HomeMy WebLinkAbout062381-CO2 - Construction-Related - Contract - The Fain Group, LLCCSC No. 62381-0O2
FORTWORTH® City of Fort Worth
*111�� Change Order Request
Project NameF ARPA Long Ave Pedestrian Improvements City Sec # 62381�
Client Project#(s) 104299
Project Intersection improvements along Long Avenue from Azle Ave to McKinley Ave. Includes new trees in the median, paving, sidewalks,
Description installation of traffic and pedestrian signals, median closures, extension of left -turn lanes, re -striping, and ADA ramps.
Contractor The Fain gnu , LLC Change Order # 2 Date 2/11/2026
City Project Mgr. Seth Cooksey City Inspector Erik Loza
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
TPW
Totals
Contract Time
(CD)
3,791,653.20
$3,791,653.20
365
$0.00
$3,882,188.20
$3,882,188.20
365
Amount of Proposed Change Order
$640,368.77
$640,368.77
80
Revised Contract Amount $4,522,556.97
Original Funds Available for Change Order
Remaining Funds Available for this CO $0.00
Additional Funding (if necessary) $640,368.77
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$4,522,556.97
445
$0.00
$640,368.77
19.28%
$4,739,566.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This Change Order No. 2 will allocate funding necessary for landscaping and irrigation installation work added to the project during construction phase of this
project. This change order also covers for the additional item for new 6" concrete driveway added to the project as well as the additional quantity of
sidewalk replacement. Additional asphalt pavement was replaced beyond what is needed for the median installation during construction due to condition of
asphalt pavement in the field, as a result additional pavement, curb and gutter items were needed for this change order.
All of the items in this change order are included in the original unit -price construction contract except the following:
Concrete Driveway (Special), LIVE OAK - 3" CAL, CEDAR ELM - 3" CAL, LACEBARK ELM - 3" CAL, SHREDDED HARDWOOD MULCH @ 2" DEPTH, 2" Meter Impact
Fee, Permanent Irrigation and TREE STAKING (3 POSTS).
The driveway, tree, mulch and staking costs have been reviewed and compared to similar items on other recently bid projects and/or the TxDOT online bid
repository and are considered to be reasonable. The Impact Fee costs are not determined by the contractor. Finally, the irrigation cost estimate provided by
the engineer is attached to this change order and is similar to the Contractor's proposed cost.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Nam Contractor (Name) Contract Signatur Date
The Fain Group, LLC Larry Frazier' 04/24/2026
r L� 05/01/2026 1��04/27/2026
Date I Senior Capital Project Officer Date
05/05/2026 1 - - 05/11/2026
Date
Director, Contracting Department (Dept)
Date
'a " `wad ark
Patricia L. Wadsack (May 14, 2026 15:24:34 CDT)
05/14/2026
d _?.
05/ 14/2026
Date
Assistant City Man
Date
oouoi�ais. xnze ia:oo:az cor
05/15/2026
rt
05/28/2026
a *on rnnp M&C Number 26-0175
a
ATTEST: _ $ 0 0p0 oa o�p9.i 0
Jannette Goodall, City Secretary Pp* sad
aaan�.......5ob
M&C Date Approved 03/10/2026
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
�7'--- Change Order Additions
Project Name ARPA Long Ave Pedestrian Improvements City Sec # 62381
Client Project# 104299
Contractor The Fain Group, LLC PM Seth Cooksey Inspector Erik Loza
Change Order Submittal # = Date 2/11/2026
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
2
Remove Sidewalks
0
240.00000000
SY
$52.00
$12,480.00
