HomeMy WebLinkAbout025334 - Construction-Related - Contract - Phoenix I Restoration and Construction, Ltd.� • CITY SECRETARY (�.�stttsC�O��t:
��" CONTRACT NO ���� r --�
Cot�cr�
�` ��C�NTRACIC?Q'S aaNDIN6 C0.
�- THE CITY OF FORT WORTH, TEXAS --�.��frFCRETARY
� cmr r�uau►a�rs o�c�
`' WILL ROGERS AUDITOI�IUM ������'
'� VVII,I, ROGER� 1VIEM012IAL CEIiTTElZ
n
�
F'OT aTH
�. �
. �:
.�
.�
���
�
c
�
L
.�
�
�
�
�
�
�,
.
�
�Nl�TTETI� BA�
MAYOR
BOB TERRELI,
CITY MANAGER
HUGO MALANGA, P. E.
DIRECTOR, TRANSPORTATION AND PUBLIC WORKS
KIRK STRICKLAND
PUBLIC EVENTS DIRECTOR
JIJLY, 1999
�
; _;;Cy��C�B�� G?�C����
�:; �� ����G?�`I�^ G��
�o , �G���Io 4��e —
,
/
G�
From: �ke Mathews 817-871-8488 To: L'nda Tayrior Date: 7J28199 Tima:14:33:00
� � .
�
�
�
�
�
a
a
�
�
�
�
a
�
�
�
�
�
�
CITY OF FORT WORTH
TRANSP4RTATION AND PUBLIC WORKS DEPARTMENT
AODENDUM NO. 1
RENOVATION 4F THE WILL ROGERS AUDITORIUM
Bid Opening Date: August 6,1999 (NO CHANGE)
The Contract Documents and Specifications for the above referenced project are
hereby revised and amended as follows:
The Mandatory Prebid Conference was heid at 1 Q:00 AM, July 20, 1999. The
following attended:
City of Fort Worth:
Mike Mathews
Nancy Richardson
Chris Harmon
Danny Rose
Contractors:
Jerry Zaskoda
Bob Prince
Alan Odom
Ken Williams
Don Johnson
Tony Rader
Ken Davis
Tiffany Pannell
Roy Parr
Jeff Rhoads
Ronald Maddox
Eugene Igbeka
Glenn Fullerton
Dale Glady
Chief, Architectural Services 871-8274 871-8488
Architectural Services 871-8014 871-8488
WRMC, Manager 871-5988 871-�3170
WRMC, Operations Supervisor 871-8165 871-8170
Tyson Bidg. Corp.
R.J.S. Painting
Phoenix 1 Rest. & Const.
K&S Coatings, Inc.
AU I
AUI
Phoenix I
Southcrest
Phoenix I Painting
Jones Blair Paint
Maddox Engr. & Const.
IKE Painting Co.
Lonestar Pla�tering
Ft. Worth
732-1471 732-1518
(972)513-19$5 (972)790-7749
{214)353-1 fi93 (214)353-1631
535-8085 535-8085
92fi-1t377 926-4387
926-4377 926-4387
353-1693 (214)363-1631
447-4367
(214�353-1693 (214)353-1631
732-3423 732-5071
922-8499 922-8819
(9�2)303-2352 (972)3Q3-2844
237-4044 237-2899
478-4078 483-4241
Addendum 1 Page 1 of 6
Page 1 af 6
l�
�
�
l�l
�
�
��l
�
LJ
�
��
l■'
l•i
l�J
lJ
lJ
I�J
�'�
From: Mik� M�hews 817-871-8488 To: Linda Taylor . Date: 7128159 Time:14:33:59
TECHNICAL SPECIFICATIONS
Addendum to Section 01010- Summary of Work
Page 2 of 6
01 PROJECT DESCRIPTION
F.1. Altemate No.1: delete "plaster repair as required".
First floor level removal af paint layers, verifv sound nlaster. scarifv
alaster laver to receiv auickset apalication, paint orie base coat, paint
two additional coats.
Plaster repair to inclu e wall area at southeast side aisle #111. All
additional plaster rep�ir to be included in chanqe orders.
Paint ceilinq tile at sid � aisle #111 … (color to match existinq).
Paint door frames at walls to be repainted (color ta match existinal
Protect doors to rema;n as existina, no paint. (Tvpical).
F.2. Alternate No. 2: d alete "plaster repair as required".
Second floor level rernoval of paint layers, verifv sound plaster, scarifv
plaster laver to receiv� quickset applicatian, p�int one base coat, paint
two additional coats. '
Plaster repair to inclu e restroom #301 ceilinq and wall. All additional
alaster reaair to be in luded in chanae orders.
Paint door frames at �valls to be repainted (color to match existinql.
Protect doors to remalm as existinq. no paint. (Tvpical).
F.3. Altemate No. 3 to be deleted.
02 CONTRACTOR USE OF Pf�EMISES
2. Base project (Prosceniur�) contractor will have control of facility without
interruption from Deceml�er 13. 1999 throuah Jar�uary 21. 2000. ,
Additional da��s required Imay be added throuqh the stock show with
continaencies includin4:, I
1. Leavinq no supplilas or debris in anv areas but thosc selected bv
the facilitv manaa�r
2. Gvt di a�l�� niu�l I�a� d4l:CSb LV �ldll:Vl ly S{Jdl:t7 LVWtxI CJ �I Itl IdL�CI
part of the stock ow as required bv facilitv manaaer
3. Contractor to pro ide e�ctreme caution for safetv of aublic.
5. Air supplv and return will be turned off in the f�cilitv durina work�
except as reauired b�'� facilities manaaer far events as sliown abave or
bv contractor. Heat nav be provided bv steam heat at the staae area.
�
Aulendum 1 Page 2 of 6
IL�J
�
l�
Fram: Mik� Malhewa 817-871-8488 To: LindaTaylor
Date:7/28199 Time:1t:35:00
Page 3 of 6
Addendum to Section 02060
�
�
f■�.
�
�
l�j
l■J
�
�
C''
l�J
�
�
L�l
�
�
02060- SURFACE PREPARATI�N
01 SCOPE
A. Remove ail paint layers to sound plaster base. Last 2 lavers of paint
were found to be alkyd base. ScarifV smooth plaster to receive thin
application of USGVpsum Imperial Brand Basecoat or equal to provide
smooth surface.
03 PROTECTIVE BARRIERS ANQ C4VERS
A. Pravide demolitian materials, barriers, protective covers to fixed seats
and carpet to complete the work as specified to ensure that no part of
the renovation is damaging to existing finishes and equipment during
the construction period. Ceilinq tile in side aisles #111 and #133 to be
reaainted. Doar frames to be repainted. Protect painted doors to
remain as existina.
Addendum to Section 92200
92200- PLASTER
01 GENERAL
Fumish all labor, materials, equipment, and services for a complete
installation of all plaster work, as shown on the drawings and as hereinafter
spec�ed, but not limited to the following:
A. Plaster repair for proscenium in Base Bid to consist of fillinq voids with
thin aaplication of non-lime containinq products, such as USGvpsum
Imaerial Brand Basecoat or equal, to provide smooth surface to match
existina. �
B. Plaster repair for Altemate #1 to include plaster application as in Base
Bid. with the exception of a 3-coat plaster patch on the southeast side
aisle #111. �
C. Plaster repair for Altemate #2 to include alaster ap�lication as in Base
Bid. with the exception of 3-coat plaster patches in Restroom #301.
Addendum 1 Page 3 of 6
��
�
�
�
�
�
�
�
�
�
�
�
�
�
1
1
1
1
�
�
Fran: Mik4 M�hews 817-871-8488 To: L'nda Taylor Dats: 7128/99 Timr 14:35:54
Page 4 of 6
02 INSTALLATION
B. Plaster
11. Cure time for thin application of finish plaster to be 2 days.
(Exceations noted above.)
3-coat plaster patch to be tesfed for condensation after
completion by placinq an 18" x 18" clear piece of polv film: duct
tape all edqes. Leave in place for 2-3 days. If condensation
forms. wait ta aa�lv aaint.
Acknowiedge the receipt of this addendum on your Proposa(.
H. A. MALANGA, P.E.
DIRECTOR OF TRANSPORTATION AND PUBLIC
WORKS
��
Nancy Richardson, Architectural Services
817-871-8014, Fax 871-8488
RELEASE DATE: July 22, 1999
Addendum 1 Page 4 af 6
l�J
�
�
L�J
I�I
�
�
Iwl
�;l
L�J
lJ
�
L�1
LJ
l�J
�
�
�
From: Mike Mathews 817-871-8488 To: Linda Taylor
Date:7l281fl9 Tim�:14:36:31
PROPOSAL
Revised Addendum 1
T0: MR. BOB TERRELL
CITY MANAGER
CITY OF FORT WORTH, TEXAS
FOR: WILL ROGERS AUDITORIUM RENOVATION
W ILL ROGERS MEMORIAL CENTER
34�1 W. LANCASTER AVE.
Page 5 of 6
Pursuant to the foregoing "Notice to Bidders," the undersigned has thoroughly examined the plans,
specifications and the site, understands the amour� of work to be done, and hereby proposes to do
all the work and furnish all labor, equipment and materials necessary to fully complete all the work as
provided in the plans and specifications, and subject to the inspection and approval of the Director of
Transpartation and Public Works of the City of Fort Wo�th.
Upon acceptance of this Proposal by the City Council, the bidder is bound to execute a contract and,
if the contract amount exceeds $25,000.00, furnish Pertormance andlor Payment Bonds approved by
the City af Fort Worth for performing and completing the Work within the time stated and for the
following sum, to wit:
DESCRIPTI�N OF ITEMS
Base Bid: (Proscenium, Front Walls}
Add Altemate 1: (Fi�st Flaor, Stai�s 11, 13, Ceiling under
Mezzanine}
Add Altemate 2: (Level 2, Mezzanine, Balcony)
Add Altemate 3: DELETE
The undersigned agrees to perform the base bid within the dates of December 13. 1999 and January
21, 2000. Work on selected alternates will be completed within 180 Calendar days and be scheduled
to avoid interference with Auditorium operations.
The City reserves the right to accept or reject any and all bids or any combination thereof proposed
for the above work.
The undersigned assures that its employees and applicants for employment and those of any labor
organization, subcontractors or employment agency in either furnishing or referring employee
applicants to the unde�signed are not discriminated against as prohibited by the terms of City
Ordinance 7278 as amended by City Ordinance 7400 (Fo�t Wotth City Code Section 13A-21 through
13A-29).
Residency of Bidders: The 1985 Session of the Texas Legislature passed house Bill 620 relative to
the award of contracts to non-resident bidders. The law provides that, in order to be awarded a
contract as low bidder, non-resident bidders (out of state cor�tr�etors whose corporate offices or
principal place of business are outside of the State of Texas} that bid projects for construction,
Addendum 1 Page 5 of,�
�
From: Mik� M�hews 817-871-8488 To: Linda Taylor Date: 7/28/99 Tims:14:37:33
a. �
Page 6 of 6
D �
improvements, supplies or services in Texas at an amount lower than the lowest Texas resident
� bidder by the same amount that Texas �esid�nt bidder would be required to underbid a non-resident
bidder in order to obtain a comparable contract in the state in which the non-residenYs principal place
of business is located. The appropriate blanks in Section A must be filled out by all non-resident ,
bidders in order for your bid to meet specifications. The failure of out of state or non-resident bidde�s
� Failure to complete the forms may disqualify that bidder. Resident bidders must check the box in
Section B.
f
I■��
A. , L� Non-resident vendors in (give state), our principal
place of business, are required to be percent lower than resident
bidders by state law.
LI Non-resident vendors in (give state), are not required to
underbid resident bidde�s.
B� LI Our principal place of business or corporate offices are in the State
of Texas.
� Withi� ten (10) days of receipt of notice of acceptance of this bid, the successful bidder will execute
the formal contract and will deliver an approved Surety Bond for the faithful pertormance of this
contact. The attached deposit check in the sum of Dollars ($_� is to become the
property of the City of Fort Worth, Texas, or the attached Bidder's Bond is to be forFeited in the event
� the contract and bond are not executed within the time set forth, as Iiquidated damages far delay and
additional work caused thereby.
'�l
I�J
�
�
�
�
L�J
�
�
�
MINORITY/WOMENS BUSINESS ENTERPRISE (M/WBE): �For bids in excess of $25,000)
• I am aware that I must submit information the Director, Transportation and Public Works,
conceming the MMIBE participation within FIVE BUSINESS DAYS of submittal of this Prapasal
in orderto be RESPONSIVE.
Respectfully submitted,
Campany Name
BY: .
Signature
Pririted Name of Principal
Address:
Street
City
Phone: Fax:
Receipt is acknowledged of the following addenda:
Addendum No. 1: Addendum No. 2:
Addendum 1 Page 6 of 6
Title
Zip
.�
u
�
O
�
�
�
�
�
�
D
a
I
�
�
�
�
�
�
�
�
From: Mike Malhews 817�871-8488 To: Linda Tayfor Date: 7/30/99 Time:18:0520
RENOVATION OF WILL ROGERS AUDITORIUM
(PP+INTING) 7/30/99
� CITY OF FORT WORTH
TRANSPORTATION AND PUBLIC WORkS DEPARTMENT
ADDENDLiM NO. 2
. ,r�, .
