HomeMy WebLinkAbout28368-03-2026 - City Council - OrdinanceOrdinance No.28368-03-2026
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE 2018 BOND PROGRAM
FUND, BY INCREASING APPROPRIATIONS IN THE CROMWELL-MARINE CREEK ROAD
PROJECT (CITY PROJECT NO. 101012) IN THE AMOUNT OF $850,000.00, AND DECREASING
APPROPRIATIONS IN THE AUTHORIZED, NOT APPROPRIATED PROJECT (CITY PROJECT
NO. U34018) BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES
IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance
27979-09-2025, as amended, is hereby further amended to make the following adjustments to
appropriations in the 2018 Bond Program Fund, by increasing appropriations in the Cromwell -Marine
Creek Road project (City Project No. 101012) in the amount of $850,000.00, and decreasing
appropriations in the Authorized, Not Appropriated project (City Project No. U34018) by the same
amount.
M=1611[07►fPJ
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27979-09-2025 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPRO D A TO FORM AND LEGALITY:
Douglas Black (May 8, 2026 09:46:51 CDT)
Assistant City Attorney
ADOPTED AND EFFECTIVE: March 10, 2026
CITY SECRETARY
Jannette S. Goodall
City Secretary
Mayor & Council Map I CPN #101012 FORT WORTH®
Cromwell Marine Creek Road Widening
1 II Jai I
�
Zt r w r; .y
f6
`t�l=•".. a»,' �F. �� r d �� ';'� f _ - k�l
�tttC]1TfI pPi r y
p
[*'- IC Z ( �' � f �. � +, Fj
CD
' ^..
fIr.tl'GrXIMCf!'111ft"
r MIrJTr�
r
I
r
�so('
IT
i ?.
>�Y?
aF '
I ' D
Y' III DOZ
�
f , Ln
'
t1v
t1CeC�f77rPPf}CII' VIEW`','�
EL D
iF?ff P
,t+ y o `�. � Jif � . ,w� � �y '+�.. � . trey. , �di+YYYYY :Yy y •
VA
pid �Y.riN Ali dY11Y1 Y9�WIi� .,, + .may r.l.�MARIN CREEK
SCHOOL
v
a
4.4
1 Ii !! ,iVlYfilil IliliAli tlgia ,�"` r�' .•
_ 4 �
.�—
ed ,MF?11Y1[Riil�rsVe€
R9 �9kifii CaMiles
,
,
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 03/10/26 M&C FILE NUMBER: M&C 26-0203
LOG NAME: 20CROMWELL MARINE CREEK ROAD CMAR C01 - SUNDT
SUBJECT
(CD 2 and CD 7) Authorize Execution of a Change Order for Extra Work in the Amount of $2,387,411.79 and the Addition of 113 Calendar Days
Under the Construction Manager at Risk Agreement with Sundt Construction, Inc., for the Cromwell Marine Creek Road Project, from Boat Club
Road (Farm to Market Road 1220) to Marine Creek Parkway, Adopt Appropriation Ordinance, and Amend the Fiscal Years 2026-2030 Capital
Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a Change Order for extra work in the amount of $2,387,411.79 and the addition of 113 calendar days under City
Secretary Contract No. 59041, a Construction Manager at Risk Agreement with Sundt Construction, Inc., for the Cromwell -Marine Creek
project (City Project No. 101012);
2. Adopt the attached appropriation ordinance adjusting appropriations in the 2018 Bond Program Fund by increasing appropriations in the
Cromwell -Marine Creek Road project (City Project No. 101012) in the amount of $850,000.00, and by decreasing appropriations in
the Authorized, Not Appropriated project (City Project No. U34018) by the same amount; and
3. Amend the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to authorize a Change Order for extra work in the amount of $2,387,411.79,
which is expected to take 113 calendar days to complete, under the Construction Manager at Risk Agreement (CMAR) with Sundt Construction,
Inc., for the Cromwell Marine Creek Road Project, from Boat Club Road (Farm to Market Road (FM) 1220) to Marine Creek Parkway.
On December 12, 2022 (M&C 22-1047) the CMAR agreement with Sundt Construction, Inc. was authorized for execution (CSC No. 59041). The
agreement was for the amount $120,000.00 for preconstruction phase services and established a 5.75% construction phase fee. The then
construction budget was $24,100,000.00 out of a then overall project budget of $39,779,237.00.
