HomeMy WebLinkAboutContract 40610-CO1 F"iwr W.Owrlm City of Fort worth CRY sEcRETARY o u�C -
Change Order Request CONTRACT NO.
• Project Name Water and Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge I City Sec No. 40610
Project No.(s P265-603170133287and P275-703170133287 I DOE No. 1 6338 City Pro.No. 01332
Project Description Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge Within the Union Pacific Railroad
Davidson Rail Yard,Part 2-Hulen Street Bridge and Water Main Extension from Hulen Street to Como Pump Station,Part 2
ContractDirl S.J. Louis Construction of TX, Ltd. Change Order# 1 1 Date: 1/25/2011
City Project Mgr.1 Liam Conlon City Inspector I Raymond Brice
Phone Number.1 817-392-6824 Phone Number. 817-392-8452
Dept. Water A-1 Water A-2 Sewer Totals Contract Time
Cabodar
Original Contract Amount 2, 410
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,958,606.73 2, $1,595,105.60 ,906,674.83 410
JAmount of Proposed ange r er
Revised Contrail Amount $1,958,60&73 4 410,
Original Funds Available for Change Orders $59,000.00 $71,000.00 F78;78 10 ,�--. 178,000.00
Remaining Funds Available for this CO 59,000.00 71,000.00 $178,000.00
Additional Funding('d necessary) ,� : .max- ,787.91 4 "� r=; 4=, 1
CHA NGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 10,9096 .
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $7, ,
The project Includes the installation of a 36/48 Inch water main to accommodate the construction of the new Hulen Street Bridge at the SH121T ross�ir+g
.The
construction of the Identified water main will require shutting down the existing water main in order to connect the new water main.
In order to maintain uninterrupted water service to residents and businesses in the vicinity that will be affected by the shut down,it is necessary to conduct the
following:
•The installation of an 84nch water main north of the Oak Park Lane/Overton Park west Intersection.
•The installation of a 10-inch water main and pressure plane valve to transfer water from the Southside II pressure plane boundary to the Holly pressure plane
boundary.
•The installation of 8 and 164nch water mains on Stonegate Boulevard. U x--00 A'Q
•The installation of an 84nch water main on Riverglen Drive. 'c *Oar ��
JCV 0 0QQ OOpop�O�O'
In addition,the change order will also allow for the relocations of the water and sanitary sewer mains that are In direct conflict with the~bfidg the CP
Fork Main Street/South Hulen Street intersection and grouting the casing pipe annual s�ratlons. 1�g
0 o o
o 0
0 y
O T
O� 000
It is understood and agreed that the acceptance of this Change Order by the con n action and re n
(both time and money)for all costs arising out of,or incidental to,the above Change Order. nannlwz 4
t �
S.J. Louis Construction of Tx, Ltd. Pete Stahl
W1 Max
d
Cdns
lo1�-1 L-ro x e-f-
OEMYOB` I1ii1sIw1{ Wwdw
OFFICIAL REC R& %
Coundl Action d
M&C Number 24699 M&C Date Approved
FO RT WO RT H City of Fort Worth
Change Order Additions
Project Name Water and Sewer Relocations for SH121T Crossing West of the Hulen Street Bride City Sec No. 1 40610
Project No.(s) P265-603170133287and P275-703170133287 DOE No. 6338 City Pro.No. 01332
Project Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge Within the Union Pacific Railroad _
Description I Davidson Rail Yard, a Z-Hulen ee t Bridge and Water am E sion from Hulen Street to Como Pump Station,Part 2
Contractor S.J. Louis Construction of TX, Ltd. Change Order# = Date: 1125/2011
City Project Mgr. Liam Conlon City Inspector Ra mond Brice
ADDITIONS
ITEM, DESCRIFTION. _.__;_ _,.. . . ._, n n osk
