HomeMy WebLinkAbout064679-CO1 - Construction-Related - Contract - Texas Materials Group, Inc.CSC No. 64679-COl FORT WORTH,,. City of Fort Worth Change Order Request Project Name 1 2026 Asphalt Resurfacing Contract 4 City Sec # 1 64679 Client Project #(s) 106167 Project Description Asphalt resurfacing providing street rehabilitation on S Hulen St and Bellaire Dr S using milling and overlaying. Contractor Texas Materials Group, Inc. Change Order # 1 Date 5/1/2026 City Project Mgr. I Marwan Hafez City Inspector Michael Perkins Dept. TPW Contract Time Totals CD Original Contract Amount $2,280,614.43 $2,280,614.43 210 Extras to Date $0.00 0 Credits to Date $0.00 0 Pending Change Orders (in M&C Process) $0.00 0 Contract Cost to Date $2,280,614.43 $2,280,614.43 210 Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1.28% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $2,850,768.04 210 IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL furnish all labor, materials, and equipment necessary to complete the work described in Change Order No.1. This change order adds a new bid item for the replacement of the existing concrete base repair item with high -early -strength (HES) concrete. This modification is necessary to address traffic impacts associated with ongoing construction on S. Hulen Street. Mill and overlay operations require repair of failed base areas prior to placement of the asphalt surface. The originally specified base repair material requires an extended curing time, which prolongs lane closures and contributes to traffic congestion and vehicle backups. The use of HES concrete will allow for accelerated curing, reduce the duration of lane closures, and improve overall traffic operations while minimizing safety risks to the traveling public. Field evaluations conducted during construction have also identified a greater extent of base failure than originally anticipated. Accordingly, the estimated quantity of base repair has been increased to 500 square yards to adequately address these conditions and ensure a stable and durable pavement structure. This change order also adds a new bid item to account for revised traffic control phasing. Modifications to the traffic control plan are necessary to better manage lane closures and maintain mobility along this high -volume corridor. These revisions include adjustments to construction phasing and the incorporation of after-hours work to reduce peak -period impacts, including during critical periods such as school zone operations. The added bid item covers the costs of implementing this revised traffic control approach. Cost: Staff has reviewed the contractor's proposed unit prices and compared them with pricing from recent, comparable projects. Based on this evaluation, the proposed pricing is determined to be fair and reasonable. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Contractor's Company Name Contractor Name Contract Si natur Texas Materials Group, Inc. Ronald D Stinson, Jr C1 6 05/11 /2026 Inspector/inspection Supervisor Date Project and Contract Compliance Manager AF Date x .0 05/05/2026 " ,, 05/14/2026 Program Manager Date Senior Capital Project Officer Date 05/14/2026 APS 05/14/2026 Date Director, Contracing De artment De AL ate Pa s 1105/14/2026 05/14/2026 Date Assistant City Manager Date 05/15/2026 05/28/2026 Council Action if required) 4,ag4UOL�n M&C Number N/A as` FORA LTT � OS °p0000 Y ATTEST: F.o Pv8 % °sd Jannette Goodall, City Secretary P0, *� aCQ�n�op°gaoa M&C Date Approved NIA OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH City of Fort Worth V— Change Order Additions Project Name 2026 Asphalt Resurfacing Contract 4 City Sec # 64679 Client Project # 106167 Contractor Texas Materials Group, Inc. PM Mangan Hafez Inspector Michael Perkins Change Order Submittal # A—J Dale 511I2026 AUDI HUNS ITEM DESCRIPTION DEPT Oty Unit Unit Cost Total 32 3.02 2 7" one Pvmt TP 5 0 5. 