RENOVATIQN OF THE WILL ROGERS AUDITORIUM
Bid Opening Date: August 12, 1999 (POSTPONED ONE WEEh�
The Caniract Documents and Specitications far the above referenced project are hereby
revised and amended as follows:
TECHNICAL SPECIFICATIONS
Sectiun 01010 - Summary of Work �
Revise U1B to read:
O1B Thz BASE BID consists of complete paint removal in the Proscenium area.
Add Paragraph 03 as follows:
Q3 RENiOVAL OF LEAD BASED PAINT
A. The Gity of Fort WoRh, Deparirnent of Environinenta! Quality, has determined
the existence uf lead in auditoriuin paint samples. See Pages AZ-2 tl�rou�h 5 of
this Addendum.
B. AlI paint shalt be removed in compliance with the 4ccupational Safenf Health
Administration (OSHA} Lead in Consiructiun standard (29 CFR 1926.62).
Acknowledge the receipt of this addendum on your Proposal.
H. A. MALANGA, P.E.
DIRECTOR OF TRANSPORTATION AND PUBLIC
WORKS
:
Nancy Richardson, Architectural Services
817-871-801�, Fax 871-8488
RELEASE DATE: July 30, 1999
ADDErIDUM 2 PAGE A2-]
Page 1 of 5
From: Miks Mathews 817-871-8488 To: Linda Taylor Date: 7/30/D9 Time: 18:06:12
� .
L�I
�
�
�
TO:
FR4M:
DATE:
, . . , ,. - - ,..,,.
l+iat�cy tidt�rdsase
'�'rartsporlaHan/Pubftc Works
MiCilae! Gange, �r. Eavirom�enql Sp�Cigli�t
�ottlplit+noe
RENOVATIONOF WILL ROt�ERS AUDITORIUM
(PAINTING) 7/30i99
Fort �arth
��`
t;��1Y[i�.71'�111t[�tt�tL
MANAG�IV�£N t'
Page 2 of 5
u
'!'J
LJ
'�
L��
L#I
L�1
�
Iq{y 30, i994
Sl.�BSF�i': W+�I lto�ens �lemaial Cvl�um —As�ditorium Ar�ea.
.�����. _.._��
'`�f
Per your reques�, d�e Department of Env�-onrneniat Quality collect,�:J g paint �mp�as
frOm t�e auditonum ��e� wails and �iting f� �nalys�s oft�ota! lead. The 5ampie5
col�ec�ted ar►d analytfca] resutt� are pre.9ertteti C,elaw and tne laboratory re�oa-t ls
atfiaclled. �rgure �. d�i.ais t�e appraxlrna�te sample locatio+�s.
I Rai�ti 5amp�les
?uiY 29. I�9�
, ID�� Samrrk F�scripebn _ � 7ata! Lead
ftt+4/1cg�
WR Qi i.tqht qray uraii paint from eas� a�s(e near exit. I iY.300 �
I YVR-0Z R.�d wall/tri�lip�irtt frt)rn east aisle t1e�r e7dG I �+.560 �
' VYR-03 Dar[c arav watf/trim paint fram east ats(e �ear exi�, ; g,41p
exi=
� Wft Q4 Qark qcay walf/[rIm Raint ft'om nactft fobby rte�r rrraiR e�dt._ 1,730
�WR-OS �qht �r�y vva(I paint frorn r� Jo�by near mai� �c1t. � 5,4�8i1
WR-45 fted wa(Iliri►n Daint fi�om north labbY �ear nnaitt e�at 3g0 `
� WR-07 8ltje Cel{tn4 qai� from r�orth tobb�y naar �st WaIL � �42 �
WR-08 B(ue c�unq na'sc�t from narth lobbv at west end of main e�aC. 1 503 �
Na�: j
Sarr�r�las w2re anal�zed hv U.S. �nv3mnmentaf ProtQcnol'1 AaertiGv Metl�od 7�ZU. �
Based an the exist�lce of Iead la the palnt plar�rted i�r renwval tt�e Contracbr(s) mu�
� corrrpty with the C�ctdpatior�a[ Safety Heattie:Admirzt�tra�ion (�) Lead tn CQ►�strvc�an
st�ndard (29 C�li 1926.62} alang witf� a�i other epplicaWe heaith a�t� s�fety regutations.
�
�
�
L�J
P4ease oontact me at 871-85'92 offic�e ar 998-i996 pager w� any ques�:ion,. Th�rtk
yau.
ADDENDUM 2 PAGE A2 �
��J
�
�
�
'
1
�
�
i
�
1
I
�
�
�
�
�
�
�
'
From: Mike Mafhews 817-871-8488 To: Linda Taylor Date: l/30199 Timm:18:07:10
RENOVATION OF WILL ROGERS AUDITORIiTh,i
(PAINTINGl7(30/99 •
� �t�u�� �-
r�
.
.
�...._....r.
�
�
,r��'� � ���ciM�� �P�� t�c�t�
ADDENDUM 2 PAGB AZ-3
� ��~�
�, ,� � ,�„ w�•ar�
L,��'� .r� . .
- � ..I
'"�� w�oi ,
.� :�:.�-�—� �
,
�
,
�
�
,
�_..
,�*�3
�',�,�c.�
� �-ot
�
Page 3 of 5
r. �..,.,.�.
� �
�
�
L!'.I
�
�
��
�
�
�
�
CI
CI�
�
l'�J
F^J
�
�
l�J
�
From: Mike Malliews 817-871-8488 To: Linda Taylor Date: 7/3W99 Time:18:07:55
RENOVATION OF WILL RO(3ERS AUDITORIUM
(PAINTING) 7/30/99 '
�'��.5 ��1•
Forensic La vratoru �
xn�xnc��•r ��,,�.7eae2
31T-�Z �s1T,295�39tCi
July?�, 79g9
►
. �,►r.�«�rha
� �s-c�wn�s. Rs
� �Ke�u�usr:t, c[rs
luh. Nfichael 11. t^i$rge
Ciiy af Port Worth
'1DOQ 7hrockn�ortrxti Str�aat •
Fat YJcxth. TX TBia2-83i 1 .
siGe' WFtMG f3aCeEE�ed: Juiy 29, t�39
24011Nest La�ncaster Sub'rn[tlbd_ 8 F*�Ir�3amples
F'ort YWt'tF4 l7( . P.a.Nn.: EOOE2�3$3
tAEfOF�ATOfiY REPORI': 99i�{2520
�o�tu� EP11 MOthOd 7420
Lah � _, . _ ._ �@L�Cdott ., ,.,, _
.. Nurn6er ^ O�Srt Res�iptinn Test Req�l�sted Resufts ; Limii Un�
�82f45t3 Wit-a1 iohf taed - - 1 i.3+D� ; � -- • rr��
es265�t � wRrU2 sorat leacf a,56o ,� o ,,,�yk�
B62862 WR-03 7o2aE lead B,d90 : r 8 mglk� .'
� WR.�I " %tal t� Z.TBU ' � 7 ��
682854 1Nit-0S Tata! le.ad 5�{I80 � 1 a mBfkq
g$2855 1MR-06 Tpt�t lea� 38A 10 ►rg/k9
B�a6 1HEiA7 Total iead 342 ' ip r�ticy
_ 882$5% WE�-08 --.- _ 7'O�! ICGd 50� i g ry�� �;
1 � � .
J I44. CAtt1, M3. L.e�borelwy Di�Or I�Ia ' Acii[�tractg� MS��H,1�tH
R�Pditatton i�o: 363 V{OB ?t�rt of S�vices
HA eL.L�A ACc�d�ced
A99.3�G.dx/an '
� Prooidi�g a W'orlrf nf Sernicrs �if
ADDENDUM 2 PAGE A2-4
Page 4 of 5
0
r � � � � � � � � � � r � � � � � � �
b
d
�
�
b
�
�
�
��
r`�Y1`t2�"�"Qf2�' .t't�Y'2YtSiC ��iflDYI��O?`"i�r �Yl�. ���r��«•c�l �:11.�:+�1.., �l�I_�___,_iZO�,t;tiStV�
�oc.�,mc-�cw+ruu �r,�aa.r«�� �eoi:.:ua� ai�,z�s�►9�t,� ez:,2rs""""saea�():�tr,N.�nr�000+ __._._..........T..._.__. �i.7roXlment3l
1J fy� � -- ......,�....�
f'1 sM. �J� l!!i f . .... ......�.......�., ,
� C�xiiact: I�� i Prv�ecf; jf�lJi ( j �� AFL Case No,: � � l. k�� ;� ��-� c�} c''3
� c�ent: � `Sii� � ��f , (,� Dat�lte�c�'ived: �- �r�'�i `R � ,�. ,
j� Add�ess: I f. � -'TA3': •� it�utar Rush i��
: ,� . 5�mpler (� tabbtrvkaxequeexd �
Qlrottc iJO.: �( �' .. . �,,• Fax No:. ,���L� . ��i ...._. ,T , �
P.Q. Na: � TeAnp 0 Re�cetys�: �,4 . �
ce
i.ab SamP1s aJornwHoo Collecdon tnfa��t auan { C.'orWaa�s.lafa ,s �
[�1a. � a t.oatlon MaL�i�c Data 'iime GIG '� Slse Pm, ,� 1� {
� � tt1K-C�t i � dq / � - • . {-; a �
�. (�-fD2.. ' U4pZ / _ � � .
- CL? 0�'t}�I :� �. . .. .
- WiZ- � U`1Qfr � , 7( �
wf� - c.��r��s� .J X � .
u�- a� �o �� � .
• ; � ORJL % E - � �
� r � -� S �z��`t �i�� f t• / � _.
� � � . .. . —
'� ,.�.____---� �_.. . �.. �� -
� i�f�4. Rc�� }SY' Q /J%% • / � L�� �� ��� � �.euw �}' � � -. /�
.. �.`..,.JL��� � � �� �r... �����'� � � l�� �- r� r' I 'r
�etcm�ci �p;
iorie ittrCivtd '�— • , _, `-..
csu���.� % '1 �� - '�.y � j �ct Lnb t9�-• _ j
.. , . �. . � .�
�rouiriing• a Wur1d nf S�mtee�
; '" U ! � . 3r1��,,��., ��P
f
�... _�%
z
O
Y
H
°z
�o
r
��
�o
o�
��
�
H
'�
�
r.
l�'
�
I�
�
NOT{CE TO BIDDERS
Sealed bids for Will Roge�s Auditorium F2enovation, Will Rogers Memorlal Center, 3401 W.
Lancaster Ave, wili be received at the Purchasing Office, City of Fort Worth, 1000 Throckmorton,
Fort Worth, 76147, until 1:30 P.M., Thursday, August b, 7989 and wiil be opened and publicly
read aloud approximately thirly minutes later in the Council Chambers.
A rnandatoty Pre-Bid Conference will be held at 10:00, Tuesday, July 20, �899, at the Will
� Rogers Auditorium.
7he Project consists of hisivric interior plasfer and paint restoration.
� 7he MWBE Goal for this project (s 2�,°f,4. Contactthe MWBE office (871-6104) to obtain lists of
cer�fied subconVactors and suppilers.
� Contractors wi11 be required to post Payment an8 Performance Bonds and provide Contractors
Genera! Liability and Statutory Workers Compensation Coverage.
Copies of the Project Manuai and plans for this project may be obtained at the Department of
� Engineering Ptans Desk, City Hall, 1000 Throckmorton Street (817.871.7910) in return for a$50
deposif for each set. Fo� additiona! information contact Nancy Richardson, Architectural Services
Section, TPW, 817-871-8014.
Advertisement: Thursday, July 8, 1999
Thursday, July 15,1999
�
�
�
�
�
i�
l+�J
I�
,�
��
NTB-1
L�
�
�
��
�
�
�
�'
�
�
�
�
�
�
�
�'
�
�
�
��
TABLE OF CONTENTS
NOTICE TO BIDDERS NTB-1
TABLE OF CONTENTS TOC-1
INSTRUCTIONS TO BIDDERS ITB-1 to ITB-3
SPECIAL INSTRUCTION FOR BIDDERS (M/WBE) MWBE - 1 to 12
PROPOSAL P-1 to P-3
EXPERIENCE RECORD
GENERAL CONDITIONS GC-1 to GC - 21
WEATHER TABLE WT-1
PROJECT DESIGNATION SIGNS PDS - 1
WAGE RATES WR - 1
TECHNICAL SPECIFICATIONS SEE NEXT PAGE
CONTRACT C-1 to G2
PERFORMANCE BOND
PAYMENT BOND
CERTIFICATE OF INSURANCE
CONTRACTOR COMPLIANCE WITH WORKERS' COMPENSATION LAW
�
T'OC - 1
�����
�I
�
�
l�J
L�J
INSTRUCTIONS TO BIDDERS
1. PROPOSAL REQUIREMENTS: The following requirements are considered in judgina
the responsiveness of a Proposal:
• Use the Proposal Forrn provided in the Project Manual.