5
Remove Conc Pvmt
1,153.97000000
SY
$35.00
$33,602.46
6
Remove Asphalt Pvmt
2,823.60000000
SY
$16.00
$0.00
7
Remove Conc Curb & Gutter
6,257.00000000
LF
$14.00
$87,598.00
8
Remove Conc Valley Gutter
316.00000000
SY
$35.00
$11,060.00
9
Remove 24" Storm Line
243.00000000
LF
$59.00
$14,337.00
23
8" Flexible Base, Type A, GR-1
461.91000000
SY
$25.00
$11,547.75
24
2" Asphalt Pvmt Type D
2,725.91000000
SY
$26.00
$0.00
26
8" Asphalt Base Type B
491.63000000
SY
$79.00
$38,838.77
27
8" Conc Pvmt
42.66000000
SY
$117.00
$4,991.22
29
Conc Sidewalk, Adjecent to Retaining Wall
72.00000000
SF
$29.00
$2,088.00
31
6" Concrete Driveway
315.00000000
SF
$159.00
$50,085.00
37
9" Conc Valley Gutter, Residential
27.34000000
SY
$135.00
$3,690.90
38
6" SLID Pvmt Markings HAS (W)
2,329.90000000
LF
$3.00
$6,989.70
39
6" SLID Pvmt Markings HAS (W)
7,658.00000000
LF
$3.00
$22,974.00
41
8" SLID Pvmt Marking HAS (W)
99.00000000
LF
$4.00
$396.00
44
Performed Themoplastic Contrast Marking - 24" Crosswalk
60.00000000
LF
$57.00
$3,420.30
48
REFL Raised Marker TY II-C-R
183.00000000
EA
$8.00
$1,464.00
50
Remove 6" Pvmt Marking
987.00000000
LF
$6.00
$5,922.00
54
Conc Ret Wall Adjacent to Sidewalk
72.00000000
LF
$231.00
$16,632.00
56
Block Sod Placement
3,000.00000000
SY
$11.00
$33,000.00
82
Furnish/Install Ground Box Dtye D
1.00000000
EA
$2,560.00
$2,560.00
110
Traffic Control
3.00000000
MO
$3,452.00
$10,266.00
111
Integal Color/Stamped 4" Concrete Median
24,81460000
SY
$177.00
$4,392.18
118
Concrete Driveway (Special)
2,280.00000000
SF
$4.00
$9,120.00
119
LIVE OAK - 3" CAL
14.00000000
EA
$650.00
$9,100.00
120
CEDAR ELM - 3" CAL
14,00000000
EA
$650.00
$9,100.00
121
LACEBARK ELM - 3" CAL
14.00000000
EA
$650.00
$9,100.00
122
SHREDDED HARDWOOD MULCH @ 2" DEPTH
39.00000000
CY
$106.25
$4,143.75
123
TREE STAKING (3 POSTS)
39.00000000
EA
$62.00
$2,418.00
124
Permanent Irrigation
1.00000000
LS
$167,090.04
$167,090.04
125
2" Meter Impact Fee
2.00000000
EA
$25,981.00
$51,962.00
TPW
$640,368.77
Sub Total Additions
$640,368.77
Change Order Additions Page 2 of 3
FORTWORTH City of Fort Worth
1j* — Change Order Deletions
Project Name ARPA Long Ave Pedestrian Improvements City Sec # 62381
Client Project # 104299
Contractor The Fain Group. LLQ PM Seth Cooksey Inspector Erik Loza
Change Order Submittal# C� Date 2/11/2026
DELETIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
TP W $0.00
Sub Total Deletions $0.00
Change Order Deletions Page 3 of 3
City of Fort Worth,
Mayor and
Texas
Council Communication
DATE: 03/10/26 M&C FILE NUMBER: M&C 26-0175
LOG NAME: 20LONG AVE ARPA PEDESTRIAN SAFETY IMPROVEMENTS CO2
SUBJECT
(CD 2) Authorize Execution of Change Order No. 2, in the Amount of $640,368.77 and the Addition of 80 Calendar Days to the Construction
Contract with The Fain Group, LLC, fka The Fain Group, Inc., for Additional Scope Including Planting Trees, Irrigation, and Paving Items for the
Long Avenue ARPA Pedestrian Safety Improvements Project for a Revised Contract Amount of $4,522,556.97 (2022 Bond Program)
RECOMMENDATION:
It is recommended that the City Council authorize execution of Change Order No. 2 in the amount of $640,368.77 and the addition of 80 calendar
days to City Secretary Contract No. 62381, a construction contract with The Fain Group, LLC, fka The Fain Group, Inc., for additional scope
including planting trees, irrigation and paving items for the Long Avenue ARPA Pedestrian Safety Improvements project (City Project No.104299)
for a revised contract of $4,522,556.97.