ISWPPP Water A-2 5.00 EA $1,000.00 $5,000.0(
18 JTrencF Safety Water A-2 1681.00 LF $0.01 $16.8'
19 Traffic Control Water A-2 4.00 EA $2,000.00 $8,000.0(
24 16-inch DI by open cut Water A-2 35.00 LF $150.00 $5,250.0(
25 12-inch DI by open cut Water A-2 15.00 LF $120.001 $1,800.0(
26 10-inch PVC by open cut Water A-2 86.00 LF $100.00 $8,600.0(
27 8-inch DI pressure pipe by open cut Water A-2 336.00 LF
$ $
28 84nch PVC pressure pipe Water A-2 1224.00 LF $100.00 $122,400.0(
29 6-inch water by open cut Water A-2 10.00 LF $30.00 $300.0(
30 3-inch water by open cut Water A-2 10.00 LF $25.00 $250.0(
31 16-inch connection-install Water A-2 2.00 EA $2,000.00 $4,000.0(
32 12-inch connection-install Water A-2 2.00 EA $3,000.00 $6,000.0(
33 10-inch connection-install Water A-2 2.00 EA $3,000.00 $6,000.0(
34 84nch connection-install Water A-2 5.00 EA $2,500.00 $12,500.0(
35 6-inch connection-install Water A-2 1.00 EA $3,000.00 $3,000.00
36 3-inch water by open cut Water A-2 1.00 EA $1,500.00 $1,500.0(
37 15-inch gate valve with vault Water A-2 3.00 EA $7,000.00 $21,000.0(
38 12-inch gate valve wth box Water A-2 2.00 EA $2,000.001 $4,000.00
39 10-inch gate valve with valve box Water A-2 2.00 EA $2,000.00 $4,000.00
40 10-inch pressure plane valve with box Water A-2 1.00 EA $18,750.00 $18,750.010
41 8-inch gate valve with valve box Water A-2 8.00 EA $1,500.00 $12,000.00
42 6-inch gate valve box with box Water A-2 1.00 EA $1,400.00 $1,400.00
43 Pipe fittings Water A-2 3.10 TN $1.00 $3.1 C
44 Abandon 8-inch water line with flowable fill Water A-2 300.00 LF $3.00 $900.00
45 84nch tapping sleeve and valve Water A-2 2.00 EA $3,500.00 $7,000.00
46 Concrete pavement-54nch min Water A-2 1800.00 LF $85.00 $153,000.00
47 Concrete sidewalk-install Water A-2 288.00 SF $6.00 $1,728.00
48 D-Hole Water A-2 1.00 EA $2,000.00 $2,000.00
49 Remove and replace concrete curb and gutter Water A-2 50.00 LF $25.00 $1,250.00
50 Concrete Encasement Water A-2 10.00 LF $100.00 $1,000.00
51 Casing pipe annular space grouting Water A-2 1444.00 LF $50.00 $72,200.00
14 Manhole Standard 4 ft diameter 0-6" Sewer 6.00 EA $3,400.00 $20,400.00
15 Manhole Standard 4 ft dia additional depth Sewer 25.00 VF $85.00 $2,125.00
17 Concrete collar-manhole Sewer 6.00 EA $350.00 $2,100.00
18 Manhole-vacuum test Sewer 6.00 EA $200.00 $1,200.00
22 Cut and plug existing sanitary sewer Sewer 4.00 EA $3,0007 $12,000.00.
23 Ins lion reconstruction cleaning and TV Sewer 390.00 LF $1.75 $682.50
24 Inspecton-post construction cleaning Sewer 600.00 LF
$1.50 $900.00
30 Traffic control Sewer 1.00 LS $2,000.00 $2,000.00
35 ITrench safety Sewer 600.00 LF
$0.01 $6.00
36 Pavement-5 inch min.concrete Sewer 600.00 SY $50.00 $30,000.00
37 10-inch SS by open cut Sewer 415.00 LF $100.00 $41,500.00
38 8-inch SS by open cut Sewer 185.00 LF 75.00
Water A-2 $516,767.91
Sewer $126,788.50
Page 2 of 4 Additions Sub Total 1 $657,431.41
.F0 RT WORTH City of Fort Worth
Change Order Deletions
Project Name Water and Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge City Sec No. 40610
Project No.(s) P265-603170133287and P275-703170133287 DOE No. 6338 City Pro.No. 01332
Project-De otinn Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge Within the Union Pacific
Railroad son Rau Yara,Part 2-7ruTen SITURe a and Water Main ension from Hulen Street to Como Pump
Contractor S.J.Louis Construction of TX,Ltd. Change Order#1E Date 1/25/2011
City Project Mgr. Liam Conlon City Inspector FRaymond Brice
DELETIONS
ITEM DESCRIPTION k . DEPT-; ,.. Unt��, Unit Co>�- '� ;
Water A-1
Water A-2
Sewer
Page 3 of 4 Deletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00.