• Entries on the Proposal Form may be handwritten or typed
• Write in contract duration if not specified
• Acknowledge all Addendums on the Proposal Form
• Have a Principal sign the Proposal
• Enclose a bid deposit of 5%. This can be in the form of a cashiers check or
standard bid bond. Personal checks are not acce�table. Note Project Name on
the check or bid bond
2. MINORITY/WOMENS BUSINESS ENTERPRISE fM/WBE)
D If your bid is in excess of $25,000, the MWBE Program applies, and you have five City business
days following the bid date to prepare and submit your M/WBE Plan. Early submittal is
encouraged. Be aware that if you elect to provide documentation of a Good Faith Effort you will
have to accomplish each and every action in the Special Instructions to Bidders, Minority and
� Women Business Enterprises Specifications, included in this Project Manual. In order to meet all
the requirements for a Good Faith Effort you will have to start at least two weeks before the Bid
date.
�I
���
The lowest responsive, responsible, bidder meeting the M/WBE requirements will be
recommended for award. Information concerning participation of Minority and Women's Business
Enterprises is not required for Projects less than $25,000. All purchases from M/WBE suppliers,
second tier subcontractors and second tier suppliers may be included in M/WBE contribution
toward meeting the goal.
� The Bidder shall submit the M/WBE UTILIZATION FORM, PRIME CONTRACTOR WAIVER
FORM and/or the GOOD FAI7H EFFORT FORM {"Documentation") as appropriate. The
Documentation must be received no later than 5:00 P.M. five (5) City business days after the bid
0 opening date. The Bidder shall obtain a receipt from the appropriate employee of the managing
department to whom detivery was made. Such receipt shall be evidence that the Documentation
was received by the City.
tJ
���
L�J
L�J'
I��
L�J
Successful Bidder will be required to submit co-signed letters of intent or executed agreements
with all M/WBE subcontractors and suppliers prior to receiving a Notice to Proceed.
3. BID SECURITY: Cashier's check or an acceptable bidder's bond payable to the City of
Fort Worth, in an amount of five (5) per cent of the bid submitted. The Bid Security must
accompany the bid and is subject to forfeit fin the event the successful bidder fails to execute the
contract documents within ten (10) days after the contract has been awarded. The Bid Security
shall be included in the envelope containing the bid proposal. Failure to submit the Bid Security
will result in the proposal not being considered for this project. Bidder's bond will be returned if
the City fails to award the contract within 49 calendar days of receipt of bids, unless an extension
is agreed to by the Bidder.
4. PAYMENT BOND AND PERFORMANCE BOND: For projects in excess of $25,000, the
successful bidder entering into a contract for the work will be required to give the City surety in a
6/4/99
1TB - 1
l�l
L!'
I:��,
sum equal to the amount of the contract awarded. The form� of the bond shall be as herein
provided and the surety shall be acceptable to the City. All bonds furnished hereunder shall meet
the requirements of Article 5160 of the Revised Civil Statutes of Texas, as amended.
In order for a surety to be acceptable to the City, (1) the name of the surety shall be included on
� the current U. S. Treasury List of Acceptable Sureties (Circular 870), or (2) the surety must have
capital and surplus equal to ten times the amount of the bond. The surety must be licensed to do
business in the state of Texas. The amount of the bond shall not exceed the amount shown on
� the Treasury list or one-tenth of the total capital and surplus. If reinsurance is required, the
company writing the reinsurance must be authorized, accredited or trusteed to do business in
Texas.
'�
I��
��
I�
'�
L�J
'�
��
'I�
L�J
LJ
No sureties will be accepted by the City which are at the �time in default or delinquent on any
bonds or which are interested in any litigation against the City. Should any surety on the contract
be determined unsatisfactory at any time by the City, notice will be given to the Contractor to that
effect and the contractor shall immediately provide a new surety to the City.
If the total contract price is $25,000 or less, payment to the contractor shall be made in one lump
sum. Payment shall not be made for a period of 45 calendar days from the date the work has
been competed and accepted by the City.
If the contract is in excess of $25,000, a Payment Bond shall be executed, in the amount of the
contract, solely for the protection of all claimants supplying labor and materials in the prosecution
of the work.
If the contract amount is in excess of $100,000, a Performance Bond shall also be provided, in the
amount of the contract, conditioned on the faithful performance of the work in accordance with the
plans, specification, and contract documents. Said bond shall be solely for the protection of the
City of Fort Worth.
5. BOND SURETY: Preferred sureties for bonds required for the project are included on the
current U. S. Department of the Treasury - Fiscal Service list of companies holding certificates of
authority as acceptable sureties on federal bonds and as acceptable reinsuring companies
(Circular 570). The limit of a bond written by any one acceptable company shall not exceed the
amount shown on the Treasury list for that company. Alternate ratings are discussed in the
General Conditions.
Surety must be admitted to do business in the State and have capital and surplus equal to ten
times the limit of the bond. Any amount in excess of the ten percent limit must be reinsured by a
company or companies duly authorized, accredited or trusteed to do business in this state.
Should any surety for the contracted project be determined unsatisfactory at any time during
Project, the Contractor shall immediately provide a new surety bond satisfactory to the City.
The Owner will not accept sureties which are at the time in default or delinquent on any bonds or
which are interested in any litigation against the owner. All bonds shall be made on the forms
furnished by the Owner, and shall be executed by an approved surety company doing business in
the City of Fort Worth, Texas, and which is acceptable to the owner. Both the Contractor and
Surety Company shall properly execute each bond.
D 6. PRE-BID SITE INVESTIGATION: Prior to filing a bid, the bidder shall examine the site(s)
of the work and the details of the requirements set out in these specifications to satisfy himself as
to the conditions which will be encountered relating to the character, quality, and quantity of the
a work to be performed and materials and equipment required. The filing of a bid by the bidder shall
be considered evidence that he has complied with these requirements.
L�J
6/4/99
ITB - 2
�
�
7. AMBIGUITY: In case of ambiguity or lack of clearness in stating prices in the proposal,
� the City reserves the right to adopt the most advantageous construction thereof to the City or to
reject the proposal.
�
�
C��
8. WAGE RATES: Not less than the prevailing wage rates set forth in Contract Documents,
must be paid on this project.
9. POST BID - PREAWARD SUBMITTALS: Bidders are required to submit the following
information to the Architectural Services Section, Building Services Division, 3409 Harley Avenue,
817-871-8274, within five business days subsequent to bid opening (Normally Thursday following
a Thursday bid opening) in order to assist City staff in determining the Contractor's capabili�ty of
performing the work and in meeting City contract requirements:
MinorityNVomen's Business Documentation (for bids in excess of $25,OOQ)
Contractors Qualification Statement (AIA Form A305)
Proposed Subcontractors and Suppliers
10. PROPOSED SUBCONTRACTORS: Acceptance of the bid in no way requires the City to
a accept the qualifications of the subcontractors. The Subcontractor lists are for use by the City in
preparing recommendations for award of the contract. The Contractor must provide and use
subcontractors listed unless the City agrees to allow a substitute.
�
L�
l�
�
L'I
11. DISCREPANCIES AND ADDENDA:
Should a bidder find any discrepancies in the drawings and specifications, or should he be in
doubt as to their meaning, he shall notify the City at once. If required, the City will then prepare a
written addendum that will be available to all Bidders at the Plans Desk or place designated for
distribution of Bid Documents by the Notice to Bidders. The Contractor is responsible for
determining if addendums are available and for securing copies prior to submitting a proposal.
Oral instructions or decisions unless confirmed by addenda will not be considered valid, legal or
binding. No extras will be authorized because of failure of the contractor to include work called for
in the addenda.
Bidder must acknowledge addenda in the Proposal. Failure to acknowledge addenda may cause
the Proposal to be ruted non-responsive. It is the Contractor's responsibility to obtain Addenda
and include its information in the Proposal.
12. WORKERS COMPENSATION INSURANCE: Bidders will be required to demonstrate
Q that coverage is in effect at time of Award of Contract. Sample Certificate of Insurance, or other
proof that Workers Compensation Insurance will be obtained, must be submitted within five
working days of bid opening.
�I
I
13. TAXES: Equipment and materials not consumed by or incorporated into the work are
subject to State sales taxes under House Bill 11, enacted August 15, 1991.
� 14. PERMITS: Contractor shall apply for all City of Fort Worth Permits and for any other
permits required by this project. City of Fort Worth Building and Trade Permit fees are waived.
Separate permits may be required for each work location.
�
LJ
r
�L�
15. CONTRACT DURATION: Time is of the essence. City will evaluate the bids based upon
construction cost and stated bid period of time for construction. Where the Bidder proposes time,
the City will evaluate the City's program needs in determining the acceptability of the proposed
6/4/99
ITB - 3
I�
LsJ
�
I�
�
I�
�
Li1
�
C�
C�'�
0
0
0
0
�
�
�
'�
��J'
16.
acceptability of the proposed contract duration. The City reserves the right to award the
contract upon those terms considered by the City to be in its best interests.
LIQUIDATED DAMAGES: Liquidated damages for this project shall be $900/ calendar
day.
17. PLAN DEPOSIT: The City will deposit plan deposit checks to its account finro weeks
following receipt of bids. Plans must be returned by all except the apparent low bidder prior to that
time. Contractors forfeit their plan deposit after that time.
18. ADJUSTMENT OF QUANTITIES: Where unit prices and estimated quantities are used to
compute the contract amount, the Owner may increase the quantities by an amount that is 20% of
the total cost for that section. Unit prices for adjustments tb unit quantities in excess to 20% may
be negotiated at the request of either party. .
18. MANUFACTURER'S REFERENCE: Catalog, brand names, and manufacturer's
references are descriptive, not restrictive. Bids on brands of like nature and quality will be
considered. For all items other than reference specifications and equivalent products listed in
each section, a full size sample and/or detailed product descriptions must be provided to the
architect within 14 calendar days after receipt of bid.
.. � ..
6/4/99
ITB - 4
LiJ
� .
n
PROPOSAL
'0: MR. BOB TERRELL
CITY MANAGER
CITY OF FORT WORTH, TEXAS
� =OR: WILL ROGERS AUDITORIUM RENOVATION
WILL ROGERS MEMORIAL CENTER
3401 W. LANCASTER AVE.
�
'ursuant to the foregoing "Notice to Bidders," the undersigned has thoroughly examined the
�lans, specifications and the site, understands the amount of work to be done, and hereby
�roposes to do all the work and furnish all labor, equipment and materials necessary to fully
� �omplete all the work as provided in the plans and specifications, and subject to the inspection
and approval of the Director of Transportation and Public Works of the City of Fort Worth.
Upon acceptance of this Proposal by the City Council, the bidder is bound to execute a contract
and, if the contract amount exceeds $25,000.00, furnish Performance and/or Payment Bonds
approved by the City of Fort Worth for performing and completing the Work within the time stated
and for the following sum, to wit:
DESCRIPTION OF ITEMS
,' Base Bid: (Proscenium, Front Walls) ��/, J(v� J���
�
Add Alternate 1: (First Floor, Stairs 11, 13, Ceiling under ,
�' Mezzanine) � ��v_ /`��
- �
Add Alternate 2: (Mezzanine, Balcony) f� �,��V
� .
� Add Alternate 3: (Tower Hali Lobby) �
— The undersigned agrees to complete the Work within 42 calendar days after the date of Notice to
Proceed.
�
The City reserves the right to accept or reject any and all bids or any combir,ation thereof
proposed for the above work.
� The undersigned assures that its employees and applicants for employment and those of any
labor organization, subcontractors or employment agency in either furnishing or referrina
� employee applicants to the undersigned are not discriminated against as prohibited by the terms
of City Ordinance 7278 as amended by City Ordinance 7400 (Fort Worth City Code Section
13A-21 through 13A-29).
� Residency of Bidders: The 1985 Session of the Texas Legislature passed house Bill 620 relative
to the award of contracts to non-resident bidders. The law provides that, in order to be awarded a
contract as low bidder, non-resident bidders (out of state contractors whose corporate offices or
� principal place of business are outside of the State of Texas) that bid projects for construction,
improvements, supplies or services in Texas at an amount lower than the lowest Texas resident
bidder by the same amount that Texas resident bidder would be required to underbid a
�.�. non-resident bidder in order to obtain a comparable contract in the state in which the
P-1
�
�
l �"
la�
�
non-residenYs principal place of business is located. The appropriate blanks in Section A must be
filled out by all non-resident bidders in order for your bid to meet specifications. The failure of out
of state or non-resident bidders Failure to complete the forms may disqualify that bidder.
Resident bidders must check the box in Section B.
A. �_� Non-resident vendors in (give state), our principal
place of business, are required to be percent lower than resident
bidders by state law.
�_� Non-resident vendors in (give state), are not required
to underbid resident bidders.
B. ��,� Our principal place of business or corporate offices are in the
State of Texas.
