Construction Allowance Request
Project Name I Grand Ave Outfall City Sec # 1 59320
Client Project #(s)[ 103664/103665/C00969
Project This will be the continuation in Phase 2 which will include the installation of (3)-72" RCPs to connect the existing Grand Avenue line with the
Description I new outfall to the West Fork downstream of the isolation gates
Contractor[S.J. Louis Construction of Texas, LTD CA # 4 1 Date 4/1312026
City Project Mgr. I Max Aransen City Inspector Jeremy Koonce
UNIT or DEPT
Original Contract Amount
Extras to Date
Credits to Date
Current Contract Amount
Amount of Pr000sed Allocation
Original Allowance Available to Allocation
Allowance Funds Previously Allocated
Revised Allowance Balance
Storm Drain
Water Dept
UNIT 3 or Dept
UNIT 4 or Dept
Totals
21,114,746.00
1,635,338.50
22,750,084.50
21,114,746.00
1,635,338.50
$22,750,084.50
4,654.65
$0.00
$0.00
0.00
4,654.65
100,000.00
$50,000.00
1
150,000.00
79,812.34
8,994.34
$88,806.68
15,533.01
41,005.66
0.00
$0.00
$56,538,67
construction allowance is needed because the mat quantities shown on the plans do not match the actual discrete sizes of Armorflex mats and do not account for required
inations. Field installation requires using multiple smaller mats instead of a single continuous piece, which changes dimensions and adds termination areas. While this
stment slightly reduces coverage due to layout efficiency, the added terminations result in a net increase in material, requiring an additional44.3 SY. The only item in this
Dance is the "articulated concrete block" which is an already existing item from the original bid that will keep the same price as the original bid.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and
satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Construction
Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and
administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name
Contractor Name
Date
S.J. Louis Construction of Texas, LTD
Adam Lunsford
ADDAM LAN FORD(�AD, 15,5,, 202814:31:58 COT1
04/15/2026
Inspector/Inspection Supervisor
---------
Date
04/21/2026
Project and Contract Compliance Manage ii, Date
e 04/21/2026
Pr ram Manager
Date
Senior Capital Project Officer Date
04/21/2026
Assistant Director (Dept)
Date
Director, Contracting Department (Dept) Date
vide �� ,u ao - ar core
04/30/2026
Assistant City Attome
Date
Assistant City Manager Date
QC`c
ATTEST:
Ja nnette Goodall, City Secreta ry
nnu
9Fonr °aa
0, �i a
°a�a ax°a—
oQo*
aaaaIl�g456
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Construction Allowance SUMMARY
Page 1 of 4
FORT WORTH City of Fort Worth
' `* s Construction Allowance Additions
Project Name I Grand Ave Outfall City Sec # 9320
Client Project # I 103664/103665/C00969
Contractor S.J. Louis Construction of Texas, LTD PM Max Aransen Inspectorl Jeremy Koonce
Construction Allowance Submittal # F-47 Date 13 2026
r_R11]"191m,
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
15 9999.0000 Articulated Concrete Block Storm Drain 44.33 SY $105.00 $4,654.65
Storm Drain $4,654.65
Water Dept $0.00
UNIT 3 or Dept $0.00
UNIT 4 or Dept $0.00
Total Additions $4,654.65
Construction Allowance Additions
Page 2 of 4
FORT WORTH. City of Fort Worth
Construction Allowance Value
Project Name I Grand Ave Outfall City Sec #
Client Project # I 103664/103665/C00969
Contractorl S.J. Louis Construction of Texas, LTD Pivil Max Aransen Inspector Jeremy Koonce
Construction Allowance Submittal # Date
CONSTRUCTION ALLOWANCE VALUE BEING USED
ITEM
DESCRIPTION
Qty
Unit
Unit Cost
Total
53
9999.0009 Contingency Allowance (to cover the cost of improvements not
previously advertised. All Work completed under this shall be approved by
the City in writing.)
1.00
LS
$100,000.00
$100,000.00
Construction Allowance Value
3of4
M/SBE for this Construction Allowance Request
rrevious Construction Nuowance
Kequesis
CAR #
DATE
AMOUNT
1
10/21 /2024
$21,972.34
2
2/14/2025
$8,994.34
3
5/27/2025
$57,840.00
Total
$88,806.68
Construction Allowance MSBE Data
Page 4 of 4
Request . for Proposal
Project Name
C.M.R. -Proposal No.
Date
Grand Avenue Bypass Storm Drain (City Project #00969)
19
April 7, 2026
City of Fort Worth, Texas
Response Required By
Transmitted By
Max Aransen, P.E.
Ronald Etter
200 Texas Street
Project Manager
Fort Worth, Texas 76102
signature
Via Email
Rotwj& Etfer
M ax.Aransen(&fortworthtexas. gov
Description
This CMR is in reference to the Armorflex Mats required for protection of the outfall structure. The plan qty does not conform to the
discrrete size for the mats nor include the terminations required. Based on the explantion below there is an extra 44.3 SY ne eded.
The additional quantity comes from the terminations and that the dimensions shown on the design plans don't conform to the
discrete size of the mats, but because we're using two mats instead of one long one, it actually reduces the amount of block used.
Contributions from these factors are listed explicitly below, followed by detailed explanations for each.
