HomeMy WebLinkAbout28444-04-2026 - City Council - OrdinanceORDINANCE NO.28444-04-2026
AN ORDINANCE INCREASING ESTIMATE RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $1,688,519.00, TRANSFERRED FROM AVAILABLE
PAYGO FUNDS IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF
FUNDING THE WATER/SANITARY SEWER REPLACEMENT CONTRACT
2020, WSM-D PROJECT (CITY PROJECT NO. 103419); PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
FORT WORTH, TEXAS THAT:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2025-
2026 in the Budget of the City Manager, there shall also be increased estimate receipts and appropriations in
the Water and Sewer Capital Projects Fund in the amount of $1,688,519.00, transferred from available PayGO
funds in the Water and Sewer Fund, for the purpose of funding the Water/Sanitary Sewer Replacement
Contract 2020, WSM-D project (City Project No. 103419).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative
or void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no
way impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27979-09-2025 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (May 21, 2026 17:12:04 CDT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED: April 28,2026
EFFECTIVE: April 28,2026
Jannette S. Goodall
City Secretary
Al 00 00000o 0
0
1
0
'C7 0
0 0 N00
0
0�0
0
0 o 00-40.
. umo
-0
N40000000 000 .4y
?*x
Ordinance No.
28444-04-2026
Page 1 of 1
MAYOR ANNC� COI IpO I .%N t1Y0N MAP
N c
60WSSC 0 CO
o o � 1 i
WHITE SETTLEMENT
ry � ON
r-
rti
POSED
N. SANITARY RO
3_ �SE ER aim
d 9��MAIN Q
Z 'POTOMAC AVE\ �' eR/5+p T V
O<
r _
��4 � _ '" ' •� j� -, , lye, �""` � . � � � �.� � I�
LENOX DR `; D
r " O ,� - -
} 4' Z
y,G _ W 4TH ST m
Z
PROP
�r
SANITARYSEWEREWER W t �.I, d��.J'- W 1_ r F
$TH ST� EXISTING SANITARY
J - s-s tiys SEWER MAIN TO BE
y
F _
ABANDONED
1. f
m..,�L W 6TH ST-.`
Ll
FORT WORTHo _
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 04/28/26 M&C FILE NUMBER: M&C 26-0282
LOG NAME: 60WSSC20WSMDC01-WOODY
SUBJECT
(CD 7) Authorize Execution of Change Order No. 1 in the Amount of $1,688,519.00 to a Contract with Woody Contractors, Inc., for a Revised
Contract Amount of $11,920,732.30 for the Water and Sanitary Sewer Replacement Contract 2020, WSM-D Project and Adopt Appropriation
Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-2030 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No. 1 in the amount of $1,688,519.00 and add an additional 150 days to City Secretary Contract No.
64641, a contract with Woody Contractors, Inc., for the Water and Sanitary Sewer Replacement Contract 2020, WSM-D project for a revised
contract amount of $11,920,732.30; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $1,688,519.00, transferred from available PayGo funds within the Water and Sewer Fund, for the purpose of funding the
Water/Sanitary Sewer Replacement Contract 2020, WSM-D project (City Project No. 103419) and to effect a portion of Water's contribution
to the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to approve execution of Change Order No. 1 in the amount of $1,688,519.00 to a
construction contract with Woody Contractors, Inc, for the Water & Sanitary Sewer Replacement Contract 2020, WSM-D project (City Project No.
103419).
On December 9, 2025, by (M&C) 25-1143, the City Council authorized a construction contract with Woody Contractors, Inc., in the amount of
$10,232,213.30 for the Water & Sanitary Sewer Replacement Contract 2020, WSM-D project (City Secretary Contract No. 64641).
Change Order No. 1 will primarily provide for the abandonment and reroute of an existing 8" deteriorated sewer main located in difficult to access
easements between Hamilton Avenue and Potomac Avenue from Lenox Drive to Monticello Drive. Relocating the sewer necessitates the
installation of new sanitary sewer mains into public right-of-way on the following streets:
II Street
IlLenox Drive
IlPotomac Avenue
IlHamilton Avenue
IlMonticello Drive
From
Potomac Avenue
Lenox Drive
Monticello Drive
Hamilton Avenue
To
Northeast 180 feet
West 4th Street
West 630 feet
Northwest 150 feet
It is also necessary to reroute the existing sanitary sewer service lines that are currently connected to the sewer main to be abandoned to the new
sanitary sewer mains on Lenox Drive, Potomac Avenue and Hamilton Avenue. Additionally, both Hamilton Avenue and Potomac Avenue will be
repaved with asphalt once sewer main installation and sewer service reroutes are complete.
It is the practice of the Water Department to appropriate its Capital Improvement Program (CIP) plan throughout the Fiscal Year, instead of within
the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants.
Funding is available in the Transfer to Water/Sewer account of the Water and Sewer Fund for the purpose of funding the W/SS REPL Contract
2020 WSM-D project within the Water & Sewer Capital Projects Fund.
FY2026 - Water PAYGO Appropriations per City Ordinance 27979-09-2025
FY2026
Amended
PayGo
FY2026 Original (includes any
Adopted PayGo council actions
subsequent to
budget
adoption)
YTD PayGo
Approved This M&C
for/Moved to
Capital Projects
FY2026
Remaining
PayGo
Balance
I1$101,090,082.0011$101,090,082.0011($45,773,977.00)1I($1,688,519.00)I1$53,627,586.001I
Note: There may be other pending actions or recently approved actions that are not reflected in the table due to timing.
Appropriations for the W/SS REPL Contract 2020 WSM-D project are as depicted below:
Fund
Existing Additional Project Total*
Appropriations
Appropriations
W&S Capital
Projects Fund
$10,148,947.00
$1,688,519.00 $11,837,466.00
56002
General Capital
Projects Fund
$1,725,167.00
$0.00 $1,725,167.00
30100
Storm Water
Capital Projects —
$192,049.00
$0.00 $192,049.00
Fund 52002
(Project Total $12,066,163.00 $1,688,519.00 $13,754,682.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund, and upon approval of the above recommendations
and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the W/SS REPL Contract 2020
WSM-D project to support the execution of the change order. Prior to any expenditure being incurred, the Water Department has the responsibility
of verifying the availability of funds.
Submitted for Citv Manaaer's Office bv: Jesica McEachern 5804
Oriainatina Business Unit Head: Chris Harder 5020
Additional Information Contact: Clayton Torrance 8528