HomeMy WebLinkAbout064158-A2 - Construction-Related - Contract - Tarrant CountyAMENDMENT NO.2 TO AGREEMENT Meacham Airport Field Maintenance Facility Project— Design Build STATE OF TEXAS 64158-A2 CITY SECRETARY CONTRACT NO. COUNTY OF TARRANT WHEREAS, the City of Fort Worth and SpawGlass Contractors, Inc. of the City of Fort Worth County of Tarrant, State of Texas (Contractor) made and entered into City Secretary Contract No. 64158 (The Contract), which was authorized by the City Council by M&C 25-0229, the 11 th day of March 2025, for Meacham Airport Design Build Contract; and WHEREAS, the initial contract price for design services was $545,055.00; and revised by Amendment Number 1 for $36,438.00, which was administratively approved on the 10th Day of February; WHEREAS, a further amendment is necessary to support contractors' ability to deliver the scope of work for the Meacham Airport Design Build Contract and related costs referred to in Attachment A; and NOW THEREFORE, City and Contractor, acting herein by and through their duly authorized representatives, enter into the following agreement, which amends the Contract: In accordance with Paragraph 5.2.1 of the contract, it is amended as follows: "The GMP shall be the cost of the Design & Construction Services, in the amount of $1,187,037.00, One Million, One Hundred Eighty -Seven Thousand,Thirty-Seven Dollars. The increase in the amount of $605,544.00, Six Hundred Five Thousand, Five Hundred Forty -Four Dollars to include: Pre -Engineered Metal Building (PEMB) Design Services, PEMB 3rd Party Design Review, furnish and erect PEMB, Replat Quit Claim, Additional Civil Design Services for Storm Drain Study, Parkway Permit, Erosion Control SWPP as defined in Article 1.4.7, plus the Design -Builders fee of 5%, which shall not exceed the Guaranteed Maximum Price set forth in the GMP Amendment." This addition will cover, at a minimum, the areas of scope listed in Attachment A: 1. SpawGlass. OCO-0002/SPG-0003 Dated 2026-06-02 OFFICIAL RECORD City of Fort Worth, Texas CITY SECRETARY Meacham Airport Field Maintenance Project Amendment 2 Page 1 of 2 FT. WORTH, TX Executed effective as of the date signed by the Assistant City Manager below. FORT WORTH: City of Fort Worth By: Name: Title: V& (�- Valerie Washington (Jun 15, 2026 13:58:54 CDT) Valerie Washington Assistant City Manager 06/15/2026 Date: Approval Recommended: By: Name: Marilyn Marvin Title: Director Property Management Attest: QF Fogt"naa pJ a Vo_b° °°8�10 orlon nezAg44 By. Name: Jannette Goodall Title: City Secretary Contractor: SPAWGLASS Contractors Inc. L oyd aver (Jun 6, 2026 08:21:22 CDT) By: Name: Lloyd Faver Title: President, North Date: Texas Region. City of Fort Worth, Texas Meacham Airport Field Maintenance Project Amendment 2 Page 2 of 2 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. By: Name Title: Nikita N. Watts Sr. Capital Project Officer Approved as to Form and Legality: ZL_V� By: Stephen Hines (Jun 12, 26 16:00:00 CDT) Name: Stephen M. Hines Title: Sr. Assistant City Attorney Contract Authorization: M&C: 25-0229 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FUNDING BREAKDOWN SHEET City Secretary Contract No. _64158_ Amendment No. 2 Fund Dept ID Account Project ID CF1- Activity Amount 53002 0550435 5330500 105655 008130 545,055.00 53002 0550435 5330500 105655 008130 36,438.00 53002 0550435 5330500 105655 008130 605,544.00 Total: $1,187,307.00 City of Fort Worth, Texas Meacham Airport Field Maintenance Project Amendment 2 Page 3 of 2 CONTRACT CHANGE ORDER Project Name: Meacham Airport Maintenance Facility Date: 2026-06-02 Owner: City of Fort Worth Change Order No.: OCO-0002 100 Fort Worth Trail, Contractor Project No.: 3024100 Fort Worth, TX 76102 Architect Project No.: Quote No. Change Order Description Amount SGP-0003 3rd Replat Update, Quit Claim Deed Exhibit, Storm Drainage Study, Parkway Permit, Storm $605,544.00 Tie-in Easement, PEMB Early Release Notes Extension of Time This Change Order 0 Previous Extension of Time 0 Total Extension of Time to Date Original Contract Completion Date TBD Revision Completion Date TBD OWNER By: Date: Original Contract Amount $545,055.00 Total Previous Change Orders $36,438.00 Contract Amt. Prior to this C.O. $581,493.00 Total This Change Order $605,544.00 Current Contract Amount $1,187,037.00 ARCHITECT CONTRACTOR By: Date: By: Date: The Contractor hereby reserves its right to claim additional time and/or monies for the cumulative impact of project changes. SpawGIass Providing the Absolute Best Construction Experience F 1 • � � 1 J E P ;"mil �.. C��ir � T 4 !