DISCUSSION:
The purpose of this Mayor & Council Communication (M&C) is to authorize execution of Change Order No. 2, in the amount of $640,368.77, and
the addition of 80 calendar days, to the construction contract with The Fain Group, LLC, fka The Fain Group, Inc.
On November 12, 2024, M&C 24-0997 awarded City Secretary Contract No. 62381 to The Fain Group, Inc., in the amount of $3,791,653.20 for
the Long Avenue ARPA Pedestrian Safety Improvements project (City Project No. 104299). The project scope includes traffic signal replacement,
intersection improvements, extension of an existing westbound right -turn lane, median modifications, sidewalk extensions, accessible pedestrian
signals (APS), and Americans with Disabilities Act (ADA) ramps at multiple intersections along Long Avenue from Azle Avenue to McKinley
Avenue.
On June 2, 2025, The Fain Group, Inc. converted to The Fain Group, LLC and filed appropriate documentation with the Texas Secretary of State.
Change Order No. 1 in the amount of $90,535.00 to provide additional funding for construction services including manhole removal, portable
message boards, and additional electrical components is anticipated to be executed before this M&C is approved.
This Change Order No. 2 will allocate funding for the planting of trees, installation of irrigation, and additional paving work added during the
construction phase of the project.
Construction Contract7l
M&C
Date
Contract Amount
Original Contract
24-0997
11/12/20241
$3,791,653.20
Change Order 1 IlAdministrative
Pending
$90,535.00
Change Order 2
IThis M&C
Pending
$640,368.77
Revised Contract Amount
$4,522,556.97
This project is included in the 2022 Bond Program. The City's Extendable Commercial Paper (ECP) (M&C 22-0607; Ordinance 25675-08-2022)
provides liquidity to support the appropriation. Available resources will be used to actually make any interim progress payments until debt is
issued. Once debt associated with a project is sold, debt proceeds will reimburse the interim financing source in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance 25515-05-2022).
Funding for this project was included in the Fiscal Years 2026-2030 Capital Improvement Program. Funding is budgeted in the 2022 Bond
Program Fund for the Transportation and Public Works Department for the purpose of funding the ARPA Pedestrian Safety Improve project, as
appropriated.
The project is located in COUNCIL DISTRICT 2.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously appropriated, in the 2022 Bond Program Fund
for the ARPA Pedestrian Safety Improve project to support the execution of the change order. Prior to an expenditure being incurred, the
Transportation and Public Works Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by Jesica McEachern 5804
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662
Expedited
CERTIFICATE OF INTERESTED PARTIES
FORM 1295
lofl
Complete Nos. 1 - 4 and 6 if there are interested parties.
OFFICE USE ONLY
Complete Nos. 1, 2. 3, 5, and 6 if there are no interested parties.
CERTIFICATION OF FILING
Certificate Number:
1 Name of business entity filing form, and the city, state and country of the business entity's place
of business.
2026-1420311
The Fain Group LLC.
Fort Worth, TX United States
Date Filed:
02/12/2026
2 Name of governmental entity or state agency that is a party to the contract for which the form is
being filed.
City of Fort Worth
Date Acknowledged:
3 Provide the identification number used by the governmental entity or state agency to track or identify the contract, and provide a
description of the services, goods, or other property to be provided under the contract.
104299
Pedestrian Safety Improvements for Long Ave
4
Name of Interested Party
City, State, Country (place of business)
Nature of interest
(check applicable)
Controlling I
Intermediary
The Fain Group LLC., Larry Frazier
Fort Worth, TX United States
X
5 Check only if there is NO Interested Party, ❑
6 UNSWORN DECLARATION
My name is Larry Frazier and my date of birth is
My address is 2500 Great Southwest Parkway , Fort Worth TX , 76106 USA
(city) (state) (zip code) (country)
I declare under penalty of perjury that the foregoing is true and correct.
