Loading...
HomeMy WebLinkAbout061533-A5 - General - Contract - EMA, Inc.CSC No. 61533-A5 FIFTH AMENDMENT TO FORT WORTH CITY SECRETARY CONTRACT NO. 61533 This Fifth Amendment to Fort Worth City Secretary Contract No. 61533 ("Fifth Amendment") is made between the City of Fort Worth ("City"), a Texas home -rule municipal corporation, by and through its duly authorized Assistant City Manager, and EMA, Inc. a Minnesota corporation ("Vendor"), by and through its duly authorized representative. The entities may be referred to individually as a "party" and collectively as the "parties." WHEREAS, the City is in the process of completing the Water Customer Information System (CIS) Meter -to -Cash Program project (City Project No. 104667) (the "CIS Project"), WHEREAS, as authorized by Mayor and Council Communication (M&C) 24-0235, on June 7, 2024, the City and Vendor entered into that certain agreement known as Fort Worth City Secretary Contract No. 61533 (the "Agreement") for Vendor to provide consulting services in three phases to replace the existing Water Department customer information system; WHEREAS, the Vendor has completed Phases 1 and 2 of its requirements as specified in the Agreement; and WHEREAS, on May 12, 2026, the Fort Worth City Council approved M&C 26-0349, which authorized the execution of a contract with Itineris NA, Inc. for the provision of a new Customer Information System to the City; and WHEREAS, as authorized under M&C 26-0349, the Fort Worth City Council authorized the City to begin Phase 3 services under the Agreement which will consist of Vendor's consulting services related to the implementation and successful launch of the CIS Project ("Phase 3 Services"); and WHEREAS, the parties desire to amend the Agreement to begin Phase 3 Services; WHEREAS, on June 12, 2025, the parties executed the Second Amendment to the Agreement, which increased the total spending authority from $385,178.00 to $454,488.00; and WHEREAS, on July 25, 2025, the parties executed the Third Amendment to the Agreement, which included a revised pricing Exhibit, but did not include language formally increasing the spending authority of the Agreement by the pricing in the Exhibit; and WHEREAS, the parties desire to amend the Agreement to clarify and formally increase the spending authority for the Phase 2 services provided by the Vendor based on Exhibit "B" from the Third Amendment; and WHEREAS, the parties also desire to increase the spending authority by $1,084,446.00 under the Agreement for the Vendor to perform the Phase 3 services, with a new total authorized amount up to $2,284,285.00. NOW THEREFORE, known by all these present, Fort Worth and Vendor, acting herein by the through their duly authorized representatives, agree to the following terms, which amend the Agreement as follows: OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 1 of 17 I. AMENDMENTS 1. The City and Vendor agree that the Third Amendment to the Agreement increased the Agreement's spending authority by $745,351.00, and that the total spending authority under the Agreement as of the execution of the Third Amendment is an amount up to $1,199,839.00. 2. The Agreement is hereby amended to incorporate the terms of the EMA Phase III Compensation and Payment Schedule, attached to this Fifth Amendment as Exhibit A-1. 3. The Agreement is hereby amended to increase the authorized spending authority by $1,084,446.00 to an amount up to $2,284,285.00 to authorize Phase 3 professional services throughout the implementation of CIS Project and related software integration. 4. All other terms, provisions, conditions, covenants and recitals of the Agreement not expressly amended herein shall remain in full force and effect. [Signature Page Follows] Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 2 of 17 Executed to be effective as of the date signed by the Assistant City Manager below. CITY OF FORT WORTH: 1 By: �� Name: Jesica McEachern Title: Assistant City Manager Date: 06/17/2026 APPROVAL RECOMMENDED: Christophor ffairder By: Christopher Harder Jun 5, 2026 10:55:10 CDT) Name: Christopher Harder Title: Director, Water Department ATTEST: 9FORTa�c ooFe, qap AOp.10 C/� QaCnn>BxP5o4 By: I\ Name: Jannette S. Goodall Title: City Secretary IN&W Name: Michael Moosavi Title: Vice President Date: 5/11 /2026 CONTRACT COMPLIANCE MANAGER: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. am Richard Lisenbee (Jun 2, 2026 17:14:41 CDT) Name: Richard Lisenbee Title: Senior IT Manager, Water Dept. APPROVED AS TO FORM AND LEGALITY: M. Kevin Anders, II (Jun 5, 2026 11 :53:27 CDT) Name: M. Kevin Anders, II Title: Assistant City Attorney CONTRACT AUTHORIZATION: M&C: 26-0349 Approval Date: 05/12/2026 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 3 of 17 EMA SOW FOR FT. WORTH WATER CIS IMPLEMENTATION IMPLEMENTATION OF CIS SOFTWARE SOLUTION AND SYSTEM INTEGRATIONS SCOPE OF WORK TABLE OF CONTENTS SCOPE OF WORK (SOW)..........................................................................1 FWWD CIS Implementation Advisory and Quality Assurance Services ...........................1 1. EXECUTIVE SUMMARY.........................................................................3 2. PHASE -BASED SCOPE OF WORK.......................................................4 Phase 1: Pre -Implementation Readiness Assessment (Duration: —4 weeks)...................4 Task 1.1 — Implementation Readiness and Gap Assessment................................................4 Task 1.2 — Data Readiness and Cleansing Assessment........................................................ 4 Phase 2: Governance and Pre -Configuration Review (Duration: —2-3 weeks) ................5 Task 2.1 — Governance Structure and Effectiveness............................................................. 5 Phase 3: Analysis Phase Advisory and QA (Duration: 3 months).....................................5 Task 3.1 — Workshop Participation and Requirements Validation .......................................... 5 Task 3.2 — Documentation Review and QA........................................................................... 6 Task 3.3 — Phase Assessment Report................................................................................... 6 Phase 4: Design Phase Advisory and QA (Duration: 4 months).......................................6 Task 4.1 — Design Validation Workshops............................................................................... 6 Task 4.2 — Testing and Acceptance Review.......................................................................... 