Within ten (10) days of receipt of notice of acceptance of this bid, the successful bidder will
execute the formal contract and will deliver an approved Surety Bond for the faithful perform2nce
of this contact. The attached deposit check in the sum of Dollars ($ ) is to
become the property of the City of Fort Worth, Texas, or the attached Bidder's Bond is to be
forfeited in the event the contract and bond are not executed within the time set forth, as
tiquidated damages for delay and additional work caused thereby.
MINORITY/WOMENS BUSINESS ENTERPRISE (M/WBE): (For bids in excess of $25,000)
� • I am aware that I must submit information the Director, Transportation and Public Works,
concerning the M/WBE participation within FIVE BUSINESS DAYS of submittal of this
Proposal in order to be RESPONSIVE.
�
1'�
Respectfully submitted,
By:
Phoenix I Restoration & Constructin, Ltd.
Com any Name
t! ,�—,�J� �
Sig ature
DALE C. SELLERS
Printed Name of Principal
la�ir
��
Addendum No. 1: g
Addendum No. 2: �
PRESIDENT/C.E.O.
Title
75235
Fax: 214/353 11631
Addendum No. 3:
Addendum No. 4:
P-2
Address: 6822 Maple Avenue
Street
Dallas Tegas
City
Phone: 214/353-1693
Receipt is acknowledged of the following addenda:
�i
Rug 24 99 �3:55p TPW
�, , 5ent by�NE00RRD CONTRRCTINB Rue-24-94 14:47
�
I�J
�
1��
L'�J
L�J
IJ
1�'
L�
l�J
�
L�J
�
�
817-871-8488 p•Z
Fro� 214353163"1�917 871 84B$ �e4� 2� 4
. nrrnCHnnskr ,�,
{'1�y O� f=qtt �/O[��t �'a9� t or7,
Minority and Wocxicn t3usiness CnEerpri5e Specificatior�s
, MB�JWBE UTlLJZAY'tON
Pbvenix i Restor�ttioa � Conatruttiun, Ltd. AugusE 5, 1999
PA1reE COMPAttY It�ME � . (!ID DATE
flil��,s Audita,civalitl�,1 Roaers l�,eaarial Ccnter
1'ROJEC N/liY1E PFiOJEC7 N�I:iFi�R
lClit"5d1AYDC PROlEC7COe[,: Z�j � ���nvpt rc►eCL'N'rnCEnG���EVED: �/ I
!
�Failure to eomplcic �t�is fvrm, In Its onti�ety rv{th aupporttnfl doGumeniation, and recclved Gy lhe Managla4 Dcpartmcn�
on or 6efore 5:00 �.ra, Gvc (5) City buslness days s(tcr b1d opCninQ, cxcluslvc of bJd openi�g date, rrU! resut� in thc bid
hcing consfdeted non�osponslvc to bfd epocl�Cations.
Tt►c understpned bidder agrees �o eater lnto a to�sat agsecment wtth the MBE andior WBE fim�s for work ��stcd In thts
eChedulC� condltlancQ upon executiCn of a contract witA !hc CJty of Fort Worih. ihc lntcntion�l andlor knowing
mtsrcpresentatlo� ot l�cts Is grounds !o� considc�stion o( disqua{ifieatfop and wi{l r�sute In sk�a bId bci�� conslcleretl
non{esaonslvc tn cpoclticauvns.
Company liamc. Conlatt Na1nC, G�rtFfi�d SpeC!(y Alf Contncting SpcClfy Af! Ilems to bc Dotlar Mnocmt
Addres�, and Telcpho�e Na. �t scvpe at 1YorK (') Supplicd('J 2� ;�
t1 �' ' U Y
� 00 e
(� b ii —
iS ~� y F-
Iice' y Pait�ta,ng . ..
t7�7_. Hi�lcreolc Ar. � paintiug
Garl.and, T!C 75Q43 . .
Su�ene I�beka
9ti2%303-2352 �
Pai.nC lst ;47,565.
{ MRNfl£s must be toeated !n the 9(nlne) taunty m�rkctplace or eurmntir dolna 6�:lecss i�� lhs msr�oepfaCe il tAE i�i11! Oi D:d. �
O Speelfy sli �rs�s In wqteh ktWR£'s a.• �o ba m��iced anaro� Irrms �o ee wPa�iea: I
('� A cornpte(� tisliag ol ftems Ia he supplied is required In orJu� to iecelvs credit lowsrd Ihe MNYpE yoat, f
�t") ��i��tlty esch Tler Jev�l. iier: Maans tne �evel 01 subtoatr�tlinp belaw t�ie prlme eontractoUconsultant, I.e., a d�reci p�y�enl 1
lrom tqe prime con�ractor to s su6canaactor !s consldcred 1" ifer, s p�ymenl 6x a sUbeQ����«or to i
if� e....n/:�r 1. �..w�l.�_�w 1M.e"
a iN1S FORM !1<t�ST HE �EGFIVEp BY THE N1ANnGINC DC•f�ARTMENT pY 5:00 p,m., wvE �s� cirY aus�HEss onYs arrc� a�a
OPC•N(NG, �XC�UStVE OF iNE flt0 OPENeNG OATE �t�� ���i9�
Psgcs 1 and 2 ot Attaclimcnl 11L n�ust be received by tt,c Managing Ucpartmcnt
�
�
MWc�E • 2
�
Rug 24 99 03:55p TPW
Sent by:NEOGHRD CONTRRC(IN& Ru9-24-99 t4:47
� , -�� '
�
� '
T
s
�
�
�I
LJ
�^J
L:_J
�
l�
LJ
�
L
L�'J
�
, 817-871-8488 �.�
fro� 2143531631a617 871 8488 Pa9e 3/ 4
nrtnc,tn,i�f,�r �
�'��jc 2 or �
> Ci1y of Fort Worth
Mino�iiy acici Women E3usiness L=nter��rise Specifications
. M��/WBE UTi�17Jaf1aN
Company KsmC, Gon[act ttafne, CerUGed �pocUy A!I Contracvn� Speclty A(l' lcems to be ' Uotfar I�nOunt
AddtCss, �nd Tcicpf�ono Ho. Scopc ot Work ('j SuRptiedt'! r�
� �� kr
�
z
� • -_....._ �
� ��_ .__.. , . _
� 71,e bidder inRher aqrees to providc� direcily !o thc City upon teqUesl.•campfe4e and accuntc ;n(orn,atio� rcgardinc
aMuat work periormed t�y atl subcontr=ttots, including M9E(s► andlor Wl3E(sj arrangements submiqcd with thes bid
ihe LidQer also agrces to a((aw an auAit anQlor cxaminst;�n ot any books, records and filcs I,eld by their companY lAai
� +NiA substanlf�tte thC aC1Ua1 wOrk pet'lormed by the M$E(s) and/o� W8E(s} on this contract, by on autAorized officer o►
empTorcc af �I�e G11y. Any intentior►at and/or knowi�g mistepresentalion o[ tacts will bc grounds lor icrminxting thc
tontract or deDarr�ent ��om City worsc tor a period ot �oi less than lhree (1) years and for initiating action uacler Federal,
S1tte or �ocs! laws eaneerning false s[�tecnents. Any (ailure ta compty with t�,is ordtnancc ana creates a materlai
� bresch o►cantract may fesufe in a determi�ation ot an trrespansibie otteror and barred frpm participaling in Cily work
. for a perioQ ot timc npt Jess lhan onc (1 } yc�r.
r��`",�� ALL MB�s and 9 s MUS7 8E CEKTIFIED BY THE CITY i3EFdRE C�tJTRACT AWARD
�7"�- J.Q,�� �� .._- �ale C. 5eilers, B.S.K.E., M..B.A.
ed 5'sgna�o-�^'' Printcd Siqnatutc
,� E.O.IPresident
�'��� • Contaet �tamc snd 7ille (i! different)
Phoeaix I Restaratioa � Coastruction. Ltd. 214f353-1b93
Company Namc � Tricphoae �1umt�cr {sj
5822 i�sple Avectue 214/353-1631
Address F�x NumUCt
��2Ias �C 75235 . 8/24/99
CilylSlatr,l"Lip Codc Oatc
� ini5 FORM MUST QE RECEiv[o OY cNE h�qNnG�NG OEPARTMENT t1Y S:oo p..n., LW[ �5) CIiY fJUS�NC5S UnrS nF riR Dto
OPENWG, EXCLVSlVE Q� Tl1� pl0 OP�NINCr OAi[ �y�„ 611/98
Paqes 1 and x of Altaci�rc,c�t 1A musl �e secrived Uy tf+c Ma�+sging pepanment
L'�'
�
iNWi�E: - �
I,I
�
n.
�
�
�
�
�
�
�
�
�
�
�� r��
�
� �
�
��
�ke paintitig Ccm�aay
has [iled with ihe Agency [iu appropriate AEfidavit and is hereby cemfied as a
-- ___ . Di�adsc�a.tag�d Buainesg �erpriae
providing setvice(s} in th� follcnving ueas:
1521-00; 1742-00; T3S9-0�
RSSIDiLi�'!'IALjC�32C�7lL CO1tTSTRIICTiON �il�{D Ilt'T�LtIaR WORiC
3
�
F-
7�his C:erri�i�ation is valid b�ginning a�tober 1998 znd supersedts anp registration or listing
previously issued. This certification n�ust be updated annually by submission of a Reccrtification Application. Ar
any tin�e there is a ciiange in ownership or cantrol oC the ficm, noti{ication must be made immediateiy co che
North Central Texa_a Regional Cerdf'icati�r: Agency.
/� ,
!,` ; � �
This Certi{i�ation expires on �Ctober ��g 99
� i rtificacioa� �drninistrator
u� r Issued at Ar[ingtcin, Trxas October 19 98
,
p CERi1F1CATlON NO. HMSD79$5Yi099
m
a� -
�
N
� , . Cwc� a<. —
�
�
0 i..�.l Q � Q � � � r_�
. ,
A
NCTR�A
D/�i/i►�1'BE CER �.��r�i�AT`IC��i
o� c--� o o Q o 0 0 0
�
�
�
l*"J
I��
�
I�
�)
�
L!'i
'�
�
�
�
L'�'1
'�"J
�
�
City� of Fort Worth, Texas
Transportat�on/Public Works Departmen!
Building Serv�ces Drvlsion/Architecturaf Services Section
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
SECTION A
DEFINITIONS, PROCEDURES AND INTERPRETATIONS
A-1 CONTRACT DOCUMENTS. By the term Contract
Documents is meant all of the written and drawn documents
setting forth or affecting the rights of the parties, including but not
necessarily limited to, the Contract, Notice to Bidders, Proposal,
General Conditions, Special Conditions, Specifications, Plans,
Bonds and all Addenda, Amendments signed by ali parties,
Change Orders, written interpretations and any written Fieid
Order for a minor change in the Work.
A-2 ENTIRE AGREEMENT. The Contract Documents
represent the entire agreement between the Parties, and no prior
or contemporaneous, oral or written agreements, instruments or
negotiations shalt be construed as altering the terms and effects
of the Contract Documents. After being executed, the Contract
Documents can be changed only by a written Amendment signed
by the Contractor and the Owner, or Change Order, or by a
written Field Order for a minor change.
A-3 WORK. By the term Work is meant ali labor,
supervision, materials and equipment necessary to be used or
incorporated in order to produce the construction required by
Contract Documents.
A-4 EXECUTION OF THE CONTRACT DOCUMENTS.
The Contract Documents shall be executed in six originals by the
Contractor and the Owner in such form as may be prescribed by
law.
A-5 FAMILIARITY WITH PROPOSED WORK. Before
filing a bid, the bidder shall examine carefully the proposal, plans,
specifications, special provisions, and the form of contract to be
entered into for the work contemplated. He shall examine the site
of work and satisfy himself as to the conditions that will be
encountered relating to the character, quality and quantity of work
to be performed and materials to be furnished. The filing of a bid
by the bidder shaii be considered evidence that he has complied
with these requirements and has accepted the site as suitable for
the work.
Claims for additional compensation due to variaticns between
conditions actually encountered in construction and as indicated
by the plans wili not be allowed.
A-6 ONE UNIFIED CONTRACT. Insofar as possible, the
Contract Documents will be bound together and executed as a
single unified Contract, the intention of the Contract pocuments
being to provide for all labor, supervision, materials, equipment
and other items necessary for the proper execution and
completion of the Work. Words that have weli recognized
technical or trade meanings are used herein in accordance with
such recognized meanings.
A-7 DIVISION OF WORK. The arrangement of Drawings
and/or Specifications into Divisions, Sections, Articles, or other
Subdivisions shall not be binding upon the contractor in dividing
the work among Subcontractors or Trades.
