will evaluate the City's program needs in determining the acceptability of the
proposed contract duration. The City reserves the right to award the contract upon those terms
considered by the City to be in its best interests.
ITB - 3
U
08/10/98
El
0
16. PLAN DEPOSIT: The City will deposit plan deposit checks to its account two weeks
a following receipt of bids. Plans must be returned by all except the apparent low bidder prior to that
time. Contractor forfeits his plan deposit after that time.
0
a
0
0
C
0
0
0
0
ID
0
0
a
ED
0
17. ADJUSTMENT OF QUANTITIES: Where unit prices and estimated quantities are used
to compute the contract amount, the Owner may increase the quantities by an amount that is 20%
of the total cost for that section. Unit prices for adjustments to unit quantities in excess to 20%
may be negotiated at the request of either party.
18. MANUFACTURER'S REFERENCE: Catalog, brand names, and manufacturer's
references are descriptive, not restrictive. Bids on brands of like nature and quality will be
considered. For all items other than reference specifications and equivalent products listed in
each section, a full size sample will be required for review at a Fort Worth location within 14
calendar days of receipt of bid.
00O00
ITB-4
4
El08/10/98
0
PROPOSAL
TO: MR. BOB TERRELL
CITY MANAGER
CITY OF FORT WORTH, TEXAS
FOR: �Ti¢�//`S C, 4rmr�a*it/i7 j�
Pursuant to the foregoing "Notice to Bidders," the undersigned has thoroughly examined the
plans, specifications and the site, understands the amount of work to be done, and hereby
proposes to do all the work and furnish all labor, equipment and materials necessary to fully
complete all the work as provided in the plans and specifications, and subject to the inspection
and approval of the Director of Transportation and Public Works of the City of Fort Worth.
Upon acceptance of this Proposal by the City Council, the bidder is bound to execute a contract
and, if the contract amount exceeds $25,000.00, furnish Performance and Payment Bonds
approved by the City of Fort Worth for performing and completing the Work within the time stated
and for the following sum, to wit:
DESCRIPTION OF ITEMS vym AIIL /urr,
Total Bid:
The undersigned agrees to complete the Work within _________ calendar days after the date of
Notice to Proceed.
The City reserves the right to accept or reject any and all bids or any combination thereof
proposed for the above work.
The undersigned assures that its employees and applicants for employment and those of any
labor organization, subcontractors or employment agency in either furnishing or referring
employee applicants to the undersigned are not discriminated against as prohibited by the terms
of City Ordinance 7278 as amended by City Ordinance 7400 (Fort Worth City Code Section
13A-21 through 13A-29).
Residency of Bidders: The 1985 Session of the Texas Legislature passed house Bill 620 relative
to the award of contracts to non-resident bidders. The law provides that, in order to be awarded a
contract as low bidder, non-resident bidders (out of state contractors whose corporate offices or
principal place of business are outside of the State of Texas) that bid projects for construction,
improvements, supplies or services in Texas at an amount lower than the lowest Texas resident
bidder by the same amount that Texas resident bidder would be required to underbid a
non-resident bidder in order to obtain a comparable contract in the state in which the
non-resident's principal place of business is located. The appropriate blanks in Section A must be
filled out by all non-resident bidders in order for your bid to meet specifications. The failure of out
of state or non-resident bidders Failure to complete the forms may disqualify that bidder.
Resident bidders must check the box in Section B.
I_I Non-resident vendors in (give state), our principal place of
business, are required to be percent lower than resident bidders by state
law.
I_1 Non-resident vendors in (give state), are not required to
underbid resident bidders.
A-1
tI_I Our principal place of business or corporate offices are in the State of
Texas.
Within ten (10) days of receipt of notice of acceptance of this bid, the successful bidder will
execute the formal contract and will deliver an approved Surety Bond for the faithful performance
of this contact. The attached deposit check in the sum of Dollars ($_) is to
e become the property of the City of Fort Worth, Texas, or the attached Bidder's Bond is to be
forfeited in the event the contract and bond are not executed within the time set forth, as
liquidated damages for delay and additional work caused thereby.
MINORITY/WOMENS BUSINESS ENTERPRISE (M/WBE):
• I am aware that I must submit information the Director, Transportation and Public Works,
concerning the M/WBE participation within FIVE BUSINESS DAYS of submittal of this
Proposal in order to be RESPONSIVE.
Respectfully submitted,
Company Name
By:
eSignature
Printed Name of Principal Title
dendum Page 3 of 3
Address: 9'�
Street
,7 ' f ii' 7 7
city zi
Phone: 7/r? _g3 -015 7 Fax: 7/3 4 —q6-2%
Receipt is acknowledged of th following addenda:
' Addendum No. 1:
Addendum No. 3:
Addendum No. 2:—_v" Addendum No. 4:
El
f
'_ APR -26-99 MON 3:41 PM BAUER SPORT FLR. FAX NO. 7139399621 P. 1
r
I
I
I
I
I
I
I
I
I
I
04-27-99A10:33 RCVD
ML UIi7of'7
ATTACI.IMENT 1A
Cit of Fort Worth Page t of 2
Minority and Women Business Enterprise Specifications
'1Bi=1VVE U ZA'CIQ
pttl COMPANY NA + "C
P OJECT NAME PROJECT NUMBER '^'•^""^^--
t:ITY'SMhvGE rROJEt�GpAL: AVFYi}E PrICCENTAC;PA IICVED; `�`"
Failure to complete this form, in Its entirety with supporting documentation, and received by the Managing pepariment
on or bofore 5;40 p.m. five (5) City business days after bid opening, exclusive of bid opening date, will result in the bid
being considered non responsive to bid specifications,
The undersigned bidder agrees to enter into a formal agreement with the MBE and/or WBE firms for work listed in this
schedule, conditioned upon execution of a contract with the City of Fort Worth. The intentional and/or knowing
misrepresentation of facts is grounds for consideration of disqualification and will result in the bid being considered
non -responsive to specifications,
;ompany Name, Contact Name, Csrtitied
Address, and Telephone No.
os
z sl
ecify AJLContracting Specify A,Ij Items to
Scope of Work (') Supplied( )
D'is'c/rte
A)#t&/c
T M14VBi s must ha 14teled In itte 9 (n:rta}county m7rkgtpiace or currently doing bustites9 in the markatpla;a at the time qt bid,wJ
(•t Specify all arcac in which MW BE a are to be utilized and/or Rem& to be supplied:
i'1 A Cornplata listing of Items to be supplied is required in order to receive credit toward the M/WBR DoaT.
each Tier
means rr•@:evel ci 3treconiractirlg bew the prima contractor/consult nl, i.e., a direct payrnant
from the prime Contractor to a subcontractor is Considered I • tier, a payment tay a subcontractor to
iii suonller to
THIS FORM Ml.$I DE RECEIVED BY THE MANAGitNiG DEPARTMENT BY 5!Qp p.m„ FIVE (5) CITY BUSINESS DAYS AFTER BID
OPENING, EXCLUSIVE OF YNg 610 OPENING DATE
Pages 1 and 2 of Attachment 1A must be received by the Managing Oopartment Rey tN2r9a
El
El
1
APR -26-99 MOM 3.42 PM BAUER SPORT FUR, FAX NO, ?139399921 P. 2
I
0
J
1
I
I
1
0
0
It
1
1
lviwp! 3 cr ATTACHMENT 1A
page 2 of 2
City of Fort Worth
Minority and Women Business Enterprise Specifications
M BEIWB EUTJ L1ZATQJ
Company Name, Contact Name. CertVieq Specify (i Contracting Specify Ali Items to be
Dolt
Address, and Telephone No. u p Stops of Work (`) Suppllod(')� er Amount
J.
The bidder further agrees to provide, directly to the City upon request, complete and accurate Information regarding
actual work performed by all subcontractors, including M$E(s) and/or VVBE(s) arrangements submitted with this bid.
The bidder also agrees to allow an audit and/or examination of any books, records and files held by their company that
will substantiate the actual work performed by the MBE(s) and/or WBE(s) on this contract, by an authorized officer or
employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the
contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal,
State or Laoal laws concerning false statements. Any failure to comply with this ordinance and creates a material
breach of contract may result In a determination of an irresponsible offeror and barred from participating in City work
for a period of time not less than one(1) year. -
At t MBEs - nd WBES MUST BE CERTIFIED BY TH ITY BEFORE CON TACT AWARD
p J
Amorlz!veoAUthorJS1naure Printed Signature
4dde s
."ity/State/Zip Code
Contact Name and Title (if different)
- 9 &7
Telephone Number (s) �'
Fax Number
Date
THIS FORM h�.VSJ BE RECEIVED BY THE MANAG'NG DEPARTMENT BY 5;Do p.m., FIVE (5t CITY BUSINESS DAYS AFTER BID
OPENING, EXCLUSIVE Or THE BID OPENING DATE
Ov, s12`3e
Pages 1 and 2 of Attachment IA must bo received by the Managing Department k
0
APR -25-99 I ON 3:43 PM BAUER SPORT FLE,
I
FAX NO. 7139399621 P. 3
MW0G 4 or?
ATTACHMENT 1B
11 a City of Fort Worth Page 1 of I
Minority and Women Business Enterprise Specifications
(� prime Caintract r giver
Prime Co pan Name
y Project Narne
Bid Opening Date Project Number
fl If both answers to this form are YES, do riot complete ATTACHMENT IC(Good Faith Effort Form).
All questions on this form must be completed and a detailed explanation provided, if applicable. If
the answer to either question is NO, then you njij..t complete ATTACHMENT 1C, This form is only
applicable IfJ answers are yes.
EliFallure-,to complete. this form fn its entirely and be received by the anagln(J Dep .cth1 ► .,,,
fOre9Q .m.fivp 15) City business dyfter bJ.d opening, exclusive of the bid opening data,
will result in. the bid being considered non -responsive to bid specifications.
1111 Will you perform this entire contract without subcontractors? __Ye No
if yes, please provide a detailed explanation that proves based on the size and scope of
this project, this is your normal business practice and provide an operational profile of
9 your business.
Will you perform this entire contract without suppliers? _Yes _„No
DIf yes, please provide a detailed explanation that proves based on the size.and scope of
this project, this is your normal business practice and provide an Inventory profile of
your business.
The bidder further agrees to provide, directly to the City upon request, complete and accurate
information regarding actual work performed by all subcontractors, including MBE(s) and/or
WBF(s) on this contract, the payment therefore and any proposed changes to the original MBE(s)
and/or WBE (s) arrangements submitted with this bid. The bidder also agrees to allow an audit
and/or examination of any books, records and files hold by their company that will substantiate
the actual work performed by the MBE(a) and/or WEE(s) on this contract, by an authorized officer
or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds
for terminating the contract or debarment from City work for a period of not less than three (3)
years and for initiating action under Federal, State or Local laws concerning false statements. Any
failure to comply with this ordinance and creates a material breach of contract may result in a
determination of an irresponsible offeror and barred from participating in City work for a period of
9 time not less than one (1) year.
0
I.
0
a
Authorlx Signature
Title
49&/_
Co pany 1lam
Addr ss
i/'
Authorized Signature
J4'VAt, Ge
Printed Signature
Contact Name (if different)
Contact Telephone Number (s)
?7c5-99-- 9 V
Fax Number
. : rn'
Company Narn
Rev. iv98
a
APR -26-99 MON 3:43 PM BAUER SPORT FLR. FAX NO, 7139399621 P. 4
U.
MWBC 5 of 7 AVrACHMENT IC
Page 1 of 3
City of Fort Worth
Minority and Women Business Enterprise
0QD FAITH EFFORT
U 90 y
Prime Company Na e Bid bate
Project Name Project Number M"
If you have failed to secure M/WBE a p rticlpatian and you have subcontracting and/or supplier oApo+tunitfas or If
your M/WBE participation Is less than the City's project goal, you complete this form.
If the bidder's method of compliance with the MBE goal is based upon demonstration of a
"good faith effort", the bidder will have the burden of correctly and accurately preparing and
a submitting the documentation required by the City. Compliance With each Item, 1 thru 6 below,
shall satisfy the Good Faith Effort requirement absent proof of fraud, intentional and/or
knowing misrepresentation the facts or Intentional discrimination by the bidder.
ElFailure to complete this form, In its entirety with supporting documentation, and received by the
Managing Department on or before 5:00 p.m. five (5) City business days after bid opening, exclusive of bid
opening date, will result in the bid being considered non -responsive to bid specifications.
U'
1.) Please fist each and every subcontracting and/or supplier opportunity (Q,Q NO'r LiS�' NAI1±1 _s nx
FtBMSI which will be used in the completion of this project, regardless of whether It is to be provided
u by a M/WBE or non- MFW81;.
0
I
0
0
0
0
0
(Use additional sheets, If necessary)
List of: S, taj7contra�ting Ogu r
List of: Sunalleri�eartun
0
APR -26-99 MON 344 PM BAUER SPORT PLR.
MWBE6o(7
FAX NO. 7139399621 P. 9
ATTACHMENT IC
Page 2 of 3
2,) Did you obtain a current list of M/WBE firms from the City's M/WF3(~ Office? The list is considered in
compliance, if it Is not more than 3 months old from the date of bid opening.
_Yes
No
Date of Listing _l 7 1
3.) Did you solicit bids from MIWBE firms,
subcontracting
listed, at least ten calendar days prior to bid open g by mail,exclus and/or supplier
e of theday the bidspreviously
are
n Opened?
Yes if yes, attach M/WBE mail listing to include name of firm and address and a dqW copy of letter mailed.
4.) Did you solicit bids from M/WBE firms, within the subcontracting and/or supplier areas previously
U
listed, at least ten calendar days prior to hid opening by telephone, exclusive of the day the bids are opened?
--�Yes If yes, attach list to include n_ ..g of M/WBE firm, M contacted,
�/ NO j�[l9 MILW anti ,
—_ �t1P and Im Of QQntaCt.
0
0
0
0
0
0
0
0
0
0
NOTE: A facsimile may be used to comply with either 3 or 4, but may not be used for both. If a facsimile. is used, attach the fax confirmation, which is to provide MIME name, date, time, fax number and
documentation faxed.
NOTE: It a SIC list of MIWBE is tenor less, the bidder must contact the entire list to be In compliance lentil questions 3 and 4, If a sic list of M/WBE is more than ten, the bidder must contact at least two-thirds of
the list but not less than ten to be in compliance with questions 3 and 4.
5.) Did you provide plans and specifications to potential MIWBEs or Information regarding the location of
plans and specifications In order to assist the MIWBEs?
_ Yes
No
6,) if MIWBE bids were received and rejected, you must.,
(1) List the MIWBE firms and the reason(s) for rejection (i.e., quotation not commercially reasonable,
qualifications, etc.) and
(2) Attach affidavit andlor documentation to support the reason(s) listed below (i.e., hatters, memos,
bids, telephone calls, meetings, etc,)
0
• APR -26-99 MON 3:45 PIS BAUER SPORT FLR, FAX NO, 71139399621 P. 6
0
M WL36 7 or7
ATTACHMENT IC
0 A� ITton,A FoR�nA7fQN: PA9n 3 of 3
Please provide additional Information you feel will further explain your good and honest efforts to obtain
aM)Wl3E participation on this project.
0
0
The bidder further agrees to provide, directly to the City upon request, complete and
accurate information regarding actual work ,performed on this contract, the payment
thereof and any proposed changes to the original arrangements submitted with this bid.
The bidder -also agrees to allow an audit andlor examinationof any books, records and
files held by their company that will substantiate the actual work performed on this
contract, by an authorized officer or employee of the City.
Any Intentional andlor knowing misrepresentation of facts will be grounds for
U- terminating the contract or debarment from City work for a period of not less than three
(3) Years and for initiating action under Federal, State or Local laws concerning false
a statements. Any failure to comply with this ordinance and creates a material breach of
contract may result in a determination of an irresponsible offeror and barred from
participating in City work for a period of time not less than one (1) year.
The undersigned certifies that the Information provided and the M/WSZ(s) listed
was/were can ac e In good faith. It Is understood that any M/WBE(s) listed in
Attachment 9C will be contacted and the reasons for not using them will be verified by
the City's MIWBE Office.
Authorized Signature
Printed Signature
a Title
Contact Name and Title (if different)
Comp
f�& ny Na
� �� Telephone Number(s)
Addrf pass J --
Fax NumberU __
CityfStata/zip
Date
0
0
APR -26-99 MON 3:46 PM BAUER SPORT FLR, FAX XO, 7139399621 P, 7
MW13E I of7
Q City of Fort Worth
Minority and Women
Business Enterprise Specifications
U�
0 AILQN OF ROt ICY
if the total dollar value of the contract is O5,666 or mare, the M/W81: goat !s applJcabia. !f tha total dollar
value of the contract is less than $25,000, the lVtiWBE goat is not a plicabla.
J
J
Ii
ii
I
0
J
0
I
IAIEM
It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minorily/women Business
Enterprises (M/WBE) ₹n the procurement of all goods and services to the City on a contractual basis. The objective
of the Policy is to increase the use of M/WBE firms to a level comparable to the availability of M/WBEs that provide
goods and services directly or indirectly to the City.
J L
The City's MBEIWBE goal on this project is -..__% of the base bid value of the contradt.
QQMEUMLQJR D, RECIF1CATjQNS
On City contracts of $25,000 or more, bidders are required to Comply with the intent of the City's M1WBE Ordinance
by either of the following:
1. Meet or exceed the above stated M/WSE goal, or;
2. Good Faith Effort documentation, or;
3. Waiver documentation.
aUMnT.4to R Di ocJJENTATlo
The applicable documents must be received by the Managing Department, within the following times allocated, in
order for the entire bid to be considered responsive to the specifications,
'. M/WBE Utilization Form: received by 5:00 p.m., five (5) City business days after the
bid opening date, exclusive of the bid opening date,
2. Prime Contractor Waiver Form: received by 5:00 p.m,, five (5) City business days after the
bid opening date, exclusive of the bid opening data.
3. Good Faith Effort Form: received by 5:00 p.m., five (5) City business days after the
bid opening date, exclusive of the bid opening date.
O rAt1 t1RE TO COMPLY WITH THE CITY'S M/WBE ORDINANCE, WILL RESULT 1N THE BID BEING
GON5tDt:i2ED NON-Ftt3SP4NSiVE TO SPECIFICATIONS.
Any questions, please contact the MIWBE Office at (817) 871.6104.
7
Rev. 612199
I
Li
City of Fort Worth, Texas
Transportation/Public Works Department
Building Services Division/Architectural Services Section
0
a
0
a
0
n
0
a
Cl
a
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
SECTION A
DEFINITIONS, PROCEDURES AND INTERPRETATIONS
A-1 CONTRACT DOCUMENTS. By the term Contract
Documents is meant all of the written and drawn documents
setting forth or affecting the rights of the parties, including but not
necessarily limited to, the Contract, Notice to Bidders, Proposal,
General Conditions, Special Conditions, Specifications, Plans,
Bonds and all Addenda, Amendments signed by all parties,
Change Orders, written Interpretations and any written Field Order
for a minor change in the Work.
A-2 ENTIRE AGREEMENT. The Contract Documents
represent the entire agreement between the Parties, and no prior
or contemporaneous, oral or written agreements, instruments or
negotiations shall be construed as altering the terms and effects of
the Contract Documents. After being executed, the Contract
Documents can be changed only by a written Amendment signed
by the Contractor and the Owner, or Change Order, or by a written
Field Order for a minor change.
A-3 WORK. By the term Work is meant all labor,
supervision, materials and equipment necessary to be used or
incorporated in order to produce the construction required by
Contract Documents.
A-4 EXECUTION OF THE CONTRACT DOCUMENTS. The
Contract Documents shall be executed in six originals by the
Contractor and the Owner in such form as may be prescribed by
law.
A-5 FAMILIARITY WITH PROPOSED WORK. Before filing
a bid, the bidder shall examine carefully the proposal, plans,
specifications, special provisions, and the form of contract to be
entered into for the work contemplated. He shall examine the site
of work and satisfy himself as to the conditions that will be
encountered relating to the character, quality and quantity of work
to be performed and materials to be furnished. The filing of a bid
by the bidder shall be considered evidence that he has complied
with these requirements and has accepted the site as suitable for
the work.
Claims for additional compensation due to variations between
conditions actually encountered in construction and as indicated
by the plans will not be allowed.
A-6 ONE UNIFIED CONTRACT. Insofar as possible, the
Contract Documents will be bound together and executed as a
single unified Contract, the intention of the Contract Documents
being to provide for all labor, supervision, materials, equipment
and other items necessary for the proper execution and
completion of the Work. Words that have well recognized
technical or trade meanings are used herein in accordance with
such recognized meanings.
A-7 DIVISION OF WORK. The arrangement of Drawings
and/or Specifications into Divisions, Sections, Articles, or other
Subdivisions shall not be binding upon the contractor in dividing
the work among Subcontractors or Trades.