7 Task 4.3 — Training Effectiveness Assessment...................................................................... 7 Task 4.4 — Phase Assessment Report................................................................................... 7 Phase 5: Development Phase Advisory and QA (Duration: 6 months) .............................8 Task 5.1 — Configuration, Process Validation, and Data Cleansing ....................................... 8 Task 5.2 — Testing Strategy and Execution............................................................................ 8 Task 5.3 — Training and Readiness Monitoring...................................................................... 9 Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 4 of 17 Task 5.4 — Phase Assessment Report................................................................................... 9 Phase 6: Deployment and Go -Live Support (Duration: 7 Months)..................................10 Task 6.1 — Deployment Monitoring....................................................................................... 10 Task 6.2 — Go -Live Advisory Support...................................................................................10 Phase 7: Post Go -Live Stabilization (Duration: 3 months)..............................................10 Task 7.1 — Operational Performance Monitoring..................................................................10 Phase 8: Governance and Communication.....................................................................11 OPTIONAL SERVICES.............................................................................12 Phase 9: Post Go -Live Module Advisory (Optional)........................................................12 Task 9.1 — Module Evaluation and Planning........................................................................ 12 Phase 10: Ongoing Advisory and Issue Resolution (As Needed)...................................12 Task10.1 — Targeted Support............................................................................................. 12 IMPLEMENTATION PRICING..................................................................13 OPTIONAL PRICING................................................................................14 Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 5 of 17 1. EXECUTIVE SUMMARY FWWD's selection of Itineris as its CIS implementation partner is an important milestone in the program. The upcoming execution phase will determine how successfully that investment delivers operational improvements, billing stability, and sustained organizational confidence. EMA's role in Phase 3 is clear and focused. We strengthen execution. As an independent utility focused advisory firm, we have supported multiple water and wastewater utilities through CIS implementations, modernization efforts, and post go live recoveries. That experience allows us to recognize patterns early, where risk tends to accumulate, where assumptions often go unchallenged, and where operational impacts surface later than expected. We do not replace FWWD leadership, and we do not duplicate Itineris responsibilities. Instead, we serve as FWWD's experienced advisor, reinforcing governance, validating completeness, and protecting operational and financial integrity across the implementation lifecycle. In our experience, projects encounter difficulty not because teams lack commitment, but because: • A requirement was assumed but never fully defined • A dependency was underestimated • Testing scenarios did not reflect real operational workflows • Data quality risks were addressed too late • Executive visibility came after a problem had already escalated Phase 3 is structured specifically to prevent those outcomes. Our involvement enhances collaboration between FWWD and Itineris by reinforcing accountability, clarifying expectations, and providing leadership with objective readiness assessments at critical points in the project. Thank you in advance for reviewing our proposal and looking forward to the opportunity to discuss how our proposal can bring transformative benefits to FWWD. Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 6 of 17 2. PHASE -BASED SCOPE OF WORK Phase 1: Pre -Implementation Readiness Assessment (Duration: -4 weeks) Task 1.1 — Implementation Readiness and Gap Assessment EMA will leverage its deep knowledge of the Fort Worth Water Department (FWWD) and experience with the Itineris CIS platform to evaluate organizational readiness and position the program for successful execution. This phase focuses on assessing FWWD's preparedness across all implementation stages, with particular emphasis on data quality, governance, and risk mitigation. Objective Assess FWWD's readiness across all implementation phases and identify risks, gaps, and success factors. Approach • Evaluate current state across organization, process, data, and technology • Review Risk Register and identify risks that may impact schedule, cost, or quality • Assess likelihood of success for each implementation phase • Conduct working sessions with key stakeholders Deliverables • Readiness and Gap Assessment Report • Risk register and mitigation strategies review • Executive summary briefing Task 1.2 — Data Readiness and Cleansing Assessment EMA will conduct a comprehensive review of ongoing data cleansing efforts, collaborating with FWWD stakeholders to identify high -risk data elements, prioritize remediation activities, and establish clear ownership across business and IT functions. By addressing data integrity issues early, this phase is designed to reduce the risk of billing errors, reconciliation challenges, and operational disruption at go -live. Objective Ensure data quality supports accurate billing and successful system conversion. Approach • Review data cleansing efforts and governance • Identify high -risk data elements • Define remediation priorities and ownership Deliverables • Data quality assessment • Data remediation roadmap Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 7 of 17 Phase 2: Governance and Pre -Configuration Review (Duration: -2-3 weeks) Task 2.1 - Governance Structure and Effectiveness During the Governance and Pre -Configuration phase, EMA will perform a structured review of project governance and planning artifacts to ensure the CIS implementation is established on a solid foundation. This includes evaluating key documents such as project plans, detailed schedules, RAID logs, and resource allocations to confirm alignment with leading practices and