HomeMy WebLinkAbout26-0060 - 2026-05-05 - Informal ReportINFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 26-0060
�pf1TE7t$
18 7'a
To the Mayor and Members of the City Council
May 5, 2026
Page 1 of 4
SUBJECT: NEIGHBORHOOD STREET PROJECT TIMELINES AND
OVERSIGHT
The purpose of this Informal Report is to clarify why some pavement resurfacing programs in the
region may appear to progress more quickly than the City's bond -funded neighborhood street
reconstruction projects, and to outline the City's approach to contractor accountability, schedule
management, and time extensions.
Differences in Project Type and Scope
Many street resurfacing programs focus on surface -level pavement preservation, such as overlays
or mill -and -fill operations. These activities are limited in scope and do not involve underground or
structural improvements, allowing projects to be completed quickly. These projects are typically
funded with PayGo. These projects are the second tier of the pavement condition index. The first
tier is crack sealing (etc.) to preserve the longevity of otherwise well performing streets. This
second tier is where streets have deteriorated to a point beyond cosmetic repairs but only such
that a replacement of the asphalt is necessary. TPW and Water review such streets to determine
whether any pipe replacement work is required.
In contrast, the third tier of street condition is where the foundation and/or the city's water, sewer,
and/or stormwater infrastructure beneath the street have deteriorated so far that a rebuild is
required. City neighborhood bond projects are full reconstruction efforts requiring complex
engineering, coordination between departments and are typically funded by bond elections.
These projects address not only pavement condition but also the underlying infrastructure that
supports long-term neighborhood function and safety. Such projects typically include:
• Water and sanitary sewer replacements
• Stormwater improvements
• Curb and gutter
• Sidewalks and ADA-compliant ramps
• Driveway approaches and other concrete elements
Each of these components introduces additional sequencing, coordination, and inspection
requirements, extending the overall project duration beyond that of an asphalt surface replacement
project.
To further illustrate the difference, recent data shows that City neighborhood street bond projects
average approximately 430 calendar days for construction due to the full scope of work involved.
The contract duration for these projects is not arbitrary; it is determined during design based on
estimates of the work quantities and expected production rates. Staff evaluates the total scope
of work, including utility installation, concrete placement, and paving, and applies industry -
standard production rates (e.g., linear feet of pipe installed per day, square yards of concrete
placed per day) to estimate how much work can realistically be completed each day. These
production -based assumptions are then combined with project complexity, sequencing
constraints, and anticipated coordination needs to establish an overall contract time. As a
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 26-0060
�pf1TE7t$
18 7'a
To the Mayor and Members of the City Council
May 5, 2026
Page 2 of 4
SUBJECT: NEIGHBORHOOD STREET PROJECT TIMELINES AND
OVERSIGHT
secondary check, the total construction cost and the project's scale are also considered to ensure
the duration aligns with comparable projects and market conditions.
In comparison, asphalt resurfacing delivered through the City's Interlocal Agreement (ILA)
program with Tarrant County averages about 40 calendar days per lane mile, reflecting the limited
nature of surface -only work. Depending on the total lane miles included, joint City and County
ILA projects may be completed in as few as 24 days for smaller segments, while larger segments
may extend beyond 150 days. This variation reflects the scale and complexity of the work, rather
than contractor performance.
Residential Construction Constraints
Construction in residential areas requires maintaining continuous access for:
• Driveways
• Mail delivery
• Trash collection
• Emergency services
• School transportation
Work occurs within constrained right-of-way and often requires coordination with multiple private
utility providers. These conditions limit the amount of work that can occur simultaneously and
reduce opportunities to accelerate construction without increasing cost or risk.
Construction Sequencing and Paving Operations
For neighborhood street projects, contractors must complete underground utilities and all concrete
improvements before placing the final asphalt pavement. This sequencing prevents damage to
new pavement and ensures concrete has adequate time to cure.
Once a project is ready, asphalt paving is typically a short -duration and smooth process.