The Contract was amended by Amendment No. 1 on May 14, 2024 (M&C 24-0387) which established a construction phase Guaranteed
Maximum Price (GMP) of $44,886,140.31, inclusive of the CMAR's 5.75% fee. The M&C also authorized increasing the project budget by the
amount of $21,239,483.92 most of which being programmed for the construction budget. The overall project budget is currently $58,479,483.92.
In summer through fall, 2025, it was determined that excavation and subsequent paving of Cromwell Marine Creek Road from the intersection with
Bob Hanger Street to the bridge over Marine Creek resulted in a roadway elevation generally incompatible with respect to the adjacent
neighborhood streets. Specifically, the new elevation of Cromwell Marine Creek Road created undesirably steep connections at the intersections
of Bob Hanger Street, Neptune Street, Provinces Street, Britannic Street, and Crystal Lake Drive as well as near the intersections of Cape Street
and Bay Lake Drive. The Design Engineer made changes to the original project design and TPW staff requested the CMAR perform the extra
work to improve the connections.
The extra work, in the amount of $2,387,411.79, provides for the removal of pavement, elevating and reconstructing the roadway to improve the
connections to the neighborhood streets. The amount includes $336,343.00 for owner's allowance/contingency to be used at the City's discretion
if needed. This extra work cost also includes additional costs for bonds and insurance, CMAR contingency and labor and materials. As
apportionment of fault has not been established, at this time the extra work is not being incorporated into the GMP and the CMAR's 5.75% fee
($117,936.46) is being withheld.
The following table summarizes previous contract action and amendments:
Contract
M&C
Date Justification
Amount
Initial Contract- Sundt
22-
12/13/2022 Preconstruction Phase Fee
$120,000.00
Construction, Inc.
1047
Amendment No. 1
24
5/14/2024 CMAR's 5.75% Construction
$2 394,270.67
0387
Phase Fee - Within GMP
Total Proposed CMAR
$2,514,270.67
Fees*
Change Order- Extra Pending This M&C Extra Work $2,387,411.79
Work
*This is the amount CMAR expects to earn in fees.
The 2022 Capital Improvement Program allocated funds for the roadway widening of Cromwell Marine Creek Road between Boat Club Road
(FM 1220) and Marine Creek Parkway. A CMAR with Sundt Construction, Inc., (Contractor) was authorized for the construction of a four -lane
arterial street from Boat Club Road (FM 1220) to Marine Creek Parkway with signalized intersections at Bowman Roberts Road, Huffines
Boulevard/Bob Hanger Street and Crystal Lake Drive. The project is currently being funded through the City's 2018 and 2022 Bond Programs,
Tarrant County 2021 Bond Program, and transportation impact fees.The action in the M&C will appropriate additional funding for Cromwell -Marine
Creek project (City Project No. 101012), as follows:
Fund
Existing
Additional Project Total
Funding
Funding
2018 Bond Program - Fund U34018
$0.00
$850,000.00 $850,000.00
2018 Bond Program - Fund 34018
$30,099,483.92
$0.00 $30,099,483.92
2022 Bond Program - Fund 34027
$10,970,000.00
$0.00 $10,970,000.00
Transportation Impact Fee Cap - Fund
$2 730,000.00
$0.00 $2,730,000.00
30108
Intergovernmental Contribution - Fund
$13,910,000.00
$0.00 $13,910,000.00
30106
�TaxNote2017 - Fund 34017
$500,000.00
$0.00 $500,000.00
Trans Impact Fee Cap Legacy - Fund
$270,000.00
$0.00I $270,000.00
39008
JProject Total
$58,479,483.92
$850,000.001$59,329,483.921
Funding for this Extra Work Change Order was not included in the Fiscal Years 2026-2030 Capital Improvement Plan. An additional $850,000.00
in funding is required to advance the extra work required by Change Order. The actions in this M&C will amend the Fiscal Years 2026-2030
Capital Improvement Program as approved in connection with Ordinance 27979-09-2025.
Funding is budgeted in the Authorized, Not Appropriated project within the 2018 Bond Program Fund within for the Transportation and Public
Works Department for the purpose of funding the Cromwell Marine Creek project.
The project is located in COUNCIL DISTRICTS 2 & 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Authorized, Not Appropriated project within the 2018 Bond Program Fund
and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the 2018 Bond
Program Fund for the Cromwell - Marine Creek project. Prior to an expenditure being incurred, Transportation & Public Works has the
responsibility to validate the availability of funds.
Submitted for Citv Manaaer's Office bv: Jesica McEachern 5804
Oriainatina Business Unit Head: Lauren Prieur 6035
Additional Information Contact:
Expedited
Monty Hall 8662