Executed in Tarrant County, State of Texas on the 12thday of February , 2026
(month) (year)
Signature of authorized agent of contracting business entity
(Declarant)
forms provicea Dy I exas ttnics commission www.ethlcs.state.tx.us Version V4.1.0.cd93a486
104299-CNCO-ARPA Long Ave Pedestrian
Safety Improvement CO#2
Final Audit Report 2026-05-22
Created: 2026-04-23
By: Andrea Munoz (Andrea. Munoz@fortworthtexas.gov)
Status: Canceled / Declined
Transaction ID: CBJCHBCAABAA4i93IfeEgiZQHTzu2rEXd2r9uz1PAzHY
"104299-CNCO-ARPA Long Ave Pedestrian Safety Improvemen
t CO#2" History
65 Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
2026-04-23 - 9:52:04 PM GMT- IP address: 204.10.90.100
Document emailed to LaKeshia Lynch (La Kesh ia. Lynch @fortworthtexas. gov) for filling
2026-04-23 - 10:07:20 PM GMT
Document emailed to Ifrazier@faingp.com for signature
2026-04-23 - 10:07:21 PM GMT
Document emailed to Erik Loza (erik.loza@fortworthtexas.gov) for signature
2026-04-23 - 10:07:21 PM GMT
Document emailed to Seth Cooksey(seth.cooksey@fortworthtexas.gov) for signature
2026-04-23 - 10:07:21 PM GMT
Email viewed by Seth Cooksey (seth.cooksey@fortworthtexas.gov)
2026-04-23 - 10:07:26 PM GMT- IP address: 51.54.38.120
Email viewed by LaKeshia Lynch (LaKeshia.Lynch@fortworthtexas.gov)
2026-04-23 - 10:22:54 PM GMT- IP address: 104.47.64.254
L=,6 Form filled by LaKeshia Lynch (LaKeshia.Lynch@fortworthtexas.gov)
Form filling Date: 2026-04-23 - 10:24:25 PM GMT - Time Source: server- IP address: 204.10.90.100
Email viewed by Ifrazier@faingp.com
2026-04-24 - 0:09:25 AM GMT- IP address: 172.225.18.110
D Email viewed by Erik Loza (erik.loza@fortworthtexas.gov)
2026-04-24 - 12:20:31 PM GMT- IP address: 166.205.58.57
FoRTWORTH. I "I'ledl:y
Adobe
Acrobat Sign
Signer Ifrazier@faingp.com entered name at signing as Larry Frazier
2026-04-24 - 1:04:33 PM GMT- IP address: 104.190.201.177
Document e-signed by Larry Frazier (Ifrazier@faingp.com)
Signature Date: 2026-04-24 - 1:04:35 PM GMT - Time Source: server- IP address: 104.190.201.177
Document e-signed by Seth Cooksey(seth.cooksey@fortworthtexas.gov)
Signature Date: 2026-04-28 - 3:12:12 AM GMT - Time Source: server- IP address: 86.62.28.240
D Email viewed by Erik Loza (erik.loza@fortworthtexas.gov)
2026-04-30 - 1:23:25 PM GMT- IP address: 51.54.38.123
Email viewed by Erik Loza (erik.loza@fortworthtexas.gov)
2026-05-01 - 7:08:56 PM GMT- IP address: 166.205.58.57
Document e-signed by Erik Loza (erik.loza@fortworthtexas.gov)
Signature Date: 2026-05-01 - 7:21:52 PM GMT - Time Source: server- IP address: 166.205.58.57
Document emailed to Chad Allen (Chad.Allen@fortworthtexas.gov) for signature
2026-05-01 - 7:21:56 PM GMT
` 6 Document e-signed by Chad Allen (Chad.Allen@fortworthtexas.gov)
Signature Date: 2026-05-05 - 3:24:30 PM GMT -Time Source: server- IP address: 204.10.90.100
Document emailed to Lissette Acevedo (Lissette.Acevedo@fortworthtexas.gov) for signature
2026-05-05 - 3:24:35 PM GMT
=1 Email viewed by Lissette Acevedo (Lissette.Acevedo@fortworthtexas.gov)
2026-05-05 - 4:14:07 PM GMT- IP address: 104.47.64.254
rc� Document e-signed by Lissette Acevedo (Lissette.Acevedo@fortworthtexas.gov)
Signature Date: 2026-05-13 - 4:48:53 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: IMAGE
- Document emailed to Patricia Wadsack (patricia.wadsack@fortworthtexas.gov) for signature
2026-05-13 - 4:48:57 PM GMT
p Signer Patricia Wadsack (patricia.wadsack@fortworthtexas.gov) entered name at signing as Patricia L.