A-8 INTERPRETATIONS. The Architect will furnish such
Interpretations of the Plans and Specifications as may be
necessary for the proper execution or progress of the work. Such
Interpretations shall be furnished at the instance of the Architect or
at the request of the Contractor, or Owner, and will be issued with
reasonable promptness and at such times and in accordance with
such schedule as may be agreed upon. Such Interpretations shall
be consistent with the purposes and intent of the Plans and
Specifications and may be effected by Field Order. In the event of
any dispute between any of the parties to the Contract and the
Architect or each other involving the interpretation of the Contract
Documents, the evaluation of work or materials performed or
furnished by the Architect Contractor, or any subcontractor or
materialsman, or involving any question of fault or liability of any
party, the decision of the Owner shall be final and binding.
In the event of inconsistency in the contract documents, the
following sequence for interpretation shall be used in order of
precedence: Change Orders and/or Field Orders (by date of
issuance); Addenda (by date of issuance); Drawings; Notes and
dimensions on Drawings; Technical Specifications; Special
Provisions; Supplementary General • Conditions; General
Conditions; and, Construction Contract.
A-9 COPIES OF WORKING DRAWINGS AND
SPECIFICATIONS. The Architect will furnish to Contractor free of
charge 15 sets of working Drawings and 15 sets of Specifications.
Contractor shall pay the cost of reproduction for all other copies of
Drawings and Specifications furnished to him.
All Drawings, Specifications and copies thereof furnished by the
Owner of the Architect are and shall remain the property of the
Owner. They are not to be used on any other project and, with the
exception of one Contract set for each Party to the Contract, are to
be returned to the Owner on request at the completion of the work.
A-10 MINORITY AND WOMENS BUSINESS ENTERPRISE
POLICY. The City of Fort Worth has goals for the participation of
disadvantaged business enterprises in City contracts. Compliance
with the policies designed to meet these goals is mandatory in
order to be considered a responsive bidder. The City policy and
procedures to be followed in submitting bids is included.
A-11 CORRELATION AND INTENT. In general, the drawings
indicate dimension, locations, positions, quantities, and kinds of
construction; the specifications indicate the quality and
construction procedures required. Work indicated on the drawings
and not specified of vice -versa, shall be furnished as though set
forth in both. Work not detailed, marked or specified shall be the
same as similar parts that are detailed, marked or specified. If the
drawings are in conflict or conflict with the specifications the better
quality or greater quantity or work or materials shall be estimated
and shall be furnished or included. Dimensions on drawings shall'
take precedence over small-scale drawings. Drawings showing
locations of equipment, piping, ductwork, electrical apparatus, etc.,
are diagrammatic and job conditions may not allow installation in
the exact location shown. Relocation shall not occur without the
Architects approval.
SECTION B
IDENTITY OF ARCHITECT
B-1 CONTRACT ADMINISTRATION. Where the term
"Architect" is used in the "General Conditions of the Contract for
Construction", it shall refer to the Director, Transportation and
Public Works or his designated Project Manager. The Director,
Transportation will designate a Project Manager and Construction
Manager to administer this contract and perform the functions of
the "Architect" as indicated in the General Conditions. The design
architect may also be designated to perform the duties of
"Architect".
08/10/98
GC -1
B-2 TERMINATION AND SUSPENSION OF WORK: The
Owner has the right to terminate the Project for any reason. If the
project is terminated, the Contractor shall:
a) Stop work under the Contract on the date and to the
extent specified on the notice of termination.
b) Place no further orders or subcontracts except as may
be necessary for the completion of the work not terminated.
c) Terminate all orders and subcontracts to the extent that
they relate to the performance of the work terminated by the notice
of termination.
After termination as above, the City will pay the contractor a
proportionate part of the contract price based on the work
completed; provided, however, that the amount of payment on
termination shall not exceed the total contract price as reduced by
the portion thereof allocatable to the work not completed and
further reduced by the amount of payments, if, any otherwise
made. Contractor shall submit its claim for amounts due after
termination as provided in this paragraph within 30 days after
receipt of such claim. In the event of any dispute or controversy
as to the propriety or allowability of all or any portion of such claim
under this paragraph, such dispute or controversy shall be
resolved and be decided by the City Council of the City of Fort
Worth, and the decision by the City Council of the City of Fort
Worth shall be final and binding upon all parties to this contract
B-3 DUTIES OF THE ARCHITECT As used herein, the term
Architect means the Architect or his authorized representative.
Nothing contained in these Contract Documents shall create any
privity of Contract between the Architect and the Contractor.
B-4 ARCHITECT AS REPRESENTATIVE OF THE OWNER
The Architect will provide general administration of the Contract on
behalf of the Owner and will have authority to act as the
representative of the Owner to the extent provided in the Contract
Documents unless changed in writing by the Owner. The Architect
will be available for conferences and consultations with the Owner
or the Contractor at all reasonable times.
B-5 ACCESS TO JOB SITES. The Architect shall at all
times have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access
so the Architect may perform its assigned functions under the
Contract Documents.
The Architect will make periodic visits to the Site to familiarize
himself with the progress and quality of the work and to determine
if the work is proceeding in accordance with the Contract
documents. On the basis of on -site observations, the Architect will
keep the Owner informed of the progress of the Work and will
endeavor to guard the Owner against defects and deficiencies in
the Work of the Contractor. Based upon such observations and
the Contractor's applications for payments, the Architect will make
determinations and recommendations concerning the amounts
owing to the Contractor and will issue certificates for payment
amounts.
B-6 INTERPRETATIONS. The Architect will be,- in the first
instance, the interpreter of the requirements of the Plans and
Specifications and the judge of the performance thereunder by the
Contractor, subject to the final decision of the Owner.
The Architect's decisions in matters relating to artistic effect will be
final if consistent with the intent of the Contract Documents.
B-7 AUTHORITY TO STOP WORK. The Architect will have
authority to reject work that does not conform to the Plans and
Specifications. In addition, whenever, in its reasonable opinion,
the Architect considers it necessary or advisable in order to insure
the proper realization of the intent of the Plans and Specifications,
the Architect will have authority to require the Contractor to stop
the Work or any portion thereof, or to require special inspection or
testing of the Work whether or not such Work be then fabricated,
installed or completed.
B-8 MISCELLANEOUS DUTIES OF ARCHITECT.
Shop Drawings. The Architect will review Shop Drawings and
Samples as provided in Section D. Two copies of each approved
Shop Drawing and submittal will be provided to the Owner by the
Architect.
Change Orders. Change Orders and Field Orders for Minor
Changes in the Work will be issued by the Owner through the
Architect in accordance with the provisions of Section L.
Guarantees. The Architect will receive on behalf of the Owner all
written guarantees and related documents required of the
Contractor. Upon completion of the project the Contractor shall
provide the Architect five copies of each guarantee. The Architect
will provide three copies of each guarantee to the Owner.
Inspections. The Architect will conduct inspections for the
purpose of determining and making his recommendations
concerning the dates of substantial, completion and final
completion.
Operation and Maintenance Manuals. The Architect will receive
on behalf of the Owner, six copies of all applicable equipment
installation, operation, and maintenance brochures and manuals
required of the Contractor. The Architect will provide three copies
of this information to the Owner.
B-9 TERMINATION OF THE ARCHITECT. In case of the
termination of the employment of the Architect by the Owner, the
Owner shall either assume the duties of the Architect through the
Director of the Department of Transportation and Public Works, or
shall appoint a successor Architect against whom the Contractor
makes no reasonable objection.
SECTION C
OWNER
C-1 IDENTIFICATION. By the term Owner is meant the City
of Fort Worth acting herein by its duly authorized representatives
in the manner provided by law. Authorized representatives include
the City Manager. Assistant City Manager, the Director and of
Transportation and Public Works Department and members of the
Building Services Division. Generally speaking a designated
representative will be identified from within the Building Services
Division to act as a point of contact for day to day contract
administration.
C-2 DUTIES OF THE OWNER. The Owner shall furnish
surveys describing the physical characteristics, legal limits and
utility locations for the site of the Work; provided, however, that the
Contractor hereby covenants that he has inspected the premises
and familiarized himself therewith and that the locations of utilities
and other obstacles to the prosecution of the Work as shown on
the Owner's survey are for information only, are not binding upon
the Owner, and the Owner shall not incur any liability for loss or
damage by virtue of any inaccuracies or deficiencies in such
surveys. The Owner shall secure and pay for title to the site and
all necessary permanent or construction easements. The Owner
will cooperate with the Contractor in the prosecution of the Work in
such manner and to such extent as may be reasonable and shall
furnish information under its control with reasonable promptness at
the request of the Contractor.
GC -2
08/10/98
C-3 INSTRUCTIONS. The Owner shall issue all instructions
to the Contractor through the Architect.
C-4 ACCESS TO JOB SITE. The Owner shall at all times
have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access
so the Owner may perform its assigned functions under the
Contract Documents.
C-5 PROGRESS INSPECTIONS. The Owner and the
Architect will make visits to the Site to familiarize themselves with
the progress and quality of the Work and to determine if the work
is proceeding in accordance with the Contract documents. On the
basis of on -site observations and reports provided by the Architect
concerning the progress and quality of the work, the Owner will
approve and authorize the Contractor's applications for payments.
C-6 AUTHORITY TO STOP WORK. The Owner will have
authority to reflect work that does not conform to the Plans and
Specifications. Whenever, in its reasonable opinion, the Owner
considers it necessary or advisable in order to insure the proper
realization of the intent of the Plans and Specifications, the Owner
will have authority to require the Contractor to stop the work or any
portion thereof, or to require the Contractor to stop the Work or
any portion thereof, or to require special inspection or testing of
the Work whether or not such Work be then fabricated, installed or
completed.
C-7 SUBSTANTIAL COMPLETION INSPECTION. Upon
agreement of the Contractor and Architect that the Work is
substantially complete, the Owner will schedule a Substantial
Completion Inspection to be conducted by the Architect and
attended by representatives of the Architect, Owner and
Contractor. Items identified during this inspection as being
incomplete, defective or deficient shall be incorporated into a
punch list to be prepared by the Architect and attached to the AIA
document G704, which is to be prepared and signed by the
Contractor, and accepted, approved and signed by the Owner.
C-8 RIGHT TO AUDIT:
Contractor agrees that the City shall, until the expiration of three
years after final payment under this contract, have access to and
the right to examine any directly pertinent books, documents,
papers and records of the contractor involving transactions relating
to this contract.
Contractor further agrees to include in all his subcontracts
hereunder a provision to the effect that the subcontractor agrees
that the City shall, until the expiration of three years after final
payment under the subcontract, have access to and the right to
examine any directly pertinent books, documents, papers and
records of such subcontractor, involving transactions to the
subcontract. The term "subcontract" as used herein includes
purchase orders.
Contractor agrees to photocopy such documents as may be
requested by the city. The city agrees to reimburse Contractor for
the costs of copies at the rate published in the Texas
Administrative Code.
SECTION D
CONTRACTOR
D-1 IDENTIFICATION. The Contractor is the person or
organization identified as such in the Contract. The term
Contractor means the Contractor or his authorized representative.
D-2 INDEPENDENT CONTRACTOR. Contractor shall
perform all work and services hereunder as an independent
contractor, not as an officer, agent, or employee of the City.
Contractor shall have exclusive control of and the exclusive right to
control the details of the work and services performed hereunder,
and all persons performing same, and Contractor shall be solely
responsible for the acts and omissions of its officers, agents,
and employees. Nothing herein shall be construed as creating a
partnership or joint enterprise between City and the Contractor, its
officers, agents and employees, and the doctrine of respondeat
superior shall not apply.
D-3 SUBLETTING: It is further agreed that the performance
of this Contract, either in whole or in part, shall not be sublet or
assigned to anyone else by said Contractor without the written
consent of the Director of Transportation and Public Works of the
City of Fort Worth.
D-4 REVIEW OF CONTRACT DOCUMENTS. The
Contractor shall carefully study and compare the Agreement,
Conditions of the Contract, Drawings, Specifications, Addenda and
modifications and shall at once report to the Owner and to the
Architect any error, inconsistency or omission he may discover.
The Contractor shall do no work without Drawings, Specifications
and Interpretations.
D-5 SUPERVISION. The Contractor shall supervise and
direct the Work, using his best skill and attention. He shall be
solely responsible for all construction means, methods,
techniques, sequences and procedures. and for coordinating all
portions of the Work under the Contract Documents.
D-6 LABOR AND MATERIALS. Unless otherwise
specifically noted, the Contractor shall provide and pay for all
labor, materials, equipment, tools, construction equipment and
machinery, water, heat, utilities, transportation and other facilities
and services necessary for the proper execution and completion of
the Work.
The successful low bidder will use its reasonable best efforts to
hire local laborers, workmen and materialmen. The general
condition is not to be constructed as limiting the right of any bidder
to employee laborers, workmen or materialmen from outside local
area.
The Contractor shall at all times enforce strict discipline and good
order among his employees, and shall not employ on the Work
any unfit person or anyone not skilled in the task assigned to him.
D-7 PREVAILING WAGE RATE. The Contractor agrees to
pay not less than the general prevailing rate of per diem wages for
Work of a similar character in the locality in which the Work is
performed, and not less than the general prevailing wage of per
diem wages for a legal holiday and overtime work to all laborers,
workmen and mechanics employed on the Work under this
Contract. The Contractor agrees to pay at least the minimum wage
per hour for all labor as the same is classified and set out by the
City of Fort Worth, Texas, a copy of which is attached hereto and
made a part hereof the same as if it were copies verbatim herein.
D-8 WARRANTY. The Contractor warrants to the Owner
and the Architect that all materials and equipment furnished under
this Contract will be new unless otherwise specified, and that all
work will be of good quality, free from faults and defects, and in
conformance with the Contract Documents. All work not so
conforming to these standards may be considered defective. If
required by the Architect or the Owner, the Contractor shall furnish
satisfactory evidence as to the kind and quality of materials and
equipment.
The warranty provided in this Section shall be in addition to and
not in limitation of any other warranty or remedy provided by law or
the Contract Documents.
GC -3
08/10/98
D-9 TAXES. The Contractor is exempt from State Sales Tax
on material incorporated into the finished construction, Excise and
Use Tax.
D-10 LICENSES. NOTICES AND FEES. The Contractor
shall obtain all Permits, Licenses, Certificates, and Inspections,
whether permanent or temporary, required by law or these
Contract Documents.
The Contractor shall give all Notices and comply with all Laws,
Ordinances, Rules, Regulations and Orders of any public authority
bearing on the performance of the Work. If the Contractor
observes or becomes aware that bearing on the performance 'of
the Work. If the Contractor observes or becomes aware that any
of the Contract Documents are at variance therewith in any
respect, he shall promptly notify the Architect in writing and any
necessary changes will be made. If the Contractor performs any
Work knowing that it is in violation of, or contrary to, any of such
Laws, Statutes, Charter, Ordinances, Orders or Directives, or
Regulations without furnishing Notice to the Architect, the
Contractor will assume full responsibility therefor and bear all
costs attributable thereto.
D-1 I CASH ALLOWANCES. The Contractor shall include in
the Contract Sum all allowances stated in the Contract
Documents. These allowances shall cover the net cost of the
materials and equipment delivered and unloaded at the site, and
all applicable taxes. The Contractor's handling costs on the site,
labor, installation costs, overhead, profit and other expenses
contemplated for the original allowance shall be included in the
Contractor Sum and not in the allowance. The Contractor shall
cause the Work covered by these allowances to be performed for
such amounts and by such persons as the Architect may direct,
but he will not be required to employ persons against whom he
makes a reasonable objection. If the cost, when determined, is
more than or less than the allowance, the Contract Sum shall be
adjusted accordingly by Change Order which will include additional
handling costs on the site, labor, installation costs, field overhead,
profit and other direct expenses resulting to the Contractor from
any increase over the original allowance.
D-12 SUPERINTENDENT. The Contractor shall employ a
competent superintendent and necessary assistants who shall be
in attendance at the Project site during the progress of the Work.
The superintendent shall be satisfactory to the Contractor and the
Owner. The superintendent shall represent the Contractor and all
communications given to the superintendent shall be binding as if
given to the Contractor. Important communications will be
confirmed in writing. Other communications will be so confirmed
on written request in each case.
D-13 RESPONSIBILITIES FOR EMPLOYEES AND SUB-
CONTRACTORS. The Contractor shall be responsible to the
Owner for the acts and omissions of all his employees and all
Sub -contractors, their agents and employees, and all other
persons performing any of the Work under a contract with the
Contractor.
D-14 FAILURE TO COMMENCE WORK: Should the
Contractor fail to begin the work herein provided for within the
time herein fixed or to carry on and complete the same according
to the true meaning of the intent and terms of said Plans,
Specifications and Contract Documents, then the Owner shall
have the right to either demand the surety to take over the work
and complete same in accordance with the Contract Documents
or to take charge of and complete the work in such a manner as
it may deem proper, and if, in the completion thereof, the cost to
the said City shall exceed the contract price or prices set forth in
the said plans and specifications made a part hereof, the
Contractor and/or its Surety shall pay said City on demand in
writing, setting forth and specifying an itemized statement of the
total cost thereof, said excess cost.
D-15 PROGRESS SCHEDULE. The Contractor, immediately
after being awarded the contract, shall prepare and submit for the
Architect's approval, an estimated progress schedule for the Work.
The progress schedule shall be related to the entire Project. This
schedule shall indicate the dates for the starting and completion of
the various states of construction and shall be revised as required
by the conditions of the Work, subject to the Architect's approval.
It shall also indicate the dates for submission and approval of shop
drawings and submittals as well as the delivery schedule for major
pieces of equipment and/or materials.
The progress schedule shall be updated at least monthly by the
contractor and submitted to the Architect for approval with the
Contractor's monthly progress payment requests.
D-16 DRAWINGS AND SPECIFICATIONS AT THE SITE.
The Contractor shall maintain at the site for the Owner one copy of
all Drawings, Specifications. Addenda, approved Shop Drawings,
Change Orders, and other Changes and Amendments in good
order and marked to record all changes made during construction.
These shall also be available to the Architect. The Drawings,
marked to record all changes made during construction, shall be
delivered to the Architect upon completion of the Work, and the
Architect will prepare, and provide to the Owner, one complete set
of reproducible record drawings of the work.
D-17 SHOP DRAWINGS AND SAMPLES. Shop Drawings
are drawings, diagrams, illustrations, schedules, performance
charts, brochures and other data which are prepared by the
Contractor or any Subcontractor, manufacturer, supplier or
distributor, and which illustrate some portion of the Work.
Samples are physical examples furnished by the Contractor to
illustrate materials, equipment or workmanship, and to establish
standards by which the Work will be judged.
The Contractor shall review, stamp with his approval and submit,
with reasonable promptness and in orderly sequence so as to
cause no delay in the Work or in the work of any other contractor,
normally within the first 90 days of the work, six copies of all shop
Drawings and Samples required by the Contract Documents or
subsequently by the Architect as covered by changes or
amendments. Shop Drawings and Samples shall be properly
identified as specified, or as the Architect may require. At the time
of submission the Contractor shall inform the Architect in writing of
any deviation in the Shop Drawings or Samples from the
requirements of the Contract Documents.
By approving and submitting Shop Drawings and Samples, the
Contractor thereby represents that he has determined and verified
all field measurements, field construction criteria, materials,
catalog numbers and similar data, and that he has checked and
coordinated each shop drawing given in the Contract Documents.
The Architect's approval of a separate item shall not indicate
approval of an assembly in which the itemfunctions.
The Architect will review and approve Shop Drawings and
Samples with reasonable promptness so as to cause no delay, but
only for conformance with the design concept of the Project and
with the information given in the Contract Documents. The
Architect's approval of a separate item shall not indicate approval
of an assembly in which the item functions.
The Contractor shall make any corrections required by the
Architect and shall resubmit the required number of corrected
copies of Shop Drawings or new Samples until approved. The
Contractor shall direct specific attention in writing or on
resubmitted Shop Drawings to revisions other than the corrections
requested by the Architect on previous submissions.
GC -4
08/10/98
a
0
17
0
0
ci
0
0
0
0
ci
0
a
0
I
0
0
The Architect's approval of Shop Drawings or Samples shall not
relieve the Contractor of responsibility for any deviation from the
requirements of the Contract Documents unless the Contractor
has informed the Architect in writing of such deviation at the time
of submission and the Architect has given written approval to the
specific deviation as authorized in Paragraph A-2, Architect's
approval shall not relieve the Contractor from responsibility for
errors or omissions in the Shop Drawings or Samples.
No portion of the Work requiring a Shop Drawing or Sample
submission shall be commenced until the Architect has approved
the submittal. All such portions of the Work shall be in accordance
with approved Shop Drawings and Samples.
D-18 SITE USE. The Contractor shall confine operations at
the site to areas permitted by law, ordinances, permits and the
Contract Documents and shall not unreasonably encumber the
site with any materials or equipment. Until acceptance of the work
by the City Council of the City of Fort Worth, the entire site of the
Work shall be under the exclusive control, care and responsibility
of the Contractor. Contractor shall take every precaution against
injury or damage to persons or property by the action of the
elements or from any other cause whatsoever. The Contractor
shall rebuild, repair, restore and make good at his own expenses
all injuries or damages to any portions of the Work occasioned by
any of the above, caused before acceptance.
