HomeMy WebLinkAbout064589-CO1 - Construction-Related - Contract - Cutler Repaving, Inc.CSC No. 64589-COl
FoR�N
City of Fort Worth
Change Order Request
Project Namel 2026 Holln Place Recycling Contract 1 City Sec # 64589
Client Project #(si 106169
Project Description) Hot -In -Place Asphalt Recycling providing street rehabilitation on S. Beach Street, James Avenue, NB McCart Avenue, and SB McCar1 Avenue. In addition,
replacing damaged curb and gutter, driveways, and non -compliant ADA ramps.
Conliacto Cutler Repaving, Inc. Change Order # 1 Dale 511/2026
City Project Merwen Ha(ez I City Inspectorl Brandon Gibson
Dept. I TPW I I I Totals
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (In M&C Process)
Contract Cost to Date
Original Funds Available for Change Orders
Remaining Funds Available for tNs CO
Additional Funding (d necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONQ AS % OFORIGINAL CONTRACT 3.26% 1
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 28%) $3.374,938.94
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: Furnish all labor and materials as specified in Change Order #1. This change orderwill add
three new bid items for the removal and replacement of existing concrete approach slabs along southbound McCort Avenue at Sycamore Creek. During construction, field
evaluations identified two existing approach slabs in significantly deteriorated condition that were not apparent during the planning phase. The slabs exhibit uneven surfaces and
distressed asphalt overlays, negatively impacting ride quality and posing a potential safety concern to the traveling public. The proposed work is necessary to address
unforeseen field conditions and ensure a safe, durable transition between pavement sections. Replacing the approach slabs at this time will also prevent the need for near -tern
maintenance repairs and avoid additional mobilization costs in the future. The new bid Items have been developed in accordance with applicable TxDOT Specifications,
Time Staff supports the contractor's request for an additional 21 calendar days to complete the expanded scope of work.
Cost Staff has reviewed the contractor's proposed unit prices, compared them with recent bid tabulations for comparable work and determined the pricing to be fair and
reasonable,
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or Incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, Including ensuring all performance and reporting requirements.
ContreoWs Nam _ _ _ Contractor ire
l a Con re
Cutler Re raw,• Inc. Charles R. Veskema
Ins ectorflns e,l n Supervisor
Data
ProW and Contract Coro Canoe Mar r
Date
I d ", p.L
-
05/05/2026
05/05/2026
' ►amMana r
Daka
swiof Capital ftied Officer
-Date
05/05/2026
05/05/2026
Asobtatill Director Do
Date
Difr' Contra ft Depsai ht Dpjo
Data
P Iric�ia L. Wads'zck (Mays G01616:28:25 CDT)
05/05/2026
?
05/06/2026
Assistant Cb
Date
Asslstml .
Date
05/08/2026
-„P -
05/16/2026
- -CouridlAcIlloriffroquiredi
44g40R n a M&C Number NIA
a �r F 000 . It
ATTEST LL BOA. d o 000 �pdd
dV8 0°=0
Jannette Goodall, City Secretary 0ia*g0 0oo*�d
�04 01o'0 s�pp
M&C Date Approved N)A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORT11 City of Fort Worth
V— Change Order Additions
Project Name 2026 Hot In Place RKydlng Contract 1 City Sec N 6/589
Client Ned N 106169
Cwt-actorl Cutler Repaving, Inc. PMJ Marwan Hafez tnspedor &andon c--h—
Change Order SubrniU N 0 Date F 51112026
ADDITIONS
Change Order Additions Page 2 of 3
Faris Woes fr City of Fort Worth
v--- Change Order Deletions
Project Name 1 2026 Hot In Place Recyding Contract 1 City Sec # 64589
Cknt Prood q 1 106169
Cary Cutler Repaving, Inc. PMI Manran Hafez Inspects 3randon CNDaon
Change Order Submittal Y 0 Date 511f2026
Change Order Deletions Page 3 of 3
FORT WORTH..
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 2026 Hot In -Place Recycling Contract 1
M&C: 25-1068 CPN: 106169 CSO: 64589 DOC#: CO#1
Date: 5/1/2026
To:
Name
Department
Initials
Date Out
1
Ann Estes (BSP)
TPW
AE
05/05/2026
2
Charles R. Veskerna/Cutler Repaving Inc.
Vendor
_C.L
05/05/2026
3
Brandon Gibson (Inspector)
TPW
96
BG
05/05/2026
4
Marwan Hafez (PM)
TPW
Pw
05/05/2026
5
Zelalem Arega (PGM)
TPW
05/05/2026
6
Mary Hanna (SCPO)
TPW
m�
05/05/2026
7
Patricia Wadsack (AD)
TPW
PLW
05/05/2026
8
Lauren Prieur (Director)
TPW
XXp prieur
05/06/2026
9
Doug Black (ACA)
Legal
oo
05/08/2026
10
Jesica McEachern (ACM)
CMO
05/16/2026
11
Jannette Goodall (CS)
CSO
nett
05/18/2026
12
TPW Contracts
TPW
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
ALSO List: - Bus Sppt: Ann Estes: Prg Mgr: Zelalem Area, Sr CPO: Mary Hanna
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and
take the next steps.
NEEDS TO BE NOTARIZED: [—]YES ®No
RUSH: DYES ®No SAME DAY: DYES ❑No NEXT DAY: DYES ®No
ROUTING TO CSO: ®YES ❑No
Action Required: ❑ Attach Signature, Initial and Notary Tabs
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
Return To: Please notify TPWContracts6ii�fortworthtexas.2ov for pickup when complete. Call ext. 7233 or ext.
8363 with questions. Thank you!
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Cutler Repaving, Inc.
Subject of the Agreement: Change Order No. 1 to CSC No. 64589, Contract for the 2026 Hot In Place
Recycling Contract 1 Project
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No 8
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 106169
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.