DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
CIBOLO HILLS WEST
CONTRACT:
(UNIT 1) WATER, (UNIT II) SEWER, (UNIT III) STORMWATER, & (UNIT IV) PAVEMENT
CHANGE
ORDER No:
CFA #
25-0057 CITY PARTICIPATION: YES
CITY PROJECT #
106117
CITY SECRETARY CONTRACT #
164780
FID #
I FID # 30114-0200431-106117-EO7685
1
X #
X-28499
FILE #
W-4019
INSPECTOR: Leticia Flores Phone No: 682-454-2732
PROJECT MANAGER: Ahmed Musa Phone No: 817-392-2084
CONTRACT UNIT
WORKING
DAYS
WATER
SEWER
DRAINAGE
PAVING
Developer
Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
ORIGINAL CONTRACT
$1,725,151.40
$98,924.60
$2,021,969.00
$0.00
$1,122,080.00
$0.00
$3,625,431.00
$0.00
300
EXTRAS TO DATE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0
CREDITS TO DATE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0
CONTRACT TO DATE
$1,725,151.40
$98,924.60
$2,021,959.00
$0.00
$1,122,080.00
$0.00
$3,625,431.00
$0.00
300
AMOUNT OF PROP. CHANGE ORDER
($269,846.40)
($98,924.60)
$8,450.00
$0.00
$5,678.00
$0.00
$0.00
$0.00
0
REVISED CONTRACT AMOUNT
$1,455,305.00
$0.00
$2,030,409.00
$0.00
$1,127,758.00
$0.00
$3,625,431.00
$0.00
300
TOTAL REVISED CONTRACT AMOUNT PER
UNIT
$1,455,305.00
$2,030,409.00
$1,127,758.00
$3,625,431.00
REVISED COST SHARE
Dev. Cost:
$8,238,903.00
City Cost:
$0.00
TOTAL REVISED CONTRACT
$8,238,903.00
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Revised: 12-17-2018 Page 1
You are directed to make the following changes in the contract documents
CIBOLO HILLS WEST - RESIDENTIAL
UNIT I: WATER IMPROVEMENTS
PAY ITEM #
CITY BID ITEM
#
QUANTITY
UNIT
ITEM DESCRIPTION
CFW Unit Price
UNIT PRICE
Developer Cost
City Cost
TOTAL
4
3305.0109
40
LF
Trench Safety
$ -
$ 1.00
$40.00
$0.00
$40.00
5
3311.0001
0.218
TON
Ductile Iron Water Fittings w/ Restraint
$
$ 11,500.00
$2,507.00
$0.00
$2,507.00
6
3311.0241
40
LF
8" Water Pipe
$ -
$ 56.00
$2,240.00
$0.00
$2,240.00
17*
3312.3002
1
EA
6" Gate Valve
$ -
$ 1,350.00
$1,350.00
$0.00
$1,350.00
11
3312.3003
1
EA
8" Gate Valve
$ -
$ 1,550.00
$1,550.00
$0.00
$1,550.00
16
9999.0004
-1
EA
4" Domestic Water Service
$
$ 22,500.00
($22,500.00)
$0.00
($22,500.00)
18*
9999.0025
1
EA
3" Domestic Water Service
$
$ 18,500.00
$18,500.00
$0.00
$18,500.00
TOTAL UNIT I: WATER IMPROVEMENTS IM87.00 0.00 $3,687.00
UNIT II: SANITARY SEWER IMPROVEMENTS
PAY ITEM #
CITY BID ITEM
#
QUANTITY
UNIT
ITEM DESCRIPTION
CFW Unit Price
UNIT PRICE
Developer Cost
City Cost
TOTAL
20*
3331.4108
4
LF
6" Sewer Pipe
$
$ 72.00
$288.00
$0.00
$288.00
10
3331.4115
-11
LF
8" Sewer Pipe
$ -
$ 76.00
($836.00)
$0.00
($836.00)
11
3331.4116
20
LF
8" Sewer Pipe - CSS Backfill
$ -
$ 96.00
$1,920.00
$0.00
$1,920.00
1
3301.0002
13
LF
Post -CCTV Inspection
$ -
$ 4.00
$52.00
$0.00
$52.00
2
3301.2101
1
EA
Manhole Vacuum Testing
$
$ 200.00
$200.00
$0.00
$200.00
3
3305.0109
13
LF
Trench Safety
$
$ 2.001
$26.00
$0.00
$26.00
4
3305.0112
1
EA
Concrete Collar for Manhole
$ -
$ 1,000.00
$1,000.00
$0.00
$1,000.00
21*
9999.0026
1
1 EA
4' Manhole with Hydraulic Slide
1 $ -1
$ 5,800.001
$5,800.00
1 $0.00
1 $5,800.00
TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS 8$ .450.00 $0.00 $8,450.00
UNIT III: DRAINAGE IMPROVEMENTS
PAY ITEM #
CITY BID ITEM
#
QUANTITY
UNIT
ITEM DESCRIPTION
CFW Unit Price
UNIT PRICE
Developer Cost
City Cost
TOTAL
5
3341.0205
12
LF
24" RCP, Class III
$ -
$ 85.00
$1,020.00
$0.00
$1,020.00
6
3341.0208
14
LF
27" RCP, Class III
$ -
$ 95.00
$1,330.00
$0.00
$1,330.00
8
3341.0309
26
LF
36" RCP, Class III
$ -
$ 120.00
$3,120.00
$0.00
$3,120.00
2
3301.0012
52
LF
Post -CCTV Inspection of Storm Drain
$ -
$ 2.00
$104.00
$0.00
$104.00
3
3305.0109
52
LF
Trench Safety
$ -
$ 2.00
$104.00
$0.00