D-19 SAFE WORK PRACTICES. The Contractor shall
employ safe practices in handling materials and equipment used
in performing required work so as to insure the safety of his
workmen, City employees and the public. The Contractor shall
keep the premise free at all times from accumulation of waste
materials or rubbish. At the completion of the work, the Contractor
shall remove all his wastes and rubbish from and about the work
area, as well as his tools, equipment and surplus materials and
shall leave the area as clean and free of spot, stains, etc., as
before the work was undertaken.
D-20 FIELD OFFICES AND SHEDS. The Contractor is not
required to provide a temporary field office or telephone for
projects under $500,000. Contractor shall equip the Project
Superintendent with a pager and provide 24 -hour contacts to the
City.
D-21 CUTTING AND PATCHING OF WORK. The Contractor
shall do all cutting, fitting or patching of his Work that may
required to make its several parts fit together properly, and shall
not endanger any Work by cutting, excavating or otherwise altering
the Work or any part of it.
D-22 CLEAN UP. The Contractor at all times shall keep the
premises free from accumulation of waste materials or rubbish. At
the completion of the Work he shall remove all his waste materials
and rubbish from and about the Project as well as all his tools,
construction equipment, machinery and surplus materials, and
shall clean all glass surfaces and leave the Work "Broom-cleanor
its equivalent, except at otherwise specified. In addition to removal
of rubbish and leaving the buildings broom -clean", Contractor
shall clean all glass, replace any broken glass, remove stains,
spots, marks and dirt from decorated work, clean hardware,
remove paint spots and smears from all surfaces, clean fixtures
and wash all concrete, tile and terrazzo floors.
If the Contractor fails to clean up, the Owner may do so, and the
cost thereof shall be charged to the Contractor.
D-23 COMMUNICATIONS. As a general rule, the Contractor
shall forward all communications to the Owner through the
Architect, and in all other instances the Contractor shall furnish the
Architect a copy of any communication sent directly to the Owner.
SUBCONTRACTORS
E-1 DEFINITION. A Subcontractor is a person or
organization who has a direct contract with the Contractor to
perform any of the Work at the site. The term Subcontractor is
referred to throughout the Contract Documents as if singular in
number and masculine in gender and means a Subcontractor or
his authorized representative.
Nothing contained in the Contract, Documents shall create any
contractual relation between the Owner and the Architect and any
subcontractor or any of his sub -subcontractors or materialmen.
E-2 AWARD OF SUBCONTRACTS. The bidder shall furnish
a list of the names of the subcontractors or other persons or
organizations (including those who are to furnish materials or
equipment fabricated to a special design) proposed for such
portions of the Work as may be designated in the bidding
requirements, or if none is so designated in the bidding
requirements, the names of the Subcontractors proposed for the
principal portions of the Work. Prior to the award of the Contract,
the Architect shall notify the successful bidder in writing if either
the Owner or Architect, after due investigation, has reasonable
objection to any person or organization on such list. Failure of the
Owner and Architect to make an objection to any person or
organization on the list prior to the award of this Contract shall not
constitute acceptance of such person or organization.
If, prior to the award of the Contract, the Owner or Architect has an
objective to any person or organization on such list, and refuses to
accept such person or organization, the apparent low bidder may,
prior to the award, withdraw his bid without forfeiture of bid
security. If such bidder submits an acceptable substitute, the
Owner may, at its discretion, accept the bid or he may disqualify
the bid. If, after the award, the Owner or Architect objects in writing
to any person or organization on such list, the Contractor shall
provide an acceptable substitute.
The Contractor shall not make any substitution for any
Subcontractor or person or organization that has been accepted
by the Owner and the Architect, unless the substitution is also
acceptable to the Owner and the Architect.
E-3 TERMS OF SUBCONTRACTS. All work performed for
the Contractor by a Subcontractor shall be pursuant to an
appropriate agreement between the Contractor and the
Subcontractor (and where appropriate between Subcontractors
and Sub -subcontractors) which shall contain provisions that:
1. preserve and protect the rights of the Owner and the
Architect under the Contract with respect to the Work to be
performed under the subcontract so that the subcontracting
thereof will not prejudice such rights;
2. require that such Work be performed in accordance with the
requirements of the Contract Documents;
3. require submission to the Contractor of applications for
payment under each subcontract to which the Contractor is a
party, in reasonable time to enable the Contractor to apply for
payment;
4. require that all claims for additional costs, extensions of time,
damages for delays or otherwise with respect to
subcontracted portions of the Work shall be submitted to the
Contractor (via any Subcontractor or Sub -subcontractor
where appropriate) in the manner provided in the Contract
Documents for like claims by the Contractor upon the Owner;
5. waive all rights the contracting parties may have against one
another for damages caused by fire or other perils covered by
the property insurance, except such rights, if any, as they
SECTION E
GC -5
IL31 08/10/98
0
ci
!l
G]
El
a
0
0
a
a
C
El
r
I
a
may have to proceeds of such insurance held• by the Owner,
and,
6. obligate each Subcontractor specifically to consent to the
provisions of this Section
All of the provisions set out in this section shall be deemed to have
been included in every subcontract, and every subcontract shall be
so construed and applied as to the Owner and the Architect,
whether or not such provisions are physically included in the sub-
contract.
E-4 MINORITY AND WOMENS BUSINESS ENTERPRISE
M/WBE Should the base bid be less than $25,000, the
requirements of this section do not apply.
In accordance with City of Fort Worth Ordinance No 11923, the
City of Fort Worth sets goals for the participation of minority
business enterprises and women business enterprises in City
contracts. Ordinance No 11923 is incorporated in these
Specifications by reference. A copy of the Ordinance may be
obtained from the Office of the City Secretary. Failure to comply
with the Ordinance shall be a material breach of contract.
The M/WBE UTILIZATION FORM, M/WBE GOALS WAIVER
FORM and GOOD FAITH EFFORT FORM, as applicable, must be
submitted within five city business days after bid opening. Failure
to submit the post bid information shall render the bid non-
responsive.
The City will consider the contractors performance on other City
Projects regarding its M/WBE program in the evaluation of bids.
Failure to comply with the City's M/WBE program, or to demon-
strate a "good faith effort", shall result in a bid being considered
irresponsible.
Upon request, Contractor must provide the City with complete and
accurate information regarding actual work performed by a
Minority or Women Business Enterprise (MIWBE) on the contract
and proof of payment thereof. Contractor further agrees to permit
an audit and/or examination of any books, records or files in it's
possession that will substantiate the actual work performed by an
M/ WBE. The misrepresentation of acts (other than a negligent
misrepresentation) and/or the commission of fraud by the
Contractor will be grounds for termination of the contract and/or
initiating action under appropriate federal, state, or local laws or
ordinances relating to false statement. Further any such
misrepresentation (other than a negligent misrepresentation)
and/or commission of fraud will result on the Contractor being
determined to be irresponsible and barred from participating in
City work for a period of time of not less than three years.
Contractor shall provide copies of subcontracts or cosigned letters
of intent with approved M/WBE subcontractors prior to issuance of
the Notice to Proceed. Contractor shall also provide monthly
reports on utilization of the subcontractors to the Construction
Manager.
The Contractor may count first and second tier subcontractors
and/or suppliers toward meeting the goals. The Contractor may
count toward its goal a portion of the total dollar amount of the
contract with a joint venture equal to the percentage of the MIWBE
participation in the joint venture for a clearly defined portion of the
work to be performed. All subcontractors used in meeting the
goals must be certified prior to the award of the Contract.
Whenever a change order affects the work of an M/WBE
subcontractor or supplier, the MIWBE shall be given an
opportunity to perform the work. Whenever a change order is in
excess of 10% of the original contract, the M/WBE coordinator
shall determine the goals applicable to the work to be performed
under the change order.
During the term of the contract the contractor shall:
1. Make no unjustified changes of deletions in it's M/WBE
participation commitments submitted with or subsequent to
the bid, and,
2. If substantial subcontracting and/or substantial supplier
opportunities arise during the term of the contract which the
contractor had represented he would perform with his forces,
the contractor shall notify the City before subcontracts or
purchase orders are let, and shall be required to comply with
modifications to goals as determined by the City, and,
3. Submit a REQUEST FOR APPROVAL OF CHANGE FORM,
if the contractor desires to change or delete any of the
M/WBE subcontractors or suppliers.
Justification for change may be granted for the following:
1. Failure of subcontractor to provide evidence of coverage by
Workers' Compensation Insurance
2. Failure of subcontractor to provide required general liability or
other insurance.
3. Failure of subcontractor to execute a standard subcontract
form in the amount of the proposal used by the Contractor in
preparing his MIWBE Participation plan
4. Default by the MIWBE subcontractor or supplier in the
performance of the subcontract.
Other reasons at the discretion of the M/WBE Coordinator
Within ten days after final payment from the City the contractor
shall provide the M/WBE Office with documentation to reflect final
participation of each MIWBE subcontractor and supplier used on
the project.
E-5 PAYMENTS TO SUBCONTRACTORS. The Contractor
shall pay each Subcontractor, upon receipt of payment from the
Owner, an amount equal to the percentage of completion allowed
to the Contractor on account of such Subcontractor's Work. The
Contractor shall also require each Subcontractor to make similar
payments to his subcontractors.
If the Architect refuses to issue a Certificate for Payment for any
cause which is the fault of the Contractor and not the fault of a
particular subcontractor, the Contractor shall pay that
Subcontractor on demand, made at any time after the Certificate
for Payment would otherwise have been issued, for his Work to
the extent completed, less the retained percentage.
The Contractor shall pay each Subcontractor a just share of any
insurance monies received by the Contractor, and he shall require
each Subcontractor to make similar payments to his
Subcontractors.
The Architect may, on request and at its discretion, furnish to any
Subcontractor, if practicable, information regarding percentages of
completion certified to the Contractor on account of Work done by
such Subcontractors.
Neither the Owner nor the Architect shall have any obligation to
pay or to see to the payment of any monies to any Subcontractor.
SECTION F
SEPARATE CONTRACTS
F-1 OWNER'S RIGHT. The Owner reserves the right to
award separate contracts in connection with other portions of the
GC -6
El08/10/98
Work. When separate contract are awarded for other portions of
the Work, the Contractor" in the Contract Documents in each
case shall be the contractor who signs each separate contract.
F-2 MUTUAL RESPONSIBILITY OF CONTRACTORS. The
Contractor shall afford other contractors reasonable opportunity for
the introduction and storage of their materials and equipment and
the execution of their work, and shall properly connect and
coordinate his work with theirs.
If any part of the Contractor's Work depends for proper execution
or results upon the work of any other separate contractor, the
Contractor shall inspect and promptly report to the Architect any
apparent discrepancies or defects in such work that render it
unsuitable for such proper execution and results. Failure of the
Contractor to inspect and report shall constitute an acceptance of
the other contractor's work as fit and proper to receive his Work,
except as to defects which may develop in the other separate
contractor's work after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property of
any separate contractor on the site, the Contractor shall, upon due
notice, settle with such other contractor by agreement, if he will so
settle. If such separate contractor sues the Owner on account of
any damage alleged to have been so sustained, the Owner shall
notify the Contractor who shall defend against such suit at the
Contractor's expense, and if any judgment against the Owner
arises therefrom, the Contractor shall pay or satisfy such judgment
and shall reimburse the Owner for all attorney's fees, court costs
and expenses which the Owner has incurred in connection with
such suit.
F-3 CUTTING AND PATCHING UNDER SEPARATE
CONTRACTS. The Contractor shall do all cutting, fitting or
patching of his Work that may be required to fit it to receive or be
received by the work of other contractors shown in the Contract
Documents. The Contractor shall not endanger any work or any
other contractors by cutting, excavating or otherwise altering any
work and shall not cut or alter the work of any other contractor
except with the written consent of the Architect.
Any costs caused by defective or ill-timed work shall be borne by
the party responsible therefor.
F-4 OWNER'S RIGHT TO CLEAN UP. If a dispute arises
between the separate contractors as to their responsibility for
cleaning up, the Owner may clean up and charge the cost thereof
to the several contractors as the Director of the Department of
Transportation and Public Works shall determine to be just.
SECTION G
MISCELLANEOUS PROVISIONS
G-1 CONFLICT OF LAWS. The law of the place where the
site is located shall govern the Contract. The Contractor must
familiarize himself and strictly comply with all Federal, State, and
County and City Laws, Statutes, Charter, Ordinances,
Regulations, or Directives controlling the action or operation of
those engaged upon the work affecting the materials used. He
shall indemnify and save harmless the City and all of its officers
and agents against any claim or liability arising from or based on
the violation of any such Laws, Statutes, Charter, Ordinances,
Regulations, or Directives, whether by himself, his employees,
agents or subcontractors.
G-2 GOVERNING LAWS. It is mutually agreed and
understood that this agreement is made and entered into by the
parties hereto with reference to the existing Charter and
Ordinances of the City of Fort Worth and the laws of the State of
Texas with reference to and governing all matters affecting this
Contract, and the Contractor agrees to fully comply with all the
provisions of the same.
G-3 PERSONAL LIABILITY OF PUBLIC OFFICIALS. In
performing their duties under the Statutes of the State of Texas
and the Charter and Ordinances of the City of Fort Worth in
connection with this Contract, or in exercising any of the powers
granted the Owner herein, the officers, agents and employees of
the City of Fort Worth are engaged in the performance of a
governmental function and shall not incur any personal liability by
virtue of such performance hereunder, except for gross negligence
or willful wrong.
G-4 COMPLIANCE WITH LAWS. Contractor agrees the
comply with all laws, Federal, state and local, including all
ordinances, rules and regulations of the City of Fort Worth, Texas.
Materials incorporated into the finished Project are not subject to
State Sales Tax.
Contractors are responsible for obtaining construction permits
from the governing agencies. Contractor shall schedule all code
inspections with the Code Inspection Division in accordance with
the permit requirements and submit a copy of updated schedule to
the Construction manager weekly. Building, plumbing, electrical
and mechanical building permits are issued without charge. Water
and sewer access fees will be paid by the City. Any other permit
fees are the responsibility of the Contractor.
G-5 INDEMNIFICATION: Contractor covenants and agrees
to, and does hereby indemnify, hold harmless and defend City of
Fort Worth and the Construction Manager, their officers, agents.
servants and employees, from and against any and all claims or
suits for property damage or loss and/or personal injury. Including
death, to any and all persons, of whatsoever kind or character,
whether real or asserted, arising out of or in connection with,
directly or indirectly, the work and services to be performed
hereunder by Contractor, its officers, agents, employees,
contractors, subcontractors, licensees or invitees, whether or not
caused, in whole or in part, by alleged negligence on the part of
officers, agents, servants, employees, contractors, subcontractors,
licensees and invitees of the City of Fort Worth: and said
Contractor does hereby covenant and agree to assume all liability
and responsibility of City of Fort Worth, their officers, agents,
servants and employees for property damage or loss, and/or
personal injuries, including death, to any and all persons of
whatsoever kind or character, whether real or asserted, arising out
of or in connection with, directly or indirectly, the work and
services to be performed hereunder by Contractor, its officers,
agents, employees, contractors, subcontractors, licensees and
invitees whether or not caused, in whole or in part, by alleged
negligence of officers, agents, servants, employees, contractors,
subcontractors, licensees or invitees of the City of Fort Worth.
Contractor likewise covenants and agrees to, and does hereby,
indemnify and hold harmless City of Fort Worth from and against
any and all injuries, loss or damages to property of the City of Fort
Worth during the performance of any of the terms and conditions
of this Contract, whether arising out of or in connection with or
resulting from, in whole or in part, any and all alleged acts or
omissions of officers, agents, servants, employees, contractors,
subcontractors, licenses, or invitees of the City of Fort Worth.
G-6 SUCCESSORS AND ASSIGNS. Except as provided in
Paragraph E-2, this contract shall be binding upon and insure to
the benefit of the parties hereto, their Successors or Assigns.
Contractor shall not assign or sublet all or any part of this Contract
or his rights or duties hereunder without the prior written consent
of the Owner. Any such purported assignment or subletting without
the prior written consent of Owner shall be void.
G-7 WRITTEN NOTICE. Written Notice shall be deemed to
have been duly served if delivered in person to the individual or
member of the firm or to an officer of the corporation for whom it
was intended, or if delivered at or sent by registered or certified
08/10/98
GC -7
mail to the last business address known to him who gives the
notice.
G-8 SURETY BONDS: Surety Bonds are required on all
City contracts in excess of $25,000. The Contractor agrees, on
the execution of this Contract, and before beginning work, to
make, execute and deliver to said City of Fort Worth good and
sufficient surety bonds for the faithful performance of the terms
and stipulations of the Contract and for the payment to all
claimants for labor and/or materials furnished in the prosecution of
the work, such bonds being as provided and required in Article
5160 of the Revised Civil Statutes of Texas, as amended, in the
form included in the Contract Documents, and such bonds shall be
100 percent of the total contract price, and the said surety shall be
a surety company duly and legally authorized to do business in
the State of Texas, and acceptable to the City Council of the City
of Fort Worth.
Bonds shall be made on the forms furnished by or otherwise
acceptable to the City. Each bond shall be properly executed by
both the Contractor and the Surety Company. Bonds required by
the City shall be in compliance with all relevant local, state and
federal statutes.
To be an acceptable surety on the bond, (1) the name of the
surety should be included on the current U. S. Treasury List of
Acceptable Securities jCircular 570]. Any surety authorized to do
business in Texas a may write performance and payment bonds
on a project without reinsurance to the limit of 10 percent of its
capital and surplus. Such a surety must reinsure any obligation
over 10 percent. The amount in excess of 10 percent must be
reinsured by reinsurers who are duly authorized, accredited, or
trusteed to do business in the State of Texas.
Should any surety for the contracted project be determined
unsatisfactory at any time during same, the Contractor shall
immediately provide a new surety bond satisfactory to the City.
G-10 OWNER'S RIGHT TO CARRY OUT THE WORK. If the
Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents or fails to perform any
provision of the Contract, the Owner may, without prejudice to any
other remedy he may have, enter the site and make good such
deficiencies. In such case an appropriate Change Order shall be
issued deducting from the payments then or thereafter due the
Contractor the cost of correcting such deficiencies, including the
cost of the Architect's additional services made necessary by such
default, neglect or failure. If the payments then or thereafter due
the Contractor are not sufficient to cover such amount, the
Contract shall pay the difference to the Owner.
G-11 ROYALTIES AND PATENTS. The Contractor shall pay
all royalties and license fees. He shall defend all suits or claims for
infringement of any patent rights and shall save the Owner
harmless from loss on account thereof and shall be responsible for
all such loss when a particular design, process or the product of a
particular manufacturer or manufacturers is specified; however, if
the Contractor has reason to believe that the design, process or
product specified is an infringement of a patent, he shall be
responsible for such loss unless he promptly gives such
information to Architect.
G-12 TESTS. If the Contract Documents, Laws, Ordinances,
Rules, Regulations or Orders of any public authority having
jurisdiction require any Work to be inspected, tested or approved,
the Contractor shall give the Architect timely notice of its readiness
and the date arranged so the Architect may observe such
inspection, testing or approval. The Owner shall bear all costs of
such inspection, tests and approvals unless otherwise provided.
If after the commencement of the Work, the Owner or Architect
determine that any Work requires special inspection, testing or
approval not included above, the Owner or the Architect, upon
written authorization from the Owner, will instruct the Contractor to
order such special inspection, testing or approval, and the
Contractor shall give notice as required in the preceding
paragraph. If such special inspection or testing reveals a failure of
the Work to comply (1) with the requirements of the Contract
Documents or (2) with respect to the performance of the work, with
Laws, Statutes, Charter, Ordinances, Regulations or Orders of any
public authority having jurisdiction, the Contractor shall bear all
costs thereof, including the Architect's additional services made
necessary by such costs; otherwise the Owner shall bear such
costs, and an appropriate Change Order shall be issued.
The Contractor shall secure certificate of inspection, testing or
approval, and three copies will be promptly delivered by him to the
Architect. The Architect will review the certificates and forward one
copy of each with his recommendation(s) to the Owner.
If the Architect or Owner wish to observe the inspections, tests or
approvals required by this Section, they will do so promptly and,
where practicable, at the source of supply.
Neither the observations of the Architect or the Owner in their
administration of the Construction Contract, nor inspections, tests
or approvals by persons other than the Contractor shall relieve the
Contractor from his obligations to perform the Work in accordance
with the Contract Documents.
G-13 INTERRUPTION OF EXISTING UTILITIES SERVICES.
The Contractor shall perform the work under this Contract with a
minimum of outage time for all utilities. Interruption shall be by
approved sections of the utility. In some cases, the Contractor
may be required to perform the work while the existing utility is in
service. The existing utility service may be interrupted only when
approved by the Owner. When it is necessary to interrupt the
existing utilities, the Contractor shall notify the Owner in writing at
least ten days in advance of the time that he desires the existing
service to be interrupted. The interruption time shall be kept to a
minimum. Depending upon the activities at an existing facility that
requires continuous service from the existing utility, an interruption
may not be subject to schedule at the time desired by the
Contractor. In such cases, the interruption may have to be
scheduled at a time of minimum requirements of demand for the
utility. The amount of time requested by the Contractor of existing
utility services shall be as approved by the Owner.