Wadsack
2026-05-14 - 8:24:32 PM GMT- IP address: 208.184.124.181
LJQ Document e-signed by Patricia L. Wadsack (patricia.wadsack@fortworthtexas.gov)
Signature Date: 2026-05-14 - 8:24:34 PM GMT - Time Source: server- IP address: 208.184.124.181 - Signature Appearance Selected:
TYPE
lc, Document emailed to Lauren Prieur (Lauren.Prieur@fortworthtexas.gov) for signature
2026-05-14 - 8:24:38 PM GMT
FoRT'WORTH. Powered by
Adobe
Acrobat Sign
6 Document e-signed by Lauren Prieur (Lauren.Prieur@fortworthtexas.gov)
Signature Date: 2026-05-14 - 9:57:05 PM GMT - Time Source: server- IP address: 208.184.124.181 - Signature Appearance Selected:
DRAW
Document emailed to Douglas Black (Douglas.Black@fortworthtexas.gov) for signature
2026-05-14 - 9:57:09 PM GMT
r Document e-signed by Douglas Black (Douglas.Black@fortworthtexas.gov)
Signature Date: 2026-05-15 - 6:00:32 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: DRAW
-'v Document emailed to Jesica McEachern aesica.mceachern@fortworthtexas.gov) for signature
2026-05-15 - 6:00:37 PM GMT
Document declined by Jesica McEachern Qesica.mceachern@fortworthtexas.gov)
Decline reason: Please see e-mail to Andrea for revisions. Thank you, Jes
2026-05-22 - 5:30:31 PM GMT- IP address: 204.10.90.100
FoRTWQRTH. I Psweredisy
Adobe
Acrobat Sign
FORT WORTH1.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: ARPA Long Ave Pedestrian Safety Improvement CO#2
M&C: 26-0175
CPN: 104299 CSO: 62381 DOC#: 1
Date:
To:
Name
Department
Initials
Date Out
1.
Lakeshia Lynch
TPW
.�
04/23/2026
2.
Larry Frazier
Vendor
! `
04/24/2026
3.
Erik Loza
TPW
E
05/01/2026
4.
Seth Cooksey
TPW
04/27/2026
5.
Chad Allen
TPW
05/05/2026
6.
Lissette Acevedo
TPW
05/13/2026
7.
Patricia Wadsack
TPW AD
P(.tiV
05/14/2026
8.
Lauren Prieur
TPW Director
A9P,
05/14/2026
9.
Doug Black
Legal
�— ��
Douglas ack
05/15/2026
10.
Jesica McEachern
CMO
05/28/2026
11
Jannette Goodall
CSO
t
„eta teGoodall
05/28/2026
12
TPW Contracts
TPW
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
ALSO List: - Bus Sppt: Alexandra Ripley
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review
and take the next steps.
NEEDS TO BE NOTARIZED: DYES ❑No
RUSH: DYES ❑No SAME DAY: DYES ❑No NEXT DAY: DYES ❑No
ROUTING TO CSO: ❑YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
❑ Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: Please notify TPWContracts a)fortworthtexas.gov for pickup when complete. Call ext. 7233 or ext.
8363 with questions. Thank you!
F0 RT WO RT H
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: The Fain C=,rni Tn I I C:
Subject of the Agreement: Change Order No. 2 to CSC No. 62381, a Contract for the Long Avenue
Pedestrian Safety Improvements Project (2022 Bond Program)
M&C Approved by the Council? * Yes 8 No ❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
1295 Form (page 8) attached per comment below
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes 8 No ❑
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 104299
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.