$104.00
TOTAL UNIT III: DRAINAGE IMPROVEMENTS 5 678.00 $0.00 $5,678.00
CIBOLO HILLS WEST - 16 INCH WATER LINE
UNIT I: WATER IMPROVEMENTS
PAY ITEM #
CITY BID ITEM
#
QUANTITY
UNIT
ITEM DESCRIPTION
CFW Unit Price
UNIT PRICE
Developer Cost
City Cost
TOTAL
1
0241.1106
-2
EA
16" Pressure Plug
$ 1,500.00
$ 2,000.00
($1,000.00)
($3,000.00)
($4,000.00)
2
3305.0109
-1321
LF
Trench Safety
$ -
$ 1.00
($1,321.00)
$0.00
($1,321.00)
3
3311.0001
-2.59
TON
Ductile Iron Water Fittings w/ Restraint
$ 7,000.00
$ 12,500.00
($20,055.00)
($12,320.00)
($32,375.00)
4
3311.0541
-1291
LF
16" Water Pipe
$ -
$ 122.00
($157,502.00)
$0.00
($157,502.00)
5
3311.0551
-30
LF
16" DIP Water
$ 54.00
$ 152.00
($2,940.00)
($1,620.00)
($4,560.00)
6
3305.0203
-383
CY
Imported Embedment/Backfill, CLSM
$ -
$ 200.00
($76,600.00)
$0.00
($76,600.00)
7
3305.1005
-20
LE
30" Casing By Open Cut
$ 254.23
$ 380.00
($2,515.40)
($5,084.60)
($7,600.00)
8
3312.0001
-1
EA
Fire Hydrant
$ -
$ 8,500.00
($8,500.00)
$0.00
($8,500.00)
9
3312.1002
-1
EA
2" Combination Air Valve As embly for Water
$ 12,500.00
$ 12,500.00
$0.00
($12,500.00)
($12,500.00)
10
3312.3006
-2
EA
16" Gate Valve w/ Vault
$ 26,950.00
1
$ 28,500.00
($3,100.00)
($53,900.00)
($57,000.00)
11
3312.6002
-1
EA
6" Blow Off Valve
$ 10,500.00
$ 10,500.00
$0.00
($10,500.00)
($10,500.00)
TOTAL UNIT I: WATER IMPROVEMENTS dZZ3 5-33.401 ($98.924.601 ($372,458.OD
Asterisk (*) indicates New Pay Iterr
Revised: 12-17-2018 Page 2
13acusign Envelope ID: B85F3CF'F-2FFBAF50-A60A-6CO7F9AC988C
REASONS FOR CHANGE ORDER
RCCOMMENCEO:
LJA Eng neudrw. Inq
Name- Nataaael Gnin ez PE -
Title: Sr. Proiect Enaineer
APPROVAL RECOMMENDED:
161 WO nuw included on separate 01an set, Ak dillonal minor revWons to Storm Line Sao, SU5 and Server Line M, Une P and litre 0 for Sd" d cennedkm-
04r23/2026
APPROVED:
'�Y1512026 1 9:31 AM: r&r
Nams anon Guthrie
Tine: Authorized &gner
APPROVEDt
Name: Brock Hu2&
TlUe, Pr and
APPROV W AS TO FOW AND LEGALMY:
GFkY -Wai 0Ly.Arrrriar:r CFW- A.66stanj CRy Manager CPA'- Aask-wnt CtPf Aname.
S,� ✓ Pf' 05/04/2026 ( ,QJ 05/07/2026 9—. W.", 05/04/2026
By, a38tQ:
MH Noma: 5421Varughass Nance; Jesica McEachern Jessika Williams
rug: Enweenng Mwager Tale: AggIstantCity Manasar Asst City Attorney
o OFOgTn�lIIdO
CFW - "Conti-O CvrnrptiRnre ManaOw ATTUT
AHWM Mara 04/28/2026 r�_--�, d ,,, app......
gy. Ahmed Musa (Apr 28. 2026 10:16:51 CDT) U� — 05/08/2026
6Y" � Dols:
Name: Ahmed Musa.
Title: Professwal Eri'Afieer
MSC Number. NtA
M$C Dale App:vued: WA
Name: Jannetta S. OgMl
Title: CI lY secretwry
cc
cc
* Contract CoMptlarkCe Marragor (Pro)rct Margery:
By signing I ackroMedge Thal I am the parson responsible
for the monlwna and adminetralion olthis contract,
and ensuring all perfwmanCe and relwrtng repulrements.
i3 disco we NO City Funds assoeaaled'with the Contract
2 Thera are City'rw'ids associated wtih this Gontrael
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Revised: 12-17-20I1'r Page 3
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Conatser Construction TX, L.P.
Subject of the Agreement: The 16" water line along Cibolo Hills Parkway will be removed from this
project (CPN 106117) and included in a separate project (CPN 106849)
Additional minor changes have been made to the storm and sewer lines.
M&C Approved by the Council? * Yes ❑ No M
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ CSN(64780) / CFA25-0057
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see backpage for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No ED
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. CPN 106117
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.