G-14 LAYING OUT WORK. The Contractor shall verify
dimensions and elevations indicated in layout of existing work.
Discrepancies between Drawings, Specifications, and existing
conditions shall be referred to Architect for adjustment before work
affected is performed. Failure to make such notification shall place
responsibility upon Contractor to carry out work in satisfactory
workmanlike manner at the Contractor's sole expense.
The Contractor shall be held responsible for the location and
elevation of all the construction contemplated by the Construction
Documents.
Prior to commencing work, the Contractor shall carefully compare
and check all Architectural, Structural, Mechanical an Electrical
drawings; each with the other that in any affects the locations or
elevation of the work to be executed by him, and should any
discrepancy be found, he shall immediately report the same to the
Architect for verification and adjustment. Any duplication of work
made necessary by failure or neglect on his part to comply with
this function shall be done at the contractors sole expense.
G-15 MEASUREMENTS: Before ordering any material or
doing any work, the Contractor shall verify all measurements at
the site or at the building and shall be wholly responsible for the
correctness of same. No extra charge or compensation will be
allowed on account of any difference between actual dimensions
GC -8
08/10/98
and dimensions indicated on the drawings. Any difference which
may be found shall be submitted to the Architect for consideration
and adjustment before proceeding with the project.
G-16 EXISTING OVERHEAD OR UNDERGROUND WORK.
The Contractor shall carefully check the site where the project is to
be erected and observe any existing overhead wires and
equipment. Any such work shall be moved, replaced or protected,
as required, whether or no shown or specified at the contractor's
sole expense.
Attention is directed to the possible existence of pipe and other
underground improvements that may or may not be shown on the
Drawings. All reasonable precautions shall be taken to preserve
and protect any such improvements whether or not shown on the
Drawings.
Location of existing underground lines, shown the Drawings are
based on the best available sources, but are to be regarded as
approximate only. Exercise extreme care in locating and
identifying these lines before excavation in adjacent areas.
G-17 ALIGNMENT OF JOINTS IN FINISH MATERIALS. It
shall be the responsibility of the Contractor to make certain in the
installation of jointed floor, wall and ceiling materials that:
1. preserve and protect the rights of the Owner and the
Architect under the Contract with respect to the Work to be
performed under the subcontract so that the subcontracting
thereof will not prejudice such rights:
2. Place joints to relate to all opening and breaks in the
structure and be symmetrically placed wherever possible.
This includes heating registers, light fixtures, equipment, etc.
If because of the non -related sizes of the various materials and
locations of openings, etc., it is not possible to accomplish the
above, the Contractor shall request the Architect to determine the
most satisfactory arrangement. The Contractor shall establish
centerlines for all trades.
G-1 8 INTEGRATING EXISTING WORK. The Contractor shall
protect all existing street and other improvements from damages.
Contractor's operations shall be confined to the immediate vicinity
of the new work and shall not in any interfere with or obstruct the
ingress or egress to an from existing adjacent facilities.
Where new site work is to be connected to existing work, special
care shall be exercised by the Contractor not to disturb or damage
the existing work more than necessary. All damaged work shall be
replaced, repaired and restored to its original condition at no cost
to the Owner.
G-19. HAZARDOUS MATERIAL CERTIFICATION: It is the
intent of the contract documents, whether expressly stated or not,
that nothing containing hazardous materials, such as asbestos,
shall be incorporated in to the project. The contractor shall
exercise every reasonable precaution to ensure that
asbestos -containing materials are not incorporated into any
portion of the project, including advising all materials suppliers and
subcontractors of this requirement. The contractor shall verify that
components containing lead do not contact the potable water
supply.
G-20 LOCATION OF EQUIPMENT AND PIPING. Drawing
showing location of equipment, piping, ductwork, etc. are
diagrammatic and job conditions may not always permit their
installation in the location shown. When this situation occurs, it
shall be brought to the Architect's attention immediately and the
relocation determined in a joint conference. The Contractor will be
held responsible for the relocating of any items without first
obtaining the Architect's approval. He shall remove and relocate
such items at his own expense if so directed by the Architect.
Where possible uniform margins are to be maintained between
parallel lines and or adjacent wall, floor or ceiling surfaces.
G-21 OVERLOADING. The Contractor shall be responsible
for loading of any part or parts of structures beyond their safe
carrying capacities by placing of materials, equipment, tools,
machinery or any other item thereon. ,No loads shall be placed on
floors or roofs before they have attained their permanent and safe
strength.
G-22 MANUFACTURER'S INSTRUCTIONS. Where it is
required in the Specifications that materials, products, processes,
equipment, or the like be installed or applied in accordance with
manufacturer's instructions, direction or specifications, or words to
this effect, it shall be construed to mean that said application or
installation shall be in strict accordance with printed instructions
furnished by the manufacturer of the material concerned for use
under conditions similar or those at the job site. Six copies of such
instructions shall be furnished to the Architect and his approval
thereof obtained before work is begun.
G-23 CLEANING UP. The Contractor shall keep the premises
free from accumulation of waste material or rubbish caused by
employees or as a result of the work.
At completion of work, the General Contractor shall, immediately
prior to final inspection of complete building, execute the following
final cleaning work with trained janitorial personnel and with
material methods recommended by the manufactures of installed
materials.
1. Sweep and buff resilient floors and base, and vacuum
carpeting.
2. Dust all metal and wood trim and similar finished materials.
3. Clean all cabinets and casework.
4. Dust all ceilings and walls.
5. Dust, and if necessary wash, all plumbing and electrical
fixtures.
6. Wash all glass and similar non -resilient materials.
7. All hardware and other unpainted metals shall be cleaned
and polished and all equipment and paint or decorated work
shall be cleaned and touched -up if necessary, and all
temporary labels, tags, and paper coverings removed
throughout the buildings. Surfaces that are waxed shall be
polished.
8. The exterior of the building, the grounds, approaches,
equipment, sidewalks, streets, etc. shall be cleaned similar to
interior of buildings and left in good order at the time of final
acceptance. All paint surfaces shall be clean and unbroken,
hardware shall be clean and polished, all required repair work
shall be completed and dirt areas shall be scraped and
cleared of weed growth.
9. Glass cleaning: Clean all glass surfaces and mirrors of putty,
paint materials, etc., without scratching or injuring the glass
and leave the work bright, clean and polished. Cost of this
cleaning work shall be borne by Contractor.
10. Cleaning, polishing, scaling, waxing and all other finish
operations indicated on the Drawings or required in the
Specifications shall be taken to indicate the required
condition at the time of acceptance of all work under the
Contract.
08/10/98
GC -9
0
n
0
a
a
D
0
D
I
a
Lii
0
p
11. Burning: Burning of rubbish on the premises will not be
permitted.
G-24 DUST CONTROL. Precaution shall be exercised at all
times to control dust created as a result of any operations during
the construction period. If serious problems or complaints arise
due to air -borne dust, or when directed by the Architect, operations
causing such problems shall be temporarily discontinued and
necessary steps taken to control the dust.
G-25 FIRE PROTECTION. The contractor shall at all times
maintain good housekeeping practices to reduce the risk of fire
damage or injury to workmen. All scrap materials, rubbish and
trash shall be removed daily from in and about the building and
shall not be permitted to be scattered on adjacent property.
Suitable storage space shall be provided outside the immediate
building area for storing flammable materials and paints; no
storage will be permitted in the building. Excess flammable liquids
being used inside the building shall be kept in closed metal
container and removed from the building during unused periods.
A fire extinguisher shall be available at each location where cutting
or welding is being performed. Where electric or gas welding or
cutting work is done, interposed shields of incombustible material
shall be used to protect against fire damage due to sparks and hot
metal. When temporary heating devices are used, a watchman
shall be present to cover periods when other workmen are not on
the premises.
The Contractor shall provide fire extinguishers in accordance with
the recommendations and NFPA Bulletins Nos. 10 and 241.
However, in all cases a minimum of two fire extinguishers shall be
available for each floor of construction.
G-26 CUTTING AND PATCHING. Wherever cutting and
removal of portions of the existing work is indicated, such work
shall be neatly sawed or cut by contractor in a manner that will
produce a neat straight line, parallel to adjacent surfaces or plumb
for vertical surfaces. Care should be exercised not to damage any
work that is to remain.
At no time shall any structural members be cut without written
consent from the Architect.
G-27 PROJECT CLOSEOUT.
Final Inspection, Record Drawings: Attention is called to General
Conditions Section I entitled, "Payments and Completion."
Maintenance Manual: Sheets shall be 8 '/" x 11", except pull out
sheets may be neatly folded to 8 '/ " x 11". Manuals shall be
bound in plastic covered, 3 ring, loose leaf binder with title of
project lettered on front and shall contain:
a) Name, address and trade of all sub -contractors.
b) Complete maintenance instructions; name, address, and
telephone number of installing Contractor, manufacturer's
local representative, for each piece of operative equipment.
c) Catalog data on plumbing fixtures, valves, water heaters,
heating and cooling equipment, temperature control, fan,
electrical panels, service entrance equipment and light
fixtures.
d) Manufacturer's name, type, color designation for resilient
floors, windows, doors, concrete block, paint, roofing, other
materials.
Submit six copies of Maintenance Manual, prior to request for final
payment.
Operational Inspection and Maintenance Instruction: The
Contractor shall provide at his expense, competent manufacturer's
representatives to completely check out all mechanical and
electrical systems and items covered by the Drawings and
Specifications. This requirement shall be scheduled just prior to
and during the initial start up. After all systems are functioning
properly the representatives shall instruct maintenance personnel
of the Owner in the proper operation and maintenance of each
item.
G-28 GUARANTEE AND EXTENDED GUARANTEE. Upon
completion of the Project, prior to final payment, guarantees
required by technical divisions of Specifications shall be properly
executed in quadruplicate by subcontractors and submitted
through the Contractor to Architect. Delivery of guarantees shall
not relieve Contractor from any obligation assumed under
Contract.
The Contractor shall guarantee the entire Project for one year. In
addition, where separate guarantees, for certain portions of work,
are for longer periods, General Contractor's guarantee shall be
extended to cover such longer periods.
Guarantees shall become valid and operative and commence
upon issuance of Certificate of Inspection and Acceptance by
Owner. Guarantees shall not apply to work where damage is result
of abuse, neglect by Owner or his successor(s) in interest.
The Contractor agrees to warrant his work and materials provided
in accordance with this contract and the terms of the Technical
Specifications contained herein. Unless supplemented by the
Technical Specifications or the manufacturers normal extended
warrantees, the Contractor shall warrant all work materials, and
equipment against defects for a period of one year from the date
of final acceptance. The Contractor further agrees to bear all
costs of making good all work that is found to be defective or not
provided in accordance with the Contract Documents. Additionally
if the facility or contents are damaged due to defective materials or
workmanship of the Contractor, the Contractor further agrees to
bear all cost of repairing and/or replacing damaged items and
components to bring such items back to at least their original
condition.
G-29 RECORD DRAWINGS. Upon completion of the Work
and prior to application for final payment, one print of each of the
drawings accompanying this specification shall be neatly and
clearly marked in red by the Contractor to show variations between
the construction actually provided and that indicated or specified in
the Contract Documents. The annotated documents shall be
delivered to Architect. Where a choice of materials and/or
methods is permitted herein and where variations in the scope or
character of the work from the entire work indicated or specified
are permitted either by award of bidding items specified for that
purpose, or by subsequent change to the drawings, the record
drawings shall define the construction actually provided. The
representation of such variations shall conform to standard
drafting practice and shall include supplementary notes, legends
and details which may be necessary for legibility and clear
portrayal of the actual construction. The record drawings shall
indicate, in addition, the actual location of all sub -surface utility
lines, average depth below the surface and other appurtenances.
G-30 CONSTRUCTION FENCE. At the Contractor's option,
he may provide a substantial chain -link construction fence around
all or a part of the site. The fences and gates must be maintained
throughout the construction period. Remove the fences and gates
upon completion of the Project and restore the site to the required
original or contract condition.
G-31 PRODUCT DELIVERY, STORAGE, HANDLING. The
Contractor shall handle, store and protect materials and products,
08/10/98
GC -10
including fabricated components, by methods and means which
will prevent damage, deterioration and loss, including theft (and
resulting delays), thereby ensuring highest quality results as the
work progresses. Control delivery schedules so as to minimize
unnecessary long-term storage at project site prior to installation.
G-32 AGE: In accordance with the policy ("Policy") of the
Executive Branch of the federal government, Contractor covenants
that neither it nor any of its officers, members, agents, employees,
program participants or subcontractors, while engaged in perform-
ing this contract, shall, in connection with the employment,
advancement or discharge of employees or in connection with the
terms, conditions or privileges of their employment, discriminate
against persons because of their age except on the basis of a
bona fide occupational qualification, retirement plan or statutory
requirement.
Contractor further covenants that neither it nor its officers, mem-
bers, agents, employees, subcontractors, program participants, or
persons acting on their behalf, shall specify, in solicitations or
advertisements for employees to work on this contract, a
maximum age limit for such employment unless the specified
maximum age limit is based upon a bona fide occupational qualifi-
cation, retirement plan or statutory equipment.
Contractor warrants it will fully comply with the Policy and will
defend, indemnify and hold City harmless against any claims or
allegations asserted by third parties or subcontractor against City
arising out of Contractor's and/or its subcontractors' alleged failure
to comply with the above referenced Policy concerning age
discrimination in the performance of this agreement.
G-33 DISABILITY: In accordance with the provisions of the
Americans With Disabilities Act of 1990 (DADA"), Contractor
warrants that it and any and all of its subcontractors will not
unlawfully discriminate on the basis of disability in the provision of
services to the general public, nor in the availability, terms and/or
conditions of employment for applicants for employment with, or
employees of Contractor or any of its subcontractors. Contractor
warrants it will fully comply with ADA's provisions and any other
applicable federal, state and local laws concerning disability and
will defend, indemnify and hold City harmless against any claims
or allegations asserted by third parties of subcontractors against
City arising out of Contractor's and/or its subcontractors' alleged
failure to comply with the above -referenced laws concerning
disability discrimination in the performance of this agreement.
SECTION H
CONTRACT TIME
H-1 DEFINITIONS. The Contract Time is the
period of time allotted in the Contract Documents for completion of
the Work.
The date of commencement of the Work is the date established in
the Notice to Proceed. If there is no notice to proceed, it shall be
the date of the Agreement or such other date as may be
established therein.
The Date of Substantial Completion of the Work or designated
portion thereof is the Date certified by the Architect with the
approval of the Owner that construction is sufficiently complete, in
accordance with the Contract Documents, so the Owner may
occupy the Work or designated portion thereof for the use for
which it is intended. Final acceptance of the completed work or
any portion thereof can be made only by the City Council of the
City of Fort Worth or it's designated Assistant City Manager, and
no other form of acceptance will be binding upon the Owner.
A calendar day constitutes 24 hours of time and is any one of the
seven days of a week, including Sunday, regardless of whether a
'Working Day" or not, and regardless of weather conditions or any
situation which might delay construction. An extension of contract
time shall be in accordance with this Section. Extensions of time
will be as recommended by the Architect with final approval by
City of Fort Worth.
A working day is defined as a calendar day, not including
Saturdays, Sundays, and legal holidays, in which weather or other
conditions not under the control of the Contractor permit the
performance of work for a continuous period of not less than
seven hours between 7:00 a.m. and 6:00 p.m. However, nothing in
these Contract Documents shall be construed as prohibiting the
Contractor from working on Saturdays if he so desires. Should the
Contractor choose to work on Saturdays, one day will be charged
as contract working time when weather or other conditions permit
seven hours of work as delineated above. Legal holidays are
defined as being New Year's Day, Independence Day, Labor Day,
Thanksgiving Day, Christmas Day, Memorial Day, and Veteran's
Day.
H-2 PROGRESS AND COMPLETION. All the time limits
stated in the Contract Documents are of essence to the Contract.
The Contractor shall begin the Work on the date of
commencement as defined in this Section. He shall carry the
Work forward expeditiously with adequate forces and shall
complete it within the Contact Time.
H-3 DELAYS AND EXTENSIONS OF TIME. If the
Contractor is delayed at any time in the progress of the Work by
any act or neglect of the Owner or the Architect, or by any
employee of the Owner, or by any separate contractor employed
by the Owner, or by any separate contractor employed by the
Owner, or by changes ordered in the Work, or by labor disputes,
fire, unusual delay in transportation, unavoidable casualties or any
causes beyond the Contractor's control, or by any cause which the
Architect determines may justify the delay, then the contract time
may be extended by Change Order for such reasonable time as
recommended by the Architect and approved by the Owner. When
the Contractor is delayed due to abnormal weather conditions, the
weather table provided as WT -1 in these Contract Documents
shall be used as the basis for providing a fair and equitable
adjustment of the contract time.
All claims for extension of time shall be made in writing to the
Architect no more than fifteen days after the occurrence of the
delay; otherwise they shall be waived.
If no schedule or agreement is made stating the dates upon which
written interpretations shall be furnished, then no claim for delay
shall be allowed on account of failure to furnish such interpretation
until fifteen days after demand is made for them, and not then
unless such a claim is reasonable.
H-4 NO DAMAGE FOR DELAY. No payment,
compensation or adjustment or any kind (other than the
extensions of time provided for) shall be made to the contractor for
damages because of hindrances or delays from an cause in the
progress of the work, whether such hindrances or delays be
avoidable or unavoidable, and the contractor agrees that he will
make no claim for compensation, damages or mitigation of
liquidated damages for any such delays, and will accept in full
satisfaction for such delays said extension of time.
SECTION I
PAYMENTS AND COMPLETION
t-1 CONTRACT SUM. The Contract Sum is
stated in the proposal as accepted and is the total amount payable
by the Owner to the Contractor for the performance of the Work
under the Contract Documents.
GC -11
08/10/98
0
d
a
Lii
0
El
a
El
a
ii
1-2 SCHEDULE OF VALUES. Before the first
Applicable for Payment, the Contractor shall submit to the
Architect a Schedule of Values of the various portions of the Work,
including quantities if required by the Architect, aggregating the
total Contract Sum, divided so as to facilitate payments to Sub-
contractors in accordance with Paragraph D-4, prepared in such
form as specified or as the Architect and the Contractor may agree
upon, and supported by such data to substantiate its correctness
as the Architect may require. Each item in the Schedule of Values
shall include its proper share of overhead and profit. This
Schedule, when approved by the Architect and the Owner, shall be
used as a basis for the Contractor's Applications for Payment.
1-3 ADJUSTMENT OF QUANTITIES: Where unit prices
and estimated quantities are used to compute the contract
amount, the Owner may increase the quantities by an amount that
is 20% of the total cost for that section. Unit prices for
adjustments to unit quantities in excess to 20% may be negotiated
at the request of either party.
1-4 PROGRESS PAYMENTS. On the first day of each
month after the first month's work has been completed, the
Contractor will make current estimates in writing for review by the
Architect of materials in place complete and the amount of work
performed during the preceding month or period and the value
thereof at the prices contracted for as shown on the approved
Schedule of Values and Progress Schedule.
If payments are to be made on account of materials or equipment
not incorporated in the Work but delivered and suitably stored at
the site or in an independent, bonded warehouse such payments
shall be conditioned upon submission by the Contractor of bills of
sale or such other procedures satisfactory to the Owner to
establish the Owner's title to such materials or equipment or
otherwise protect the Owner's interest including applicable
insurance and transportation to the site.
The Contractor warrants and guarantees that title to all Work,
materials and equipment covered by an Application for Payment,
whether incorporated in the Project or not, will pass to the Owner
upon the receipt of such payment by the Contractor, free and clear
of all liens, claims, security interests or encumbrances hereinafter
referred to as "liens"; and that. no Work, materials or equipment
covered by an Application for Payment will have been acquired by
the Contractor, or by any other persons performing the Work at the
site or furnishing materials and equipment for the Work, subject to
an agreement under which an interest therein or an encumbrance
thereon is retained by the seller or otherwise imposed by the
Contractor or such other person.
The Contractor shall prepare each application for payment on AIA
Document G702, "Application and Certificate for Payment", and
attached thereto AIA Document G703, "Continuation Sheet", to
indicate the progress made to date and the period or month for
which payment is requested for each Item listed in the Schedule of
Values. A copy of the revised monthly work progress schedule
must be attached before the pay request can be accepted.
1-5 CERTIFICATES FOR PAYMENT. If the Contractor has
made Application for Payment as above, the above, the Architect
will, with reasonable promptness but not more than seven days
after the receipt of the Application, prepare a Certificate of
Payment, with a copy to the Contractor, for such amount
determined to be properly due, or state in writing reasons for
withholding a Certificate.
The issuance of a Certificate for Payment will constitute a
representation by the Architect to the Owner, based on the
Architect's observations at the site and the data comprising the
Application for Payment, that the Work has progressed to the point
indicated; that the quality of the Work is in accordance with the
Contract Documents (subject to an evaluation of the Work as a
functioning whole upon Substantial Completion, to the results of
any subsequent tests required by the Contract Documents, to
minor deviations from the Contract Documents correctable prior to
completion, and to any specific qualifications stated in the
Certificate); and recommendations to the Owner that the
Contractor be paid in the amount certified. In addition, the
Architect's approval of final payment assures the Owner that the
conditions precedent to the Contractor's being entitled to final
payment as set forth in this Section have been fulfilled.