Previous Change Orders
CO# DATE. AMOUNT.
Total $0.00
Official site of the City of Fort'North,Tcxas
CITY COUNCIL AGENDA FORT it
COUNCIL ACTION: Approved on 1/25/2011
DATE: 1/25/2011 REFERENCE NO.: **C-24699 LOG NAME: 6040610001-
SJLOUIS
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Change Order No. 1 in the Amount of$643,556.41 to City Secretary Contract
No. 40610 with S.J. Louis Construction of TX, Ltd., for Water and Sanitary Sewer
Relocations for SH121T Crossing West of the Hulen Street Bridge within the Union
Pacific Railroad Davidson Rail Yard, Part 2-Hulen Street Bridge and Water Main
Extension from Hulen Street to Como Pump Station, Part 2 (COUNCIL DISTRICT 3)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Change Order No. 1
in the amount of$643,556.41 to City Secretary Contract No. 40610 with S.J. Louis Construction of
TX, Ltd., for Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street
Bridge within the Union Pacific Railroad Davidson Rail Yard, Part 2-Hulen Street Bridge and Water
Main Extension from Hulen Street to Como Pump Station, Part 2, thereby increasing the contract
amount to $6,550,231.24.
DISCUSSION:
On July 20, 2010, (M8,C C-24358)the City Council authorized the City Manager to execute a contract
in the amount of$5,906,674.83 with S.J. Louis Construction of TX, Ltd., for Water and Sanitary
Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge within the Union Pacific
Railroad Davidson Rail Yard, Part 2-Hulen Street Bridge and Water Main Extension from Hulen
Street to Como Pump Station, Part 2.
The project includes the installation of a 36/48 inch water main to accommodate the construction of
the new Hulen Street Bridge at the SH121T crossing. The construction of the identified water main
will require shutting down the existing water main in order to connect the new water main.
In order to maintain uninterrupted water service to residents and businesses in the vicinity that will be
affected by the shut down, it is necessary to conduct the following via Change Order No. 1:
The installation of an eight-inch water main north of the Oak Park Lane/Overton Park west
intersection.
The installation of a 10-inch water main and pressure plane valve to transfer water from the
Southside II pressure plane boundary to the Holly pressure plane boundary.
The installation of eight and 16-inch water mains on Stonegate Boulevard.
The installation of an eight-inch water main on Riverglen Drive.
In addition, the change order will also allow for the relocations of the water and sanitary sewer mains
that are in direct conflict with the proposed bridge at the Clear Fork Main Street/South Hulen Street
intersection and grouting the casing pipe annular space at all tunnel locations.
Staff considers the change order amount to be fair and recommends approval.
M/WBE - S.J. Louis Construction of TX, Ltd., is in compliance with the City's M/WBE Ordinance by
committing to an additional 66 percent M/WBE participation on this Change Order No. 1. The City's
goal on this change order is 10 percent.
Logname: 604061000I-SJLOUIS Page 1 of 2
This project is located in COUNCIL DISTRICT 3.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
bud apttal-Pfaj
TO Fund/Account/Centers FROM Fund/Account/Centers
P275 541200 703170133287 $126,78at50
P265 541200 603170133287 $516,767.91
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: S. Frank Crumb (8246)
Additional Information Contact: Liam Conlon (6824)
ATTACHMENTS
604061000l-SJLOUIS MAP.pdf
Logname: 604061000 I-SJLOUIS Page 2,-gf 2,