HomeMy WebLinkAbout064641-CO1 - Construction-Related - Contract - Woody Contractor's Inc.CSC No. 64641-COl
FORT wowrH
Change Order Request
Project Name Water and Sanitary Sewer Replacements Contract 2020, WSM-D City Sec No. 64641
Project No.(s) 5600210600430107004301020043115740010 DOE No. N/A City Pro. No.1 103419
Project Water and Sanitary Sewer Replacements Contract 2020, WSM-D
Descrlpllon
Contfaclorl Woody contractors, Inc. Change Order 9 Dale: 4129I2026
City Project Mgr.1 Clayton Torrance City Inspector I Michael Barron
Phone Number: 817-392.8528 Phone Number: 682-210-7047
Dept.
Original Contract Amount
Extras to Date
Credits to Dale
Pending Change Orders (In M&C Process)
Contract Cost to Date
(Amount of Proposed Change Order
Revised Contract Amount
Orig. Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
Water Unit 1
Sewer Unit 2
Paving Unit 3
Storm Drain Unit
4
Totals
Conl(adThe
lcataodarDays)
$6,194,507.15
$2,322,886.00
$1,657.360.15
3157,460.00
$10,232.213.30
620
$2,322.886.00
$1,557,360.15
$157,460.00
$10,232,213.30
620
V114,507.15
$0.00
51,688,519,00
50.00
50.00
51,668,619,00
0150
6,194,507.15
$4,011,405.00
$1,557,360.15
$157,460.00
S11,920,732,30
770
$247,780.00 1 592,915.0 1 $71,868.00 1 515,746.00 1 5434,309.00
$247,780.00 $92,915.00 $77,868.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1 16.50a/o
S12, 990.266.63
JUSTIFICATION (REASONS) FOR CHANGE ORDER I
Change Order No, 1 will primarily provide for the abandonment and reroute of an existing 8" deteriorated
sewer main located in difficult to access easements between Hamilton Avenue and Potomac Avenue from
Lenox Drive to Monticello Drive.
Staff agrees with the contractor requested 150 additional days,
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It Is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
In full (both time and money) for all costs arising out of, or Incidental to, the above Change Order.
Contractor's Com om Name
Contractor Natne
Date.. _
Woody Contractors, Inc.
Troy Woody
�a -��
y 3P-x
Inspector
Project Manager. _ ..
Dale .
5/1 /202
Director Water Dept)
Co ruck Su ervisor TPW D
Date.
IV1
Senlorkiislani[CilyAllomay
Asslslanl Clt . Manager
Date
_G I(May 71. 2026163621 CDT)
Council Action If required)
M&C Number F-2-6-0-28-2---1 M&C Dale Approved
FORT WORTH City of Fort Worth
---az; - -
4,__ Change Order Additions
Project Name Water and Sanitary Sewer Re lacements Contract 2020, WSM D
City Sec No. 64641
Prcjecl No.(s) 66002/0600430/070043010200431/5740010 DOE No. N A CityPro. No. 103419
Project Description Water and Sanitary Sewer Replacements Contract 2020, WSM-D
Contractor Woody Contractors, Inc. Change Order # u Date: 4129/2028
City Project Mgr. Clayton Torrance City Inspector Michael Barron
annlTlnnlc
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Water and sanitary Sewer Replacements Contracl2020, WSM•D City Sec No. 64641
Project No.(s) 56002/0600430/0700430/0200431/5740010 DOE No, N/A City Pro. No. 103419
Project Description I Water and Sanitary Sewer Replacements Contract 2020. WSM•D
Contractor Woody Contractors, Inc. Change Order 40 Date 4/2912026
City Project Mgr. Clayton Torrance City Inspector Michael Barron
DELETIONS
Page 1 of 1
4/29/2026
CPN 103419
W&SS Replacement Contract 2020 WSM-D
Change Order 1 Notes
Staff has reviewed the request for additional calendar days and prices and considers
them to be fair and reasonable.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
rL /d2�:CLlZf�
Signa ure
Clayton M. Torrance, P.E.