After the Architect has issued a Certificate for Payment, the Owner
shall approve or disapprove same within ten days after it has been
delivered to the Director of the Department of Transportation and
Public Works. For contracts less than $400,000, Owner shall pay
90% of the approved estimate to the Contractor within seven days
after its approval, and the remaining 10% of each such estimate
will be retained by the Owner until the final estimate is approved
and the Work is accepted by the City Council of the City of Fort
Worth. For contracts in excess of $400,000. the Owner will retain
only 5% of each estimate until the final estimate is approved and
work accepted by the City Council of the City of Fort Worth.
No Certificate for a progress payment, nor any progress payment,
nor any partial or entire use or occupancy of the Project by the
Owner, shall constitute an acceptance of any Work not in
accordance with the Contract Documents, or relieve the
Contractor of liability in respect to any warranties or responsibility
for faulty materials pr workmanship. The Contractor shall promptly
remedy any defects in the Work and pay for any damage to other
work resulting therefrom that shall appear within a period of one
year from the date of final acceptance of the Work unless a longer
period is specified.
1-6 PAYMENTS WITHHELD. The Architect may decline to
approve an Application for Payment and may withhold his
Certificate in whole or in part if in his opinion he is unable to make
the representations to the Owner as provided in this Section. The
Architect may also decline to approve any Applications for
Payment or , because of subsequently discovered evidence or
subsequent inspections, may nullify the whole or any part of any
Certificate for Payment previously issued to such extent as may be
necessary in his opinion to protect the Owner from loss because
of:
a) defective work not remedied;
b) claims filed or reasonable evidence indicating probable filing
of claims;
c) failure of the Contractor to make payments properly to
Subcontractors, or for labor, materials or equipment;
d) reasonable doubt that the Work can be completed for the
unpaid balance of the Contract Sum;
e) damage to another contractor;
f) reasonable indication that the Work will not be completed
within the Contract Time; or
g) unsatisfactory prosecution of the Work by the Contractor.
When such grounds for the refusal of payment are removed,
payment shall be made for amounts withheld because of them.
The Owner reserves the right to withhold the payment of any
monthly estimate, without payment of interest, if the Contractor
fails to perform the Work in accordance with the specifications or
instructions of the Architect.
1-7 UNRESOLVED CLAIMS: In the event a written claim
for damages against the Contractor or its subcontractors remains
unsettled at the time all work on the project has been completed
to the satisfaction of the Director of the Transportation and Public
Works Department, as evidenced by a final inspection, final
payment to the Contractor shall not be recommended by the
Director of the Transportation and Public Works Department for a
period of 30 days after the date of such final inspection, unless the
Contractor shall submit written evidence satisfactory to the
08/10/98
GC -12
Director that the claim has been settled and a release has been
obtained from the claimant involved.
Although the claim concerned remains unsettled at the expiration
of the above 30 -day period, the Contractor may be deemed to be
entitled to a semi-final payment for work completed, such
semi-final payment to be in an amount equal to the total dollar
amount then due less the dollar value of any written claims
pending against the Contractor arising out of the performance of
such work, and such semi-final payment may then be
recommended by the Director.
The Director shall not recommend final payment to a Contractor
against whom such a claim for damages is outstanding for a
period of six months following the date of the acceptance of the
work performed unless the Contractor submits evidence in writing
satisfactory to the Director that:
(1) The claim has been settled and a release has been obtained
from the claimant involved, or
(2) Good faith efforts have been made to settle such outstanding
claims, and such good faith efforts have failed.
If condition (1) above is met at any time within the six month
period, the Director shall recommend that the final payment to the
Contractor be made. If condition (2) above is met at any time
within the six month period, the Director may recommend that the
final payment to the Contractor be made. At the expiration of the
six- month period the Director may recommend that final payment
be made if all other work has been performed and all other
obligations of the Contractor have been met to the satisfaction of
the Director.
The Director may. if he deems it appropriate, refuse to accept bids
on other Transportation and Public Works Department contract
work from a Contractor against whom a claim for damages is
outstanding as a result of work performed under a City contract.
1-8 LIQUIDATED DAMAGES: The deduction for liquidated
damages shall be as follows:
Amount of Contract • Liquidated Damages Per Day
$15,000 or less
$45
$15,001 to $25,000
$ 63
$25,001 to $50,000
$105
$50,001 to $100,000
$154
$100,000 to $500,000
$210
$500,001 to $1,000,000
$315
$1,000,001 to $2,000,000
$420
$2,000,001 to $5,000,000
$630
$5,000,001 to $10,000,000 '
$840
over $10,000,000
$980
1-9 FAILURE OF PAYMENT. If, without fault on the part of
the Contractor, the Architect should fail to issue any Certificate for
Payment within seven days after receipt of the Contractor's
Application for Payment, if the Contractor's Application for
Payment, or if, without fault on the part of the Contractor, the
Owner should fail to approve such estimate or to pay to the
Contractor 90% or 95% (as applicable) of the amount thereof
within the period of time specified in Paragraph 1-4, then the
Contractor may, upon seven (7) days additional written notice to
the Contractor may, upon seven days additional written notice to
the Owner and to the Architect, stop the Work until payment of the
amount owing has been received.
1-10 SUBSTANTIAL COMPLETION AND FINAL PAYMENT.
Prior to the request for final payment, the Contractor must meet all
provisions for Project Closeout. When the Contractor determines
that the Work or a designated portion thereof acceptable to the
Owner is substantially complete, the Contractor shall prepare the
submission to the Architect a list of items to be completed or
corrected. The failure to include any items on such list does not
alter the responsibility of the Contractor to complete all Work in
accordance with the Contract Documents. When the Architect, on
the basis of an inspection, determines that the Work is
substantially complete, he then will prepare a Certificate of
Substantial Completion which, when approved by the Owner, shall
establish the Date of Substantial Completion, shall state the
responsibilities of the Owner and the Contractor for maintenance,
heat, utilities, and insurance, and shall fix the time within which the
Contractor shall complete the items listed therein, said time to be
within the Contract time unless extended.
Upon receipt of written notice that the Work is ready for final
inspection and acceptance and upon receipt of a final Application
for Payment and upon receipt of a final application for payment,
providing the record drawings have been received by the Architect,
the Architect will conduct such test and/or inspections as he
deems necessary, and if in his opinion the Work has been
completed in accordance with the Contract Documents, the
Architect will promptly issue a final Certificate of Completion
stating that to the best of his knowledge, information and belief,
and on the basis of his observations and inspections, the Work
has been completed in accordance with the terms and conditions
of the Contract Documents and that the entire balance found to be
due the Contractor is due and payable. Final acceptance can be
made by the City Council of the City of Fort Worth or it's
designated representative, and no other form of acceptance will be
binding upon the Owner. Final payment and release of the
retainage amount will become due within fifteen days following
approval of the City Council of the City of Fort Worth in accepting
the work as complete.
Neither the final payment nor the remaining retained percentage
shall become due until the Contractor submits to the Architect (1)
an Affidavit that all payrolls, bills for materials and equipment, and
other indebtedness connected with the Work for which the Owner
or his property might in any way be responsible, have been paid or
otherwise satisfied, (2) consent of surety, if any, to final payment
and, (3) if required by the Owner, other data establishing payment
or satisfaction of all such obligations, such as receipts, releases
and waivers of liens arising out of the Contract, to the extent and
in such form as may be designated by the Owner. If any
Subcontractor, materialman or laborer refuses to furnish a release
or waiver required by the Owner, the Contractor may, at the
election of the Owner, furnish a bond satisfactory to the Owner to
indemnify him against any right, claim or lien which might be
asserted by such Subcontractor, materialman or laborer. If any
such right, claim or lien remains unsatisfied after all payments are
made. The Contractor shall refund to the Owner all monies that
the latter may be compelled to pay to discharging such right, claim
or lien, including all costs and reasonable attorney's fees.
The acceptance of final payment shall constitute a waiver of all
claims by the Contractor except those previously made in writing
and still unsettled.
SECTION J
PROTECTION OF PERSONS AND PROPERTY
J-1 SAFETY PRECAUTIONS AND PROGRAMS. The
Contractor shall be responsible for initiating, maintaining and
supervising all safety precautions and programs in connection with
the Work. The Contractor shall designate a responsible member of
his organization at the site whose duty shall be the prevention of
accidents. This person shall be the Contractor's superintendent
unless otherwise designated in writing by the Contractor to the
Architect.
J-2 SAFETY OF PERSONS AND PROPERTY. The
Contractor shall take all reasonable precautions for the safety of,
08/10/98
GC -13
9
El
a
a
I
0
I]
0
ci
D
a
0
0
Q
0
0
C
and shall provide all reasonable protection to prevent damage.
injury or loss to:
(1) all employees on the Work and all other persons who may be
affected thereby;
(2) all the Work and all materials and equipment to be
incorporated therein, whether in storage on or -off the site,
under the care, custody or control of the Contractor or any of
his Subcontractors or Sub -contractors: and
(3) other property at the site or adjacent thereto, including trees,
shrubs, lawns, walks, pavements, roadways, structures and
utilities not designated for removal, relocation or replacement
in the course of construction.
Until acceptance of the Work, it shall be under the charge and
care of the Contractor, and he shall take every precaution against
injury or damage to the Work by the action of the elements or from
any other cause whatsoever, whether arising from the execution or
from the non -execution of the Work. The Contractor shall rebuild,
repair, restore and make good, at his own expense, all injuries or
damages to any portion of the Work occasioned by any of the
above, caused before its completion and acceptance.
The Contractor shall comply with all applicable Laws, Ordinances,
Rules, Regulations and Orders of any public authority having
jurisdiction for the safety of persons or property or to protect them
from damage, injury or loss. He shall erect and maintain, as
required by existing conditions and progress of the Work, all
reasonable safeguards for safety and protection, including posting
danger signs and other warnings against hazards, promulgating
safety regulations and notifying owners and users of adjacent
utilities.
When the use or storage of explosives or other hazardous
materials or equipment is necessary for the execution of the Work,
the Contractor shall exercise the utmost care and shall carry on
such activities under the supervision of properly qualified
personnel.
All damage or loss to any property referred to in the preceding
paragraphs caused in whole or in part by the Contractor, any
Subcontractor, or anyone directly or indirectly employed by any of
them, or by anyone for whose acts any of them may be liable,
shall be remedied by the Contractor, including damage or loss
attributable to faulty Drawings or Specifications and acts or
omissions of the Architect or anyone employed by him or for
whose acts he may be liable, and not attributable to the fault or
negligence of the Contractor or anyone claiming through the
Contractor for such damage or loss.
The Contractor shall not load or permit any part of the Work to be
loaded so as to endanger its safety.
J-3 HARD HATS. Hard Hats will be required at all
construction sites included in this Contract from start to completion
of work. Each Contractor, employee and visitor at any
construction site included in the Contract will be required to wear a
hard hat. The Contractor shall enforce the wearing of hard hats by
Contractor, employees and visitors. These requirements are in
addition to the Accident Prevention Clause in the General
Conditions of the Contract. Contractor shall provide ten hard hats
for use by the consulting Architects and Engineers and visitors.
J-4 EMERGENCIES. In any emergency affecting the safety
of persons or property, the Contractor shall act at his discretion to
prevent threatened damage, injury or loss. Any additional
compensation or extension of time claimed by the Contractor on
account of emergency work shall be determined as provided in
Changes in the Work.
SECTION K - INSURANCE
K-1 insurance Required. The Contractor shall not
commence work under this Contract until he has obtained all
insurance required under this Section and such insurance has
been approved by the City of Fort Worth, nor shall the Contractor
allow any Subcontractor to commence work to be performed under
this Contract until all similar insurance of the Subcontractor has
been so obtained and approved.
K-2 WORKERS' COMPENSATION INSURANCE. The
Contractor shall procure and maintain during the term of this
Contract, statutory Workers' Compensation Insurance for all of his
employees at the site of the Project, and in case any work is
sublet, the Contractor shall require the Subcontractors similarly to
provide Workers' Compensation Insurance for all of the latter's
employees unless such employees are covered by the Workers'
Compensation Insurance maintained by the Contractor.
Employer's Liability shall be included and such insurance shall be
maintained at the $500,000 limit for each accident, disease -each
employee, disease -policy limit.
K-3 LIABILITY INSURANCE. The Contractor shall procure
and maintain during the term of this Contract such Liability
Insurance as shall protect him, the City of Fort Worth and any
Subcontractor performing work covered by this Contract, from
claims of damage which may arise from operations under this
Contract, including, blasting, when blasting is done on, or in
connection with the Work of the Project, whether such operations
be by himself or by any Subcontractor or by anyone directly or
indirectly employed by either of them and the limits of such
insurance shall be not less than the following:
A) Automobile Liability: $1,000,000 each accident, or
reasonably equivalent split limits for bodily injury and property
damage. Coverage shall be on "any auto" including leased, hired,
owned, non -owned and borrowed vehicles used in connection with
this Contract.
B) Commercial General Liability: $1,000,000 each occurrence.
Coverage under the policy shall be as comprehensive as that
provided in a current Insurance Services Office (ISO) policy form
approved for use in Texas and the policy shall have no exclusions
by endorsement unless such are approved by the City.
C) Asbestos Abatement Liability Insurance: When the Project
specifically requires the removal of Asbestos Containing Materials,
the Contractor shall be required to maintain Asbestos Abatement
Liability Insurance as follows: $1,000,000 per occurrence;
$2,000,000 aggregate limit. The coverage shall include any
pollution exposure, including environmental impairment liability,
associated with the services and operations performed under this
contract in addition to sudden and accidental contamination or
pollution liability for gradual emissions and clean-up costs.
K-4 BUILDER'S RISK INSURANCE.
Unless stated otherwise in the Proposal or Invitation, the
Contractor shall procure, pay for and maintain at all times during
the term of this Contract, Builder's Risk Insurance against the
perils of fire, lightning, windstorm, hurricane, hail, riot, explosion.
civic commotion, smoke, aircraft, land vehicles, vandalism, and
malicious mischief, at a limit equal to 100% of the Contract Sum.
The policy shall include coverage for flood and earthquake plus for
materials and supplies while in transit and while being stored on or
off site. Different sublimits for these coverages shall be approved
by the City.
Consequential damage due to faulty workmanship and/or design
performed by the Contractor or his agents shall be covered.
n GC -14
08/10/98
0
0
6
0
a
0
ii
a
D
0
0
0
0
ci
Upon completion of the Work, the Contractor shall notify the City
of Fort Worth in writing before terminating this insurance.
K-5 PROOF OF CARRIAGE OF INSURANCE. The
Contractor shall provide a certificate of insurance documenting the
Transportation and Public Works Department, City of Fort Worth
as a "Certificate Holder", and noting the specific project(s) covered
by the Contractor's insurance as documented on the certificate of
insurance. More than one certificate may be required of the
Contractor depending upon the agents an/or insurers for the
Contractor's insurance coverages specified for the project(s).
K-6 OTHER INSURANCE RELATED REQUIREMENTS.
(1) The City of Fort Worth shall be an additional insured, by
endorsement, on all applicable insurance policies.
(2) Applicable insurance policies shall each be endorsed with a
waiver of subrogation in favor of the City of Fort Worth.
(3) Insurers of policies maintained by Contractor and its
subcontractor(s), if applicable, shall be authorized to do
business in the State of Texas, or otherwise approved by the
City of Fort Worth, and such shall be acceptable to the City of
Fort Worth insofar as their financial strength and solvency are
concerned. Any company through which the insurance is
placed must have a rating of at least A:VII, as stated in
current edition of A. M. Best's Key Rating Guide. At the
City's sole discretion, a less favorable rate may be accepted
by the City.
(4) Deductible limits on insurance policies and/or self insured
retentions exceeding $10,000 require approval of the City of
Fort Worth as respects this Contract.
(5) The City of Fort Worth shall be notified in writing a minimum
of thirty days prior to an insurer's action in the event of
cancellation, non -renewal or material change in coverage
regarding any policy providing insurance coverage required in
this Contract.
(6) Full limits of insurance shall be available for claims arising
out of this Contract with the City of Fort Worth.
(7) Certificates of insurance shall be provided by the Contractor
to the City prior to commencement of operations pursuant to
this Contract. Any failure on part of the City of Fort Worth to
request such documentation shall not be construed as a
waiver of insurance requirements specified herein.
(8) The City of Fort Worth shall be entitled, upon request and
without incurring expense, to review the insurance policies
including endorsements thereto and, at its discretion, to
require proof of payment for policy premiums.
(9) The City of Fort Worth shall not be responsible for paying the
cost of insurance coverages required herein.
(10) Notice of any actual or potential claim and/or litigation that
would affect insurance coverages required herein shall be
provided to the City in a timely manner.
(11) "Other insurance" as referenced in any policy of insurance
providing coverages required herein shall not apply to any
insurance policy or program maintained by the City of Fort
Worth.
(12) Contractor shall agree to either require its subcontractors to
maintain the same insurance coverages and limits thereof as
specified herein or such coverage on the Contractor's
subcontractors shall be provided by the Contractor.
K-7 CONTRACTOR'S COMPLIANCE WITH WORKER'S
COMPENSATION LAW:
Contractor agrees to provide the City of Fort Worth a certificate of
insurance documenting that it has obtained a policy of Workers
Compensation Insurance covering each of its employees working
on the Project in compliance with State law. No Notice to Proceed
will be issued until the Contractor has complied with this condition.
The Contractor shall ensure that its subcontractors' employees
working on the Project are covered by statutory workers'
compensation insurance.
The Contractor shall provide the City of Fort Worth a certificate
that it has obtained, or has been provided proof by its -
subcontractors, that a policy of workers compensation insurance
covering each of its and its subcontractor's employees employed
on the project.
Contractor shall provide a copy of a letter from all subcontractors
with no employees who can not meet requirements for
"Workman's Compensation Insurance". Contractor shall include
executed letters in the contract at the time of execution as needed.
SECTION L
CHANGES IN THE WORK
L-1 CHANGE ORDER. The Owner, without invalidating the
Contract, may order Changes in the Work within the general scope
of the Contract consisting of additions, deletions or other revisions,
the Contract Sum and the Contract Time being adjusted
accordingly. All Such Changes in the Work shall be authorized by
Change Order, and shall be executed under the applicable
conditions of the Contract Documents.
A Change Order is a written order to the Contractor signed by the
Contractor, Owner and the Architect, issued after the execution of
the Contract, authorizing a Change in the Work or adjustment in
the Contract Sum or the Contract Time. The Contract Sum and the
Contract Time..may be changed only by Change Order.
Any changes in work required due to changed or unforeseen
conditions, or by request of either the Contractor or the City, shall
be coordinated with the Director, Department of Transportation
and Public Works. A change order must be written and duly
negotiated and executed prior to performing changed work.
The cost or credit to the Owner resulting from a Change in the Fort
Worth shall be determined in one or more of the following ways:
a) by mutual acceptance of a lump
sum property itemized, including the allowance to Contractor for
overhead and profit stipulated in the original contract proposal;
b) by unit prices stated in the Contract
Documents or subsequently agreed upon; or
C) by cost and a mutually acceptable
fixed or percentage fee.
If none of the methods set forth herein above is agreed upon, the
Contractor, provided he receives a Change Order, shall promptly
proceed with the Work involved. The cost of such work shall then
be determined on the basis of the Contractor's reasonable
expenditures and savings, including a reasonable allowance for
overhead and profit as indicted in the original contract proposal. In
such cases, the Contractor shall keep and present, in such form
as the Architect shall prescribe, an itemized accounting together
with appropriate supporting data. Pending final determination of
cost to the Owner, payments on account shall be made on the
Architect's Certificate of Payment as approved by the Owner.
El08/10/98 GC -15
If after the contract has been executed, the Architect, requests a
price proposal from the Contractor for a proposed change in scope
of the work, Contractor shall process such proposal within seven
days of receipt and return the price quote to the Architect in
writing. The Architect shall review the price quotation and if
approval is recommended, forward the proposed change order
request and price proposal to the Owner for approval. If the
Architect will attempt to negotiate with Contractor to revise the
proposal to a figure which is fair and reasonable and forward it on
to the Owner for approval. If the negotiations do not result in an
equitable solution, the Architect shall prepare a cost-plus type
Change Order with a price -not -to -exceed figure for approval by the
City and require specific documentation to be provided by
Contractor in accordance with the paragraph above.
Contractor is advised that according to City of Fort Worth Charter,
that when the cumulative effect of Change Orders results in an
increase in cost of the contract amount by over $3,000, the City
Council must approve all such Change Orders which will exceed
this limit. Normal processing time for the City Staff to obtain City
Council approval, once the recommended change order has been
received at the City, is approximately thirty (30) days . Owner,
Architect and Contractor shall endeavor to identify Change Order
items as early in the Construction process as possible to minimize
their impact on the construction schedule.