*; s' � �` 4. _, ,. � . �-r I �' ' • . • . � ��r- '_���{/-. -fit r ; '' �, �. r`' TABLE OF CONTENTS TAB 1 TAB 6 EXECUTIVE SUMMARY TAB 2 TAB 7 PEMB EARLY RELEASE GMP TAB 3 TAB 8 ASSUMPTIONS & CLARIFICATIONS N/A TAB 4 TAB 9 LIST OF DOCUMENTS TAB 5 TAB 10 PROJECT SCHEDULE UP � ice D/B Meacham Airport Field Maintenance Facility PEMB Early Release GMP 5.2.1 Guaranteed Maximum Price Proposal ("GMP"). The Design -Builder shall submit a Budget update to the Owner for each phase working toward a GMP. The GMP approved to date for Design Services, is at a value of Five Hundred and Eighty -One Thousand and Four Hundred and Ninety -Three Dollars ($581,493) after execution of Amendment No. 1. Construction as defined in Article 1.4.7 plus the Design -Builder's fee of 5% shall not exceed the Guaranteed Maximum Price set forth in the GMP Amendment. No adjustments in Design -Builder's fee shall be made for deductive changes. A mutually agreed Contractor's and Owner's Contingency will be included in Budget Updates. All unspent contingencies belong to the City at the completion of the project. The number shown above has been committed to SpawGlass as of 03/31/2026. After execution of Amendment No. 2 (requested herein) priced at $605,544, the updated contract value will be $1,187,037 as shown on page 1. Multistage GMP The City of Fort Worth has agreed and authorized SpawGlass Contractors to move forward with an early solicitation package to procure the pre-engineered metal building scope prior to full GMP amount being finalized. As such, SpawGlass is proposing to submit a multistage GMP as follows: • GMP 1 — Early Release of PEMB • GMP 2 — All remaining scopes SpawGlass Contactors, Inc. hereby submits phase 1 GMP Amendment No. 2 to procure the design, fabrication and erection of pre-engineered metal building for the City of Fort Worth Meacham Airport Field Maintenance Facility project. This amendment also includes the PEMB engineering design peer review, SWPPP narrative and inspections, replat review and quit claim coordination, SDS (Storm Drainage Study), parkway permit coordination & application fees, and storm sewer tie-in coordination. UP � ice Detail Report PEMB Early Release GMP Rev 2 Estimate Date: 06/02/2026 Documents Date: 02/18/2026 Project Size (SF): 14,076 Project #: 3024100 Project Location: Fort Worth, TX Lead Estimator: Justin Hyder ITEM QUANTITY I UM UNIT COST TOTAL COST /1 - General Requirements ff I / General Conditions 34,400 Repiat Review / Quit Claim 1.0 LS 3,750.00 3,750 Additional Design Services for Storm Drainage 1.0 LS 21,200.00 21,200 Study Parkway Permit / Storm Tie -In 1.0 LS 1 9,450.00 1 9,450 Pre -Engineered Metal Buildings 455,628 Engineering Design Peer Review 1.0 LS 12,300.00 12,300 Pre-engineered Metal Building 14,076.0 SF 31.50 443,328 Erosion Control 6,700 SWPPP Narrative 1.0 Each 3,500.00 3,500 SWPPP Inspections 8.0 Mos 400.00 3,200 PEMB Early Release GMP Estimate Date: 0610212026 Rev 2 Page 1 of 2 Documents Date: 0211812026 Total - Direct Costs $ 496,728 Builder's Risk Insurance General Liability Insurance Payment and Performance Bonds Warranty Contractor's Contingency Owner's Contingency Overhead and Profit 1,453 0.10 5,874 0.42 12,171 0.86 1,514 0.11 12,111 0.86 45,416 3.23 30,277 2.15 0.24 % 0.97 % 2.01 % 0.25 % 2.00 % 7.50 % 5.00 % Total Cost $ 605,544 $ 43.02 100.000/0 PEMB Early Release GMP Estimate Date: 0610212026 Rev 2 Page 2 of 2 Documents Date: 0211812026 Providing the Absolute Best Construction Experience D/B Meacham Airport Field Maintenance Facility PEMB Early Release GMP Division 01 — General Requirements and General Conditions 1. Assume normal working hours M-F, 7:00 a.m. to 5:30 p.m. We are assuming early morning concrete pours will be acceptable for SOG and site concrete as deemed necessary. We are assuming we can work on Saturdays as needed to maintain schedule or make-up for weather. 