HomeMy WebLinkAbout064130-CO1 - Construction-Related - Contract - C. Green ScapingCSC No. 64130-COl FORT WORTH. City of Fort Worth — Change Order Request Project Name I Streams & Valleys Plaza City Sec # 64130 Client Project #(s) 104094 Project Description Construction of the new Streams & Valleys Plaza off of Phyllis J. Tilley Pedestrian Bridge Contractor C. Green Scalping Change Order # 1 Date 4/15/2026 City Project Mgr. I Jessica Alvarado City Inspector Andre Taylor Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date PARD Totals Contract Time (CD) $906,528.80 $906,528.80 180 $0.00 $0.00 $906,528.80 $906,528.80 1 180 Amount of Proposed Change Order 1 $8,990.24 1 1 1 1 $8,990.24 1 0 Revised Contract Amount $915,519.04 $915,519.04 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding (if necessary) $8,990.24 $8,990.24 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.99% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $1,133,161.00 JUSTIFICATION (REASONS) FOR CHANGE ORDE The contractor is needing to put in a non -slip grate (4 sheets that 1/2" x 38-1/2" x 142-1/2") on top of a shallow active Sewer line where the new sidewalk runs over it. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Contractor's Company Name Contractor (Name) Contract Signature D C. Green Scaping Carson Green frUi Y &&Pt/ c rson creep rJuo 3 202s :4 :32 QQT7 Inspector/Inspection Supervisor Project and Contract Compliance Manager Date Andre Taylor Z'�°G`�' Program Manager FEEDate Senior Capital Project Officer Date sit e i ct r (Dept) c ing Departme Teresa Thomason (Jun 4. 2026 1631 45 CDT) Date Assistant City Attorney Date Assistant City Manager Date Dana Bur-I'idoff I Jun 5 2V9416:4£t:� 1 Council Action (if required) o�� M&C Number N/A M&C Date Approved NIA e ATTEST: ia�c.� A S1a."� .,tSz �3i�� ® Kabfaiu �'�urrPa OFFICIAL RECORD Jannette Goodall, City Secretary CITY SECRETARY FT. WORTH, TX FORTWORTH City of Fort Worth V1--- Change Order Additions Project Name Streams & Valleys Plaza City Sec # 64130 Client Project # 104094 Contractor C. Green Scaping PM Jessica Alvarado Inspector Andre Taylor Change Order Submittal # = Date 411512026 ADDITIONS ��ylr�rrs►•rFsarn:�rlrirr�fn�ra�►c���rs�r`�rcicbrf�al{7Cybri�]Y� • �yy�.��r�r�r�r�r�r�r�w�:���16� ��16�9 .99024 Sub =Total Addifinns 78 Change Order Additions Page 2 of 4 FoRT-?WORTH City of Fort Worth Change Order Deletions Project Name Streams & Valleys Plaza City Sec # 64130 Client Project # 104094 Contractor C. Green Scaping PM Jessica Alvarado Inspector Andre Taylor Change Order Submittal # Date 4/1512026 Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO N/A Total $0.00 Previous Change Orders CO # DATE AMOUNT Total $0.00 Signature: 7�2 Email: andre.taylor@fortworthtexas.gov FORT WORTH. City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: C Green Scaping Subject of the Agreement: Change Order #1 for A Metal Grate to protect active Sewer Line on Site. M&C Approved by the Council? * Yes ❑ No M If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes ❑ No 0 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes ❑ No 0 If unsure, see backpage for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: If different from the approval date. Expiration Date: If applicable. Is a 1295 Form required? * Yes ❑ No 21 *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. 104094 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes 0 No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department.