If unit prices are stated in the Contract Documents or
subsequently agreed upon, and if the quantities originally
contemplated are so changed in a proposed Change Order that
application of the agreed unit prices to the quantities of Work
proposed will create a hardship on the Owner or the Contractor,
the applicable unit prices shall be equitably adjusted to prevent
such hardship.
If the Contractor claims that additional cost or time is involved
because of (1) any written interpretation issued pursuant to
Section A, (2) any order by the Architect or Owner to stop the
Work pursuant to Section B, where the Contract was not at fault,
or (3) any written order for a minor change in the Work, the
Contractor shall make such claim.
L-2 CLAIMS FOR ADDITIONAL COST OR TIME. If the
Contractor wishes to make a claim for an increase in the Contract
Sum or an extension in the Contract Time, he shall give the
Architect written notice thereof within a reasonable time after the
occurrence of the event that gave rise to such claim. This notice
shall be given by the Contractor before proceeding to execute the
Work, except in an emergency endangering life or property in
which case the Contractor shall proceed in accordance with
Section J. No such claim shall be valid unless so made. Any
change in the Contract Sum or Contract Time resulting from such
claim, if approved by the Owner, shall be authorized by Change
Order.
L-3 OVERHEAD ALLOWANCES FOR CHANGES: Should
any change in the work or extra work be ordered, the following
applicable percentage shall be added to Material and Labor costs
to cover overhead and profit:
1. Allowance to the Contractor for overhead and profit for extra
work performed by the Contractor's own forces shall not exceed
fifteen percent fl.
2. Allowance to the Contractor for overhead and profit for extra
work performed by a Subcontractor and supervised by the
Contractor shall not exceed ten percent 10% .
L-4 MINOR CHANGES IN THE WORK. The Architect shall
have authority to order minor changes in the Work not involving an
adjustment in the Contract Sum or an extension of the Contact
Time and not inconsistent with the intent of the Contract
Documents. Such changes may be effected by Field Order or by
other written order. Such changes shall be confirmed in writing by
the Architect and shall be binding on the Owner and the
Contractor.
L-5 FIELD ORDERS. The Architect may issue written Field
Orders which interpret the Contract Documents in accordance with
Section A. or which order minor changes in the Work in
accordance with Section L without change in Contract Sum or
Contract Time. The Contractor shall carry out such Field Orders
promptly.
SECTION M
UNCOVERING AND CORRECTION OF WORK
M-1 UNCOVERING OF WORK. If any Work should be
covered contrary to the request of the Owner or Architect, it must
be uncovered for observation and replaced, at the Contractor's
expense.
If any other work has been covered which the Owner or Architect
have not specifically requested to observe prior to being covered.
the Architect or the Owner may request to see such work and it
shall be uncovered by the Contractor. If such Work be found in
accordance with the Plans and Specifications, the cost of
uncovering and replacement shall, by appropriate Change Order.
be charged to the Owner. If such work be found not in accordance
with the Plans and Specifications, the Contractor shall pay such
costs unless it bejound that this condition was caused by a
separate contractor employed by the Owner.
M-2 CORRECTION OF WORK. The Contractor shall
promptly correct all work rejected by the Owner or Architect as
defective or as failing to conform to the Plans and Specifications
whether observed before or after Substantial Completion and
whether or not fabricated, installed or completed. The Contractor
shall bear all costs of correcting such rejected Work, including the
cost of the Architect's additional service thereby made necessary.
If, within one year after the Date of Substantial Completion or
within such longer period of time as may be prescribed by law or
by the terms of any applicable special guarantee required by the
Contract Documents, any of the work is found to be defective or
not in accordance with the Contract Documents, the Contractor
shall correct it promptly after receipt of a written notice from the
Owner to do so, unless the Owner has previously given the
Contractor a written acceptance of such condition, describing
same specifically and not generally. The Owner shall give such
notice promptly after discovery of the condition.
All such defective or non -conforming work under the preceding
paragraphs shall be removed from the site where necessary, and
the work shall be corrected to comply with the Contract
Documents without cost to the Owner.
The Contractor shall bear the cost of making good all work of
separate contractors destroyed or damaged by such removal or
correction.
If the Contractor does not remove such defective or non-
conforming work within a reasonable time fixed by written notice
from the Architect or the Owner, the Owner may remove it and
may store the materials or equipment at the expense of the
Contractor. If the Contractor does not pay the cost of such
removal and storage within ten days thereafter, the Owner may
upon ten additional days' written notice sell such work at auction
or at private sale and shall account for the net proceeds thereof,
after deducting all the costs that should have been borne by the
Contractor including compensation for additional architectural
services. If such proceeds of sale do not cover all costs that the
Contractor should have borne, the difference shall be charged to
the Contractor and an appropriate Change Order shall be issued.
If the payments then or thereafter due the Contractor are not
08/10/98
GC -16
I]
0
ci
0
LU
Q
Q
0
0
0
0
9
4
a
0
0
sufficient to cover such amount, the Contractor shall pay the
difference to the Owner.
If the Contractor fails to correct such defective or non -conforming
work, the Owner may correct it in accordance with Section G.
The obligation of the Contractor under this Section shall be in
addition to and not in limitation of any obligations imposed upon
him by special guarantees required by the Contract Documents or
otherwise prescribed by law.
M-3 ACCEPTANCE OF DEFECTIVE OR NON-
CONFORMING WORK. If the Owner prefers to accept defective
or non -conforming work, he may do so instead of requiring its
removal and correction, in which case a Change Order will be
issued to reflect an appropriate reduction in the Contract Sum, or,
if the amount is determined after final payment, it shall be paid by
the Contractor.
SECTION N
TERMINATION OF THE CONTRACT
N-1 TERMINATION BY THE CONTRACTOR. If the work is
stopped for a period of 30 days under an order or any court or
other public authority having jurisdiction, through no act or fault of
the Contractor or a Subcontractor or their agents or employees or
any other persons performing any of the work under a contract
with the Contractor, or if the work should be stopped for a period of
30 days by the Contractor for the Owner's failure to make payment
thereon as provided in Section I, then the Contractor may after the
end of such period of 30 days and upon seven additional days'
written notice to the Owner and the Architect, terminate the
Contract.
N-2 TERMINATION BY THE OWNER. If the contractor is
adjudged as bankrupt, or if he makes a general assignment for the
benefit of his creditors, or if a receiver is appointed on account of
his insolvency, of if the Contractor refuses, except in cases for
which extension of time is provided, to supply enough properly
skilled workmen or proper materials, or if he fails to make prompt
payment to Subcontractors or for materials or labor, or fails to
comply with al Laws, Statutes, .Charter, Ordinances, Regulations
or Orders of any public authority having jurisdiction, or otherwise is
guilty of a substantial violation of a provision of the Contract
Documents, then the Owner, on its own initiative or upon
certification by the Architect that sufficient cause exists to justify
such action, may, without prejudice to any rights or remedy and
after giving the Contractor and his surety, if any, seven (7) days'
written notice, terminate the employment of the Contractor and
take possession of the site and of all materials, equipment, tools,
construction equipment and machinery thereon owned by the
Contractor and may finish the work by whatever method he may
deem expedient. In such case the Contractor shall not be entitled
to receive any further payment until the Work is finished.
If the costs of finishing the Work, including compensation for the
Architect's additional services., exceed the unpaid balance of the
Contract, the Contractor shall pay the difference to the Owner.
The City of Fort Worth may terminate this contract in whole, or
from time to time, in part, whenever such termination is in the best
interest of the City. Termination will be effected by delivering to
the Contractor a notice of termination specifying to what extent
performance of the work of the contract is being terminated and
the effective date of termination. After receipt of termination the
contractor shall:
a) Stop work under the Contract on the date and to the extent
specified on the notice of termination.
b) Place no further orders or subcontracts except as may be
necessary for the completion of the work not terminated.
c) Terminate all orders and subcontracts to the extent that they
relate to the performance of the work terminated by the notice
of termination.
After termination as above, the City will pay the contractor a
proportionate part of the contract price based on the work
completed; provided, however, that the amount of payment on
termination shall not exceed the total contract price as reduced by
the portion thereof allocatable to the work not completed and
further reduced by the amount of payments, if, any otherwise
made. Contractor shall submit its claim for amounts due after
termination as provided in this paragraph within 30 days after
receipt of such claim. In the event of any dispute or controversy
as to the propriety or allowability of all or any portion of such claim
under this paragraph, such dispute or controversy shall be
resolved and be decided by the City Council of the City of Fort
Worth, and the decision by the City Council of the City of Fort
Worth shall be final and binding upon all parties to this contract
SECTION O
SIGNS
The Contractor shall construct and install the project designation
sign as required in the Contract Documents and in strict
accordance with the Specifications for "Project Designation Signs."
This sign shall be a part of this Contract and shall be included in
the Contractor's Base Bid for the Project.
SECTION P
TEMPORARY FACILITIES
P-1 SCOPE. The Contractor shall furnish, erect, and
maintain facilities and perform temporary work required in the
performance of this Contract, including those shown and specified.
P-2 USE OF TEMPORARY FACILITIES. All temporary
facilities shall be made available for use by all workmen and
subcontractors employed on the project, subject to reasonable
directions by the Contractor as to their proper and most efficient
utilization.
P-3 MAINTENANCE AND REMOVAL. The Contractor shall
maintain temporary facilities in a proper, safe operating and
sanitary condition for the duration of the Contract. Upon
completion of the Contract, all such temporary work and facilities
shall be removed from the premises and disposed of unless
otherwise directed or specified hereunder.
P-4 FIELD OFFICES AND SHED. The Contractor shall
provide a temporary field office building for himself, his
subcontractors and use by the Architect. For construction
contracts with a bid price in excess of $1,000,000.00, the
Contractor shall provide a separate field office for the City's field
representative (but the separate office may be in the same
structure). The buildings shall afford protection against the
weather, and each office shall have a lockable door, at least one
window, adequate electrical outlets and lighting, and a shelf large
enough to accommodate perusal of the project drawings.
Openings shall have suitable locks. Field offices shall be
maintained for the full time during the operation of the work of the
Contract. During cold weather months, the field offices shall be
suitably insulated and equipped with a heating device to maintain
70 degree Fahrenheit temperature during the workday. During
warm weather the offices shall be equipped with an air
conditioning device to maintain temperature below 75 degrees F.
Upon completion of the work of the Contract, the Contractor shall
remove the building from the premises. In addition to the drawing
shelf, provide for the City field representatives office: one deck,
four chairs, plan rack and a four drawer filing cabinet (with lock).
Each office shall contain not less than 120 square feet of floor
space.
08/10/98
GC -17
7
0
0
0
0
0
0
0
0
0
ci
D
a
0
ci
0
0
The Contractor shall provide and maintain storage sheds, other
temporary buildings or trailers on the project site as required for
his use. Location of sheds and trailers shall be as approved by the
Architect. Remove sheds when work is completed, or as directed.
P-5 TELEPHONE. The Contractor shall provide and pay for
telephone installation and service to the field offices described
above. Service shall be maintained for the duration of operations
under this contract. The Contractor shall provide for and pay for an
automatic telephone -answering device at the site office for the
duration of the project. The contractor shall provide a separate
telephone line, and instrument for use by the City's field
representatives.
P-6 TOILET FACILITIES. The Contractor shall provide
proper, sanitary and adequate toilet facilities for the use of all
workmen and subcontractors employed on the project.
P-7 UTILITIES. Contractor shall make all necessary
arrangements and provide for temporary water and electricity
required during the construction. Contractor shall provide and
install temporary utility meters during the contract construction
period. These meters will be read and the Contractor will be billed
on this actual use. The Contractor shall provide all labor and
materials required to tap into the utilities. The Contractor shall
make the connections and extend the service lines to the
construction area for use of all trades. Upon completion of the
work all utility lines shall be removed and repairs made to the
existing lines. Only utilities at existing voltages, pressures.
frequencies, etc. will be available to the Contractor.
Water. Provide an ample supply of potable water for all purposes
of construction at a point convenient to the project or as shown on
the Drawings. Pipe water from the source of supply to all points
where water will be required. Provide sufficient hose to carry water
to every required part of the construction and allow the use of
water facilities to subcontractors engaged on the work. Provide
pumps, tanks and compressors as may be required to produce
required pressures.
Electric Service. Provide adequate electric service for power and
lighting to all points where required. Temporary, electric service
shall be of sufficient capacity and characteristics to supply proper
current for various types of construction tools, motors, welding
machines, lights, heating plant, air conditioning system, pumps,
and other work required. Provide sufficient number of electric
outlets so that 50 foot long extension cords will reach all work
requiring light or power.
Lighting. Supply and maintain temporary lighting so that work of
all trades may be properly and safely performed, in such areas
and at such time that day -lighting is inadequate. Provide at least
0.75 watts of incandescent lighting per squqr4e foot and maintain
a socket voltage of at least 110 volts. Use at least 100 watt lamps.
In any event, the lighting intensity shall not be less than 5 foot
candles in the vicinity of work and traffic areas.
P-8 HEATING. Heating devices required under this
paragraph shall not be electric. The Contractor shall provide heat,
ventilation, fuel and services as required to protect all work and
materials and to keep the humidity down to the extent required to
prevent corrosion of any metal and to prevent dampness or
mildew which is potentially damaging to materials and finishes. All
such heating, ventilation and services shall be provided and
maintained until final acceptance of all work. In addition, the
Contractor shall provide heat ventilation prior and during the
following work operations as follows:
a) At all times during the placing, setting and curing of concrete
provide sufficient heat to insure the heating of the spaces
involved to not less than 40 F.
08/10/98
GC -18
b) From the beginning of the application of drywall and during
the setting and curing period, provide sufficient heat to
produce a temperature in the spaces involved of not less than
55 F.
c) For a period of seven (7) days previous to the placing of
interior finish materials and throughout the placing of finish
painting, decorating and laying of resilient flooring materials,
provide sufficient heat to produce a temperature of not less
than 60 F.
P-9 TEMPORARY CONSTRUCTION, EQUIPMENT AND
PROTECTION
The Contractor shall provide, maintain, and remove upon
completion of the work all temporary rigging, scaffolding, hoisting
equipment, rubbish chutes, ladders to roof, barricades around
openings, and all other temporary work as required to complete all
work of the Contract. Contractor shall coordinate the use and
furnishing of scaffolds with his sub -contractors.
The Contractor shall provide, maintain, and remove upon
completion of the work, or sooner, if authorized by the Architect, all
fences, barricades, lights, shoring, pedestrian walkways,
temporary fire escapes, and other protective structures or devices
necessary for the safety of workmen, City employees, equipment,
the public and property.
All temporary construction and equipment shall conform to all
regulations, ordinances, laws and other requirements of the
authorities having jurisdiction, including insurance companies, with
regards to safety precautions, operation and fire hazard.
The Contractor shall provide and maintain pumping facilities,
including power, for keeping the site, all times, whether from
underground seepage, rainfall, drainage of broken lines.
The Contractor shall maintain provision for closing and locking the
building at such time as possible to do so. If this is not feasible,
maintain a night
The Contractor shall provide and maintain all barricades or
enclosures, required to protect the work in progress from outside
elements, dusts, and other disturbances as a result of work under
this Contract. Such protection shall be positive, shall meet the
approval of the Architect and shall be maintained for the duration
of the construction period or as required to provide for the
protection as specified.
P-10 PROJECT BULLETIN BOARD. The Contractor shall
furnish, install and maintain during the life of the project a weather -
tight bulletin board approximately 3 feet high by 5 feet wide having
not less than two hinged or sliding glass doors with provisions for
locking. The bulletin board shall be mounted where and as
approved by the Architect, in a prominent place accessible to
employees of the Contractor and sub -contractors, and to
applicants for employment. The bulletin board shall remain the
property of the Contractor and shall be removed by him upon
completion of the Contract work. The following information which
will be furnished by the City to the Contractor, shall be posted on
the bulletin board and shall be maintained by the Contractor in
easily readable condition at all times for the duration of the
Contract.
a. The Equal Opportunity Poster and Notice
Nondescrimination of Employment (Standard Form 38).
b. Wage Rate Information Poster (Form SOL 155), with the
Contract Schedule of minimum wage rates as required
by the Davis -Bacon Act.
c. Safety Posters.
C
Eli SECTION Q
VENUE
Should any action arise out of the terms and conditions of this
contract, venue for said action shall lie in Tarrant County, Texas.
Ii
I
I
0
0
I
urn
I
0
0
I
0
71
I
11
a08/10/98 GC -19
C
SECTION Q
VENUE
Should any action arise out of the terms and conditions of this
contract, venue for said action shall lie in Tarrant County, Texas.
I
I
U
C
G
0
C
0
L
I
0
0
I
I
a08/10/98 GC -19
C
0
oA
DEFINITIONS PROCEDURES AND
INTERPRETATIONS
GENERAL CONDITIONS
INDEX
A-1 Contract Documents
A-2 Entire Agreement
A-3 Work
A-4 Execution of the Contract Documents
A-5 Familiarity with Proposed Work
A-6 One Unified contract
A-7 Division of Work
A-8 Interpretations
A-9 Copies of Working Drawings and Specifications
A-10 Minority and Women's Business Enterprise Policy
A-11 Correlation and Intent
B IDENTITY OF ARCHITECT
B-1 Contract Administration
B-2 Termination and Suspension of Work
B-3 Duties of Architect
B-4 Architect as Representative of the Owner
B-5 Access to Job Site
B-6 Interpretations
B-7 Authority to Stop Work
B-8 Miscellaneous Duties of Architect
B-9 Termination of Architect
C OWNER
C-1 Identification
C-2 Duties of the Owner
C-3 Instructions
C-4 Access to Job Site
C-5 Progress Inspections
C-6 Authority to Stop Work
C-7 Substantial Completion Inspection
C-8 Right to Audit
D CONTRACTOR
D-1 Identification
D-2 Independent contractor
D-3 Subletting
D-4 Review of contract Documents
D-5 Supervision
D-6 Labor and Materials
D-7 Prevailing Wage Rate
D-8 Warranty
D-9 Taxes
D-10 Licenses, Notices and Fees
D-1 1 Cash Allowances
D-12 Superintendent
D-13 Responsibility for Employees and Sub -contractors
D-14 Failure to Commence work
D-15 Progress Schedule
D-16 Drawings and Specifications at the Site
D-17 Shop Drawings and Samples
D-18 Site Use
D-19 Safe Work Practices
D-20 Field Offices and Sheds
D-21 Cutting and Patching of Work
D-22 Cleaning Up
D-23 Communications
E SUBCONTRACTORS
E-1 Definition
08/10/98
E-2 Award of Subcontracts
E-3 Terms of Subcontracts
E-4 Minority and Women's Business Enterprise
(M/WBE)
E-5 Payments to Sub -Contractors
F SEPARATE CONTRACTS
F-1 Owner's Right
F-2 Mutual Responsibility of Contractors
F-3 Cutting and Patching Under Separate Contracts
F-4 Owner's Right to Clean Up
G MISCELLANEOUS PROVISIONS
G-1
Conflict of Laws
G-2
Governing Laws
G-3
Personal Liability of Public Officials
G-4
Compliance with Laws
G-5
Indemnification
G-6
Successors and Assigns
G-7
Written Notice
G-8
Surety Bonds.
G-9
Owner's Right to Carry Out the Work
G-10
Royalties and Patents
G-11
Tests
G-12
Interruption of Existing Utilities Services
G-13
Laying Out Work
G-14
Measurements
G-15
Existing Overhead or Underground Work
G-16
Alignment of Joints in Finish Materials
G-17
Integrating Existing Work
G-18
Hazardous Material Certification
G-19
Location of Equipment and Piping
G-20
Overloading
G-21
Manufacturer's Instruction
G-22
Cleaning Up
G-23
Dust Control
G-24
Fire Protection
G-25
Cutting and Patching
G-26
Project Closeout
G-27
Guarantee and Extended Guarantee
G-28
Record Drawings
G-29
Construction Fence
G-30
Product Deliver, Storage, Handling
G-31
Age
G-32
Disability
H CONTRACT TIME
H-1 Definitions
H-2 Progress and Completion
H-3 Delays and Extension of Time
H-4 No Damage for Delay
I
PAYMENTS AND COMPLETION
I-1
Contract Sum
1-2
Schedule of Values
1-3
Adjustment of Quantities
1-4
Progress Payments
1-5
Certificates for Payment
1-6
Payments Withheld
1-7
Unresolved Claims
I-8
Liquidated Damages
1-9
Failure of Payment
1-10
Substantial Completion and Final Payment
GC -20
0
0
0
0
0
0
0
0
0
0
0
0
0
ci
£
0
0
0
0
J PROTECTION OF PERSONS AND PROPERTY
J-1 Safety Precautions and Programs
J-2 Safety of Persons and Property
J-3 Hard Hats
J-4 Emergencies
K INSURANCE
K-1
Insurance Required
K-2
Workers Compensation Insurance
K-3
Liability Insurance
K-4
Builder's Risk Insurance
K-5
Proof of Insurance
K-6
Other Insurance Related Requirements
K-7
Contractor's Compliance with Worker's
Compensation Law
L CHANGES IN THE WORK
L-1 Change Order
L-2 Claims for Additional Cost or Time
L-3 Overhead Allowance for Changes
L-4 Minor Changes in the Work
L-5 Field Orders
M UNCOVERING AND CORRECTION OF WORK
M-1 Uncovering of Work
M-2 Correction of Work
M-3 Acceptance of Defective or Non -Conforming Work
N TERMINATION OF THE CONTRACT
N-1 Termination by the Contractor
N-2 Termination by the Owner
O SIGNS
P TEMPORARY FACILITIES
P-1
Scope
P-2
Use of Temporary Facilities
P-3
Maintenance and Removal
P-4
Field Offices and Sheds
P-5
Telephone
P-6
Toilet Facilities
P-7
Utilities
P-8
Heating
P-9
Temporary Construction, Equipment and
Protection
P-10
Project Bulletin Board
Q VENUE
08/10/98
00O00
GC -21
General Decision Number TX970061
Superseded General Decision No. TX960061
State: TEXAS
Construction Type:
BUILDING
County (ies) :
JOHNSON PARKER TARRANT
BUILDING CONSTRUCTION PROJECTS (does not include single family
homes and apartments up to and including 4 stories). Use curren
heavy and highway General Wage Determination for Paving
Incidental to Building Construction in Tarrant County and for
Paving and Utilities incidental to Building Construction in
remaining Counties.)