Contributions of additional quantity by category:
Reduced quantity due to plan dimensions: -3.4 SYAdditionol quantity due to terminations: 44.3 SY
Detailed explanations:
Plan Dimensions The dimensions shown on the plans are 55.84' wide by 27.25' long, which is 1521.64 SF or just over 169 SY
(the quantity shown on the design plans) In the direction of the plan -view dimension indicated to be 55.84 , a minimum of
43 block widths of 1.3' is needed, or 55.9' In the direction of the plan -view dimension indicated to be 27.25, a minimum of
20 block lengths is needed, or 26.67' (not including a seam between mat ends of about 6") In this case, instead of using one
mat 32' long (includes terminations, explained below), we used two 16 foot mats (or one 16' and one 13.33 , again
explained below) This was for on -site ease of handling purposes The gap between the loop ends of the mats is assumed to
be about 6", but in practice can be anywhere between 4-8"; this is not a critical dimension. This reduces the ACB coverage
area by about 3.4 SY. This allowed the reduced number of blocks, 20, instead of the 21 that would have been necessary to
achieve the required coverage. This totals about 165.6 SY Terminations In the direction of the plan -view dimension
indicated to be 55.84, two -block terminations on each side add four block widths to the 55.9' from above, for a total of 47
block widths (this is depicted on our mat layout drawing as 7 mats that are 5 blocks wide, or 6.5, and 2 mats that are 6
blocks wide, or 7.8) This results in an overall width of 61. 1'(55.9'+ 5.2) In the direction of the plan -view dimension
indicated to be 27.25, two -block terminations on each side for a portion of the area (extending a minimum of 10' from the
side of the outlet structure) and on just one side for the rest of the area add different amounts, On each side of the outlet
structure, two mats totaling about 26' in width (13' on each side) add a total of 4 block lengths, resulting in a total length
of 32' (adds 2.67' on each end, for a total of 5.33' over that 26, for an added 138. E SF) For the rest, only 2 block lengths are
added downstream, and nothing is added at the interface with the outlet structure, resulting in a total length of 29.33'
(adds 2.57' on only one end of that 35.1 , for an added 93.7 SF) The quantity added for terminations is then the sum of
f[31.5' * 2.67] + [26' * 5.33] + (32' * 5.2 ]] = [93.7 SF] + [138.6 SF] + [166.4] = 398.8 SF, or about 44.3 SY. However, this
counts the corners twice; subtract 4 * (2.6 * 2.67) = 27.8 SF or about 3.1 SY The total quantity is then 165.6 + 44.3 - 3.1 =
206.8 SY (which is simplified to 207 SY)
Breakdown of Proposal
Grand Avenue Bypass Storm Drain & Sanitary Sewer Improvements
Additional Cost for Armorflex Mats
Item
Description
Quantity
Unit Price
Extension
15
9999.0000 Articulated Concrete Block
44.3
SY
$105.00
$4,654.65
Net Change :
$4,654.65
Additional Calendar Days:
If acceptable, please provide an authorization signature below and return one (1) copy to our office.
S.J. Louis Construction Action
xc: S. J. Louis Project No. 22305
S.J. Louis Construction of Texas Ltd
520 S. 6th Avenue
Mansfield, Texas 76063
(817) 477-0320 Office (817) 477-0552 Fax
FORTWORTH.
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: Grand Ave Outfall Construction Allowance 4
M&C: CPN: 103664,103665, CSO: 59320 DOC#:
C00969
Date:
To:
Name
Department
Initials
Date Out
I
Adam Lunsford
AdamL car SJLouis.Com
Contractor
AHL
AHL
04/15/2026
2.
Jeremy Koonce
TPW - Inspector
-�u
Jemmy Koonoe
04/21 /2026
3
1 Max Aransen
TPW - Project Manager
M
04/21/2026
4.
Thanaa H. Maksimos
TPW — Program Manager
TM
04/21 /2026
5.
Lissette Acevedo
TPW — Sr. CPO
C�v
04/29/2026
6.
Patricia Wadsack
TPW — Assistant Director
I>LW
04/30/2026
7.
Lauren Prieur
TPW - Director
�—
05/01/2026
g.
Doug Black
Legal - Assistant City Attorney
Bey
05/08/2026
9.
Jesica McEachern
CMO — Assistant City Manager
05/19/2026
10.
Katherine Cenicola
CSO — City Secretary
05/19/2026
11.
Jannette Goodall
CSO — City Secretary
05/19/2026
12.
Allison Tidwell
CSO — City Secretary"!
05/20/2026
13.
Tpw_SW_Contract
TPW Stormwater
CC: Program Manager — Thanaa Maksimos, Sr. CPO — Lissette Acevedo, TPW BSPAP Recon
Team — Cindy Sengathith
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ❑YES ®No SAME DAY: []YES ®No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: tpw sw contractsn,fortworthtexas.gov Call 817-229-3283 with questions. Thank you!
F I ORTWORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: S.J. Louis Construction of Texas
Subject of the Agreement: This Construction Allowance is required for net increase in material,
requiring additional material. The mat quantities shown on the plans do not match the actual
discrete sizes of Armorflex mats and do not account for reauired terminations.
M&C Approved by the Council? * Yes ❑ No x❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No x❑
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes x❑ No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No x❑ If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 04/25/2023
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No ❑x
*Ifso, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable.
103664/103665
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes x❑ No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be