Name of Employee
Professional Engineer
Title
nn
pad PORT IlCO
ATTEST: o== s
ma'°o
44 ,�10
V Qa�4b�aa5a'.o�
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas
Mayor and Council Communication
DATE: Tuesday, April 28, 2026 REFERENCE NO.: **M&C 26-0282
LOG NAME: 60WSSC20WSMDC01-WOODY
SUBJECT:
(CD 7) Authorize Execution of Change Order No. 1 in the Amount of $1,688,519.00 to a Contract with
Woody Contractors, Inc., for a Revised Contract Amount of $11,920,732.30 for the Water and Sanitary
Sewer Replacement Contract 2020, WSM-D Project and Adopt Appropriation Ordinance to Effect a Portion
of Water's Contribution to the Fiscal Years 2026-2030 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No. 1 in the amount of $1,688,519.00 and add an additional
150 days to City Secretary Contract No. 64641, a contract with Woody Contractors, Inc., for the
Water and Sanitary Sewer Replacement Contract 2020, WSM-D project for a revised contract
amount of $11,920,732.30; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water and Sewer Capital Projects Fund in the amount of $1,688,519.00, transferred from available
PayGo funds within the Water and Sewer Fund, for the purpose of funding the Water/Sanitary
Sewer Replacement Contract 2020, WSM-D project (City Project No. 103419) and to effect a portion
of Water's contribution to the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to approve execution of Change Order
No. 1 in the amount of $1,688,519.00 to a construction contract with Woody Contractors, Inc, for the Water
& Sanitary Sewer Replacement Contract 2020, WSM-D project (City Project No. 103419).
On December 9, 2025, by (M&C) 25-1143, the City Council authorized a construction contract with Woody
Contractors, Inc., in the amount of $10,232,213.30 for the Water & Sanitary Sewer Replacement Contract
2020, WSM-D project (City Secretary Contract No. 64641).
Change Order No. 1 will primarily provide for the abandonment and reroute of an existing 8" deteriorated
sewer main located in difficult to access easements between Hamilton Avenue and Potomac Avenue from
Lenox Drive to Monticello Drive. Relocating the sewer necessitates the installation of new sanitary sewer
mains into public right-of-way on the following streets:
Street
Fro
FTo
Lenox Drive
Potomac Avenue
Northeast 180 feet
Potomac Avenue
Lenox Drive
West 4th Street
Hamilton Avenue
Monticello Drive
West 630 feet
Monticello Drive
Hamilton Avenue
Northwest 150 feet
It is also necessary to reroute the existing sanitary sewer service lines that are currently connected to the
sewer main to be abandoned to the new sanitary sewer mains on Lenox Drive, Potomac Avenue and
Hamilton Avenue. Additionally, both Hamilton Avenue and Potomac Avenue will be repaved with asphalt
once sewer main installation and sewer service reroutes are complete.
It is the practice of the Water Department to appropriate its Capital Improvement Program (CIP) plan
throughout the Fiscal Year, instead of within the annual budget ordinance, as projects commence,
additional funding needs are identified, and to comply with bond covenants.
Funding is available in the Transfer to Water/Sewer account of the Water and Sewer Fund for the purpose
of funding the W/SS REPL Contract 2020 WSM-D project within the Water & Sewer Capital Projects Fund.
FY2026 - Water PAYGO Appropriations per City Ordinance 27979-09-2025
FY2026
Amended
FY2026
PayGo
YTD PayGo
FY2026
Original
(includes any
Approved
This M&C
Remaining
Adopted PayGo
council actions
for/Moved to
PayGo
subsequent to
Capital Projects
Balance
budget
adoption)
$101,090,082.00
$101,090,082.00
($45,773,977.00)
($1,688,519.00)
1$53,627,586.00
Note: There may be other pending actions or recently approved actions that are not reflected in the table
due to timing.