Modification Number Publication Date
0 02/14/1997
1 09/05/1997
TX970061 Page: 1
0
0
0
0
0
0
ci
0
0
0
0
R
0
0
ci
ci
Ii]
D
COUNTY(ies):
JOHNSON PARKER
TARRANT
BRTX0006A 05/08/1992
BRICKLAYERS
Rates
Fringes
--
------------------------------------14_00-----------2.50------
CARP1421A 05/01/1995
MILLWRIGHTS
Rates
Fringes
---------------------
-----------------16_49-----------3.92------
* ELEC0116C 06/01/1997
ELECTRICIANS
Rates
Fringes
CABLE SPLICERS
17.80
2.20+10.50
--
17.80
* IRON0263B 06/01/1997
IRONWORKERS (Structural)
Rates
Fringes
--------------------------------------15.00-----------3.75------
* SFTX0669A 04/01/1997
SPRINKLER FITTERS
Rates
Fringes
--------------------------------------19_22-----------6.30------
* SUTX1073A 11/01/1989
ACOUSTICAL INSTALLERS
CARPENTERS (Excluding drywall
hangers, acoustical installers &
batt insulators)
Carpenters doing drywall hanging
only
CEMENT MASONS
DRYWALL FINISHERS
GLAZIERS
LABORERS (Including Mason
Tenders & Pipelayers)
LANDSCAPE LABORERS
MECHANICAL •INSULATORS
PAINTERS, BRUSH & SPRAY
(excluding Drywall Finishing)
PLASTERERS
PLUMBERS & PIPEFITTERS (Including
HVAC work)
POWER EQUIPMENT OPERATORS:
Backhoes
Cranes
Foundation Drill Operators
Graders
Rates Fringes
11.23
12.27
2.22
10.00
10.16
.76
11.18
2.21
11.37
1.31
7.46
1.00
5.15
10.92
1.00
10.47
2.21
11.50
13.34
2.15
12.30
1.82
14.26
2.44
8.54
11.69
1.80
TX970061 ------------------------------------------------------
C1Page: 2-------
U
COUNTY (ies) :
JOHNSON PARKER
TARRANT
BRTX0006A 05/08/1992
aBRICKLAYERS
Rates
Fringes
------------------------------14_00-----------2.50------
U
CARP1421A 05/01/1995
MILLWRIGHTS
Rates
Fringes
a--------------------------------------16_49-----------3.9?------
* ELEC0116C 06/01/1997
Q
ELECTRICIANS
Rates
Fringes
CABLE SPLICERS
17.80
2.20+10.50
--------------------------------------17_80-----------2.20+10_5%
III
* IRON0263B
06/01/1997
IRONWORKERS (Structural)
Rates
Fringes
--------------------------------------15_00-----------3--79------
* SPTX0669A 04/01/1997
Rates
SPRINKLER FITTERS
Fringes
--------------------------------------19_22-----------6.30------
* SUTX1073A 11/01/1989
fl
ACOUSTICAL INSTALLERS
CARPENTERS (Excludin
Rates
•11.23
Fringes
dr
hangers, acoustical installers &
batt insulators)
fl
Carpenters doin d
g rywall hanging
12.27
2.22
only
CEMENT MASONS
10.00
DRYWALL FINISHERS
10.16
.76
a
GLAZIERS
11.18
2.21
•
LABORERS (Including Mason
11.37
1.31
Tenders & Pipelayers)
a
LANDSCAPE LABORERS
7.46
1.00
MECHANICAL INSULATORS
5
5.15
PAINTERS, BRUSH & SPRAYfl
10.92
1.00
(excluding Drywall Finishing)
PLASTERERS
10.47
2.21
PLUMBERS & PIPEFITTERS (Including
11.50
work)
QHVAC
POWER EQUIPMENT OPERATORS:
13.34
2.15
Backhoes
Cranes
12.30
1.82
14.26
2.44
Foundation Drill Operators
Graders
8.54
11.69
1.80
TX970061 -----------------------------------------------------
0 Page: 2 --------
ROOFERS
SHEET METAL WORKERS (INCLUDING 9.50 .99
Q HVAC Duct Work)
12.63 2.10
WELDERS - Receive rate prescribed for craft performing operation
to which welding is incidental.
Unlisted classifications needed for work not included wi
a the scope of the classifications listed may be ad thin
ter
award only as provided in the labor standards conted ractafclauses
(29 CFR
lJ In the listing above t - --""- des---------------------------------
listed under that identifier donotgnatj0 means
reflect collectively
bargained wage and fringe benefit rates. Other designations
indicate unions whose rates have been determined to be
prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a
position on a wage determination matter
* a conformance (additional classification and rate)
ruling
fl On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted
because those Regional Offices have responsibility for the
Davis -Bacon survey program. If the response from this initial
contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
D With regard to any other matter not yet ripe for the fo
process described here, initial contact should be with thermal
Branch
of Construction Wage Determinations. Write to:
Branch of Constru
ction Wage Determinations
Wage and Hour Division
U. S. Department of Labor
200 Constitution Avenue, N. W.
Washington, D. C. 20210
0 2.) If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
TX970061-------------------Page: 3
a
Lil
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N. W.
Washington, D. C. 20210
aThe request should be accompanied by a full statement of the
interested party's position and by any information
nt
data, project description, area practice material, etc.) thatethe
requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an
El interested party may appeal directly to the Administrative Review
Board (formerly the Wage Appeals Board). Write to:
0
0
0
0
j
0
0
0
Li
ci
0
0
It,
Administrative Review Board
U. S. Department of Labor
200 Constitution Avenue, N. W.
Washington, D. C. 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
0 TX970061 -------------------------------------------------------------
Page: 4
0
General Decision Number TX970045
Superseded General
Decision No. TX960045
QState:
TEXAS
Construction Type:
HEAVY
j"y
�j
HIGHWAY
County(ies) :
COLLIN
GRAYSON ROCKWALL
DALLAS
JOHNSON TARRANT
DENTON
KAUFMAN WICHITA
ELLIS
PARKER
HEAVY AND HIGHWAY CONSTRUCTION PROJECTS IN WICHITA COUNTY ONLY.
HIGHWAY CONSTRUCTION PROJECTS ONLY FOR REMAINING COUNTIES
Modification Number
Publication Date
0
02/14/1997
a
0
0
a
ci
a
ci
a
a
ci
X970045 ---------------------------Page:----- -----------------------
0
0
I
I
I
0
0
ci
0
ci
0
a
0
El
ci
0
ID
0
COUNTY ( i e s) :
COLLIN GRAYSON
ROCKWALL
DALLAS JOHNSON
TARRANT
DENTON KAUFMAN
WICHITA
ELLIS PARKER
SUTX2043A 11/18/1991
Rates Fringes
AIR TOOL OPERATOR
$7.554
ASPHALT RAKER
8.565
ASPHALT SHOVELER
8.255
BATCHING PLANT WEIGHER
9.371
BATTERBOARD SETTER
8.920
CARPENTER
9.447
CONCRETE FINISHER -PAVING
9.345
CONCRETE FINISHER -STRUCTURES
9.058
CONCRETE RUBBER
7.733
ELECTRICIAN
12.761
FLAGGER
5.598
FORM BUILDER -STRUCTURES
8.717
FORM LINER -PAVING & CURB
8.913
FORM SETTER -PAVING & CURB
8.686
FORM SETTER -STRUCTURES
8.427
LABORER -COMMON
6.402
LABORER -UTILITY
7.461
MANHOLE BUILDER
11.000
MECHANIC
10.658
OILER
8.698
SERVICER
8.104
PAINTER -STRUCTURES
10.913
PILEDRIVER
7.500
PIPE LAYER
8.509
BLASTER
11.333
ASPHALT DISTRIBUTOR OPERATOR
8.404
ASPHALT PAVING MACHINE
9.053
BROOM OR SWEEPER OPERATOR
7.908
BULLDOZER, 150 HP & LESS
8.703
BULLDOZER, OVER 150 HP
9.160
CONCRETE PAVING CURING MACHINE
8.213
CONCRETE PAVING FINISHING MACHINE
9.453
CONCRETE PAVING FORM GRADER
8.500
CONCRETE PAVING JOINT MACHINE
9.042
CONCRETE PAVING JOINT SEALER
7.350
CONCRETE PAIVNG FLOAT
7.875
CONCRETE PAVING SAW
9.290
CONCRETE PAVING SPREADER
9.750
PAVING SUB -GRADER
9.000
SLIPFORM MACHINE OPERATOR
9.000
CRANE, CLAMSHELL, BACKHOE,
DERRICK, DRAGLINE, SHOVEL
LESS THAN 1 1/2 C.Y.
9.513
CRANE, CLAMSHELL, BACKHOE,
DERRICK, DRAGLINE, SHOVEL
1 1/2 C.Y. & OVER
10.517
TX970045 Page: 2
II
CRUSHER OR SCREENING PLANT
OPERATOR
FORM LOADER
9.500
U
FOUNDATION DRILL OPERATOR
12.000
fl
CRAWLER MOUNTED
FOUNDATION DRILL OPERATOR
10.000
TRUCK MOUNTED
11.138
FRONT END LOADER 2 1/2
fl
C.Y. & LESS
8.823
FRONT END LOADER OVER 2 1/2 C.Y.
9.311
HOIST - DOUBLE DRUM
8.917
II
MILLING MACHINE OPERATOR
6.650
MIXER (OVER 16 C.F.)
9.000
MIXER (16 C.F. & LESS)
7.913
fl
MIXER - CONCRETE PAVING
MOTOR GRADER OPERATOR
9.500
FINE GRADE
MOTOR GRADE OPERATOR
10.346
PAVEMENT MARKING MACHINE
9.891
6.402
ROLLER, STEEL WHEEL PLANT -MIX
PAVEMENTS
ROLLER, STEEL WHEEL OTHER
8.339
III
FLATWHEEL OR TAMPING
7.963
ROLLER, PNEUMATIC, SELF-PROPELLED
7.403
fl
SCRAPER -17 C.Y. & LESS
8.138
U
SCRAPER -OVER 17 C.Y.
8.205
U
SIDE BOOM
TRACTOR -CRAWLER TYPE 150 HP
7.793
& LESS
Q
TRACTOR -CRAWLER TYPE OVER
8.448
150 HP
TRACTOR -PNEUMATIC
8.873
TRAVELING MIXER
7.735
TRENCHING MACHINE -LIGHT
7.615
fl
TRENCHING MACHINE -HEAVY
8.188
12.498
Q
POST HOLE DRILLER OPERATOR
9.000
WAGON -DRILL, BORING MACHINE
9.000
fl
REINFORCING STEEL SETTER PAVING
REINFORCING STEEL
9.218
SETTER
U
STRUCTURES
STEEL WORKER -STRUCTURAL
11.548
SIGN ERECTOR
SPREADER BOX
12.860+3.440
11.436
OPERATOR
BARRICADE SERVICER
6.988
ZONE WORK
fl
MOUNTED SIGN ISNTALLER
6.402
PERMANENT GROUND
TRUCK DRIVER -SINGLE AXLE
6.402
LIGHT
Q
TRUCK DRIVER -SINGLE AXLE
7.465
HEAVY
TRUCK DRIVER -TANDEM AXLE
8.067
SEMI TRAILER
TRUCK DRIVER-LOWBOY/FLOAT
7.816
a
9.653
U
TX970045 -------------------------------------------------------------
Page: 3
ci
TRUCK DRIVER -TRANSIT MIX
fl LJ
TRUCK DRIVER -WINCH
(J VIBRATOR OPERATOR
WELDER
0
a
0
L
I
a
ci
a
a
0
7.507
8.200
7.000
10.459
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29 CFR 5.5 (a) (1) (v)) .
--------------------------------
In the listing above, the "SU" designation means that rates
listed under that identifier do not reflect collectively
bargained wage and fringe benefit rates. Other designations
indicate unions whose rates have been determined to be
prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a
position on a wage determination matter
* a conformance (additional classification and rate)
ruling
On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted
because those Regional Offices have responsibility for the
Davis -Bacon survey program. If the response from this initial
contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal
process described here, initial contact should be with the Branch
of Construction Wage Determinations. Write to:.
Branch of Construction Wage Determinations
Wage and Hour Division
U. S. Department of Labor
200 Constitution Avenue, N. W.
Washington, D. C. 20210
2.) If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can
request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
TX970045------------------------Page:
--4-------------------------
n
200 Constitution Avenue, N. W.
Washington, D. C. 20210
The request should be accompanied by a full statement of the
interested party's position and by any information (wage payment
!'j data, project description, area practice material, etc.) that the
U requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative Review
Board (formerly the Wage Appeals Board). Write to:
flAdministrative Review Board
U. S. Department of Labor
200 Constitution Avenue, N. W.
Washington, D. C. 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
0
0
0
0
ill
0
0
0
a
0
---TX970045 -------Page: 5
U
A
n
I
0
El
0
0
Q
L
0
0
a
0
ci
0
0
WEATHER TABLE
�� Month JAverage Days of Rain
Inches of Rainfall Snow/Ice Pellets
�I January 7
1.80 1
February
7
2.36
•
March
7
2.54
April
8
4.30
0
r.1a „
o
.1 t7 I„
II j -;
�• •iy ; a
- ;:
-
U
eprne
Ij October
^ e
q f J0Ve.-,1„U.,r
it Decerno r
jl ANNUALLY
Iii (182 I'
E1 _ ___
is
i s Nican nurmbei or days rainfall, C.31•. ,*:` .•i 1r•_
(2) A.verage normal precipitation, in inches
(3) Mean nur,iber of days 1.0 inch or more
* __:...`, than 0.5 inches
This tabie is based on information reported rrom Dallas -Fort Voith Regional Airport, Texas. Latitude 32
deg 54 mm north• for ngirude 97 deg 02 ruin West, elevation (around) 551 ft.
Means are based on records covering a period of 27 years. Normals based on record of 1941-1970
period.
This table is to be used as a basis for calculation of excess rain or weather days for projects with
duration in calendar days. If the site records indicate that the Contractor was unable to carry out
operations due to weather, it is counted as a weather day. If the number of weather days exceeds the
number of average rain days plus the snowiicepellet days for a given month, the contract period will be
adjusted by Change Order.
0
a
BERTHA COLLINS COMMUNITY CENTER
1501 MLK FREEWAY NORTH
U
DIVISION 09590
GYMNASIUM WOOD FLOORING
0
PART ONE -GENERAL
PROJECT SCOPE:
REMOVE EXISTING FLOOR, TO CONCRETE SLAB. REMOVE SHOE
MOULD, WOOD BASE, AND EXPANSION JOINT COVERS AT ENTRANCE
DOORS, EXIT DOORS, AND DOORS TO ADJACENT AREAS. INSTALL NEW
EXPANSION JOINT COVERS AT ALL DOORS OPENING INTO GYMNASIUM.
DUE TO SLAB SETTLEMENT, PORTIONS OF FLOOR SHALL REQUIRE
SHIMS TO MAKE ENTIRE AREA LEVEL AND MATCH EXISTING WOOD
FLOOR THAT REMAINS. SEE LIMITS OF WORK REQUIRED.
Q
0
0
0
0
0
a
0
a
0
0
09590 -1
0
I
0
0
a
D
0
1
LI
0
SECTION 09590
GYMNASIUM WOOD FLOORING
PART 1 GENERAL
1.01 DESCRIPTION
A. Provide maple sports flooring systems of T&G strip maple on resiliently mounted wood sleepers as
herein specified including waterproofing work.
B. Related work specified under this section.
1. Provide shop drawings and submittals
2. Expansion Joint Cover Assemblies
3. Athletic Equipment
1.02 QUALITY ASSURANCE
A. Installer Qualifications: Firm specializing in installation of gymnasium wood flooring, with not less
than 3 years successful experience in installation of the types of flooring required and acceptable to
manufacturer.
B. Single Installer Responsibility: The entire gymnasium wood floor system shall be installed by a single
firm (herein called the Installer), for undivided responsibility. Include moisture barrier, anchorage
system, sleepers mastics, resilient mounts flooring trim, expansion provisions, finish markings and
other accessory items as indicated.
C. General Standards: Comply with Maple Flooring Manufacturing Association (MFMA) standards and
recommendations for flooring including grading rules, and comply with Wood and Synthetic Flooring
Institute (WSFI or equal) standards and recommendations applicable to materials and methods of
installation, except as otherwise indicated.
Q1.03 SUBMITTALS
A. Manufacture's Product Data: Submit manufacturer's detailed technical product data and installation
instructions for each gymnasium flooring system. Include instructions for handling moisture
protection, anchorage, finishing, protection and maintenance.
B. Shop Drawings: Submit shop drawings indicating method of construction, relationships to surrounding
construction, base and trim details and other information and components not fully dimensioned or
detailed in manufacturer's product data. Include layout, colors, widths and dimensions of game lines
fj and markings.
C. Sample: Submit samples of flooring finish together with color chips for game line markings.
D. Maintenance Literature: Submit copies of "MFMA Care and Preservation of Your Wood Floors."
0
09590-2
D
ci
0
a
a
ci
11
I
0
D
0
0
I
E. Suppliers shall submit certificates attesting that materials furnished will meet specifications for grade,
quality, and dryness, if required.
F. Special Project Warranty: Submit copies of 2 -year warranty for finished wood flooring and associated
work, agreeing to repair or replace flooring which shrinks, warps, cracks or otherwise deteriorates
excessively, or which buckles, delaminates or breaks its anchorage or bond with substrate or fails
otherwise to perform as required or as represented by manufacturer, due to failure of materials and
workmanship and not due to unusual exposure to moisture or other abusive forces and elements not
anticipated for application. Warranty shall be signed by Installer and by Contractor who shall assume
responsibility for obtaining adequate warranties on materials from manufacturers.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Materials shall not be delivered, stored or installed until existing floor has been removed. Deliver in
unopened bundles and store in a dry place. Place wood flooring materials in space to be floored 7 days
in advance of start of installation. Open packages of wood flooring which are sealed (if any) to permit
natural adjustment of moisture content. Installation/storage conditions are to be the same as those that
will prevail when building is occupied. Maintain ambient temperature in range of 65 degrees F to 90
degrees F 72 hours prior to installation until 48 hours after installation of wood flooring. Thereafter,
keep the temperature above 55 degrees until final acceptance of the building.
1.05 JOB CONDITIONS
A. Do not install floor system until new grades have been established.
1.06 PROTECTION
A. Protect wood flooring from damage during and after installation. Cover traffic areas with paper,
maintain until final acceptance of building.
PART 2 PRODUCTS
2.01 ACCEPTABLE MANUFACTURERS
A. Manufacturer: Subject to compliance with requirements, provide gymnasium wood flooring system
by AGA — Durachusion II, Robbins Sports Flooring Systems or approved equal.
a2.02 WOOD STRIP GYMNASIUM FLOORING
A. Grade, Cut and Species: Comply with MFMA grading rules for the following:
1. Grade: First Grade
2. Cut: Edge -Grain
13 3. Species: Northern Hard Maple
I
r] 09590-3
El
0
0
0
0
0
0
0
0
0
ci
ci
ci
0
III
ci
4. Wood flooring shall be certified by MFMA or by an equivalent certification standard. The
Contractor shall be responsible for demonstrating that an alternative certification is equivalent to
MFMA.
B. Lengths: Comply with MFMA grading rules, except as otherwise indicated for special patterns.
C. Matching: Tongued and grooved and end matched; steel spline may replace tongues, at
manufacturer's option.
D. Back Channeling: Back channel each piece in accordance with manufacturer's standards.
E. Thickness: 33/32"
F. Face Width: 2— ¼"
G. Seasoning: Kiln dried before milling
2.03 ACCESSORY MATERIALS FOR GYMNASIUM FLOORING
A. 8 mil polyethylene.
B. Asphalt Compound: Solvent type asphalt mastic, for cold application, as a cemented material for
polyethylene.