A-8 INTERPRETATIONS. The Architect will furnish such
Interpretations of the Pians and Specifications as may be
necessary for the proper execution or progress of the work. Such
Interpretations shall be furnished at the instance of the Architect
6/23/99
GC-1
or at the request of the Contractor, or Owner, and will be issued
with reasonable promptness and at such times and in accordance
with such schedule as may be agreed upon. Such Interpretations
shall be consistent with the purposes and intent of the Plans and
Specifications and may be effected by Field Order. In the event
of any dispute between any of the parties to the Contract and the
Architect or each other involving the interpretation of the Conir2ct
Documents, the evaluation of work or materials performed or
furnished by the Architect Contractor, or any subcontractor or
materialsman, or involving any question of fault or liability of any
party, the decision of the Owner shall be final and binding.
In the event of inconsistency in the contract documents, the
following sequence for interpretation shall be used in order of
precedence: Change Orders and/or Field Orders (by date of
issuance); Addenda (by date of issuance); Drawings; Plotes and
dimensions on Drawings; Technical Specifications; Special
Provisions; Supplementary General Conditions; General
Conditions; and, Construction Contract.
A-9 COPIES OF WORKING DRAWING� AND
SPECIFICATIONS. Th� Architect will furnish to Contractor free
of charge 15 sets of working Drawings and 15 sets of
Specifications. Contractor shall pay the cost of reproduction for
all other copies of Drawings and Specifications furnished to him.
All Drawings, Specifications and copies thereof furnished by the
Owner of the Architect are and shall remain the property of the
Owner. They are not to be used on any other project and, with
the exception of one Contract set for each Party to the Ccntract,
are to be returned to the Owner on request at the compietion of
the work.
A-10 MINORITY AND WOMENS BUSINESS ENTERPRISE
POLICY. The City of Fort Wo�th has goals for the participation o�
disadvantaged business enterprises in City contracts.
Compliance with the policies designed to meet these goals is
mandatory in order to be considered a responsive bidder. The
City policy and procedures to be followed in submitting bids is
included.
A-11 CORRELATION AND INTENT. In general, the
drawings indicate dimension, locations, positions, quantities, and
kinds of construction; the specifications indicate the quality and
construction procedures required. Work indicated en the
drawings and not specified of vice-versa, shall be furnished as
though set forth in both. Work not detailed, marked or specified
shall be the same as similar parts that are detailed, marked or
specified. If the drawings are in conflict or conflict with the
specifications the better quality or greater quantity or work or
materials shall be estimated and shall be furnished or i�cluded.
Dimensions on drawings shall take precedence over smaif-scale
drawings. Drawings showing locations of equipment, piping,
ductwork, electrical apparatus, etc., are diagrammatic and job
conditions may not allow installation in the exact locatio� shown.
Relocation shall not occur without the Architects approval.
SECTION B
IDENTITY OF ARCHITECT
B-1 CONTRACT ADMINISTRATION. Where the term
"Architect" is used in the "General Conditions of the Contract for
Construction", it shall refer to the Director, Transportation and
Public Works or his designated Project Manager. The Director,
Transportation wili designate a Project Manager and Construction
I�
�
t�J
�
�
�
'�
C��
�
��
�l
�
���
�
�
�
�
L�J
l�J
Manager to administer this contract and perform the funciions of
the "Architect" as indicated in the General Conditions. The
design architect may also be designated to perform the duties of
"ArchitecY'.
B-2 TERMINATION AND SUSPENSION OF WORK: The
Owner has the right to terminate the Project for any reason. If the
project is terminated, the Contractor shall:
a) Stop work under the Contract on the date and to the
extent specified on the notice of termination.
b) Place no further orders or subcontracts except as may
be necessary for the completion of the work not terminated.
c) Terminate all orders and subcontracts to the extent that
they relate to the performance of the work terminated by the
notice of termination.
After termination as above, the City will pay the contractor a
proportionate part of the contract price based on the work
completed; provided, however, that the amount of payment on
termination shall not exceed the total contract price as reduced
by the portion thereof allocatable to the work not completed and
further reduced by the amount of payments, if, any otherwise
made. Contractor shall submit its claim for amounts due after
termination as provided in this paragraph within 30 days after
receipt of such claim. In the event of any dispute or controversy
as !o the propriety or allowability of all or any portion of such
claim under this paragraph, such dispute or controversy shall be
resolved and be decided by the City Council of the City of Fort
Worth, and the decision by the City Council of the City of Fort
Worth shall be final and binding upon all parties to this contract
B-:i DUTIES OF THE ARCHITECT As used herein, the
term Architect means the Architect or his authorized
representative. Nothing contained in these Contract Documents
shall create any privity of Contract between the Architect and the
Contractor.
B-4 ARCHITECT AS REPRESENTATIVE OF THE
OWNER The Architect will provide general administration of the
Contract on behaif of the Owner and will have authority to act as
the representative of the Owner to the e�ent provided in the
Con:ract Documents unless changed in writing by the Owner.
The Architect will be available for conferences and consultations
with the Owner or the Contractor at all reasonable times.
B-5 ACCESS TO JOB SITES. The Architect shall at all
times have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access
so the Architect may perForm its assigned functions under the
Contract Documents.
The Architect will make periodic visits to the Site to familiarize
himself with the progress and quatity of the work and to
determine if the work is proceeding in accordance with the
Contract documents. On the basis of on-site observations, the
Architect will keep the Owner informed of the progress of the
Work and wili endeavor to guard the Owner against defects and
deficiencies in the Work of the Contractor. Based upon such
observations and the ContractoPs applications for payments, the
Architect will make determinations and recommendations
concerning the amounts owing to the Contractor and will issue
ceitificates for payment amounts.
B-6 INTERPRETATIONS. The Architect will be, in the first
instance, the interpreter of the requirements of the Plans and
Specifications and the judge of the performance thereunder by
the Contractor, subject to the final decision of the Owner.
� 6/23/99
�
GC-2
The ArchitecYs decisions in matters relating to artistic effect will
be final if consistent with the intent of the Contract Documents.
B-7 AUTHORITY TO STOP WORK. The Architect will
have authority to reject work that does not conform to the Plans
and Specifications. In addition, whenever, in its reasonable
opinion, the Architect considers it necessary or advis2ble in order
to insure the proper realization of the intent of the Plans and
Specifications, the Architect will have authority to require the
Contractor to stop the Work or any portion thereof, or to require
special inspection or testing of the Work whether or noi such
Work be then fabricated, installed or completed.
B-8 MISCELLANEOUS DUTIES OF ARCHITECT.
Shoq Drawinas. The Architect will review Shop Drawings and
Samples as provided in Section D. Two copies of each approved
Shop Drawing and submittal will be provided to the Owner by the
Architect.
Chanae Orders. Change Orders and Field Orders for Minor
Changes in the Work will be issued by the Owner through the
Architect in accordance with the provisions of Section L.
Guarantees. The Architect will receive on behalf of the Owner all
written guarantees and related documents required �f the
Contractor. Upon completion of the project the Contrac;or shall
provide the Architect five copies of each guarantee. The Architect
wili provide three copies of each guarantee to the Owner.
Ins�ections. The Architect wili conduct inspections for the
purpose of determining and making his recommenciations
concerning the dates of substantial completion and final
completion.
Ooeration and Maintenance Manuals. The Architect wiil receive
on behalf of the Owner, six copies of all applicable .equ:pment
installation, operation, and maintenance brochures and manuals
required of the Contractor. The Architect wiil provide three copies
of this information to the Owner.
B-9 TERMINATION OF THE ARCHITECT. In case of the
termination of the employment of the Architect by the Own�r, the
Owner shall either assume the duties of the Architect through the
Director of the Department of Transportation and Public lNorks,
or shall appoint a successor Architect against whom the
Contractor makes no reasonable objection.
SECTION C
OWNEd2
C-1 IDENTIFICATION. By the term Owner is meant the
City of Fort Worth acting herein. by its duiy authorized
representatives in the manner provided by law. Authorized
representatives include the City Manager, Assistant City
Manager, the Director and of Transportation and Public Works
Department and members of the Building Seroices Division.
Generally speaking a designated representative will be identified
from within the Building Services Division to act as a point of
contact for day to day contract administration.
C-2 DUTIES OF THE OWNER. The Owner shall furnish
surveys describing the physical characteristics, legal limits and
utility locations for the site of the Work; provided, however, that
the Contractor hereby covenants that he has inspected the
premises and familiarized himself therewith and that the locations
of utilities and other obstacies to the prosecution of the VVork as
shown on the Owner's survey are for information only, are not
binding upon the Owner, and the Owner shall not incur any
liability for loss or damage by virtue of any inaccuracies or
deficiencies in such surveys. The Owner shall secure and pay for
l�f
�
'i1
�.J
�
LJ
�
LJ
���
�
�
�
�
l'!' 1
��
��
�
LJ
title to the site and all necessary permanent or construction
easements. The Owner will cooperate with the Contractor in the
prosecution of the Work in such manner and to such extent as
may be reasonable and shail furnish information under its control
with reasonabie promptness at the request of the Contractor.
C-3 INSTRUCTIONS. The Owner shall issue all
instructions to the Contractor through the Architect.
C-4 ACCESS TO JOB SITE. The Owner shall at all times
have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access
so the Owner may perform its assigned functions under the
Contract Documents.
C-5 PROGRESS INSPECTIONS. The Owner and the
Architect will make visits to the Site to familiarize themselves with
the progress and quality of the Work and to determine if the work
is proceeding in accordance with the Contract documents. On
the basis of on-site observations and reports provided by the
Architect concerning the progress and quality of the work, the
Owner will approve and authorize the Contractor's applications for
payments.
C-6 AUTHORITY TO STOP WORK. The Owner will have
authority to reflect work that does not conform to the Plans and
Specifications. Whenever, in its reasonable opinion, the Owner
considers it necessary or advisable in order to insure the proper
realization of the intent of the Plans and Specifications, the
Owner will have authority to require the Contractor to stop the
work or any portion thereof, or to require the Contractor to stop
the Work or any portion thereof, or to require special inspection or
testing of the Work whether or not such Work be then fabricated,
instailed or completed.
C-7 SUBSTANTIAL COMPLETION INSPECTION. Upon
agreement of the Contractor and Architect that the Work is
substantially complete, the Owner will schedule a Substantial
Completion Inspection to be conducted by the Architect and
attended by representatives of the Architect, Owner and
Contractor. Items identified during this inspection as being
incomplete, defective or deficient shatl be incorporated into a
punch list to be prepared by the Architect and attached to the AIA
document G704, which is to be prepared and signed by the
Contractor, and accepted, approved and signed by the Owner.
C-8 RIGHT TO AUDIT:
Contractor agrees that the City shall, until the expiration of three
years after final payment under this contract, have access to and
the right to examine any directly pertinent books, documents,
papers and records of the contractor involving transactions
relating to this contract. '
Contractor further agrees to include in all his subcontracts
hereunder a provision to the effect that the subcontractor agrees
that the City shall, until the expiration of three years after final
payment under the subcontract, have access to and the right to
examine any directly pertinent books, documents, papers and
records of such subcontractor, involving transactions to the
subcontract. The term "subcontracY' as used herein includes
purchase orders.
Contractor agrees to photocopy such documents as may be
requested by the city. The city agrees to reimburse Contractor
for the costs of copies at the rate published in the Texas
Administrative Code.
�
6/23/99
�
SECTION 0
GC-3
CONTRACTOR
D-1 IDENTIFICATION. The Contractor is the person or
organization identified as such in the Contract. The term
Contractor means the Contractor or his authorized representative.
D-2 INDEPENDENT CONTRACTOR. Contractor shall
perform all work and services hereunder as an independent
contractor, not as an officer, agent, or employee of the City.
Contractor shall have exclusive control of and the exclusive right
to controi the details of the work and services performed
hereunder, and all persons performing same, and Contractor
shall be solely responsible for the acts and omissions of its
officers, agents, and emptoyees. Nothing herein shail be
construed as creating a partnership or joint enterprise between
City and the Contractor, its officers, agents and employees, and
the doctrine of respondeat superior shall not apply.
D-3 SUBLETTING: It is further agreed th2t the
performance of this Contract, either in whole or in part, shal! not
be sublet or assigned to anyone else by said Contractor without
the written consent of the Director of Transportation and Public
Works of the City of Fort Worth.
D-4 REVIEW OF CONTRACT DOCUMENTS. The
Contractor shall carefully study and compare the Aareement,
Conditions of the Contract, Drawings, Specifica4ions, Addenda
and modifications and shali at once report to the Owner ar,d to
the Architect any error, inconsistency or omission he may
discover. The Contractor shall do no work without Drawings,
Specifications and Interpretations.
D-5 SUPERVISION. The Contractor shall supervise and
direct the Work, using his best skill and attention. He sha(1 be
solely responsible for all construction means, methods,
techniques, sequences and procedures and for coordinating all
portions of the Work under the Contract Documents.
D-6 LABOR AND MATERIALS. Unless otherwise
specifically noted, the Contractor shall provide and pay for atl
labor, materials, equipment, tools, construction equipment and
machinery, water, heat, utilities, transportation and other facilities
and services necessary for the proper execution and completion
of the Work.
The successful low bidder will use its reasonable best ef�orts to
hire local laborers, workmen and materiaimen. The general
condition is not to be constructed as limiting the right of any
bidder to employee laborers, workmen or materialmen from
outside local area.