2. Includes delegated design for pre-engineered metal building. 3. Includes 3rd party review of PEMB engineered shop drawings and waterproofing details. 4. Includes additional costs to revise replat for third time and provide Quit Claim Exhibit. 5. Includes additional design services and application fees related to storm drainage study. 6. Includes coordination for parkway permit and storm sewer tie-in easement requirements. 7. Includes 2013 prevailing wage rates. 8. Does not include any alternates. 9. Does not include General Conditions or General Requirements. These will be included in second phase of GMP. Division 13 — Special Construction 1. Includes design, fabrication and installation of pre-engineered metal building with Gabled Tapered Columns frame type. a. Includes 22 ga standing seam roof, Galvalume finish. b. Does not include skylights c. Includes PBR wall panels, 22 ga d. Includes FW-120-2 soffit panels, 22 ga e. Includes PBR liner panel around shop area inside, 22 ga x 8' tall. f. Includes roof insulation system, R-30 g. Includes wall insulation system, R-19 h. Includes (4) structural canopies over doors. 2. Assumes standard colors. 3. Includes 20 yr NDL weathertightness warranty 4. Assumes IBC 2021 Risk Category II, with wind speed 106 mph, wind exposure C, live load of 20 psf with live load reduction allowed, and seismic site class D. S. Assumes a 10 psf collateral load between grid lines 8-11. Division 31 — Earthwork 1. Includes SWPPP book and weekly inspections. Page 1 of 2 PU xS is C4 4 (SI ILIA-) IQ] F-I 1. Taps, meters and related fees by utility providers not provided. 2. Building permits 3. Material testing services 4. Contaminated soils, asbestos abatement 5. FF&E 6. Sales Tax 7. Anything not listed above as specifically included. Page 2 of 2 N Li LIST OF DOCUMENTS SpawGlass Meacham Airport - Maintenance Facility Fort Worth, Texas 05/20/2026 Sheet No. -J� TITLE DRAWINGS ISSUE DATE REVISION DATE GENERAL G0.0 COVER 04.28.2026 GO.1 SHEET INDEX 04.28.2026 G0.2 TEXAS ACCESSIBILITY STANDARDS O4.28.2026 G0.3 TEXAS ACCESSIBILITY STANDARDS O4.28.2026 G0.4 TEXAS ACCESSIBILITY STANDARDS O4.28.2026 G0.5 FRAMING DETAILS O4.28.2026 G0.6 MOUNTING HEIGHTS O4.28.2026 G0.7 FIRE PENETRATION DETAILS O4.28.2026 CIVIL C1.1 COVER SHEET 04.28.2026 C1.2 GENERAL NOTES O4.28.2026 C2.1 FINAL PLAT 04.28.2026 C3.1 EXISTING CONDITIONS PLAN 04.28.2026 C3.2 DEMOLITION PLAN 04.28.2026 C4.1 SITE & DIMENSION CONTROL PLAN 04.28.2026 C5.1 OVERALL UTILITY PLAN 04.28.2026 05.01.2026 C7.1 SANITARY SEWER PLAN 04.28.2026 C7.2 UTILITY DETAILS O4.28.2026 C8.1 PAVING & STRIPING PLAN 04.28.2026 C8.2 PAVING DETAILS O4.28.2026 C8.3 PAVING DETAILS O4.28.2026 C9.1 GRADING PLAN 04.28.2026 C10.1 EXISTING DRAINAGE AREA MAP 04.28.2026 C10.2 PROPOSED DRAINAGE AREA MAP 04.28.2026 C11.1 DETENTION POND 04.28.2026 C11.2 DETENTION POND 04.28.2026 C11.3 DETENTION POND CALCULATIONS O4.28.2026 C12.1 EROSION CONTROL PLAN 04.28.2026 C12.2 EROSION CONTROL DETAILS O4.28.2026 List of Drawings & Specifications - Page 1 of 7 LANDSCAPE L1.1 EXISTING CONDITIONS PLAN 04.28.2026 L1.2 LANDSCAPE PLAN 04.28.2026 L1.3 LANDSCAPE SPECIFICATIONS AND DETAILS O4.28.2026 ARCHITECTURAL A0.1 LIFE SAFETY PLAN 04.28.2026 A0.2 3-HR FIRE RATED WALL ASSEMBLY 04.28.2026 A1.0 ARCHITECTURAL SITE PLAN 04.28.2026 A1.1 SITE DETAILS O4.28.2026 A2.1 DIMENSION PLAN 04.28.2026 A2.2 FLOOR PLAN 04.28.2026 A2.3 FLOOR PLAN - ADD ALTERNATE #06 - COVERED PARKING 04.28.2026 A2.4 ENLARGED FLOOR PLANS O4.28.2026 A3.1 EXTERIOR ELEVATIONS O4.28.2026 A4.0 BUILDING SECTIONS O4.28.2026 A4.1 WALL SECTIONS O4.28.2026 A4.2 SECTION DETAILS