0 61 19999.000 Traffic Control Phasing ITPW I 40.00000000 EA I 5309.75 1 ,390.00 TPW S64,890.00 Sub Total Additions 64,890.00 Change Order Additions Page 2 of 3 FORTWORTH City of Fort Worth Change Order Deletions Project Name 2026 Asphalt Resurfacing Contract 4 City Sec # 64679 Client Project # 106167 Contractor Texas Materials Group, Inc. I PM Marwan Hafez Inspector Michael Perkins Change Order Submittal # O1 Date 51112026 DELETIONS Change Order Deletions Page 3 of 3 106167-CNCO-2026 Asphalt Resurfacing Contract 4 Final Audit Report 2026-05-23 Created: 2026-05-05 By: Andrea Munoz (Andrea.Munoz@fortworthtexas.gov) Status: Canceled / Declined Transaction ID: CBJCHBCAABAA-zKKerWIED_TBzWjZvgwGUcTBROf450D "'I 06167-CNCO-2026 Asphalt Resurfacing Contract 4" History � 3 Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov) 2026-05-05 - 2:52:06 PM GMT- IP address: 204.10.90.100 Document emailed to Ann Estes (ann.estes@fortworthtexas.gov) for filling 2026-05-05 - 3:07:46 PM GMT Document emailed to ronaid.stinson@texasmaterials.com for signature 2026-05-05 - 3:07:46 PM GMT Document emailed to Michael Perkins (Michael.Perkins@fortworthtexas.gov) for signature 2026-05-05 - 3:07:47 PM GMT Email viewed by Michael Perkins (Michael.Perkins@fortworthtexas.gov) 2026-05-05 - 3:08:03 PM GMT- IP address: 107.115.163.123 Document e-signed by Michael Perkins (Michael.Perkins@fortworthtexas.gov) Signature Date: 2026-05-05 - 3:23:59 PM GMT - Time Source: server- IP address: 107.115.163.123 Email viewed by Ann Estes (ann.estes@fortworthtexas.gov) 2026-05-05 - 4:26:48 PM GMT- IP address: 104.47.65.254 Form filled by Ann Estes (ann.estes@fortworthtexas.gov) Form filling Date: 2026-05-05 - 4:28:53 PM GMT - Time Source: server- IP address: 204.10.90.100 Email viewed by ronald.stinson@texasmaterials.com 2026-05-05 - 11:52:34 PM GMT- IP address: 174.246.130.178 '!Ii Email viewed by ronald.stinson@texasmaterials.com 2026-05-09 - 9:18:57 PM GMT- IP address: 47.161.7.93 FORTWORTH. "ll' Adobe Acraba#Sign 12 Email viewed by ronald.stinson@texasmaterials.com 2026-05-11 - 4:26:45 PM GMT- IP address: 170.85.100.101 C` Signer ronald.stinson@texasmaterials.com entered name at signing as RD Stinson Jr 2026-05-11 - 5:12:18 PM GMT- IP address: 170.85.100.101 c'y® Document e-signed by RD Stinson Jr (ronald.stinson@texasmaterials.com) Signature Date: 2026-05-11 - 5:12:20 PM GMT -Time Source: server- IP address: 170.85.100.101 -Signature Appearance Selected: IMAGE I„ Document emailed to Michael Glover (Michael.Glover@fortworthtexas.gov) for signature 2026-05-11 - 5:12:23 PM GMT Document emailed to Marwan Hafez (marwan.hafez@fortworthtexas.gov) for signature 2026-05-11 - 5:12:23 PM GMT Email viewed by Marwan Hafez (marwan.hafez@fortworthtexas.gov) 2026-05-11 - 5:19:15 PM GMT- IP address: 204.10.90.90 Email viewed by Michael Glover (Michael.Glover@fortworthtexas.gov) 2026-05-12 - 11:29:53 AM GMT- IP address: 104.47.64.254 Document e-signed by Michael Glover (Michael.Glover@fortworthtexas.gov) Signature Date: 2026-05-12 - 11:30:41 AM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: IMAGE 6 Document e-signed by Marwan Hafez(marwan.hafez@fortworthtexas.gov) Signature Date: 2026-05-14 - 4:41:36 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: DRAW Document emailed to Zelalem Arega (Zelalem.Arega@fortworthtexas.gov) for signature 2026-05-14 - 4:41:39 PM GMT t�l Email viewed by Zelalem Arega (Zelalem.Arega@fortworthtexas.gov) 2026-05-14 - 5:09:57 PM GMT- IP address: 104.47.65.254 6" Document e-signed by Zelalem Arega (Zelalem.Arega@fortworthtexas.gov) Signature Date: 2026-05-14 - 5:11:41 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: DRAW Document emailed to Mary Hanna (Mary.Han na@fortworthtexas.gov) for signature 2026-05-14 - 5:11:45 PM GMT !)`I Email viewed by Mary Hanna (Mary.Hanna@fortworthtexas.gov) 2026-05-14 - 5:57:59 PM GMT- IP address: 104.47.65.254 Document e-signed by Mary Hanna (Mary.Han na@fortworthtexas.gov) Signature Date: 2026-05-14 - 6:21:22 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: DRAW FORTWQRTIL P "e'wb' Adobe Acraba#Sign Document emailed to Patricia Wadsack (patricia.wadsack@fortworthtexas.gov) for signature 2026-05-14 - 6:21:24 PM GMT C` Signer Patricia Wadsack (patricia.wadsack@fortworthtexas.gov) entered name at signing as Patricia L. Wadsack 2026-05-14 - 8:27:53 PM GMT- IP address: 208.184.124.181 c Document e-signed by Patricia L. Wadsack (patricia.wadsack@fortworthtexas.gov) Signature Date: 2026-05-14 - 8:27:55 PM GMT - Time Source: server- IP address: 208.184.124.181 - Signature Appearance Selected: TYPE - Document emailed to Lauren Prieur (Lauren.Prieur@fortworthtexas.gov) for signature 2026-05-14 - 8:27:58 PM GMT Document e-signed by Lauren Prieur (Lauren.Prieur@fortworthtexas.gov) Signature Date: 2026-05-14 - 9:52:23 PM GMT - Time Source: server- IP address: 208.184.124.181 - Signature Appearance Selected: DRAW Document emailed to Lorita Lyles (Lorita.Lyles@fortworthtexas.gov) for approval 2026-05-14 - 9:52:27 PM GMT Email viewed by Lorita Lyles (Lorita.Lyles@fortworthtexas.gov) 2026-05-15 - 12:35:53 PM GMT- IP address: 104.47.64.254 C% Document approved by Lorita Lyles (Lorita.Lyles@fortworthtexas.gov) Approval Date: 2026-05-15 - 12:40:44 PM GMT -Time Source: server- IP address: 204.10.90.100 Document emailed to Douglas Black (Douglas.Black@fortworthtexas.gov) for signature 2026-05-15 - 12:40:48 PM GMT Document e-signed by Douglas Black (Douglas.Black@fortworthtexas.gov) Signature Date: 2026-05-15 - 10:59:34 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: DRAW ie Document emailed to Jesica McEachern Oesica.mceachern@fortworthtexas.gov) for signature 2026-05-15 - 10:59:37 PM GMT - . New document URL requested by ronald.stinson@texasmaterials.com 2026-05-19 - 1:14:54 PM GMT- IP address: 170.85.98.84 L ,, Document declined by Jesica McEachernOesica.mceachern@fortworthtexas.gov) �ay Decline reason: Unable to locate CSC 64679 in Laserfiche in order to verify CO 1. Please work with CSO to ensure the agreement is in the records system and then re-route this change order. Thank you, Jes 2026-05-23 - 4:43:18 AM GMT- IP address: 204.10.90.100 FoRTWaRTH. pa -dby Adobe Acraba#Sign 106167-CNCO-2026 Asphalt Resurfacing Contract 4 Interim Agreement Report 2026-05-26 Created: 2026-05-24 By: Andrea Munoz (Andrea.Munoz@fortworthtexas.gov) Status: Draft Transaction ID: CBJCHBCAABAAf2spa4GZIcR1mLDpFo774iYldUXKS3_h Agreement History Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will be generated when the agreement is complete. "106167-CNCO-2026 Asphalt Resurfacing Contract 4" History Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov) 2026-05-24 - 1:59:34 AM GMT- IP address: 204.10.90.100 F_ ORT WQRTH., I power¢d by Adobe Acrobat Sign FORT WORTH. Routing and Transmittal Slip Transportation & Public Works Department DOCUMENT TITLE: 2026 Asphalt Resurfacing Contract 4 M&C: 25-1067 CPN: 106167 CSO: 64679 DOC#: CO#1 Date: 5/1/2026 To: Name Department Initials Date Out 1 Ann Estes (BSP) TPW nAE 05/05/2026 2 Ronald D Stinson/Texas Materials G, Inc. Vendor 05/11 /2026 3 Michael Perkins (Inspector) TPW 05/05/2026 4 Marwan Hafez (PM) TPW N!1 05/14/2026 5 Zelalem Arega (PGM) TPW 05/14/2026 6 Mary Hanna (SCPO) TPW 05/14/2026 7 Patricia Wadsack (AD) TPW p(�/' 05/14/2026 8 Lauren Prieur (Director) TPW xxy Lauren Prieur 05/14/2026 9 Doug Black (ACA) Legal oou las Black � 05/15/2026 10 Jesica McEachern (ACM) CMO CM 05/28/2026 11 Jannette Goodall (CS) CSO teGoodall 05/28/2026 12 TPW Contracts TPW CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts ALSO List: - Bus Sppt: Ann Estes; Prg Mgr: Zelalem Arega; Sr CPO: Mary Hanna DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review and take the next steps. NEEDS TO BE NOTARIZED: DYES ®No RUSH: DYES ®No SAME DAY: DYES ❑No NEXT DAY: [—]YES ®No ROUTING TO CSO: ®YES ❑No Action Required: ❑ Attach Signature, Initial and Notary Tabs ❑ As Requested ❑ For Your Information ® Signature/Routing and or Recording ❑ Comment ❑ File Return To: Please notify TPWContracts(&fortworthtexas.gov for pickup when complete. Call ext. 7233 or ext. 8363 with questions. Thank you! FORT WORTH. City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: Texas Materials Group, Inc. Subject of the Agreement: Change Order No. 1 to CSC No. 64679, Contract for the 2026 Asphalt Resurfacing Contract 4 Project M&C Approved by the Council? * Yes ❑ No 8 If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes ❑ No 8 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes 8 No ❑ If unsure, see back page for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: If different from the approval date. Expiration Date: If applicable. Is a 1295 Form required? * Yes ❑ No 8 *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. 106167 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes 8 No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department.