project objectives. EMA will identify gaps, risks, and inconsistencies that may impact execution and provide targeted recommendations to strengthen governance, accountability, and delivery discipline. All findings and feedback will be coordinated closely with the FWWD Project Manager to ensure alignment, clarity of ownership, and timely incorporation into the project framework, enabling a well -controlled and efficiently managed implementation moving into subsequent phases. Objective Ensure governance supports effective oversight and timely decision -making. Approach • Review governance structure, roles, and escalation paths • Participate in Executive Team and Steering Committee meetings in an advisory capacity • Provide recommendations to strengthen governance and accountability Deliverables • Governance assessment and recommendations • Ongoing advisory input during governance meetings Phase 3: Analysis Phase Advisory and QA (Duration: 3 months) During the Analysis phase, EMA will provide independent oversight and advisory support to validate the completeness, accuracy, and readiness of key project activities and deliverables. Task 3.1 - Workshop Participation and Requirements Validation EMA will participate in analysis workshops, as needed, to assess the rigor of Itineris in identifying and documenting business, functional, and technical requirements, as well as FWWD's ability to provide the necessary level of detail and maintain alignment with project timelines. Objective Ensure completeness and accuracy of business and system requirements. Approach • Participate in Analysis Phase workshops, including: o Customer and account management o Billing and rate structures o Meter -to -cash processes o Service orders and field operations o Collections and revenue recovery o Reporting and integrations • Evaluate requirement completeness and alignment • Provide real-time feedback Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 8 of 17 Deliverables • Workshop observations and feedback • Requirements completeness assessment Task 3.2 — Documentation Review and QA EMA will review and provide real-time feedback on critical artifacts, including the project plan, business scenario documentation, product (rate) catalog, gap list, master training strategy, and core team training plan, ensuring consistency, quality, and alignment with leading practices. EMA will also participate in regular status meetings and coordinate all observations and recommendations with the FWWD Project Manager to maintain transparency and accountability. Objective Validate key project deliverables for accuracy and completeness. Approach Review and provide feedback on: • Project plan • Business scenarios • Rate and product catalog • Gap list • Training strategy Deliverables • QA review log • Consolidated recommendations Task 3.3 — Phase Assessment Report The phase will conclude with a post -phase assessment report, delivered no later than 30 days after completion of the Analysis phase, summarizing performance, identifying outstanding gaps, and recommending corrective actions to support downstream success. Deliverables • Post -Analysis Phase Report • Readiness assessment for Design Phase Phase 4: Design Phase Advisory and QA (Duration: 4 months) EMA will provide independent oversight and advisory support to validate whether system design activities are aligned with project objectives, business requirements, future -state operations, and data readiness objectives. To ensure transparency and timely issue resolution, we will participate in regular status meetings and maintain close coordination with the FWWD Project Manager. Task 4.1 — Design Validation Workshops EMA will participate in Design Validation Workshops to assess end -to -end process design, billing configuration, integration design, data cleansing effectiveness, data conversion readiness, and reporting and controls. Through these activities, EMA will proactively identify design risks and gaps and provide targeted feedback to strengthen solution alignment and implementation quality. Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 9 of 17 Objective Ensure system design aligns with business requirements and future -state operations. Approach • Participate in Design workshops covering: o End -to -end process design o Billing configuration o Integration design o Data conversion o Reporting and controls • Identify design risks and gaps Deliverables • Design validation feedback • Risk and gap log Task 4.2 — Testing and Acceptance Review EMA will review and provide real-time feedback on key testing artifacts, including the unit test plan and system acceptance criteria, ensuring that the testing strategy is complete, accurate, and aligned with defined requirements. Objective Ensure testing strategy supports successful validation. Approach • Review unit testing and system acceptance criteria • Validate alignment to requirements Deliverables • Testing readiness assessment Task 4.3 — Training Effectiveness Assessment EMA will monitor Core Team Training sessions to evaluate training effectiveness, participant comprehension, and overall organizational readiness, offering actionable recommendations to enhance knowledge transfer and preparedness. Objective Ensure core team readiness. Approach • Monitor training sessions • Evaluate effectiveness and readiness Deliverables • Training assessment summary Task 4.4 — Phase Assessment Report The phase will conclude with a comprehensive post -phase assessment report, delivered no later than 30 days after completion of the Design phase, summarizing performance, identifying remaining Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 10 of 17 risks and gaps, and recommending corrective actions to support successful progression into subsequent phases. Key outputs will include design validation feedback, a risk and gap log, testing readiness assessment, and training assessment summary to support successful progression into subsequent phases. Deliverables • Post -Design Phase Report Phase 5: Development Phase Advisory and QA (Duration: 6 months) During the Development phase, EMA will provide independent oversight and advisory support to ensure that system configuration, data readiness, testing preparation, and training development activities are progressing in alignment with project objectives and leading practices. EMA will participate in development workshops, as needed, to provide targeted review and feedback on configuration decisions and solution alignment. To ensure timely communication of