The Contractor shall at all times enforce strict discipline and c�ood
order among his employees, and shail not employ on the Work
any unfit person or anyone not skilled in the task assigned to him.
D-7 PREVAILING WAGE RATE. The Contractor agrees to
pay not less than the general prevailing rate of per diem wages
for Work of a similar character in the Iocaiity in which the Work is
performed, and not less than the general prevaiting wage of per
diem wages for a legal holiday and overtime work to all laborers,
workmen and mechanics employed on the Work under this
Contract. The Contractor agrees to pay at least the mii�imum
wage per hour for all labor as the same is classified 2nd set cut
by the City of FoR Worth, Texas, a copy of which is attached
hereto and made a part hereof the same as if it were copies
verbatim herein.
D-8 WARRANTY. The Contractor warrants to the Owner
and the Architect that all materials and equipment furnished
under this Contract will be new unless othervvise specified, and
that all work will be of good quality, free from faults and defects,
L"J
L�:!
�
L_J
�
f�1
�
�
l�
�
�
C�J
�
�
�
�
I�1
�'
and in conformance with the Contract Documents. All work not so
conforming to these standards may be considered defective. If
required by the Architect or the Owner, the Contractor shall
furnish satisfactory evidence as to the kind and quality of
materials and equipment.
The warranty provided in this Section shail be in addition to and
not in limitation of any other warranty or remedy provided by law
or the Contract Documents.
D-9 TAXES. The Contractor is exempt from State Sales
Tax on material incorporated into the finished construction,
Excise and Use Tax.
D-10 LICENSES. NOTICES AND FEES. The Contractor
shall obtain all Permits, Licenses, Certificates, and Inspections,
whether permanent or temporary, required by law or these
Contract Documents.
The Contractor shall give all Notices and comply with all Laws,
Ordinances, Rules, Regulations and Orders of any public
authority bearing on the pertormance of the Work. if the
Contractor observes or becomes aware that bearing on the
performance of the Work. If the Contractor observes or becomes
aware that any of the Contract Documents are at variance
therewith in any respect, he shall promptiy notify the Architect in
writing and any necessary changes will be made. If the
Contractor performs any Work knowing that it is in violation of, or
contrary to, any of such Laws, Statutes, Charter, Ordinances,
Orders or Directives, or Regulations without furnishing Notice to
the Architect, the Contractor will assume fuil responsibility
therefor and bear all costs attributable thereto.
D-11 CASH ALLOWANCES. The Contractor shall include in
the Contract Sum all aliowances stated in the Contract
Documents. These allowances shall cover the net cost of the
materials and equipment detivered and unloaded at the site, and
all applicable taxes. The Contractor's handling costs on the site,
labor, installation costs, overhead, profit and other expenses
contemplated for the original ailowance shall be included in the
Contractor Sum and not in the allowance. The Contractor shall
cause the Work covered by these allowances to be performed for
such amounts and by such persons as the Architect may direct,
but he will not be required to employ persons against whom he
makes a reasonable objection. If the cost, when determined, is
more than or less than the allowance, the Contract Sum shall be
adjusted accordingly by Change Order which will inciude
additional handling costs on the site, labor, installation costs, field
overhead, profit and other direct expenses resulting to the
Contractor from any increase over the original allowance.
D-92 SUPERINTENDENT. The Contractor shall employ a
competent superintendent and necessary assistants who shall be
in attendance at the Project site during the progress of the Work.
The superintendent shall be satisfactory to the Contractor and the
Owner. The superintendent shall represent the Contractor and all
communications given to the superintendent shall be binding as if
given to the Contractor. important communications will be
confirmed in writing. Other communications wiil be so confirmed
on written request in each case.
D-13 RESPONSIBILITIES FOR EMPLOYEES AND SUB-
CONTRACTORS. The Contractor shall be responsible to the
Owner for the acts and'omissions of all his employees and ail
Sub-contractors, their agents and employees, and ali other
persons performing any of the Work under a contract with the
Contractor.
D-14 FAiLURE TO COMMENCE WORK: Should the
Contractor fail to begin the work herein provided for within the
time herein fixed or to carry on and complete the same according
6/23/99
D
GC-4
to the true meaning of the intent and terms of said Plans,
Specifications and Contract Documents, then the Owner shall
have the right to either demand the surety to take over the work
and complete same in accordance with the Contract Documents
or to take charge of and compiete the work in such a manner as
it may deem proper, and if, in the completion thereof, the cost to
the said City shall exceed the contract price or prices set forth in
the said plans and specifications made a part hereof, the
Contractor and/or its Surety shall pay said City on demand in
writing, setting foRh and specifying an itemized statement of the
total cost thereof, said excess cost.
D-15 PROGRESS SCHEDULE. The Contractor,
immediately after being awarded the contract, shall prepare and
submit for the ArchitecYs approval, an estimated progress
schedule for the Work. The progress schedule shall be related to
the entire Project. This scheduie shall indicate the dates for the
starting and completion of the various states of construction and
shall be revised as required by the conditions of the Work,
subject to the ArchitecYs approval. It shall also indicate the dates
for submission and approval of shop drawings and submittals as
well as the delivery schedule for major pieces of equipment
andlor materials.
The progress schedule shall be updated at least monthly by the
contractor and submitted to the Architect for approval with the
Contractor's monthly progress payment requests.
D-16 DRAWINGS AND SPECIFICATIONS AT THE SITE.
The Contractor shall maintain at the site for the Owner one copy
of all Drawings, Specifications, Addenda, approved Shop
Drawings, Change Orders, and other Changes and Amendments
in good order and marked to record all changes made during
construction. These shall also be available to the Architect. The
Drawings, marked to record all changes made during
construction, shall be delivered to the Architect u�on completion
of the Work, and the Architect will prepare, and provide to the
Owner, one complete set of reproducible record drawings of the
work.
D-17 SHOP DRAWINGS AND SAMPLES. Shop Drawings
are drawings, diagrams, illustrations, schedules, performance
charts, brochures and other data which are prepared by the
Contractor or any Subcontractor, manufacturer, supplier or
distributor, and which iilustrate some portion of the Work.
Samples are physical examples furnished by the Contractor to
illustrate materials, equipment or workmanship, and to establish
standards by which the Work will be judged.
The Contractor shail review, stamp with his approval and submit,
with reasonabie promptness and in orderly sequence so as to
cause no delay in the Work or in the work of any other contractor,
normally within the first 90 days of the work, six copies of all shop
Drawings and Samples required by the Contract Documents or
subsequently by the Architect as covered by changes or
amendments. Shop Drawings and Samples shall be properly
identified as specified, or as the Architect may require. At the
time of submission the Contractor shall inform the Architect in
writing of any deviation in the Shop Drawings or Samples from
the requirements of the Contract Documents.
By approving and submitting Shop Drawings and Samples, the
Contractor thereby represents that he has determined and
verified all field measurements, field constructio� critsria,
materials, catalog numbers and similar data, and that he has
checked and coordinated each shop drawing given i� the
Contract Documents. The Architect's approval of a separate item
shall not indicate approval of an assembly in which the item
functions.
lil
�
L`1
0
�J
�
`�'
�
(� .
�
�
�
�
�
�
�
Li
l�1
The Architect will review and approve Shop Drawings and
Samples with reasonable promptness so as to cause no delay,
but only for conformance with the design concept of the Project
and with the information given in the Contract Documents. The
ArchitecYs approval of a separate item shall not indicate approval
of an assembly in which the item functions.
The Contractor shall make any corrections required by the
Architect and shall resubmit the required number of corrected
copies of Shop Drawings or new Samples until approved. The
Contractor shall direct specific attention in writing or on
resubmitted Shop Drawings to revisions other than the
corrections requested by the Architect on previous submissions.
The ArchitecYs approval of Shop Drawings or Samples shall not
relieve the Contractor of responsibility for any deviation from the
requirements of the Contract Documents unless the Contractor
has informed the Architect in writing of such deviation at the time
of submission and the Architect has given written approval to the
specific deviation as authorized in Paragraph A-2, ArchitecYs
approval shall not relieve the Contractor from responsibility for
errors or omissions in the Shop Drawings or Sampies.
No portion of the Work requiring a Shop Drawing or Sample
submission shall be commenced until the Architect has approved
the submittal. All such portions of the Work shall be in
accordance with approved Shop Drawings and Samples.
D-18 SITE USE. The Contractor shall confine operations at
the site to areas permitted by law, ordinances, permits and the
Contract Documents and shall not unreasonably encumber the
site with any materials or equipment. Until acceptance of the work
by the City Council of the City of Fort Worth, the entire site of the
Work shall be under the exclusive control, care and responsibility
of the Contractor. Contractor shall take every precaution against
injury or damage to persons or property by the action of the
elements or from any other cause whatsoever. The Contractor
shall rebuild, repair, restore and make good at his own expenses
ali injuries or damages to any portions of the Work occasioned by
any of the above, caused before acceptance.
D-19 SAFE WORK PRACTICES. The Contractor shall
employ safe practices in handling materials and equipment used
in performing required work so as to insure the safety of his
workmen, City employees and the public. The Contractor shall
keep the premise free at all times from accumulatio� of waste
materials or rubbish. At the completion of the work, the
Contractor shall remove all his wastes and rubbish from and
about the work area, as well as his tools, equipment and surplus
materials and shall leave the area as clean and free of spot,
stains, etc., as before the work was undertaken.
D-20 FIELD OFFICES AND SHEDS. The Contractor is not
required to provide a temporary field office or telephone for
projects under $500,000. Contractor shall equip the Project
Superintendent with a pager and provide 24-hour contacts to the
City.
D-21 CUTTING AND PATCHING OF WORK. The
Contractor shall do all cutting, fitting or patching of his Work that
may be required to make its several parts fit together properly,
and shall not .endanger any Work by cutting, excavating or
otherwise altering the Work or any part of it.
D-22 CLEAN UP. The Contractor at all times shall keep the
premises free from accumulation of waste materials or rubbish.
At the completion of the Work he shall remove all his waste
materials and rubbish from and about the Project as well as all
his tools, construction equipment, machinery and surplus
materials, and shall clean all glass surfaces and leave the Work
"Broom-clean" or its equivalent, except at otherwise specified. In
6/23/99
GC-5
addition to removal of rubbish and leaving the buildings "broom-
clean°, Co�tractor shall clean all glass, replace any broken glass,
remove stains, spots, marks and dirt from furniture a�d carpet,
clean hardware, remove paint spots and smears from all
surfaces, clean fixtures and wash all concrete, tile and terrazzo
floors.
If the Contractor fails to clean up, the Owner may do so, and the
cost thereof shall be charged to the Contractor.
D-23 COMMUNICATIONS. As a general rule, the
Contractor shall forward all communications to the Owrer through
the Architect, and in all other instances the Contractor shall
furnish the Architect a copy of any communication sent directly to
the Owner.
SECTION E
SUBCONTRACTORS
E-1 DEFINITION. A Subcontractor is a person or .
organization who has a direct contract with the Contractor to
perform any of the Work at the site. The term Subcontractor is
referred to throughout the Contract Documents as if singuiar in
number and masculine in gender and means a Subcontra�tor or
his authorized representative.
Nothing contained in the Contract, Documents shall create any
contractual relation between the Owner and the Architect and any
subcontractor or any of his sub-subcontractors or materialmen.
E-2 AWARD OF SUBCONTRACTS. The bidder shail
furnish a list of the names of the subcontractors or oiher persons
or organizations (including those who are to furnish materials or
equipment fabricated to a special design) proposed for such
portions of the Work as may be designated in the bidding
requirements, or if none is so designated in the bidding
requirements, the names of the Subcontractors proposed for the
principal portions of the Work. Prior to the award of the Contract,
the Architect shall notify the successful bidder in writing if either
the Owner or Architect, after due investigation, has reasonable
objection to any person or organization on such list. Failure o` the
Owner and Architect to make an objection to any person or
organization on the list prior to the award of this Contract shall not
constitute acceptance of such person or organization.
If, prior to the award of the Contract, the Owner or Architect has
an objective to any person or organization on such list, and
refuses to accept such person or organizatior., the apparent low
bidder may, prior to the award, withdraw his bid without forfeiture
of bid security. If such bidder submits an acceptable substitute,
the Owner may, at its discretion, accept the bid or he may
disqualiy the bid. If, after the award, the Owner or Architect
objects in writing to any person or organization on such list, the
Contractor shall provide an acceptable substitute.
The Contractor shail not make any substitution for any
Subcontractor or person or organization that has been accepted
by the Owner and the Architect, unless the substitution is also
acceptable to the Owner and the Architect.
