HomeMy WebLinkAboutContract 40610-CO4 CITY SECRLET�olQ,o CONTRACT N0. FORT WORTH['H City of Fort Worth Change Order Request Project Name I Water and Sanitary Sewer Relocations for SH121T Crossing West of Hulen Bridge City Sec No. 40610 Project No.(s) P265-603170133287 and P275-703170133287 I DOE No. 6338 City Pro.No. 01332 Project Description Water and Sanitary Sewer Relocations for SH121 Crossing West of the Hulen Street Bridge within the UPRR Davidson Rail Yard Part 2-Hulen Street Bridge and Water Main Extension to Como Pump Station,Part 2 Contractorl S.J.Louis Construction of Tx,Ltd. Change Order# ® Date: 12/21/2012 City Project Mgr.1 Liam Conlon City Inspector I Raymond H.Brice Phone Number:1 817-392-6824 Phone Number: 817-319-7943 Dept. Water Al Water A2 Sewer Totals Contract Time (Calendar days) Original Contract Amount $1,958,606.73 $2,352,962.50 $1,595,105.60 410 Extras to Date $98,134.51 $834,289.33 $224,436.54 ,I " 44 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date :_ � # � f lf .$ 2.E Amount of Proposed Change Order 014 Revised Contract Amount ,. Original Funds Available for Change Orders $50,000.00 $80,000.00 $48,000.00 Remaining Funds Available for this CO Additional Funding(if necessary) �• CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) The change order will provide additional pay items for the following: • The removal and reinstallation of a project sewer tunnel across Vickery Boulevard due to survey error by City forces that placed the tunnel 15 feet off the intended location. • The removal of a previously unknown abandoned 36-inch steel pipe that was encountered in direct conflict with a project sewer tunnel across Union Pacific Railroad. • Emergency repair of a recently installed project main that broke apart due to excessive pressure on the line and necessitated the replacement of a 12-inch gate valve and related appurtenances. The water main had passed City testsg n service. a-0" ORT �4 Staff concurs with the contractor'sppe�b4 P94t {inal calendar days on this change order. At 00d br- Q�° o V C 0 0 t isaahan r I actor constitutes an accord and satisfaction and represents payment in (both time nd )for all costs arising out ir4' ntal to�b@ aboohange Order. S.J.Louis Consstruction of TX,Ltd Jus F itrran 1 ?�S �. - �-- —�a l2— ORD M&C Number N/A M&C Date Approved Y SECRE RY FT.WORTH, TX FORT WC>a`FH City of Fort Worth Change Order Additions Project Name Water and Sanitary Sewer Relocations for SH121T Crossing West of Hulen Bride City Sec No. 1 40610 Project No.(s) P265-603170133287 and P275-703170133287 DOE No. 6338 City Pro.No. 01332 Project Water and Sanitary Sewer Relocations for SH121 Crossing West of the Hulen Street Bridge within the UPRR Davidson Rail Description Yard,Part 2-Hulen Street Bridge and Water Main Extension to Como Pump Station,Part 2 Contractor S.J.Louis Construction of Tx,Ltd. Change Order# ® Date:F 2/2112012 City Project Mgr. Liam Conlon City Inspector -Raymond H.Brice ADDITIONS DESCRIIIIIINTION DEPT Unit Uni Cost Total 43 lRemove and Re-Install the SS-1 Tunnel Under Vickery Sewer 1.00 LS $8,745.75 $8,745.75 emove Existing "Steel Pipe in Proposed "Tunnel Sewer 1.00 LS $15,180.00 $15,180.00 Emergency Leak Repair Water Al 1.00 LS $34,206.47 $34,206.47 Water Al $34,20647 Water A2 Sewer $23,925.75 Additions Sub Total $58,132.22 Page 2 of 4 FORT WORTH City of Fort Worth Change Order Deletions Project Name Water and Sanitary Sewer Relocations for SH121T Crossing West of Hulen Bridge City Sec No. 40610 Project No.(s) P265-603170133287 and P275-703170133287 I DOE No. E338 City Pro. No. 01332 Project Description Water and Sanitary Sewer Relocations for SH121 Crossing West of the Hulen Street Bridge within the UPRR Davidson Rail Yard Part 2-Hulen Street Bridge and Water Main Extension to Como Pump Station Part 2 Contractor S.J. Louis Construction of Tx, Ltd. Change Order#[E Date 2/21/2012 City Project Mgr. Liam Conlon City Inspector Raymond H. Brice DELETIONS DESWUPT10N DEPT Qty JUnlftt Unk Cod otad 20 Pipe- Pressure-Extra Depth Greater Water Al 300.00 VF $$1.00.50 $4,204.50 $3,000.00 26 Inspection-Post Construction Clean and TV Water Al 2803.00 LF $1 13 Pipe-Pressure-Extra Depth Greater Water A2 250.00 VF $10.00 $2,500.00 23 Inspection-Post Construction Clean and TV Water A2 1894.00 LF $1.50 $2,841.00 12 Remove and Salvage Gate Valve Water Al 2.00 EA $5,000.00 $10,000.00 14 Manhole-Std 4-foot Diameter(to 6 foot) Sewer 6.00 EA $3,400.00 $20,400.00 Water Al $1720450 Water A2 $5,341.00 Sewer $20,400.00 Page 3 of 4 Deletions Sub Total $42,945.50 MMBE Breakdown for this Change Order MME Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders BATE AOUivT ;; Total 0.0