Appropriations for the W/SS REPL Contract 2020 WSM-D project are as depicted below:
Fund
Existing
Appropriations
Additional
Appropriations
project Total*
W&S Capital
Projects Fund
$10,148,947.00
$1,688,519.00
$11,837,466.00
56002
General
Capital
Projects Fund
$1,725,167.00
$0.00
$1,725,167.00
30100
Storm Water
Capital
Projects —
$192,049.00
$0.00
$192,049.00
Fund 52002
Project Total
$12,066,163.00
$1,688,519.00
$13,754,682.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund, and upon
approval of the above recommendations and adoption of the attached appropriation ordinance, funds
will be available in the W&S Capital Projects Fund for the W/SS REPL Contract 2020 WSM-D project to
support the execution of the change order. Prior to any expenditure being incurred, the Water Department
has the responsibility of verifying the availability of funds.
FUND IDENTIFIERS (FIDs),:
TO
Fund
Department
Accoun
Project
Program
ctivity
Budget
Reference #
mount
ID
I
ID
Year
(Chartfield 2)
FROM
Fund
Department
Accoun
Project
Program
ctivity
Budget
Reference #
mount
ID
I I
ID
I
Year
(Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by: Jesica McEachern (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Clayton Torrance (8528)
ATTACHMENTS
1. 1295 Form CO#1.pdf (CFW Internal)
2.60WSSC20WSMDC01-WOODY.pdf (Public)
3. 60WSSC20WSMDC01-WOODY FID Table (WCF 03.19.26)_(3).x1sx (CFW Internal)
4. 60WSSC20WSMDC01-WOODY funds avail.docx (CFW Internal)
5.ORD.APP 60WSSC20WSMDC01-WOODY 56002 A026(R2)_(2).docx (Public)
6. PBS CPN 103419.pdf (CFW Internal)
60WSSC20WSNIDCOI-WOODY FID T.W
i
Rec #
Fund
Dept tt
Account
Project ID Activity
FIDs
Budget CF 2
Year
(Budget)
Program Amount Purpose Xfer
FIDs
Actual
Rec #
Fund
Dept#
Account
Project ID Activity
Budget CF 2
Year
_
Program Amount Purpose 1Xfer
FIDs REVENUE
or EXPENSE
- No KK or GL Entries
Needed
Rec #
Fund
Dept #
Account (Project
ID Activity
Budget CF 2
Year
Program Amount
J
Purpose Xfer
CERTIFICATE OF INTERESTED PARTIES
FORM 1.295
1 of 1
Complete Nos. 1- 4 and 6 if there are interested parties.
OFFICE USE ONLY
Complete Nos. 1, 2, 3, 5, and 6 if there are no interested parties.
CERTIFICATION OF FILING
Certificate Number:
2026-1435010
1 Name of business entity filing form, and the city, state and country of the business entity's place
of business.
Woody Contractors, Inc.
Kennedale, TX United States
Date Filed:
03/18/2026
2 Name of governmental entity or state agency that is a party to the contract for which the forms
being filed.
City of Fort Worth
Date Acknowledged:
3 Provide the identification number used by the governmental entity or state agency to track or Identify the contract, and provide a
description of the services, goods, or other property to be provided under the contract.
103419 2020 WSM-D C01
Water, Sewer, Paving
4
Name of Interested Party
City, State, Country (place of business)
Nature of interest
(check applicable)
Controlling I
Intermediary
Woody, Troy
MANSFIELD, TX United States
X
Woody, Trent
MANSFIELD, TX United States
X
5 Check only if there is NO Interested Party. a
6 UNSWORN DECLARATION
My name is Troy Woody and my date of birth is
My address is 5413 Hidden Valley Ct Mansfield TX 76063 USA
(city) (state) (zip code) (country)
I declare under penalty of perjury that the foregoing is true and correct.
Executed in Tarrant County, State of Texas on the18th day of March 2026
(month) (year)
gn re o 1a� Ofri ed agen of<o tracting business entity
/ .(I:reclarant)
Forms provided by Texas Ethics Commission www.ethics.state.tx;us Version V4.1.0.b6ef2aab
FORTWORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Woody Contractors, Inc.
Subject of the Agreement:
Water and Sanitary Sewer Replacements Contract 2020, WSM-D
M&C Approved by the Council? * Yes 8 No ❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ 64641-CO1
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If zrnsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 4/28/2026
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes B No ❑
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103419
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
"Indicates the information is required and if the information is not provided the contract will be