E-3 TERMS OF SUBCONTRACTS. All work performed for
the Contractor by a Subcontractor shali be pursuant to an
appropriate agreement between the Contractor and the
Subcontractor (and where appropriate between Subcontractors
and Sub-subcontractors) which shall contain provisions that:
1. preserve and protect the rights of the Owner ar.d the
Architect under the Contract with respect to the Work to be
performed under the subcontract so that the subcontracting
thereof will not prejudice such rights;
�
�
�
'�1
�/)
�Lr�
�
�
li.`i
�
�
�
L"1
L�J
�
���
�
IL�J
�r�
2. require that such Work be performed in accordance with the
requirements of the Contract Documents;
3. require submission to the Contractor of applications for
payment under each subcontract to which the Contractor is
a party, in reasonable time to enable the Contractor to apply
for payment;
4. require that all claims for additional costs, extensions of
time, damages for delays or otherwise with respect to
subcontracted portions of the Work shall be submitted to the
Contractor (via any Subcontractor or Sub-subcontractor
where appropriate) in the manner provided in the Contract
Documents for like claims by the Contractor upon the
Owner;
5. waive all rights the contracting parties may have against one
another for damages caused by fire or other perils covered
by the property insurance, except such rights, if any, as they
may have to proceeds of such insurance held by the Owner,
and,
6. obligate each Subcontractor specifically to consent to the
provisions of this Section
All of the provisions set out in this section shall be deemed to
have been included in every subcontract, and every subcontract
shall be so construed and applied as to the Owner and the
Architect, whether or not such provisions are physically included
in the sub-contract.
E-4 MINORITY AND WOMENS BUSINESS ENTERPRISE
Mf /WBE), Should the base bid be less than $25,000, the
requirements of this section do not apply.
In accordance with City of Fort Worth Ordinance No 11923, the
City of Fort Worth sets goals for the participation of minority
business enterprises and women business enterprises in City
contracts. Ordinance No 11923 is incorporated in these
Specifications by reference. A copy of the Ordinance may be
obtained from the Office of the City Secretary. Failure to comply
with the Ordinance shall be a material breach of contract.
The M/WBE UTILIZATION FORM, M/WBE GOALS WAIVER
FORM and GOOD FAITH EFFORT FORM, as applicable, must
be submitted within five city business days after bid opening.
Failure to submit the post bid information shall render the bid
non-responsive.
The City will consider the contractor's performance on other City
Projects regarding its MIWBE program in the evaluation of bids.
Failure to comply with the City's M/WBE program, or to demon-
strate a"good faith effort", shall result in a bid being considered
irresponsible.
Upon request, Contractor must provide the City with complete
and accurate information regarding actual work performed by a
Minority or Women Business Enterprise (M/WBE) on the contract
and proof of payment thereof. Contractor further agrees to permit
an audit and/or examination of any books, records or fites in it's
possession that will substantiate the actual work performed by an
M! WBE. The misrepresentation of acts (other than a negligent
misrepresentation) and/or the commission of fraud by the
Contractor will be grounds for termination of the contract and/or
initiating action under appropriate federal, state, or local laws or
ordinances relating to false statement. Further any such
misrepresentation (other than a negligent misrepresentation)
and/or commission of fraud will result on ihe Contractor being
determined to be irresponsible and barred from participating in
City work for a period of time of not less than three years.
� 6/23199
d
GC-6
Contractor shall provide copies of subcontracts or cosigned
letters of intent with approved M/WBE subcontractors pri�r to
issuance of the Notice to Proceed. Contractor shall also provide
monthly reports on utilization of the subcontractors !o the
Construction Manager.
The Contractor may count first and second tier subcontractors
and/or suppliers toward meeting the goals. The Contractor may
count toward its goal a portion of the total dollar amount of the
contract with a joint venture equal to the percentags of the
M/V1fBE participation in the joint venture for a clearly defined
portion of the work to be performed. Ail subcontractors used in
meeting the goals must be certified prior to the award of the
Contract.
Whenever a change order affecis the work of an M/WBE
subcontractor or supplier, the MlVUBE shall be given an
oppoRunity to perform the work. Whenever a change order is in
excess of 10% of the original contract, the M/WBE coon�inator
shail determine the goals appiicable to the work to be per�ormed
under the change order.
During the term of the contract the contractor shaN:
1. Make no unjustified changes of deletions in it's IL1lWBE
participation commitments submitted with or subsequent to
the bid, and,
2. If substantial subcontracting and/or substantial supplier
opportunities arise during the term of the contract which the
contractor had represented he would perform with his
forces, the contractor shall notify the City before
subcontracts or purchase orders are let, and shall be
required to comply with modifications to goals as determined
by the City, and,
3. Submit a REQUEST FOR APPROVAL OF CHANGE
FORM, if the contractor desires to change or delete any of
the M/VVBE subcontractors or suppliers.
Justification for change may be granted for the following:
1. Failure of subcontractor to provide evidence of coverage by
Workers' Compensation Insurance
2. Failure of subcontractor to provide required general liability
or other insurance.
3. Failure of subcontractor to execute a standard subcontract
form in the amount of the proposal used by the Contractor in
preparing his M/WBE Participation plan
4. Default by the M/WBE subcontractor or supplier in the
performance of the subcontract.
Other reasons at the discretion of the M/WBE Coordinator
Within ten days after final payment from the City the contractor
shall provide the M/WBE Office with documentation to reflect final
participation of each M/V116E subcontractor and supplier used on
the project.
E-5 PAYMENTS TO SUBCONTRACTORS. The
Contractor shall pay each Subcontractor, upon receipt of
payment from the Owner, an amount equal to the percentage of
completion allowed to the Contractor on account of such
Subcontractor's Work. The Contractor shall also require each
Subcontractor to make similar payments to his subcontractors.
If the Architect refuses to issue a Certificate for Payment for any
cause which is the fault of the Contractor and not the fault of a
�
�
L�'*J
�
�
�
�
."�J
�
(�
�
�
E��
L:.J
L�
�
Lrf
�
�L_fi
particular subcontractor, the Contractor shail pay that
Subcontractor on demand, made at any time after the Certificate
for Payment would otherwise have been issued, for his Work to
the extent completed, less the retained percentage.
The Contractor shall pay each Subcontractor a just share of any
insurance monies received by the Contractor, and he shall
require each Subcontractor to make similar payments to his
Subcontractors.
The Architect may, on request and at its discretion, furnish to any
Subcontractor, if practicable, information regarding percentages
of completion certified to the Contractor on account of Work done
by such Subcontractors.
Neither the Owner nor the Architect shail have any obligation to
pay or to see to the payment of any monies to any Subcontractor.
SECTION F
SEPARATE CONTRACTS
F-1 OWNER'S RIGHT. The Owner reserves the right to
award separate contracts in connection with other portions of the
Work. When separate contract are awarded for other portions of
the Work, "the Contractor" in the Contract Documents in each
case shall be the contractor who signs each separate contract.
F-2 MUTUAL RESPONSIBILITY OF CONTRACTORS.
The Contractor shall afford other contractors reasonabie
opportunity for the introduction and storage of their materials and
equipment and the execution of their work, and shall properly
connect and coordinate his work with theirs.
If any part of the Contractor's Work depends for proper execution
or results upon the work of any other separate contractor, the
Contractor shall inspect and promptly report to the Architect any
apparent discrepancies or defects in such work that render it
unsuitable for such proper execution and results. Failure of the
Contractor to inspect and report shall constitute an acceptance of
the other contractors work as fit and proper to receive his Work,
except as to defects which may develop in the other separate
contractor's work after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property of
any separate contractor on the site, the Contractor shall, upon
due notice, settle with such other contractor by agreement, if he
wili so settle. If such separate contractor sues the Owner on
account of any damage alleged to have been so sustained, the
Owner shall notify the Contractor who shall defend against such
suit at the Contractor's expense, and if any judgment against the
Owrer arises therefrom, the Contractor shali pay or satisfy such
judgment and shali reimburse the Owner for ali attorney's fees,
court costs and expenses which the Owner has incurred in
connection with such suit.
F-3 CUTTING AND PATCHING UNDER SEPARATE
CONTRACTS. The Contractor shall do all cutting, fitting or
patching of his Work that may be required to fit it to receive or be
received by the work of other contractors shown in the Contract
Documents. The Contractor shall not endanger any wor�C or any
other contractors by cutting, excavating or otherwise alt ring any
work and shall not cut or alter the work of any other c�ntractor
except with the written consent of the Architect.
Any costs caused by defective or ill-timed work shall be �orne by
the party responsible therefor.
F-4 OWPIER'S RIGHT TO CLEAN UP. If a dispute arises
between the separate contractors as to their responsjbility for
cleaning up, the Owner may clean up and charge the cost thereof
I
6/23/99
GC-7
to the several contractors as the Director of the Department of
Transportation and Public Works shall determine to be just.
SECTION G
MISCELLANEOUS PROVISIONS
G-1 CONFLICT OF LAWS. The law of the place w�hpre the
site is located shall govern the Contract. The Contractor must
familiarize himself and strictiy comply with ali Federat, Sta:e, and
County and City �aws, Statutes, Charter, Ordinances,
Regulations, or Directives controlling the action or operation of
those engaged upon the work affecting the materials used. He
shall indemnify and save harmless the City and all of its officers
and agents against any claim or liabi�ity arising from or based on
the violation of any such Laws, Statutes, Charter, Ordinances,
Regulations, or Directives, whether by himself, his emp;oyees,
agents or subcontractors.
G-2 GOVERNING LAWS. It is mutually agreed and
understood that this agreement is made and entered into by the
parties hereto with reference to the existing Charter and
Ordinances of the City of Fort Worth and the laws of the State of
Texas with reference to and governing all matters affecting this
Contract, and the Contractor agrees to fully comply with all the
provisions of the same.
G-3 PERSONAL LIABIIITY OF PUBLIC OFFICIALS. In
performing their duties under the Statutes of the State of Texas
and the Charter and Ordinances of the City of Fort Worth in
connection with this Contract, or in exercising any of the powers
granted the Owner herein, the o�cers, agents and employees o`
the City of Fort Worth are engaged in the performance of a
governmental function and shall not incur any personal liability by
virtue of such performance hereunder, except for gross
negligence or willful wrong.
G-4 COMPLIANCE WITH LAWS. Contractor aorees the
comply with all laws, Federai, state and tocal, including ali
ordinances, rules and regulations of tne City of Fort 'vVoRh,
Texas. Materials incorporated into the finished Project are not
subject to State Sales Tax.
Contractors are responsible for obtaining construction permits
from the governing agencies. Contractor shall schedule all code
inspections with the Code Inspection Division in accordance with
the permit requirements and submit a copy of updated schedute
to the Construction manager weekly. Building, plumbing,
electrical and mechanical building permits are issued �vithcut
charge. Water and sewer access fees will be paid by the City.
Any other permit fees are the responsibiiity of the Contractor.
G-5 I DEMNIFICATION: Contractor covenants and agrees
to indemni�y City's engineer and architect, and their personnel at
the project site for Contractor's sole negligence. In addition,
Contractor covenants and agrees to indemnify, hold harmless
and defend, at its own expense, the Owner, its officers, servants
and employees, from and against any and all claims or suits for
property loss, property damage, personal injury, including death,
arising out of, or alleged to arise out of, the work and services to
be performed hereunder by Contractor, its officers, agents,
employees, subcontractors, licensees or invitees, whefhar or not
anv such iniurv. damaae or deafh is caused. in who/e or in
part, by the neqliaence or alleqed nealiqence of Owner, iis
offlcers. servants. or emnlovees. Contractor likewise
covenants and agrees to indemnify and hold harmless ihe Owner
from and against any and all injuries to Owner's officers, servants
and employees and any damage, loss or destruction to property
of the Owner arising from the performance of any of the terms
and conditions of this Contract, whether or not artv such 7niury
or damaqe is caused in whole or in oaK bv the neali4ence or
�
LaJ
L�J
�
l�J
u
�
L�J
�
L'�J
�
L�J
�
�.
�
L_1
Ld
�
��i
a!leaed rtealiaence of Owner. its o�cers. servants or
emn/ovees.
In the event Owner receives a written claim for damages against
the Contractor or its subcontractors prior to final payment, final
payment shall not be made until Contractor either (a) submits to
Owner satisfactory evidence that the claim has been settled
and/or a reiease from the claimant involved, or (b) provides
Owner with a letter from Contractor's liability insurance carrier
that the claim has been referred to the insurance carrier.
The Director may, if he deems it appropriate, refuse to accept
bids on other Ciry of Fort Worth public work from a Contractor
against whom a claim for damages is outstanding as a result of
work performed under a City Contract.
G-6 SUCCESSORS AND ASSIGNS. Except as provided in
Paragraph E-2, this contract shall be binding upon and insure to
the benefit of the parties hereto, their Successors or Assigns.
Contractor shall not assign or sublet all or any part of this
Contract or his rights or duties hereunder without the prior written
consent of the Owner. Any such purported assignment or
subletting without the prior written consent of Owner shall be void.
G-7 WRI77EN NOTICE. Written Notice shall be deemed to
have been duly served if delivered in person to the individual or
member of the firm or to an officer of the corporation for whom it
was intended, or if delivered at or sent by registered or certified
mail to the last business address known to him who gives the
notice.