O4.28.2026 A5.1 ROOF PLAN 04.28.2026 A6.1 DOOR SCHEDULE AND DETAILS O4.28.2026 A7.1 REFLECTED CEILING PLAN 04.28.2026 A7 2 REFLECTED CEILING PLAN - ADD ALTERNATE #03 - HVLS FANS 04.28.2026 A8.1 INTERIOR ELEVATIONS O4.28.2026 A8.2 CASEWORK DETAILS O4.28.2026 A9.1 FINISH PLAN, SCHEDULE, AND NOTES O4.28.2026 STRUCTURAL S1.1 SPECIAL INSPECTIONS & GENERAL NOTES O4.28.2026 S2.1 FOUNDATION PLAN 04.28.2026 S2.2 SCHEMATIC ROOF FRAMING PLANS O4.28.2026 S3.1 FOUNDATION DETAILS O4.28.2026 S3.2 FOUNDATION DETAILS O4.28.2026 MECHANICAL M0.1 MECHANICAL LEGEND, SCHEDULES & NOTES O4.28.2026 List of Drawings & Specifications - Page 2 of 7 M0.2 MECHANICAL DETAILS O4.28.2026 M2.1 FLOOR PLAN - MECHANICAL 04.28.2026 M2 2 FLOOR PLAN - MECHANICAL - ADD ALTERNATE 04.28.2026 PLUMBING P0.1 PLUMBING LEGEND, SCHEDULES & NOTES O4.28.2026 P0.2 PLUMBING DETAILS O4.28.2026 P2 1 FLOOR PLAN - PLUMBING - WASTE, DRAIN, & VENT 04.28.2026 P2.2 FLOOR PLAN - PLUMBING - DOMESTIC SERVICES O4.28.2026 P2 3 FLOOR PLAN - PLUMBING - DOMESTIC SERVICES - ADD ALTERNATE #02 04.28.2026 ELECTRICAL E0.1 ELECTRICAL SINGLE LINE & DETAILS O4.28.2026 E0.2 ELECTRICAL DETAILS O4.28.2026 E1.1 SITE PLAN - ELECTRICAL 04.28.2026 E2.1 FLOOR PLAN - ELECTRICAL 04.28.2026 E3.1 FLOOR PLAN - LIGHTING 04.28.2026 E3.2 FLOOR PLAN - LIGHTING DAYLIGHT ZONES O4.28.2026 E6.1 ELECTRICAL PANEL SCHEDULES O4.28.2026 E6.2 ELECTRICAL PANEL SCHEDULES O4.28.2026 ES1.1 FLOOR PLAN - SECURITY 04.28.2026 FA2.1 FLOOR PLAN - FIRE ALARM 04.28.2026 SPECIFICATIONS DIVISION 00 — PROCUREMENT & CONTRACTING REQUIREMENTS 0001 10 Table of Contents 04.28.2026 DIVISION 01 -- GENERAL REQUIREMENTS 01 1000 Summary 04.28.2026 01 23 00 Alternates 04.28.2026 DIVISION 03 -- CONCRETE 03 05 16 Underslab Vapor Barrier 04.28.2026 03 10 00 Concrete Formwork 04.28.2026 List of Drawings & Specifications - Page 3 of 7 03 20 00 Concrete Reinforcement 04.28.2026 03 30 00 Cast -in -Place Concrete 04.28.2026 03 35 11 Concrete Floor Finishes 04.28.2026 DIVISION 04 -- MASONRY 04 20 00 Unit Masonry 04.28.2026 DIVISION 05 -- METALS 05 50 00 Metal Fabrications 04.28.2026 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES 06 1000 Rough Carpentry 04.28.2026 0641 00 Architectural Wood Casework 04.28.2026 0661 00 Cast Polymer Fabrications 04.28.2026 0683 16 Fiberglass Reinforced Paneling 04.28.2026 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION 07 21 00 Thermal Insulation 04.28.2026 0741 13 Metal Roof Panels 04.28.2026 0742 13 Metal Wall Panels 04.28.2026 0762 00 Sheet Metal Flashing and Trim 04.28.2026 0771 00 Roof Specialties 04.28.2026 07 8400 Firestopping 04.28.2026 07 92 00 Joint Sealants 04.28.2026 DIVISION 08 -- OPENINGS 08 11 13 Hollow Metal Doors and Frames 04.28.2026 08 14 16 Flush Wood Doors 04.28.2026 08 31 00 Access Doors and Panels 04.28.2026 08 3344 Overhead Coiling Fire Shutters 04.28.2026 08 36 13 Sectional Doors 04.28.2026 0843 13 Aluminum -Framed Storefronts 04.28.2026 08 71 00 Door Hardware 04.28.2026 08 80 00 Glazing 04.28.2026 DIVISION 09 -- FINISHES List of Drawings & Specifications - Page 4 of 7 09 21 16 Gypsum Board Assemblies 04.28.2026 09 22 16 Non -Structural Metal Framing 04.28.2026 09 30 00 Tiling 04.28.2026 09 51 00 Acoustical Ceilings 04.28.2026 09 65 00 Resilient Flooring 04.28.2026 09 91 13 Exterior Painting 04.28.2026 09 91 23 Interior Painting 04.28.2026 DIVISION 10 -- SPECIALTIES 10 26 00 Wall and Door Protection 04.28.2026 10 28 00 Toilet, Bath, and Laundry Accessories 04.28.2026 10 44 00 Fire Protection Specialties 04.28.2026 10 51 13 Metal Lockers 04.28.2026 10 73 10 Prefinished Aluminum Canopies And Shade Structures 04.28.2026 DIVISION 11 -- EQUIPMENT 11 30 13 Residential Appliances 04.28.2026 DIVISION 12 -- FURNISHINGS 12 2400 Window Shades 04.28.2026 12 36 00 Countertops 04.28.2026 DIVISION 13 -- SPECIAL CONSTRUCTION 13 34 19 Metal Building Systems 04.28.2026 DIVISION 22 - PLUMBING 22 00 10 BASIC PLUMBING REQUIREMENTS O4.28.2026 22 05 12 PLUMBING AND ELECTRICAL COORDINATION 04.28.2026 22 05 19 PLUMBING METERS AND GAUGES O4.28.2026 22 05 29 PLUMBING SUPPORTS AND ANCHORS O4.28.2026 2205 53 PLUMBING IDENTIFICATION 04.28.2026 22 0593 PLUMBING TESTING, ADJUSTING AND BALANCING 04.28.2026 2207 16 PLUMBING PIPING AND EQUIPMENT INSULATION 04.28.2026 22 10 00 PLUMBING PIPING 04.28.2026 22 10 01 PLUMBING SPECIALTIES O4.28.2026 22 11 19 PIPING SPECIALTIES O4.28.2026 22 30 00 PLUMBING EQUIPMENT 04.28.2026 List of Drawings & Specifications - Page 5 of 7 22 40 00 PLUMBING FIXTURES O4.28.2026 DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC) 23 00 10 BASIC MECHANICAL REQUIREMENTS O4.28.2026 23 05 12 MECHANICAL AND ELECTRICAL COORDINATION 04.28.2026 23 05 29 MECHANICAL SUPPORTS AND ANCHORS O4.28.2026 23 05 53 MECHANICAL IDENTIFICATION 04.28.2026 23 0593 MECHANICAL TESTING, ADJUSTING AND BALANCING 04.28.2026 23 07 13 HVAC DUCT INSULATION 04.28.2026 23 31 13 METAL DUCTWORK 04.28.2026 23 31 13.19 DUCTWORK ACCESSORIES O4.28.2026 23 3400 FANS O4.28.2026 23 37 13 AIR OUTLETS AND INLETS O4.28.2026 23 37 23 GRAVITY VENTILATORS O4.28.2026 23 51 00 BREECHING, CHIMNEYS, AND STACKS O4.28.2026 23 55 00 FUEL -FIRED HEATERS O4.28.2026 2381 26 SPLIT DX COOLING/HEATING SYSTEMS O4.28.2026 23 89 65 MOTOR CONTROLLERS O4.28.2026 DIVISION 26 - ELECTRICAL 2605 10 GENERAL REQUIREMENTS FOR ELECTRICAL WORK 04.28.2026 2605 12 MECHANICAL AND ELECTRICAL COORDINATION 04.28.2026 2605 19 WIRES AND CABLES O4.28.2026 26 05 26 GROUNDING 04.28.2026 26 05 26.01 WIRE CONNECTION AND DEVICES (EXO-THERM WELD 04.28.2026 26 05 27 SEALING OF PENETRATIONS O4.28.2026 26 05 29 SUPPORTING DEVICES O4.28.2026 2605 32 PULL AND JUNCTION BOXES O4.28.2026 2605 33 CONDUITS O4.28.2026 26 05 34 OUTLET BOXES O4.28.2026 2605 35 WIREWAY 04.28.2026 26 09 26 MISCELLANEOUS ITEMS O4.28.2026 26 22 13 DRY TYPE TRANSFORMERS O4.28.2026 2624 16 PANELBOARDS O4.28.2026 List of Drawings & Specifications - Page 6 of 7 2624 17 DISTRIBUTION PANELBOARDS O4.28.2026 26 27 13 ELECTRIC SERVICE ENTRANCE 04.28.2026 2627 16 CABINETS O4.28.2026 26 27 26 WIRING DEVICES O4.28.2026 2628 16 OVERCURRENT PROTECTIVE DEVICES O4.28.2026 2628 17 DISCONNECT SWITCHES O4.28.2026 2629 13 MOTORS, MOTOR STARTERS AND CONTROLS O4.28.2026 2641 13 LIGHTNING PROTECTION FOR STRUCTURES O4.28.2026 2643 13 SURGE PROTECTION DEVICES (SPDS) 04.28.2026 26 51 13 LIGHTING 04.28.2026 DIVISION 27 - COMMUNICATIONS 27 05 28 EMPTY CONDUIT SYSTEMS O4.28.2026 DIVISION 28 - ELECTRONIC SAFETY AND SECURITY 28 31 00 ANALOG ADDRESSABLE FIRE ALARM SYSTEM 04.28.2026 DIVISION 31 -- EARTHWORK 31 63 29 Drilled Concrete Piers and Shafts 04.28.2026 END. List of Drawings & Specifications - Page 7 of 7 7 1 474! r- I � - - i--- 11 TAB 5 PROJECT SCHEDULE SpawGlass JMeacham Air Miesternes 517 263 13-May-25A 23Jun-27 49.13% 0 MJegtones At OM City Council Meeting with Mayor 1 0 13-May-25A 13-May-25A 100% City Cpuncil.Meedng with May., A1550 Programming Approval 0 0 29Jul-25A 100%4 Pm®ramAting Approyal A1520 Test FRApproval 0 0 07-Op-25A 100% :0 T9st Fit NpProval �', A1500 Schematic Design Approval 0 0 14-Nov.25A 100% - ----------' - ♦ Bchamatcgeagh Approval ------ ---------- A1530 Executed Contract /Issue PO 0 0 19-Nov-25A 100% ♦Exeadedcontract /Issue PO',',',, A1110 Owner Change Ober #01 4 0 07Jan-26A 17Feb-26A 100°b ;mmlim,Onngr Ghdnge rder#Ot A1510 Design Development Approval 0 0 29Jan-26A 100% �Design Devekipm APProvat', A1050 GMP#1APEMB Approval - 0 0 11J n-26 0°l- 8 ♦GMP #1 Approval:- PEMB A1080 pP .I GMPiF2A I 0 0 23JL26 0% 18 -- ...L .........:.........:.....��,.... _ - ,- ___ ♦GMP #2 van At 240 Notice to Proceed 0 0 19-Aug-26 0°b 0 ♦ N t to Proceed A1350 PEMB Com lete 0 0 05-Feb-27 0% 12 P MB Oom Meta A1310 Substantial Completion 0 0 27-qpr-27 0°h 0 •`, Subistantpl Completio A1360 Final Completion 0 0 23Jun-27 0% g •Final Compl Pfeconshudon - 433 106 11-Feb.25A 23.0U-26 75.52% 78 ......,•....'•....:....•-...• ..........------.----------------------- ..;, Pre�nstuotbn:.-. ....:....:....:.--.......', ..... Program hg _ A1410 Predesign N.1roff Meeting 1 0 11-1`eb-25 A 11-Feb-25A 100% Predesign Wdm1f Meeting �0wner A1400 Owner Contract Routlrg 15 0 28-MayQ5A 19-Nov-25A 100% Corftact:RouHh9 A1000 Programming and Spare Planning 15 0 26J-25A 17Jul-25A 100% r Progromming and Specs Plennirg :... A1420 -_. ) Programming Review (CRY of Fort Worth) 10 0 18JuF25A 29Ju1-25A 100% :..., Pn+gmmlrng Aewe Cd ofF nW... W( Y 4 ....:... :....:. .. .,. .. A1630 SO Test FH-Ste 0ptinsl&2 20 0 22-Aug-25A 298ap-25A 100% '�, ', SDITetl Sit-Ske 0p'Imsi&2 A1640 City Review& Approval SO Test Ft 5 0 29Sep-25A 07-01-25A 100% City ReNew&Appmval SDTed Ft: A1650 SD Dwgsl Budget 5 0 08-01 15-0ct-25A 700% SD Dwgsl Budget A1660 City Revlewof SDDwgs/Budget-Rd1 5 0 16-W-25A r 27-0d-25A 100% r. CRy Revew of $D D,wgs/:Budget _ d1 A1670 SD Dwgsl Budget_ReV1 5 0 28-0d-25A 31-Oct-25A 100% i SDI, Dvgs/Budgi1 A1680 City Review of SO Dwgs/Budget -Rd2 5 0 31-0d-25A 06-Nov-25A 100% '�, Y Ciky Review of SD';Dwgs/Budget 'Rd 2: A1690 SD Dwgs/BudgeLRav2 5 0 06-Nav-25A 07-N-25A 100% SDDw{ks/Budget R.V,.2 ' A1700 City Review of SO Dwga/Budget -Rd3 5 0 1O-Nav-25A 14Nov-25A 100% i City Ravlew':of S©Dwgs/Budg !-Rd3 a� -.. � � Design OeveWPm DO Dwgs 18 0 0 10 0 17-Nov-25A 15•Deo-25A 07J-26A 1SD-25A OBJan-�A 29Jani 100% 100%DBudget 100% ', T DD Dpgs '� '� '� '� '� �� City Rev(ew&iepp'val- DD Budget15 1City Review&Approval PA1820 MB Edy Release Pkg Soldt &ds-PEMB Early Release Pkg 10 0 27Feb-26A 12Ma �6A 700%SaIil Bids 'PEMB Eady Rel4ase Plg ' 1 I GMP#1 Submission- PEMB Early Release Pig 10 0 13-Mar-26A 30Mar-26A 100% GMP ill 'SubrYissiorf-PEMB Ebdy ReliPkg A1860 CI1Y Review & Approval -PEMB Early Release 40 11 30Ma1-26A 11Jon-26 72.5%W City Review S Approval'; PEMB EaR'. R4 ine, A1870 PEMB Design 35 35 12Jun-26 30-Ju1-26 i 0% 8 o' PE61B Design, A1880 PEMB Design Review 10 10 31 Ju426 13,Aug-26 0% 26 �' b PEMB Design Reyew - A1890 PEMB Fabrication 50 50 14dwg-26 23-0d-26 0°6 26 PEMB F.bricefidr, •50%CU. ''�Construction Doeuma'tns A1740 20 0 29Jan-26A 18Feb-26A 100% r i50%CD's A1750 50%CD Budget 10 0 19Feb-26A 30Mar-26A 100% �� 50ysC ,Budget Stall Date: Finish Date: Data Date: Run Date: 11-Feb-25 23Jun-Jun 28-May.25 26May-26 ActualWork• c� Remaining Work rfr. Cmiral Remaining Work •Milestone — Summary aaaaaaar. Level df EROH Actual Level of ERort Meacham Airport Field Maintenance Facility WBS Layod-All Activities Page 1 of 4 � A1760 City Review of 50%CD's 10 0 1&Feb-26A 174ar-26A 100% CityR uew of 50%CD's A1770 90%CD's 10 0 194an26A 3140ar-26A 100% --F.. .... ... -... ........ ,. -q 90g6Ctla , A1780 City Reviewof 90%CDs 10 0 01-Apr-26A 20-May-26A 100% ".-i—',CTy Review of 90%Cite '. BWloing Remit A2220 100% CDs l Permit Set 5 0 21-Apr-26A 29-Apr-26A 100% 1 %CD's/Pemtsat A2280 Submit Bldg Pent 3 0 29-Apr-26A 04-May-26A iW% ',, �. • Submit ®Idg Permit A2230 Initial Review Comments(Pemiitting) 10 0 04May-26A 15-May,26A 100% r Initial kaview Comments(Pannt[ng) A2290 Respond to Review Comments (Addendum 01) 10 8 18-May-26A 08Jun-26 20% 18 - o Respond to Revie}v Commerits(Ardendum 01) A2330 City Approval/Issue Bldg Permit 5 5 12-1wg-26 18dwg-2& 0% 0 City 4PiovW/ Issue Bldg Rermk! Gad Hg Pehnit A2340 Sumbit Grading P.-it a 0 01-May-26A 100% ♦ S. m bit Ladino to ninit ��' �� -... �,I A2350 1st Rd of Review Comments 15 0 01-May-26A 14MaY-26A 100% . �-,--', •....•. .... •. .. --���, -����� •'� ^ lost Rtlof REview:ComMenl'..... •....:.... '', '� s A2360 Respond to Review Comment. (Addendum 01) 15 a 15-10ay-26A 06J-26 46.67% 18 ii - - R¢apcmd to Review Comments(Addendum Qi) A2370 SWPPP Book 10 10 12Jun26 25Jun-26 0°% 18 c=SW?PP gook; - A2380 City Review /Issue Grading Permit 15 15 26Jurv26 16-JuF25 0% 18 o City R ' / Isw G dig P 2 �. .. .. .. ' St m, Dra Sway - A2390 Storm Damage Study Submitted. 0 0 01-May-26A 100% ♦ St Drains, St tly Sdbmittad - A2400 1 st Rd of Review Comments 15 0 01-May-25A 14May-26A 100% ', - r• d Rd of ReNew:Comment6 - - - A2410 Respond to Review Comments (Addendum 01) a 8 28-Mey-26 08-J 26 0% 0 ', ', ', ', ', ', ', ', - Respond to Review Comment,(Addendum 61) ' A2420 C,ty Review/Approval of BIDS 15 15 09Jun-26 29Jun-26 0% 0 ', � City, ReNgw l App—I of$DS -•.. .. - ©���� �� ROWAbapdonment A2430 ROW Abandonment Fxhbds 5 0 17-Feb-26A 26Feb-26A 100% ', '�, r•� ROW Pb ndofimenP Exh lnAs A2410iROW Abandonment R—dirg Information Co., 5 19 27Feb-26A 23Jun-26 0% 4 ROWAbandanMeni RewMing lhfomiatorl (Ctly:Courldl M) Quit Claim'' A24So Quit Claim Fxhbil 5 0 05-May626A 12-MaY-26A 100% uit Chime bR' ',, A2460 Quit Clem R—w(City CoundlMassing) 19 19 28-10ay-26 23Jun-26 0% 4 Quit Claim�ReNBw(City CqumilMeeting) ® •� .., .. - spied... , - A2470 RePlat BAPPf tnn Submitted 0 0 15-Deo-25A 100% - • Repk1&Pypf tion Subm ed A2480 FrWise Rapist 5 5 30-Jun-26 08Ju}26 0% 0 Y Finalize ReplAt - A2490 (City Review&Approval 26 26 07Ju1-25 11Aug-26 0% CRy Review;&ApPaval: r. GMP A1840 Soliat Bids. 100%CD's/Pemlit Set 16 16 28-May-26 18JUR26 0% 18 SofgC B'tlsf 100%Cgsl Permit Set A2190 Issue Addendum 01 to Blddea: 1 1 09Jun-26 09Jun-26 0% 18 - r Issue Aod-n -Ql to giddels A2240 Sub Bids Due 7 7 10Jun-26 18Jun-26 0% 18 © Bub Bids Due A1850 GMP#2 Development 10 10 1U-26 02JuF26 0% 18 --i GMP#2:Dsv9loPment A179 City Review& GMP Approval GMP#2 15 15 03Jul-26 23Jul,26 W/. 18 o', City Review& GMP Approval GMP#2 ------------ A2200 Delegated Design 15 15 07Aug-26 27Aug-26 0% 88',',', - o Delegated Design,, A2210 Retaining Wnll Perm't 20 20 28Aug-26 25Sep-26 0% 98 Ret;ming N§YPa-mi Constucton 174 174 20-Aug-26 27Apr-27 0% Coris<ruclian A1150 InstaIISWPPP/Temporary FencelOffica Trailer 5 5 20Jwg-26 2sfwg-26 0% 0 -- ', - ----- '-------- ---------'--�� Tempoary, ce/O Inst4il SWPPPi Fen,- -'------------- - - ffice Tailed - - 1 1 _ Sitewow A1070 DemolEadhwodc lExrevate Detention Porttl 8lmporl 1 1 30 1 30 27Aug-26 0&Q.426 0% 0 DemolEarthdodc (€nmvate Detention Pbnd & Impdrt Fill)' Stan Date: Finish Date: 11-Feb-25 23Jun-Jun Actualising • • sum Milestone Actual Level of Effort c� Remaining Work — Summary Meacham Airport Field Maintenance Facility WBS Layou[ - All Activities � Data Date: 28-May-25 fir. Critical Remaining Work � Level of ERod Page 2 of 4 Run Date: 26-May46 A1130 UG Utilities (Stone, Sewar, ElegrS) 15 15 11-Sep-2fi 01-0ct-26 0% 10 o UQ Utilities (Storm, Sewer ElecMc) A1090 BluetoplUme 10 10 02-Od-26 15-0cF25 0% 22 c Rluet9plUtne A1100 Ske Paving R. Lane 10 10 1SOd-Cot 29JM-26 0% 22 ---- - ---'- --- - - ._ _ . __ ._ - - --1-_o Site Pavimg Rm Lane A1140 Stacked Stone Retaining W4.11/ �dei 15 15 30.0d-26 Nov-NOV 0°6 74 - '� b Stad(ed Stone Retaining MI/ Backlll A1260 Install Guardrail at Retaining NAll 10 10 20.Nov-26 DeF26 :19-Feb-27 0% 79 o Install GuaMllail at;Retal' WAll A1180 Pour Site Paving(Parking Lot) - East aide 10 10 08-Feb-27 0% 22 o Pour,Site Paving(Parking I:at) -Fa A1230 Sidewalks 5 5 iSMar-27 19-Mar-27 0% 7 - o bdevpIls - A1250 Payment Markings l Landscaping 10 10 22-Mar-27 02-Apr-27 0% 7 -- - _ _ - _ L P-nmm Maifclrgs/ Land: Building 8'.PaurPiersP6): A1190 DO&Four Pkrs(26) 5 5 09-Od-26 15-W-26 0% 0 A1120 Underground MEP 10 10 16-Oct-26 29-0ct-26 G% 0 ', ', �'� UndergroFlnd MEP A1160 Concrete Foundation 15 15 30.0d-26 19-Nov-2fi 0°6 0 ^ Concrete Foundation' At 570 Wet Cure Slab 7 7 20.Nov-26 02-Deo-26. Oo,3 0 ---- - et Cum siab - -- � A1170 Install PFMB 45 45 03-D-26 OSFeb-27 fN.b 0 how REMBi A1320 Storefront/E#error Doors (SYNndovs&4-Exl Daois) 10 10 01-Feb-27 12-Feb-27 0% 17' Slorc(bnt/',E#sdor Doors (Staled A1340 Coding Doom (12) 10 10 O8-FebZ7 18-Feb27 0% 22 :', ®; Coillr7g Doors (12) A1600 Insbll Awningsaver a#edardo ors 5 5 15-27 1g-Feb-27 0% 17 a Insta�lAw*pigs over eaianor dao� 5 A1590 Install Exterior Wall Packs 5 5 08-Mar-27 12-Mar-27 l 0% 7 L -; lijskl#eripr WTI Pa c{a --- Warehouse GO 50 01-Feb-27 0BApr-27 0% 2 i�i�N N3iehouse: A1960 Eleom. RoughJn 15 15 01-Feb-27 19-Feb-27 w/. 0 EledFk RoughJP A1970 Plumbing & Melmnioal RoughJn 15 5 15 5 01-Feb-27 OB-Feb 19Feb-27 12 FeF ?7 0% 0 � 10 Plumb ng& McChantal Rdughah o CMU Wo ' : k;* at Wddatatlon Wells at Workstation A1920 CMU W jj A1940 _ Dr"d Padifions 5 5 151`eb-27 19-Feb-77 - 0% 10 A1900 Radiant Hastens 10 10 22-Feb-27 O5-Ma1-27 w/< 2 R;d7aMHeatRrs A1910 Install LightslHose Reals 10 10 22-Feb-27 05.14ar-27 096 2 r-'+ Insbll L'gMslHose Reeld A1930 Chainlink Fence at Storage Area 5 5 22-Feb-27 2 - b.27 0% 27 d Chdinlink Fenre at Soralle Area r A2000 Install Door &He—, 2 2 22-Feb-27 23-Feb-27 0% 10 Insel0 or&H rd,em A1950 Paint Exposed SbudureM41§ 10 10 08-10ar-27 19-Mar-27 0% 2 _ _ _ Ra 1',Exposed $[n�c14reM/af§ A2010 Seal Concrete Flo 5 5 22-Mar-27 26-Mar-27 D% 2 o Sea! Concrete �borg r Al.. install R. Akira Devices 5 5 29-Mar-27 02-Apr-27 0% 2 6 Insal Fiie AIa m Devices: A1990 Install Plumbing Flxtures8 Hookup 5 5 23Mar-27 02-Ayr-27 0% 2 a Instal Pltmbhg Pod... 8 A2170 Fnal Clean 5 5 05-Apr-27 09-4r-27 0% 2 ) o Final Clean _ OfficeArea 62 62 01-Feb-27 27,Apr-27 0% l 0 ; ; ; ��, -Off". A2020 OH MEP RoughJn 15 15 01-Feb-27 19Feb-27 0% 0 ^ OH MEP RoughJn A2030 Freme&One side UA ls./Rome Celir®s 10 10 15-Feb-27 26-Feb-27 0% 0 F2me&;One Side Nkls/,Ramp A2040 In Wall MEP RoughJn 10 10 22-Feb-27 05-Mar-27 0% i In VWI MEPRough4n A2050 Cbse Up WAii/ Cel'nga 5 5 08-Mar-27 12-Mar-27 0% 0 • Close Up W41§/ Celnds A2090 Paint NAls/Calings 10 10 15-Mar-27 26-Mar-27 0% ' 0 L A2110 Install Ta 5 5 17Mar-27 23-M -27 N. 10 ; o Install Tie gssm., 30.M r27� r` InsstIIAQT cm:Re A2180 Install Lights R g egi Gflke 5 5 310.Mar-Mar 06-.4pr- o '; ens stallLghts Reg st G A2060 Install(12) Intenor Doom &(2)Windowv 5 5 07Ppr-27 13-API-27 0",ir 5 o Ihsta1112)Ihterbt Doolk A2070 Install 3 5 3 5 07�r.27 07 � � -- : II stall MlMro 9 ---, � •• stal Fbonn 8Sase , r A2(180 InstallFl Roung n BBase .42120 Install & Hooki p Plumbing Fndu 5 5 07-1W 3-Ap o n�aYB Hook up Plum ai Start Date: Finish Date: 11-Feb-25 23Jun-Jun f� Actual Wont c� Remaining Wont • •summare — Summary Actual Level of Effort Meacham Airport Field Maintenance Facility ASS Layod-All Activities � Data D. 28-May-26 fay Critical Remaining Work — Level of ERod Page 3 of 4 Run Date: 2&May-26 A2130 Iretall appliances, lockers, bench, foist acceswnes 5 5 12-Apr-27 16Apr-27 0% 2 m5a11 appliarkeslockq A2100 MEP Tnm Out&Fire Alarm 5 5 I4Apr-27 20-Apr-27 0% 0 •';MEP;Tn'm bw B, Fire /Ua A2140 Irn•,iall FF&E 5 5 14Apr-27 20-Apr-27 0% 0 - ---- ---' ---'- --- - ------ �, �IrMaR FF&E ; A2160 Final Clean 5 5 21.Apr.27 27.Apr-27 0% 0 1 i i W F'n21 CkAn I Testln BComleson A1370 SG P-P.m h 10 10 14-Apr-27 27-Apr-27 0% 0 '., �'� SG F-Punch: A1580 Fnal Cty lnspedi ns 5 5 21-Apr-27 27Apr-27 0% 0 1•' Rnal City; Insp: ins A1490 Tess & Balance 5 5 21.Apr.27 27API-27 0% T 0 - -- -�I TeQ & Bdlenoe, -- - Cioseout 40 40 2&Apr-27 23Jun-27 0% 0 '., :Closeout A1330 Owner Punchlist 20 20 28-Ppr-27 25May-27 0% 0 1--: Oanjer Py'nchIW A1380 Closeout Documents 20 20 28-4r-27 25-May-27 I._ N.M. A7560 Final Payment 20 20 26May.27 23JUri-27 0% 0 '. -i— : Final Payme Start Date: 11-Feb-25 Finish Date: 23-Jun-27 Work rs� Remaining Work Remaining • • Summate _ Summary ACMuaI Level of ERort Meacham Airport Field Maintenance Facility WBS Layou[-All Activities ` Data Date: 26-May.25 Critical Remalnirg Work � Ll of Egon eve Page 4 of 4 II`ul Run Date: 26-May-26 SpawGlass Contractors, Inc. 3000 W. Loop 820 S. Fort Worth, TX 76116 817-288-0890 www.SpawGIass.com Connect with us today! FORT WORTH. City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: SpawGlass Subject of the Agreement: Amendment No. 2 - Early Construction Release Package - Pre -Engineered Building engineered design and purchase. Replat Exhibits for Quit Claim Deed, Strom Drainage Study, Parkway permit and Storm Tie in for Easement M&C Approved by the Council? * Yes 0 No ❑ If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes 0 No ❑ 64158 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes 0 No ❑ If unsure, see backpage for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: Expiration Date: If different from the approval date. If applicable. Is a 1295 Form required? * Yes ❑ No 21 *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. 105655 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes 0 No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department.