findings and recommendations, EMA will participate in regular status meetings and close coordination with the FWWD Project Manager. Task 5.1 — Configuration, Process Validation, and Data Cleansing EMA will participate in development workshops, as needed, to provide targeted review and feedback on configuration decisions and solution alignment. Ongoing assessment of data cleansing efforts will continue to ensure data quality risks are being effectively mitigated in advance of testing and conversion. Objective Ensure system configuration aligns with approved design. Approach • Review configuration and process documentation • Review and assess ongoing data cleansing activities • Validate alignment with requirements Deliverables • Configuration and process QA feedback • Data cleansing feedback Task 5.2 — Testing Strategy and Execution During the Testing phase, EMA will provide structured oversight and advisory support to ensure testing activities are executed with discipline, operational realism, and a strong focus on data integrity and revenue protection. EMA will validate that testing is comprehensive, business -driven, and aligned with FWWD's operational requirements to support a stable and confident transition to production. Objective Ensure the CIS solution is thoroughly tested across all phases, with validated data integrity, system functionality, and billing accuracy, minimizing risk to operations and revenue at go -live. Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 11 of 17 Approach • Integration Testing: Validate end -to -end data exchanges and interface functionality across upstream and downstream systems, ensuring accurate data flow, reporting outputs, and cross -system process integration. • System Testing: Assess overall system functionality, configuration accuracy, and process execution to confirm that the CIS operates as designed across core business functions. • User Acceptance Testing (UAT): Support development and execution of business -driven test scenarios aligned to FWWD's real -world operations, including exception workflows and edge conditions, to ensure operational readiness and user confidence. • Parallel Shadow Billing Testing: Oversee parallel billing validation against the legacy system to confirm rate accuracy, calculation logic, and reconciliation of billing outputs, ensuring discrepancies are identified and resolved prior to customer impact. Deliverables • Testing assessment Testing plans and governance framework review • Testing execution and readiness assessment • Data integrity and reconciliation validation summary • Shadow billing variance analysis and revenue risk assessment • Consolidated testing findings and recommendations for go -live readiness Task 5.3 — Training and Readiness Monitoring EMA will review end -user training course specifications and the master training strategy, while monitoring select training classes to assess team knowledge transfer and readiness. Objective Ensure team readiness. Approach • Evaluate training delivery and readiness • Monitor select training classes Deliverables • Readiness assessment Task 5.4 — Phase Assessment Report The phase will conclude with a post -phase assessment report, delivered no later than 30 days after completion of the Development phase, summarizing overall performance, identifying outstanding gaps, and recommending corrective actions to support successful transition into testing and deployment. Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 12 of 17 Deliverables • Post -Development Phase Report Phase 6: Deployment and Go -Live Support (Duration: 7 Months) During the Deployment and Go -Live Support phase, EMA will provide independent oversight and targeted advisory services to support a stable, controlled, and low -risk transition to production operations. EMA will also participate in regular status meetings to maintain visibility into progress, facilitate cross -team communication, and enable prompt issue resolution. Task 6.1 — Deployment Monitoring EMA will monitor the execution of deployment and cutover activities in real time, ensuring alignment with the approved deployment strategy while proactively identifying risks and issues that could impact billing accuracy, customer service, or system performance. Objective Ensure successful execution of deployment activities. Approach • Monitor cutover planning and execution • Provide advisory support during deployment Deliverables • Deployment readiness feedback Task 6.2 — Go -Live Advisory Support Working closely with the FWWD Project Manager, EMA will validate the effectiveness of cutover execution, provide timely and actionable recommendations, and support rapid decision -making during this critical transition period. Approach • Support FWWD during go -live • Monitor issue resolution and system performance Deliverables • Go -live assessment summary Phase 7: Post Go -Live Stabilization (Duration: 3 months) During the Post Go -Live Stabilization phase, EMA will provide oversight and advisory support to ensure system stability, operational continuity, and performance optimization following deployment. Task 7.1 — Operational Performance Monitoring EMA will monitor system performance, track and assess issues, and participate in regular status meetings to maintain visibility into operational conditions and emerging risks. This phase focuses on confirming that the CIS solution is functioning as intended, identifying opportunities for process and system optimization, and supporting FWWD in transitioning from project mode to steady-state operations. EMA will deliver an operational assessment and provide targeted recommendations to Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 13 of 17 enhance performance, improve efficiency, and address any residual issues to ensure long-term success. Objective Ensure stable operations and performance. Approach • Participate in status meetings • Monitor system performance and issues • Identify optimization opportunities Deliverables • Operational assessment • Optimization recommendations Phase 8: Governance and Communication Governance and Communication activities will be maintained throughout the CIS implementation to ensure strong oversight, proactive risk management, alignment, and effective decision -making across all levels of Fort Worth Water Department. EMA will serve in an overarching governance and advisory role, leveraging its knowledge of FWWD's environment to continuously assess readiness, validate execution capacity, identify risks to schedule and outcomes, and ensure gaps are actively managed with clear mitigation strategies. Approach Throughout the project lifecycle, EMA will: • Assess Readiness and Performance: Continuously evaluate FWWD's ability to execute each phase, identify risks and gaps impacting schedule, budget, or quality, and provide actionable recommendations to improve outcomes. • Maintain Governance Cadence: Support structured governance forums with real-time advisory input to drive timely decisions, course correction, and alignment across all workstreams. • Monitor Schedule and Risks: Track schedule adherence and cross-workstream dependencies, identify early warning indicators, and escalate critical risks and decisions through established governance channels. • Support Executive Governance and Coordination: Provide data -driven insights to Executive and Steering Committees, advise on key decisions, and ensure alignment, accountability, and effective communication across FWWD, vendors, and stakeholders. Deliverables • Early warning insights with recommended corrective actions • Independent review of the PM's risk and issue logs • Periodic review of schedule health and critical path Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 14 of 17 OPTIONAL SERVICES In addition to the core implementation support, EMA proposes a set of optional advisory services designed to enhance long-term value, optimize system utilization, and support continuous improvement following go -live. These optional services extend EMA's role as a trusted advisor beyond implementation, ensuring sustained success, improved decision -making, and continued alignment between FWWD's business objectives and its CIS investment. Phase 9: Post Go -Live Module Advisory (Optional) EMA will provide strategic advisory support to assist FWWD in evaluating and planning for the potential adoption of additional CIS modules. Task 9.1 — Module Evaluation and Planning This focuses on informed decision -making aligned with organizational priorities, operational needs, and long-term technology strategy. EMA will participate in planning and decision -making sessions, offering objective guidance on module suitability, sequencing, and value realization based on industry leading practices and project experience. Through this effort, EMA will deliver actionable recommendations to support FWWD in selecting and prioritizing modules that enhance system capabilities, improve operational efficiency, and maximize return on investment. Objective Support decision -making for additional modules. Approach • Participate in planning and decision meetings • Provide advisory input Deliverables • Module advisory recommendations Phase 10: Ongoing Advisory and Issue Resolution (As Needed) EMA will provide flexible, on -demand support to address emerging issues and evolving operational needs following system implementation. Key outcomes will include actionable issue resolution recommendations and guidance to strengthen processes, enhance system utilization, and sustain long-term operational success. Task 10.1 — Targeted Support This is designed to deliver targeted, deep -dive analysis and advisory services to resolve complex challenges, optimize system performance, and support continuous improvement. EMA will engage as needed through approved task orders, ensuring that support is aligned with FWWD's priorities and delivered efficiently. Approach • Provide deep -dive support for emerging issues • Execute through approved task orders Fifth Amendment to Fort Worth City Secretary Contract No. 61533 Page 15 of 17 Deliverables Issue resolution recommendations This scope of work positions EMA as a trusted advisor embedded within both the governance structure and day-to-day execution of the FWWD CIS implementation. Through active participation in Executive Team and Steering Committee meetings, combined with structured phase -based advisory services, EMA will provide continuous insight, oversight, and guidance throughout the lifecycle of the project. By leveraging EMA's experience in CIS implementations, system integration oversight, and implementation quality assurance, FWWD strengthens its ability to proactively identify risks, improve decision -making, and maintain alignment between business objectives and system delivery. This approach enhances execution discipline, reinforces accountability across all stakeholders, and significantly increases the likelihood of a successful, on -time, and high -quality implementation that delivers long-term value to FWWD and its customers. IMPLEMENTATION PRICING The pricing presented below aligns with the level of effort, expertise, and oversight required to successfully implement the Itineris UMAX solution while minimizing risk and maximizing long-term value. It supports the resources needed across each phase of the implementation and leverages EMA's deep experience in utility CIS and Itineris implementation programs. EMA applies this expertise to proactively identify risks, drive informed decision -making, and strengthen execution discipline throughout the project lifecycle. Task 1.1 — Implementation Readiness and Gap Assessment HoursDollars 58 18,460 Task 1.2 — Data Readiness and Cleansing Assessment 48 10,176 Task 2.1 — Governance Structure and Effectiveness 30 9,492 Task 3.1 — Workshop Participation and Requirements Validation 484 135,736 Task 3.2 — Documentation Review and CIA 64 20,032 Task 3.3 — Phase Assessment Report 58 14.114 Task 4.1 — Design Validation Workshops 342 80,988 Task 4.2 — Testing and Acceptance Review 138 36,428 Task 4.3 — Training Effectiveness Assessment 84 17,808 Task 4.4 — Phase Assessment Report 41 10,864 Task 5.1 — Configuration, Process Validation, and Data Cleansing 240 58,960 Task 5.2 — Testing Strategy and Execution 772 167,704 Task 5.3 — Training and Readiness Monitoring 110 24,028 Task 5.4 — Phase Assessment Report 52 14,056 Task 6.1 — Deployment Monitoring 210 55.836 Task 6.2 — Go -Live Advisory Support 143 38,248 Task 7.1 — Operational Performance Monitoring 144 30,528 Phase 8: Governance and Communication 572 180,056 Sub -Total 3.590 S923,514 Expenses g 12% S110,822 Grand Total 3,590 S1.034.336 Fifth Aniendirient to Fort Worth City Secretary Contract No. 61533 Page 16 of 17 OPTIONAL PRICING In addition to core implementation support, EMA offers optional advisory services to supplement FWWD's team capacity and expertise. These services help enhance long-term value, optimize system utilization, and support continuous improvement after go -live, while reinforcing EMA's role as a trusted advisor aligned with FWWD's business objectives. Task 9.1 — Module Evaluation and Planning HoursTask 70 Dollars 22.420 Task 10.1 — Targeted Support - 22,000 Sub -Total 70 S44,420 Expenses (q! 12% S5,330 Grand Total 70 S49.750 Fifth Arnendirient to Fort Worth City Secretary Contract No. 61533 Page 17 of 17 CITY COUNCIL AGENDA Create New From This M&C Official site of the City of Fort Worth, Texas FoRTWORTH REFERENCE **M&C 26- 60WATER CIS DATE: 5/12/2026 NO.: 0349 LOG NAME: PROFESSIONAL CONSULTING SERVICES CODE: C TYPE: CONSENT PUBLIC NO HEARING: SUBJECT. (ALL) Authorize Execution of Amendment No. 5 in the Amount Up to $1,829,797.00 for a Vendor Services Agreement with EMA, Inc. for Professional Consulting Services Related to the Implementation of a New Customer Information System for the Water Department, Adopt Resolution Expressing Official Intent to Reimburse Expenditures from Proceeds of Future Debt, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-2030 Capital Improvement Program RECOMMENDATION: It is recommended that the City Council: 1. Authorize execution of Amendment No. 5 in an amount up to $1,829,797.00 to City Secretary Contract No. 61533, a vendor services agreement with EMA, Inc., for professional consulting services related to the implementation of the new Customer Information System for the Water Department for a revised contract amount of $2,284,285.00; 2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds of future enterprise fund debt for the Customer Information System Replacement; and 3. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Water & Sewer Commercial Paper Fund by increasing estimated appropriations in the Water CIS Meter to Cash Program project (City Project No. 104667) in the amount of $1,084,285.00 and decreasing estimated appropriations in the Commercial Paper project (City Project No. UCMLPR) by the same amount to effect a portion of Water's contribution to the Fiscal Years 2026-2030 Capital Improvement Program. DISCUSSION: The purpose of this Mayor and Council Communication (M&C) is to formally authorize Amendment No. 5 for an additional amount up to $1,829,797.00, to City Secretary Contract (CSC) No. 61533, the vendor service agreement with EMA, Inc., for professional consulting services throughout implementation of the new system and related integrations for a revised contract amount of $2,284,285.00, and appropriate $1,084,285.00 of additional funding. The Fort Worth Water Utility currently manages billing and revenue collection for water, wastewater, stormwater, solid waste, and environmental protection services through a legacy Customer Information System (CIS) that is more than thirty years old. In Fiscal Year 25, the CIS system billed more than $735 million in revenues for these services through 3.6 million transactions. This aging platform no longer aligns with modern operational or customer -service standards and requires extensive manual processes to support core business functions. The utility engaged consultant services from EMA, Inc. to perform a comprehensive needs assessment and identify the new CIS software solution. As requirements were developed, staff determined that the CIS replacement should include closely integrated systems, including the Customer Relationship Management System, meter data management integration, payment processing, and a new mobile workforce management component for field services. On November 14, 2023, M&C 23-0980 appropriated $500,000.00 for the hiring of a Water Utility Customer Information System Consultant. On March 26, 2024, M&C 24-0235, approved the execution of a contract with EMA, Inc. in the amount of $1,200,000.00 and appropriated $700,000.00. On June 7, 2024, the City entered into CSC No. 61533 with EMA, Inc. for Phase I services to provide a needs assessment and assistance in the development of the Request for Proposal specifications for the new CIS software solution in an amount up to $385,178.00. On June 18, 2024, the City executed the First Amendment with EMA, Inc. to replace the Payment Schedule of the contract. On June 12, 2025, the City executed the Second Amendment with EMA, Inc. to increase the spending authority of $385,178.00 for Phase I by $69,310.00 for additional project management advisory assistance for a total spending authority of $454,488.00. On July 25, 2025, the City executed the Third Amendment with EMA, Inc. to proceed with Phase II and incorporated a new pricing schedule of $745,351 for Phase II services through vendor selection but the amendment did not increase the spending authority for the contract. This spending authority will be added to Amendment No. 5. On August 26, 2025, the City executed the Fourth Amendment with EMA, Inc. to update Phase II project schedule documents. Amendment No. 5 will add the $745,351.00 from Amendment No. 3 and provide for professional consulting services in the amount of $1,084,446.00 for assistance throughout the implementation of the new system and related integrations for a revised contract amount of $2,284,285.00. EMA, Inc. will actively serve as an independent advisor and quality assurance partner throughout the process. EMA, Inc.'s involvement will strengthen data governance structures, improve data integrity, reduce operational and revenue risk, elevate deliverable quality, and drive accountability to ensure a controlled go -live and stable long-term operations. It is the practice of the Water Department to appropriate its Capital Improvement Program plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants. Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation authority authorized under the Callable Commercial Paper Program (CP) will be used to provide interim financing for this project until debt is issued. Once debt associated with this project is sold, bond proceeds will be used to reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution. Federal regulations require the City, as the bond issuer, to declare its intent to reimburse these portfolios with bond proceeds. Funding is budgeted in the Commercial Paper project within the W&S Commercial Paper Fund for the purpose of funding the Water Customer Information System Meter to Cash Program project. Appropriations for Water CIS METER TO CASH PGRM project are as depicted be Fund W&S Capital Projects - Funs 56002 W&S Commercial Paper - Fund 56026 Existing Additional project Total* Appropriations I Appropriations i $1,612,000.00 $0.00 $0.00 1$1,612,000.00 $1,084,285.00 $1,084,285.00 Project Total $1,612,000.00 $1,084,285.00 $2,696,285.00 There are two pending M&Cs that will appropriate additional funds to this project: 13PRFP25-0128 WATER CUSTOMER INFORMATION SYSTEM SOFTWARE WTR HO in the amount of $23,740,044.00 in Commercial Paper; and M&C 60WATER CIS INTERNAL STAFFING SUPPORT in the amount of $1,718,500.00 in Commercial Paper and $90,000.00 in PayGo. This project is located in ALL COUNCIL DISTRICTS. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that funds are available in the Commercial Paper project within the W&S Commercial Paper Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Commercial Paper Fund for the WATER CIS METER TO CASH PRGM project. Prior to any expenses being incurred, the Water Department has the responsibility of verifying the availability of funds. TO Fund Department Account Project Program Activity Budget Reference # Amount ID ID Year (Chartfield 2) FROM Fund Department Account Project Program Activity Budget Reference # Amount ID ID Year (Chartfield 2) Submitted for City Manager's Office by_ Originating Department Head: Additional Information Contact: ATTACHMENTS Jesica McEachern (5804) Chris Harder (5020) Chris Harder (5020) 60WATER CIS PROFESSIONAL CONSULTING SERVICES FID Table.xlsx (CFW Internal) 60WATER CIS PROFESSIONAL CONSULTING SERVICES funds avail.docx (CFW Internal) Commerical Paper Fund Balance.xlsx (CFW Internal) ORD.APP 60WATER CIS PROFESSIONAL CONSULTING SERVICES 56002 A026(R3).docx (Public) PBS CPN 104667.pdf (CFW Internal) Res.WATER CIS PROFESSIONAL CONSULTING SERVICES - JLM.docx (Public) CITY COUNCIL AGENDA Create New From This M&C REFERENCE **M&C 24- 13P RFP 24-0002 WATER CIS DATE: 3/26/2024 NO.: 0235 LOG NAME: CONSULTING SERVICES AW WATER CODE: P TYPE: CONSENT PUBLIC NO HEARING: SUBJECT. (ALL) Authorize Execution of Agreement with EMA, Inc. for the Purchase of Consulting Services Related to the Implementation of a New Water Customer Information System for the Water Department for a Contract Amount Up to $1,200,000.00 for a Five - Year Initial Term, Authorize Annual Renewal Options, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2024-2028 Capital Improvement Program RECOMMENDATION: It is recommended that the City Council: Official site of the City of Fort Worth, Texas Foe, T� rH Authorize execution of an agreement with EMA, Inc. for the purchase of consulting services related to the implementation of a new Water Customer Information System for the Water Department for a contract up to $1,200,000.00 for an initial five-year agreement term and authorize annual renewal options to be used only in the event that the project is not completed during the initial term; and Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water & Sewer Capital Projects Fund in the amount of $700,000.00, from available funds, for the purpose of funding the Water Customer Information System (CIS) Meter to Cash Program project (City Project No. 104667) to effect a portion of Water's contribution to the Fiscal Years 2024-2028 Capital Improvement Program. DISCUSSION: The Water Department approached the Purchasing Division for assistance with securing an agreement for the purchase of Water Customer Information System consulting services to replace their current CIS. The consulting services will be used to perform a needs assessment and assist in the development of the Request for Proposal (RFP) specifications for the CIS, and assist in selecting and implementing the new CIS. The project will take place in phases: phase 1 consists of the needs assessment and RFP development; phase 2 will consist of selecting a CIS replacement solution and system implementor; phase 3 will consist of implementation and successful launch of the new CIS. Purchasing issued an RFP that consisted of expectations and deliverables for each phase of the project, the qualifications and experience preferred, and the communication and project management requirements. The RFP was advertised in the Fort Worth Star - Telegram on November 1, 2023, November 8, 2023, November 15, 2023, November 22, 2023, November 29, 2023, and December 6, 2023. The City received twelve responses. However, upon an initial evaluation of responsiveness and responsibility, four proposers, Avero LLC dba Avero Advisors, Bid Lab, LLC, Ernst & Young, LLP, and Software Professionals, Inc. did not meet the minimum requirements for their proposal to be evaluated and were deemed non -responsive in accordance with the proposal documents. An evaluation panel consisting of representatives from the Water and Financial Management Services Departments reviewed and scored the proposals using Best Value criteria. During the technical evaluation, three proposers, Utility Planning Network, Validos, LLC, and Whitlock Consulting Group, LLC dba WCG Consulting, did not score at least 50\% of the total available points for technical criteria and were deemed non -responsive in accordance with the proposal documents. After the initial technical evaluations, the two firms with the highest scores, Raftelis Financial Consultants, Inc. dba Raftelis and EMA, Inc. were interviewed on January 17, 2024, and January 19, 2024, respectively. The City requested a Best and Final Offer (BAFO). EMA, Inc. submitted a BAFO resulting in changes to the points allocated for the cost of service; Raftelis chose not to submit a BAFO, and stayed firm on their initial offer. The individual scores were averaged for each of the criteria and the final scores are listed in the table below. Bidder F EMA, Inc. Raftelis Financial Consultants, Inc. dba Raftelis Berry, Dunn, McNeil & Parker, LLC 33 30 16 00 11 40 F35.10 14.80 9.90 — — _i 2'3.401'0.408.40F_ E Source Companies, LLC 24.30 13.60 7.20 Evaluation Factors 20.00 14.45 Proposer was not selected for an interview; therefore, cost was not evaluated Proposer was not selected for an interview; therefore, cost was not Total score 80.70 74.25 Proposer was not selected for an interview; therefore, cost was not evaluated Proposer was not selected for an interview; therefore, cost was not evaluated evaluated West Monroe Partners, Proposer was not selected for an Proposer was not selected for an LLC 25.20 10.80 7.20 interview; therefore, cost was not interview; therefore, cost was not evaluated evaluated Proposer did not score 50\% of the Proposer did not score 50\% of the Utility Planning Network 18.00 8.00 6.00 technical points; therefore, cost was technical points; therefore, cost was not evaluated not evaluated Proposer did not score 50\% of the Proposer did not score 50\% of the Validos, LLC 13.50 6.80 4.80 technical points; therefore, cost was technical points; therefore, cost was not evaluated not evaluated Whitlock Consulting Group, 23.40 7.20 Proposer did not score 50\% of the Proposer did not score 50\% of the 9.20 LLC dba WCG Consulting technical points; therefore, cost was technical points; therefore, cost was not evaluated not evaluated Best Value Criteria: a. Consultant's project approach and methodology for all three phases to provide services such as project management and execution of services b. Consultant's qualifications, project experience, and references c. Team's Key Personnel d. Cost of service After evaluation, the panel concluded that EMA, Inc. presented the best value. Therefore, the panel recommends that Council authorize an agreement with EMA, Inc. No guarantee was made that a specific amount of services would be purchased. Staff certifies that the recommended vendor's proposal met specifications. The initial phase of the project is estimated to cost $400,000.00. If the contractor and the City both agree to proceed with Phase 2 and 3 of the project, the contract will be amended to add the additional $800,000.00 as approved by this M&C up to $1,200,000.00. If not, the City will proceed with a new bid for a contractor for the remaining phases. Mayor & Council 23-0980, approved on November 14, 2023, funded phase 1 of this project. This M&C will fund the remaining balance needed for the entire project including any renewal option that may be exercised by the City. It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year, instead of within the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as follows: 6013P RFP 24-0002 WATER CIS CONSULTING SERVICES AW WATER - Work Capital Fund Name Project Name FY2024 CIP Authority Budget Revised FY2024 y Appropriations Adjustment Budget W&S Capital Projects — 104667 - Water CIS Meter To $500,000.00 This M&C $700,000.00 $1,200,000.00 Fund 56002 Cash Prgm Funding is currently available in the Unspecified -All Funds project within the Water & Sewer Capital Projects Fund for the purpose of funding the Water CIS Meter To Cash Program project. Appropriations for the Water CIS Meter To Cash Program project are as depicted below: Fund Existing Appropriations Additional Appropriations Project Total* W&S Capital Projects Fund 56002 $500,000.00 $700,000.00 $1,200,000.00 Project Total $500,000.00 $700,000.00 $1,200,000.00 *Numbers rounded for presentation purposes. DVIN-BE: A waiver of the goal for Business Equity subcontracting requirement is approved by the DVIN-BE, in accordance with the Business Equity Ordinance, because the purchase of goods or services is from sources where subcontracting or supplier opportunities are negligible. AGREEMENT TERMS: Upon City Council approval, this agreement shall begin upon execution and expire five years from that date. RENEWAL TERMS: This agreement may be renewed annually only in the event that the project is not completed during the initial term The expiration date of the agreement will not alter the maximum funding authorized for the agreement.This action does not require specific City Council approval provided that the City Council has appropriated sufficient funds to satisfy the City's obligations during the renewal term. ADMINISTRATIVE CHANGE ORDER: An administrative change order or increase may be made by the City Manager up to the amount allowed by relevant law and the Fort Worth City Code and does not require specific City Council approval as long as sufficient funds have been appropriated. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that funds are available in the Unspecified -All Fund project within the W&S Capital Projects Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the Water CIS Meter To Cash Prgm project to support the above recommendations and execution of the contract. Prior to any expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds. BQN\\ TO Fund Department Account Project Program —A—&—ivi—ty-F—Budg—e-il Reference # Amount ID ID Year I (Chartfield 2) FROM Fund Department Account Project Program Activity Budget I Reference # Amount ID ID Year Chartfield 2 Submitted for City Manager's Office by_ Originating Department Head: Additional Information Contact: ATTACHMENTS Reginald Zeno (8517) Fernando Costa (6122) Reginald Zeno (8517) Christopher Harder (5020) Jo Ann Gunn (8525) Alyssa Wilkerson (8357) 13P RFP 24-0002 WATER CIS CONSULT SVS AW WATER FID Table (WCF02.02.24).xlsx (CFW Internal) 13P RFP 24-0002 WATER CIS CONSULTING SERVICES AW WATER funds availabilitypdf (CFW Internal) Business Equity Waiver.pdf (CFW Internal) Form 1295- EMA, Inc.pdf (CFW Internal) ORD.APP 13P RFP 24-0002 WATER CIS CONSULTING SERVICES AW WATER 56002 A024(r2).docx (Public) pbs cpn 104667.pdf (CFW Internal) SAMs Report- EMA, Inc..pdf (CFW Internal) FORT WORTH. City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: EMA, Inc. Subject of the Agreement: Fifth Amendment to Fort Worth City Secretary Contract No. 61533 to ammend the Agreement to begin Phase 3 Services and increase spending authority. M&C Approved by the Council? * Yes 0 No ❑ If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes 0 No ❑ 61533 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes ❑ No 0 If unsure, see backpage for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: If different from the approval date. Expiration Date: If applicable. Is a 1295 Form required? * Yes 0 No ❑ *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. 104667 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes 0 No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department. FORT WORTH Water Routing and Transmittal Slip DOCUMENT TITLE: EMA, Inc. Amendment No. 5 to CSC 61533 for Water Department DOCUMENT OVERVIEW: Amendment No. 5 to CSC 61533, Vendor Services Agreement with EMA, Inc., for Professional Consulting Services Related to the Implementation of a New Customer Information System for the Water Department. TO ROLE APPROVER INITIALS EMA, Inc. Vendor Sr. IT Solutions Manager, Richard Lisenbee, Water Department Signer Shane Zondor, Assistant Director, Water Department Approver avid Zondor Jan Hale, Deputy Director, Water Department Approver X JH Chris Harder, Director, Water Department Signer Kevin Anders, Assistant City Attorney Signer Jesica McEachern, Assistant City Manager Signer Katherine Cenicola, Assistant City Secretary Approver K� Jannette Goodall, City Secretary Signer Allison Tidwell, Lead Admin Assistant, City Secretary's Office Form Filler Tim Shidal, Sr. IT Business Planner, Water Department Acceptor