C. Wood Sleepers: standard grade Hemlock, or Pine, treated by Penta Dip System, Kiln dried to 15%
maximum moisture content. Discard bowed and twisted pieces (all subfloor material shall be fire
retardent treated)/
D. Rubber Mounts: '/2" thick hollow EPDM, rubber or neoprene, pneumatic (hermetically sealed voids)
pads, sized to provide optimum floor resiliency for spacing specified by manufacturer.
E. Nail and Screws: Type and size recommended by manufacturer, but not less than recommended by
MFMA for each application.
F. Gym Floor Finish
1. Finish: Oil base floor finish, by World Class Finishes as recommended by flooring manufacturer
and approved by MFMA.
G. Floor Wax: Liquid, solvent -type, slip -resistant; FS P -W-158, Type I, Class 2.
H. Expansion Joint Cover:
1. Equal to Balco Metalines, Type 1120, Flush Mill Finish Aluminum No. 1420 smooth.
2. Pemco Saddle No. 2748A 8" x 1/a" x opening Mill Finish Aluminum
0
09590-4
0
I. Volleyball Inserts:
Dl.Provide and install two (2) floor sleeves with flush cover plate and floor ring for 3 '/2" diameter
post (not included) as manufactured by Porter Equipment Company.
PART 3 EXECUTION
3.01 INSPECTION
13 A. Inspect concrete subfloors for proper tolerance and dryness, and report any discrepancies to the owners
representative.
B. All work required to put the new wood floor in level and true shall be the responsibility of the
Contractor.
C. Subfloor should be vacuum clean prior to installation.
U3.02 INSTALLATION
A.
General: Comply with flooring manufacturer's instructions and recommendations for applications
indicated, but not less than MFMA standards and WSFI standards.
B.
Pattern Direction: Lay flooring lengthwise with space to be floored except as otherwise indicated.
C.
Tolerances: Level gymnasium wood flooring system stem to a tolerance of 1/8" in 10'-0".
D.
Expansion Spaces: Provide spaces as indicated or required by instructions and standards, at
obstructions, interruptions, and terminations of flooring. Cover spaces with bases, trim, saddles, and
thresholds, except fill flush with cork expansion strip when indicated to be uncovered.
E.
Check for Dryness: Before proceedin
g p g with installation of gymnasium wood flooring over concrete
substrate, check for dryness. If not sufficiently dry, as determined by Installer, continue to dry
substrate, or provide extra moisture protection for flooring.
F.
Treated Wood: When treated wood must be cut for installation, apply Penta Dip on ends after cutting.
3.03 RESILIENTLY
-MOUNTED WOOD SLEEPER SYSTEM
flA.
Install moisture barrier, consisting of a cemented lapped joint layer of polyethylene as specified.
fl
B.
Apply rubber mounts to bottom side of 2 x 4 wood sleeper units, of lengths and spacing of mounts as
specified by manufacturer. Install
sleepers without anchorage over substrate, spaced 12" o.c., and
running crosswise with long dimension of spaces.
C.
install 'A" thick plywood subfloor over sleepers.
Q
('y 09590-5
a
D. Install hard maple gymnasium flooring by nailing to each sleeper through subfloor.
�.! 3.04 SANDING AND FINISHING
A. Allow installed gymnasium
flooring to acclimate to ambient conditions for a minimum period of 10
days before sanding.
B. Machine sand wit
h coarse, medium and fine grades of sandpaper, followed by disc sanding with 000
sandpaper. Clean with power vacuum, and check to confirm that entire surface of each piece has been
0 sanded, and that floor is level and smooth, without ridges or cups. Proceed immediately with finish.
C. High -Build Gym Finish: Apply gym floor finish in accordance with manufacturer's instructions,
including a first coat of penetrating sealer of type recommended. Apply as many coats as needed to
build a minimum dry film thickness of 3 mils. Follow manufacturer's recommendations for drying
D time between coats. Buff between each coat. Retain empty containers for confirmation of film
thickness. Prevent traffic on finished floor for a minimum of 10 days.
UI. Lines and Markers: Prior to application of last coat of floor finish, lay out lines, fields and other
markings as indicated for colored enamel application. Mask flooring to provide sharp edges.
Apply gym enamel in colors as indicated, or as selected by Architect. Where game lines cross,
break minor game line at intersection; do not overlap lines.
D. Install other cover trim as detailed for expansion spaces at edges and interruptions of flooring.
3.05 PROTECTION
A. Protect complete gymnasium wood flooring during remainder of construction period with heavy Kraft
Paper or other suitable covering, so that flooring and finish will be without damage or deterioration at
time of acceptance.
9 3.06 EXTRA STOCK
0 A. Provide 2% of material used.
END OF SECTION
4
ci
a
f!1
09590-6
JUL-13-99 TUB 9:52 AM TPW ADMIN FAX NO, 817 871 8092 P. 2
I
CITY OF FORT WORTH, TEXAS
CONSTRUCTION PONTR.AT
THE STATE OF TEXAS El
COUNTY OF TARRANT KNOW ALL MEN BY THESE PRESENTS:
0
I
0
0
Ii
0
m
This agreement made and entered into this the l$ day of Jun! AD 19 by and between the CITY OF FORT WORTH, a municipal corporation
existing under and by virtue of a � of Tarrant County, Texas, organized and
special charter adopted by the qualified voters within said City on the 11th day of December, AD. 1924, under the authority (vested in said voters by the "Home Rule" provision) of the
Constitution of Texas, and in accordance with a resolution duly passed at a regular meeting of the City
Council of ea' city, hereinafter called OWNER, and Bluer SpQrt Floors. Inc, of the City of. Hou r
County of t/i'.e/5 State of Texas hereinafter caned CONTRACTOR.
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned to be
made and performed by the Owner, and under the conditions expressed in the bond bearing even date
herewith, the said Contractor hereby agrees with the said Owner to commence and complete the
construction of certain improvements described as follows:
BERTHA COLLINS COMMUNITY CENTER
GYMNASIUM FLOOR REPLACEMENT
That the work herein contemplated shall consist of furnishing as an independent contractor all labor, tools,
appliances and materials necessary for the construction and completion of said project in accordance with
the Plans and Specification$ and Contract Documents adopted by the City Council of the City of Fort Worth,
which Plans and Specifications and Contract Documents are hereto attached and made a part of this
contract the same as if written herein.
The Contractor hereby agrees and binds himself to commence the construction of said work within tan (10)
days after being notified in writing to do so by the Owner.
The Contractor hereby agrees to prosecute said work with reasonable diligence after the commencement
thereof and to fully complete and finish the same ready for the Inspection and appravai of the Transportation
and Public Works Director of the City of Fort Worth and the City Council of the City of Fort Worth within a
U
period of _ Socalendar da .
The agreed upon total contract amount shall be -1-41 p0.00 and includes the Access Controllers, Central
Control and Administration System and the CCTV Surveillance System as detailed in Pages 19 through 29 of
the Proposal. Contractor agrees to complete the project, suitable for occupancy and beneficial use, within 90
calendar days from Notice to Proceed,
III �
0
0
I
0
City agrees and binds itself to pay, and the said Contractor agrees to receive, for all of the aforesaid work,
and for stated additions thereto or deductions therefrom, the price shown on the Proposal submitted by the
successful bidder hereto attached and made a part hereof. Payment will be made in monthly installments
upon actual work completed by contractor and accepted by the Owner and receipt of invoice from the
Contractor,
The Contractor will provide a Certificate of Insurance listing the Transportation and Public Works Department
as certificate holder, showing the required General Contractors Liability coverage, Auto Liability, Builder's
Risk and Worker's Compensation coverage. If this Contract is In excess of $25,000, the Contractor shall
provide Payment Bond. If the Contractor is In excess of $100,000, the Contractor shall provide both
Payment and Performance Bonds for the full amount of the contract, Contractor shall apply for ail City of Fort
C -I
I
JUL-13-99 TUE 9:52 AM TPW ADMIX FAX N0, 917 871.8092 ?, 3
Worth Permits and for any other permits required by this project City of Fort Worth Permit fees are waived,
Separate permits will be required for each facility.
If the Contractor should fall to complete the work as set forth In the Plans and Specifications and Contract
Documents within the time so stipulated, plus any additional time allowed as provided in the General Condi-
tions, there shall be deducted from any monies due or which may thereafter become due him, the liquidated
damages outlined in the General Conditions, not as a penalty but as liquidated damages, the Contractor and
his Surety shall be liable to the Owner for such derciency,
IN WITNESS WHEREOF, the City of Fort Worth has caused this instrument to be signed in counterparts in its name and on Its behalf by the City Manager and attested by its Secretary, with the
corporate seal of the City of Fort Worth attached, The Contractor has executed this instrument through its
duly authorized officers in SIX (6! counterparts with its corporate seal attached.
I
I
u
M
Done in Fort Worth, Texas, this the 15'r" day of June
AD, 19,x..
7Z(Z-$
D 2f C
Contractor
By: APPRO
Office By'
Assistant City Manager ~'
APPROVAL RECOMMENDED,
By-
Transportation and Public Works
APPROVED AS TO FORM AND LEGALITY:
H
By:
Assistant C ttomey
I
C-2
RECORDED:
By:
City
Date
Contract Authorization
- /5—Q
Date
I
9 PAYMENT BOND
THE STATE OF TEXAS BOND NO. 'r" Oo i bp-)'
9 COUNTY OF TARRANT
KNOW ALL MEN BY THESES PRESENTS: That we, Bauer Sport Floors, Inc. a
fl corporation of 1._AQQ_S County, Texas , hereinafter called Principal
and (3) EUI _p. o Sw'�St�r�• � �
a corporation organized and existing under the laws of the State and fully authorized
0 to transact business in the State of Texas, as Surety, are held and firmly bound unto the City of Fort
Worth, a municipal corporation organized and existing under the laws of the State of Texas, hereinafter
called Owner, and unto all persons, firms, and corporations who may furnish materials for, or perform
9 labor upon, the building or improvements hereinafter referred to in the penal sum of:
Forty Nine Thousand, Two Hundred Dollars & No Cents
LI$49,200.00 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for the
payment of which sum well and truly be made, we bind ourselves, our heirs, executors, administrators
0 and successors jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a
certain contract with the City of Fort Worth, the Owner dated the 15th day of June , 1999, a
copy of which is hereto attached and made a part hereof, for the construction of:
9
BERTHA COLLINS COMMUNITY CENTER
GYMNASIUM FLOOR REPLACEMENT
0 designated as Project Number GG01/0205002 copy of which contract is hereto attached, referred to,
and made a part hereof as fully and to the same extent as if copied at length herein, such project and
construction being hereinafter referred to as the "works".
NOW, THEREFORE, the condition of the obligation is such'that, if the Principal shall promptly
make payment to all claimants as defined in Article 5160 of the Revised Civil Statutes of Texas,
supplying labor and materials in the prosecution of the work provided for in said Contract, then this
9 obligation shall be null and void, otherwise it shall remain in full force and effect.
THIS BOND IS MADE AND ENTERED into solely for the protection of all claimants supplying
a
labor and material in the prosecution of the work provided for in said Contract, as claimants are defined
in said Article 5160, and all such claimants shall have a direct right of action under the bond as provided
0 in Article 5160 of the Revised Civil Statutes.
PROVIDED FURTHER, that if any legal action be filed upon this bond, venue shall lie in
Tarrant County, State of Texas, and that the said Surety, for value received, hereby stipulates and agrees
that no change extension of time, alteration or addition to the terms of the contract or to the work to be
performed thereunder or the specification accompanying the same shall in any wise affect its obligations
on this bond, and it does hereby waive notice of any such change, extension of time, alteration or
9 addition to the terms of the contract or to the work or the specifications.
PROVIDED FURTHER, that no final settlement between the Owner and the Contractor shall
AMPAYBOND.FRM
r
I
9 abridge the right of any beneficiary hereunder whose claim shall be unsatisfied.
IN WITNESSETH WHEREOF, this instrument is executed in 6 counterparts, each one of which
9 shall be deemed an original, this the :7 - day of 1999.
11
ATTEST:
a
(Principal) Secretary
a
(SEAL)
U
ci
(Address)
[I ATTEST:
0
I
0
I
0
£
0
0
(Surety) Secretary
(SEAL)
Witness as to Surety
/ /1e/C y/9-iy rho o <J 4i
(Printed Name/Title)
eo BOX Q —
ADDRESS
7, 77c?9
CITY/STATE/ZIP
(Surety)
By:
Attorney -F -Fact) (5)
(Printed Attorney -in -Fact)
Note: Date of Bond must not be prior to date of
Contract
(1) Correct name of Contractor
(2) A Corporation, a Partnership or and
Individual, as case may be
(3) Correct Name of Surety
(4) If Contractor is Partnership all Partners
should execute bond
I
-POWER OF ATTORNEY
LI ACCEPTANCE INSURANCE COMPANY REDLAND INSURANCE COMPANY
LW
TEX DO 1O O iT
ALL MEN BY THESE PRESENTS: That ACCEPTANCE INSURANCE COMPANY AND REDLAND INSURANCE COMPANY (Collectively
referred to as "Company"), having its executive Offices in County of Douglas, State of Nebraska, has made, constituted and appointed, and does by these
R
resents make, constitute and appoint: Fred Thetford Tom Young
itrue and lawful Attomey(s)-in-Fact, with full power and authority hereby conferred in its name, place and stead, to execute, seal, acknowledge and
deliver any and all bonds, undertakings, recognizances or other written obligations in the nature thereof in any amount up to $3,000,000 for any single
obligation and to bind the Corporation thereby as fully and to the same extent as if such bonds were signed by the President, sealed with the corporate seal
of the Corporation and duly attested by its Secretary, hereby ratifying and confirming all that the said Attorney(s)-in-Fact may do in the premises.
This power of attorney is signed and sealed under and by the authority of the following Resolution adopted by the Board of Directors of the Company at
a meeting duly called and held on the 18th day of October, 1993, and said Resolution has not been amended or repealed:
U"O'
that the Chairman of the Board, the President, an Executive Vice President or a Vice President be, and that each of them is, authorized to
execute Powers of Attorney qualifying the Attorney(s)-in-Fact named in the given Power of Attorney to execute in behalf of the Company, bonds,
undertakings and other instruments of similar nature, and said officers may rename any such Attorney(s)-in-Fact or agent and revoke any Power of Attorney
previously granted to such person.
FURTHER RESOLVED, that the signatures of such officers and the seal of the Company may be affixed to any such Power of Attorney or to any certificate
relating thereto by facsimile, and any such Power of Attorney or certificate bearing such facsimile signatures or facsimile seal shall be binding upon the
ocompany when so affixed and in the future with respect to any bond, undertaking or instruments of similar nature to which it is attached." IN WITNESS WHE OF, the Company has caused these presents to be signed by its Vice President and its corporate seal to be hereunto affixed this
7 day of
"�1SURq "' "'•SURA/y� ACCEPTANCE INSURANCE COMPANY
s�o�� "�F ,tea\ ' REDLAND INSURANCE COMPANY
U�y 'GOPPORgTF ��: ,rfi ,-... SW ORPORgr ;y: �'•'
SEAL tom= > ° :'�' , n SEAL t*
Sis°°' .� \C3 by:
'HA:NES .." 'oC/< BLUFF,••' '�. t.f/tr 7tt j: ₹,
John R. Svoboda, Vice President
]STATE OF NEBRASKA )
COUNTY OF DOUGLAS )53
'On this 22nd day of April, 1999, before me personally came John R. Svoboda to me known, who, being by me duly sworn, did depose and say: that
he is a Vice President of ACCEPTANCE -INSURANCE COMPANY and REDLAND INSURANCE COMPANY, the Corporations described in and which
executed the above instrument; that he knows the seals of said Corporations; that the seals affixed to the said instrument are such corporate seals; that they
Tere so affixed by order of the Board of Directors of said Corporations and that he signed his name thereto by like order.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed my official seal, the day and y herein rst ove� written.
GENERAL NOTARY -State of Nebraska
CAROL A. ERN Carol A. Em, Notary Public
My Comm. Exp. March 7, 2000 CERTIFICATE
11 STATE OF NEBRASKA )
COUNTY OF DOUGLAS )"
I, the undersigned, Secretary of ACCEPTANCE INSURANCE COMPANY and REDLAND INSURANCE COMPANY, DO HEREBY CERTIFY that
the above and foregoing is a true and correct copy of the POWER OF ATTORNEY executed by said Companies which is in full force and has not been
revoked; and furthermore that the Resolution of the Board of Directors set forth in the Power of Attorney is now in force. (y��
Signed and sealed at the County of Douglas. Dated the I day of , )
..`'�F,\NSURAryf'C<'`(.,,, ,•`Q\NSURANCCf''•',. ��.- ,/` 4 '�.
w: •OFPORgT'-, 4 Ac. ft .. 1 �W ,t''OpPORgTc��y i 4� '.a 1. i •f F !, fl SEAL _ .. .rc. SEAL efl
., t S t'r Peter A. Kirglla, Secretary
o�4''4 NEBPPs,F4''. ,,GBL OFFS o, a it!!'I"
IF YOUHA VEANY QUESTIONS CONCERNING THEA UTHENTICITY OF THIS DOCUMENT, YOUARE URGED TO CONTACT OUR POWER OF
ATTORNEY CUSTODL4NAT 402-344-8800 WHOSE OFFICE IS LOCATED AT 222 SOUTH 15th STREET, SUITE 600 N.; OMAHA, NE 68102.
CONTRACTOR COMPLIANCE WITH
WORKER'S COMPENSATION LAW
Pursuant to Article 8308-3.23 of Vernon's Annotated Civil Statutes, Contractor= Bauer Sport Floors,
Inc. certifies that it provides worker's compensation insurance coverage for all of its employees
employed on City of Fort Worth project Bertha Collins Community Center — Gymnasium Floor
Replacement project number, GG01/0205002.
LI By:fJ
LITitle
Q�
ate
STATE OF TEXAS 3 2D
COUNTY OF TARRANT 3
BEFORE ME, the undersigned authority, on this
day personally
appeared
___1 %A//Y/8 �.- U`�,C�.
, known to me
to be the
person whose name is subscribed to the foregoing instrument, and
acknowledged to me that he
executed thesame as the act
and deed
of
sQbg e-7 ,1-h5 /4PG
, for the
purposes
LI.
and considerations therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OF CE t s day of
JL /y , 19 _q g
[I / Not _ : : in �;�ivt��te of exas
OMMISSION EXPIRES
February 21, 2000
I
I
I
J
(a) Contractor agrees to provide to the City a certificate showing that it has obtained a policy
of workers compensation insurance covering each of its employees on the project in compliance
with state law. No Notice to Proceed will be issued until the Contractor has complied with this
section.
(b) Contractor agrees to require each and every subcontractor who will perform work on the
project to provide to it a certificate from such subcontractor stating that the subcontractor has a
policy of workers compensation insurance covering each employee employed on the project.
Contractor will not permit any subcontractor to perform work on the project until such certificate
has been acquired. Contractor shall provide a copy of all such certificates to the City.
I
A:13WORKCOM.FRM
City of Fort Worth, Texas
qVinvor And Council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
6/15/99 **C-17463 20FLOOR 1 of I
SUBJECT AWARD OF CONSTRUCTION CONTRACT TO BAUER SPORT FLOORS FOR THE
REPLACEMENT OF THE WOOD GYM FLOOR AT THE BERTHA COLLINS
RECREATION CENTER
RECOMMENDATION:
It is recommended that the City Council approve the execution of a construction contract with Bauer
Sport Floors, Inc. for the replacement of the oak floor in the gymnasium at Bertha Collins Recreation
Center in the amount of $49,200, with a duration of 60 calendar days.
DISCUSSION:
Due to heavy usage and multiple refinishing, the oak floor in the gymnasium at the Bertha Collins
Recreation Center is in need of replacement. Severe wear has caused the floor grooves to loosen.
During replacement, the existing wood "sleepers" (supports between the wood flooring and the
concrete foundation) will be adjusted and reused.
The project was`advertised for bid in the Fort Worth Star Telegram on March 25 and April 1, 1999. On
April 22, 1999, the following bids were received:
Bidder Bid Duration
Bauer Sport Floors. Inc. $49.200 60 Days
Long Flooring 56,970 60 Days
Brunson Construction 68,875 45 Days
Bauer Sport Floors, Inc. is in compliance with the City's MWBE Ordinance: by committing to 10%
M/WBE participation. The City's goal on this project is 10%.
The project is located in, COUNCIL DISTRICT o
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current operating budget, as appropriated,
of the General Fund.
MG:k
Submitted for City Manager's
Office by: „
Mike Groomer 6140
FUND
ACCOUNT
CENTER
AMOUNT
CITY SECRETARY
(to)
APPROVED
CITY COUNCIL
JUN 15 1999
y i
9� lei e•�-� J
City Secretary of tht'
City of Fort Worth, Texas
Originating Department Head:
Hugo Malanga 7801
(from)
GG01
536010
0205002
$49,200.00•
Additional Information Contact:
Hugo Malanga 7801