Contractors often pave multiple streets in a single mobilization to maximize efficiency and control
costs. Requiring paving to occur block -by -block would increase mobilization frequency and could
result in additional contract expenses.
Contractor Accountability and Schedule Management
The City enforces contractor performance through established contract requirements and active
project oversight. Each project includes a defined contract duration, and contractors are required
to maintain updated schedules throughout construction.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 26-0060
�pf1TE7t$
1875
To the Mayor and Members of the City Council
May 5, 2026
Page 3 of 4
SUBJECT: NEIGHBORHOOD STREET PROJECT TIMELINES AND
OVERSIGHT
City staff monitors performance through:
• Regular schedule reviews and updates
• Field inspections and progress tracking
• Coordination meetings with contractors and utility partners
• Written notices when progress falls behind schedule
When contractors fail to meet contract timelines, the City enforces contractual remedies, including
liquidated damages (LD). For neighborhood street projects, LDs are typically assessed at $650
per calendar day for delays beyond the approved contract time, unless additional time is justified
and approved through a formal change order.
Time Extensions — Recent Project Review
In response to concerns raised regarding time extensions, staff reviewed seven bond -funded
neighborhood street projects completed or nearing completion within the past year. Key findings
include an average time extension of 54 days, or approximately 13% of the total contract duration.
• Four projects required additional time due to unforeseen field conditions
• One project required additional time due to expanded sanitary sewer scope
• One project experienced delays due to utility conflicts requiring plan revisions
• One project experienced delays due to severe weather conditions
• One project required additional time due to a scope change associated with the Quiet Zone
improvements
It should be noted that one project experienced two different types of delays and is therefore
included in multiple categories above.
Time extensions are carefully evaluated and approved through formal change orders. Contractors
may continue working on other aspects of the project during this time, but minor extensions are
sometimes necessary to account for:
• Scope changes
• Design revisions
• Administrative processing
City staff thoroughly reviews each request to ensure it is fair, reasonable, and directly related to
required work. The goal is to minimize schedule impacts while maintaining quality and ensuring
the project is completed correctly.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 26-0060
�pf1TE7t$
18 7'a
To the Mayor and Members of the City Council
May 5, 2026
Page 4 of 4
SUBJECT: NEIGHBORHOOD STREET PROJECT TIMELINES AND
OVERSIGHT
Contractor Performance
The City actively tracks contractor performance across all capital projects. Based on recent project
reviews, there is no pattern of repeat underperforming contractors on neighborhood street bond
projects. Liquidated damages amounts are incorporated into every contract. When unjustified
delays occur, staff have withheld the daily amount from a contractor's retainage payout at the close
of a contract.
When performance issues arise, the City addresses them through contract -based remedies. These
may include issuing formal notices, withholding payment, or, when necessary, suspending or
terminating the contractor in accordance with contract provisions. In addition, contractor
performance may be considered during the procurement process. Contractors with poor
performance histories may not be recommended for award on future projects. Ultimately, the City
Council retains discretion in awarding contracts and may choose not to award contracts to
contractors who have not demonstrated satisfactory performance.
Moving Forward, the City Will Continue to:
• Enforce contract time and schedule requirements consistently
• Improve transparency in communicating schedules and updates to Council and residents
• Evaluate contract strategies that support accelerated delivery when appropriate
• Strengthen upfront planning and design to reduce the need for changes during construction
Summary
While some resurfacing programs progress more quickly, City neighborhood bond projects
involve significantly broader scope, deeper infrastructure improvements, and more
complex coordination requirements. These elements are essential to delivering durable,
long-lasting improvements that serve residents for decades.
The City remains committed to contractor accountability, transparent communication, and
continuous improvement in project delivery.
For additional information, please contact Lauren Prieur, Transportation and Public Works Director,
by e-mail to lauren.r)rieur(a.fortworthtexas.gov.
Jesus "Jay" Chapa
City Manager
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS