HomeMy WebLinkAbout063969-FP1 - Construction-Related - Contract - Dallas Underground, LLC.-FP1
City Secretary
Contract No. 63969
FORT WORTH.
Date Received 6/15/2026
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Alto Carter Park 35
City Project No.: 106260
Improvement Type(s): Water 0 Sewer 0
Original Contract Price:
$85,910.36
Amount of Approved Change Order(s):
Revised Contract Amount:
$85,910.36
Total Cost of Work Complete:
$85,910.36
Contractor
Dallas Underground, LLC.
Title
Dallas Underground, LLC
Company Name
Dana Carr (Jun 12, 2026 11:09:17 CDT)
Project Inspector
Khal Jaafari PE. (Jo 14, 2 ' 23:16:33CDT)
Project Manager
CFA Manager
Oe. /".w
Lauren Prieur (Jun 15, 2026 11:41:46 CDT)
TPW Director
06/12/2026
Date
Date
06/14/2026
Date
06/15/2026
Date
06/15/2026
Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Alto Carter Park 35
City Project No.: 106260
City's Attachments
Final Pay Estimate 0
Change Order(s): ❑ Yes Z N/A
Pipe Report: 0 Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety a
Statement of Contract Time
Contract Time: 7 WD
Days Charged: 81 WD
Work Start Date: 1/6/2026 Work Complete Date: 5/13/26
Completed number of Soil Lab Test: 14
Completed number of Water Test: 4
Page 2 of 2
FoRT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name ALTO CARTER PARK 35
Contract Limits
Project Type WATER & SEWER
City Project Numbers 106260
DOE Number 6260
Estimate Number 1 Payment Number 1
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor DALLAS UNDERGROUND, LLC
PO BOX 1117
For Period Ending 5/13/2026
WD
ENNIS , TX 75120
Inspectors G.DEYON / D.CARR
Contract Time WD
Days Charged to Date 81
Contract is 100.00 Complete
Monday, June 8, 2026 Page 1 of 4
City Project Numbers 106260
Contract Name ALTO CARTER PARK 35
Contract Limits
Project Type WATER & SEWER
Project Funding
UNIT I: WATER IMPROVEMENTS
DOE Number 6260
Estimate Number I
Payment Number 1
For Period Ending 5/13/2026
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
TRENCH SAFETY
52 LF
$15.00
$780.00
52
$780.00
2
DUCTILE IRON WATER FITTINGS W/
1.57 TN
$1,750.00
$2,747.50
1.57
$2,747.50
RESTRAINT
3
8" PVC WATER PIPE
40 LF
$45.30
$1,812.00
40
$1,812.00
4
12" PVC WATER PIPE
12 LF
$65.00
$780.00
12
$780.00
5
WATER SAMPLING STATION
3 EA
$2,500.00
$7,500.00
3
$7,500.00
6
CONNECTION TO EXISTING 16" WATER MAIN
3 EA
$10,161.71
$30,485.13
3
$30,485.13
7
2" WATER SERVICE
3 EA
$6,977.82
$20,933.46
3
$20,933.46
8
8" GATE VALVE
2 EA
$2,565.00
$5,130.00
2
$5,130.00
9
12" GATE VALVE
1 EA
$3,200.00
$3,200.00
1
$3,200.00
Sub -Total of Previous Unit
$73,368.09
$73,368.09
UNIT It. SEWER IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
REMOVE 8" SEWER LINE
5 LF
$86.00
$430.00
5
$430.00
2
FINAL MH-CCTV INSPECTION
1 EA
$850.00
$850.00
1
$850.00
3
MANHOLE VACUUM TESTING
1 EA
$1,200.00
$1,200.00
1
$1,200.00
4
4' MANHOLE
1 EA
$9,512.27
$9,512.27
1
$9,512.27
5
CONCRETE COLLAR
1 EA
$550.00
$550.00
1
$550.00
Sub -Total of Previous Unit
$12,542.27
$12,542.27
Monday, June 8, 2026 Page 2 of 4
City Project Numbers 106260
Contract Name ALTO CARTER PARK 35
Contract Limits
Project Type WATER & SEWER
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Total Contract Price
DOE Number 6260
Estimate Number 1
Payment Number 1
For Period Ending 5/13/2026
$85,910.36
$85,910.36
Total Cost of Work Completed
$85,910.36
Less % Retained
$0.00
Net Earned
$85,910.36
Earned This Period $85,910.36
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$85,910.36
Monday, June 8, 2026 Page 3 of 4
City Project Numbers 106260
Contract Name ALTO CARTER PARK 35
Contract Limits
Project Type WATER & SEWER
Project Funding
Project Manager NA
Inspectors G.DEYON / D.CARR
Contractor DALLAS UNDERGROUND, LLC
PO BOX 1117
ENNIS, TX
DOE Number 6260
Estimate Number 1
Payment Number 1
For Period Ending 5/13/2026
City Secretary Contract Number
Contract Date
Contract Time 7 WD
Days Charged to Date 81 WD
75120 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
------------------------------------
Total Cost of Work Completed $85,910.36
Less % Retained $0.00
Net Earned $85,910.36
Earned This Period $85,910.36
Retainage This Period S0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$85,910.36
Monday, June 8, 2026 Page 4 of 4
FORT WORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME:
Alto Carter Park 35
PROJECT NUMBER:
106260
DOE NUMBER:
WATER
PIPE LAID
SIZE
TYPE OF PIPE
LF
8" Water Pipe
8"
PVC
40
12" Water Pipe
12"
PVC
12
FIRE HYDRANTS:
VALVES (16" OR LARGER)
PIPE ABANDONED
SIZE
TYPE OF PIPE
LF
N/A
DENSITIES:
NEW SERVICES:
2" Water Service
Copper
30
SEWER
PIPE LAID
SIZE
TYPE OF PIPE
LF
PIPE ABANDONED
SIZE
TYPE OF PIPE
LF
8" Sewer Line Removed
8"
PVC
5
DENSITIES:
NEW SERVICES:
TRANSPORTATION AND PUBLIC WORKS
FORT WORTH.
TRANSPORTATION AND PUBLIC WORKS
June 4, 2026
Dallas Underground, LLC
PO Box 1117
Ennis, TX 75120
RE: Acceptance Letter
Project Name: Alto Carter Park 35
Project Type: Water, Sewer
City Project No.: 106260
To Whom It May Concern:
On June 2, 2026 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on June 4, 2026. The final inspection and
the corrected punch list items indicate that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on June 4, 2026, which is the date of the
punch list completion and will extend of two (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at Khal
JaafariCFW/IPRC 817-392-7872 100 Fort Worth Trail, Fort Worth, TX 76102.
Sincerely,
Khal Jaafari, Project Manager Khal Jaafart P.E.(J 14.223:16:33 CDT)
Greg Robbins, Program Manager
Cc: Dana Carr, Inspector
Gary Deyon, Inspection Supervisor
Lorie Pitts, Senior Inspector
Andrew Goodman, P.E., Program Manager
Kimley Horn, Consultant
Dallas Underground, LLC, Contractor
Alto South Fort Worth, LP, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared BEN BRATCHER,
CEO Of BRATJEN CONSTRUCTION, known to me to be a credible
person, who being by me duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
ALTO Carter Park 35 / 7953 & 7973 South Freeway / Fort Worth, TX,
76134
Subscribed and sworn before me on
Notary Public
County, State
BRATCHER, CEO
12th of June, 2026.
Melonie Commission
n Lowrie
My Commisslon Expires
* 1/29/2028
Notary ID126455575
CONSENT OF SURETY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
TO OWNER:
(Name and address)
City of Fort Worth
311 W. 10th Street,
Fort Worth, TX 76102
PROJECT:
(Name and address)
Water & Sewer Improvements to Service Alto Carter Park 35
Public Utilities
Bond No: 108315305
OWNER
ARCHITECT
CONTRACTOR
SURETY
OTHER
ARCHITECT'S PROJECT NO.:
CONTRACT FOR: OCP: $85,910.36
FCP: $85,910.36
CONTRACT DATED:
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(Insert name and address of Surety)
----Travelers Casualty and Surety Company of America
One Tower Square,
Hartford, CT 06183
,SURETY,
on bond of
(Insert name and address of Contractor)
Bratjen Construction Company
1701 E. Lamar Blvd., Suite 150,
Arlington, TX 76006
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve the Surety of any
of its obligations to
(Insert name and address of Owner)
City of Fort Worth
311 W. 10th Street,
Fort Worth, TX 76102
OWNER,
as set forth in said Surety's bond.
IN WITNESS WHEREOF, the Surety has hereunto set its hand on this date: June 11, 2026
(Insert in writing the month followed by the numeric date and year)
Attest: / 0m,
Crosby Guercio, Witness
Travelers Casualty and Surety Company of America
(Surety)
(Signature of authorized representative)
Sean J. McCauley, Jr. Attorney -in -Fact
(Printed name and title)
S-2134/GE 10101
XDP
Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
TRAVELERS J St. Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and
St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein
collectively called the "Companies"), and that the Companies do hereby make, constitute and appoint SEAN J MCCAULEY JR of
DALLAS , Texas , their true and lawful Attorney(s)-in-Fact to sign, execute, seal and
acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of
the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April,
2021.
�iIM.M
i°��yC �Jp}.TY Aka
c g W "
w osm
• P� " - o
State of Connecticut
City of Hartford ss.
By:
Robert L. Raney4tenior Vice President
On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior
Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the
purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF, I hereunto set my hand and official seal. ;/f%//fy�7 JJyry ptf/J/f
My Commission expires the 30th day of June, 2026 �* �z
n PUs1ac : Anna P. Nowik, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of
the Companies, which resolutions are now in full force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice
President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint
Attorneys -in -Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority
may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings
obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may
remove any such appointee and revoke the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or
any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided
that each such delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance,
or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive
Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the
Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary;
or (b) duly executed (under seal, if required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her
certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President,
any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to
any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys -in -
Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of
Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed
and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or
understanding to which it is attached.
I, Kevin E. Hughes, the undersigned, Assistant Secretary of each of the Companies, do hereby certify that the above and foregoing is a
true and correct copy of the Power of Attorney executed by said Companies, which remains in full force and effect.
Dated this 11th day of June , 2026
i
S/CHAKFFw H CNN. n j C+fl1SG4a RG.
mot, � c
Kevin E. Hughes, Assi tant Secretary
To verify the authenticity of this Power ofAttorney, please call us at 1-800-421-3880,
Please refer to the above -named Attorneys) -in -Fact and the details of the bond to which this Power ofAttorney is attached.