G-8 SURETY BONDS: Surety Bonds are required on all
City contracts in excess of $25,000. The Contractor agrees, on
the execution of this Contract, and before beginning work, to
make, execute and deliver to said City of Fort Worth good and
su�cient surety bonds for the faithful performance of the terms
and stipulations of the Contract and for the payment to all
claimants for labor and/or materials furnished in the prosecution
of the work, such bonds being as provided and required in Article
5160 of the Revised Civil Statutes of Texas, as amended, in the
form included in the Contract Documents, and such bonds shall
be 100 percent of the total contract price, and the said surety
shall be a surety company duly and legally authorized to do
business in the State of Texas, and acceptable to the City
Council of the City of Fort Worth.
Bonds shall be made on the forms furnished by or otherwise
acceptabie to the City. Each bond shall be properly executed by
both the Contractor and the Surety Company. Bonds required by
the City shall be in compliance with all relevant local, state and
federal statutes.
To be an acceptable surety on the bond, (1) the name of the
surety should be included on the current U. S. Treasury List of
Acceptable Securities [Circular 570]. Any surety authorized to do
business in Texas a may write performance and payment bonds
on a project without reinsurance to the �imit of 10 percent of its
capital and surplus. Such a surety must reinsure any obligation
over 10 percent. The amount in excess of 10 percent must be
reinsured by reinsurers who are duly authorized, accredited, or
trusteed to do business in the State of Texas.
Should any surery for the contracted project be determined
unsatisfactory at any time during same, the Contractor shall
immediately provide a new surety bond satisfactory to the City.
G-9 OWNER'S RIGHT TO CARRY OUT THE WORK. If
the Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents or fails to perform any
provision of the Contract, the Owner may, without prejudice to
any other remedy he may have, enter the site and make good
6/23/99
�
GC-8
such deficiencies. In such case an appropriate Change Order
shall be issued deducting from the payments then or thereafter
due the Contractor the cost of correcting such deficiencies,
including the cost of the ArchitecYs additional services made
necessary by such default, neglect or failure. If the payments
then or thereafter due the Contractor are not su�cient to cover
such amount, the Contract shall pay the difference to the Owner.
G-10 ROYALTIES AND PATENTS. The Contractor shali
pay all royalties and license fees. He shall defend all suits or
claims for infringement of any patent rights and shalt save the
Owner harmless from loss on account thereof and shall be
responsible for all such loss when a particular design, process or
the product of a particular manufacturer or manufacturers is
specified; however, if the Contractor has reason to be{ieve that
the design, process or product specified is an infringement of a
patent, he shall be responsible for such loss unless he promptly
gives such information to Architect.
G-11 TESTS. If the Contract Documents, Laws, Ordinances,
Rules, Regulations or Orders of any public authority having
jurisdiction require any Work to be inspected, tested or zpproved,
the Contractor shall give the Architect timely notice of its
readiness and the date arranged so the Architect may observe
such inspection, testing or approval. The Owner shall be2r all
costs of such inspection, tests and approvals untess otherwise
provided.
If after the commencement of the Work, the Owner or Architect
determine that any Work requires speciai inspection, testing or
approval not included above, the Owner or the Architect, upon
written authorization from the Owner, will instruct the Contractor
to order such special inspection, testing or approval, and the
Contractor shall give notice as required in the preceding
paragraph. If such special inspection or testing reveals a failure of
the Work to comply (1) with the requirements of the Contract
Documents or (2) with respect to the psrFormance of the work,
with Laws, Statutes, Charter, Ordinances, Regulations or Orders
of any public authority having jurisdiction, the Contractor shall
bear all costs thereof, including the Architect's additional services
made necessary by such costs; otherwise the Owner shall bear
such costs, and an appropriate Change Order shall be issued.
The Contractor shall secure certificate of inspection, testing or
approval, and three copies will be promptly delivered by him to
the Architect. The Architect will review the certificates and
forward one copy of each with his recommendation(s) to the
Owner.
If the Architect or Owner wish to observe the inspections, tests or
approvals required by this Section, they will do so promptly and,
where practicable, at the source of supply.
Neither the observations of the Architect or the Owner in their
administration of the Construction Contract, nor inspections, tests
or approvals by persons other than the Contractor shall relieve
the Contractor from his obligations to perForm the VlrorR in
accordance with the Contract Documents.
G-1� INTERRUPTION OF EXISTING UTI! ITIES
SER ICES. The Contractor shall perform the work under this
Con�iact with a minimum of outage time for all utiiities:
Inter�uption shail be by approved sections of the utility. In some
cases, the Contractor may be required to perForm the work while
the existing utility is in service. The existing utility service may be
interrupted only when approved by the Owner. When it is
necessary to interrupt the existing utilities, the Contractor shall
notify the Owner in writing at least ten days in advance of the
time that he desires the existing service to be interru�ted. The
interruption time shall be kept to a minimum. Depending upon the
activities at an existing facility that requires continuous service
�
�
LJ
�
�
�
L�7
i�.l
�
�
L'�
L,
���
l�l
�
�
��
from the existing utiliry, an interruption may not be subject to
schedule at the time desired by the Contractor. In such cases,
the interruption may have to be scheduled at a time of minimum
requirements of demand for the utility. The amount of time
requested by the Contractor of existing utility services shail be as
approved by the Owner.
G-13 LAYING OUT WORK. The Contractor shall verify
dimensions and elevations indicated in layout of existing work.
Discrepancies between Drawings, Specifications, and existing
conditions shall be referred to Architect for adjustment before
work affected is performed. Failure to make such notification shall
place responsibility upon Contractor to carry out work in
satisfactory workmanlike manner at the Contractor's sole
expense.
The Contractor shall be held responsible for the location and
elevation of all the construction contemplated by the Construction
Documents.
Prior to commencing work, the Contractor shall carefuliy compare
and check all Architectural, Structural, Mechanical an Electrical
drawings; each with the other that in any affects the locations or
elevation of the work to be executed by him, and should any
discrepancy be found, he shall immediately report the same to
the Architect for verification and adjustment. Any duplication of
work made necessary by failure or neglect on his part to comply
with this function shall be done at the contractors sole expense.
G-14 MEASUREMENTS: Before ordering any material or
doing any work, the Contractor shall verify all measurements at
the site or at the building and shall be wholty responsible for the
correctness of same. No extra charge or compensation will be
allowed on account of any difference between actual dimensions
and dimensions indicated on the drawings. Any difference which
may be found shali be submitted to the Architect for consideration
and adjustment before proceeding with the project.
G-15 EXISTING OVERHEAD OR UNDERGROUND WORK.
The Contractor shall carefully check the site where the project is
to be erected and observe any existing overhead wires and
equipment. Any such work shall be moved, replaced or protected,
as required, whether or no shown or specified at the contractor's
sole expense.
Attention is directed to the possible existence of pipe and other
underground improvements that may or may not be shown on the
Drawings. All reasonable precautions shall be taken to preserve
and protect any such improvements whether or not shown on the
Drawings.
Location of existing underground lines, shown the Drawings are
based on the best available sources, but are to be regarded as
approximate only. Exercise extreme care in locating and
identifying these lines before excavation in adjacent areas.
G-76 ALIGNMENT OF JOINTS IN FINISH MATERIALS. It
shall be the responsibility of the Contractor to make certain in the
installation of jointed floor, wall and ceiling materials that:
1. preserve and protect the rights of the Owner and the
Architect under the Contract with respect to the Work to be
performed under the subcontract so that the subcontracting
thereof will not prejudice such rights;
2. Place joints •to relate to all opening and breaks in the
structure and be symmetrically placed wherever possible.
This, includes heating registers, light fixtures, equipment, etc.
If because of the non-related sizes of the various materials and
locations of openings, etc., it is not possible to accomplish the
above, the Contractor shall request the Architect to determine the
6/23/99
GC-9
most satisfactory arrangement. The Contractor shall establish
centerlines for all trades.
G-17 INTEGRATING EXISTING WORK. The Con;ractor
shail protect all existing street and other improvements from
damages.
Contractor's operations shall be confined to the immediate
vicinity of the new work and shall not in any interfere with or
obstruct the ingress or egress to an from existing adjacent
facilities.
Where new site work is to be connected to existing work, special
care shall be exercised by the Contractor not to disturb or
damage the existing work more than necessary. AII damaged
work shali be replaced, repaired and restored to its original
condition at no cost to the Owner.
G-18. HAZARDOUS MATERIAL CERTIFICATION: It is the
intent of the contract documents, whether expressiy stated or not,
that nothing containing hazardous materials, such as asbestos,
shall be incorporated in to the project. The contractor shall
exercise every reasonable precaution to ensure that
asbestos-containing materials are not incorporated into 2ny
portion of the project, including advising all materiais suppliers
and subcontractors of this requirement. The contractor shal!
verify that components containing lead do not contact the potable
water supply.
G-19 LOCATION OF EQUIPMENT AND PIPING. Dra�aing
showing location of equipment, piping, ductwork, etc. are
diagrammatic and job conditions may not always permit their
installation in the location shown. When this situation occurs, it
shall be brought to the Architect's attention immediately and the
relocation determined in a joint conference. The Contractor will
be held responsible for the retocating of any items without first
obtaining the ArchitecYs approval. He shall remove and relocate
such items at his own expense if so directed by the Architect.
Where possible uniform margins are to be maintained between
parallel lines and or adjacent wall, floor or ceiling surfaces.
G-20 OVERLOADING. The Contractor shall be responsible
for loading of any part or parts of structures beyond their safe
carrying capacities by placing of materials, equipme�t, tools,
machinery or any other item thereon. No Ioads shali be placed on
floors or roofs before they have attained their permanent ard safe
strength.
G-21 MANUFACTURER'S INSTRUCTIONS. Where it is
required in the Specifications that materiafs, products, processes,
equipment, or the like be installed or applied in accordance with
manufacturer's instructions, direction or specifications, or words
to this effect, it shali be construed to mean that said application
or installation shall be in striot accordance with printed
instructions furnished by the manufacturer of the material
concerned for use under conditions similar or those at the job
site. Six copies of such instructions shall be furnished to the
Architect and his approvai thereof obtained before work is begun.
G-22 CLEANING UP. The Contractor shall kesp the
premises free from accumulation of waste material or rubbish
caused by employees or as a result of the work.
At completion of work, the General Contracter shail, immediately
prior to final inspection of complete building, execute the following
final cleaning work with trained janitorial personnel and with
material methods recommended by the manufactures of installed
materials.
1. Sweep and buff resilient floors and base, and vacuum
carpeting.
I�i
�
�
�
l..�J
L��
�
'�!
�
�
�
�
l�!1
�
�
�
LJ
�
��
2. Dust all metal and wood trim and similar finished materials.
3. Ciean all cabinets and casework.
4. Dust al� ceilings and walls.
5. Dust, and if necessary wash, all piumbing and electrical
fixtures. '
6. Wash all glass and similar non-resilient materials.
7. All hardware and other unpainted metals shall be cleaned
and polished and all equipment and paint or decorated work
shall be cleaned and touched-up if necessary, and all
temporary labels, tags, and paper coverings removed
throughout the buildings. Surfaces that are waxed shall be
polished.
8. The exterior of the building, the grounds, approaches,
equipment, sidewalks, streets, etc. shall be cleaned similar
to interior of buildings and left in good order at the time of
final acceptance. AII paint surfaces shall be clean and
unbroken, hardware shall be clean and polished, all required
repair work shall be completed and dirt areas shall be
scraped and cleared of weed growth.
9. Clean ali glass surfaces and mirrors of putty, paint materials,
etc., without scratching or injuring the glass and leave the
work bright, clean and polished. Cost of this cieaning work
shali be borne by Contractor.
10. Cleaning, polishing, scaling, waxing and all other finish
operations indicated on the Drawings or required in the
Specifications shall be taken to indicate the required
condition at the time of acceptance of all work under the
Contract.
11. Burning: Burning of rubbish on the premises will not be
permitted.
G-23 DUST CONTROL. Precaution shall be exercised at all
times to control dust created as a result of any operations during
the construction period. If serious problems or complaints arise
due to air-borne dust, or when directed by the Architect,
operations causing such probfems shall be temporarily
discontinued and necessary steps taken to control the dust.
G-24 FIRE PROTECTION. The contractor shall at all times
maintain good housekeeping practices to reduce the risk of fire
damage or injury to workmen. All scrap materials, rubbish and
trash shall be removed daily from in and about the building and
shall not be permitted to be scattered on adjacent property.
Suitable storage space shall be provided outside the immediate
building area for storing flammable materials and paints; no
storage wiil be permitted in the building. Excess flammabie
liquids being used inside the building shall be kept in closed
metal container and removed from the building during unused
periods.
A fire extinguisher shall be available at each location where
cutting or welding is being performed. Where electric or gas
welding or cutting work is done, interposed shields of
incombustible material shall be used to protect against fire
damage due to sparks and hot metal. When temporary heating
devices are used, a watchman shatl be present to cover periods
when other workmen are not on the premises.
The Contractor shall provide fire e�inguishers in accordance with
the recommendations and NFPA Builetins Nos. 10 and 241.
6/23/99
�
GC-10
However, in ail cases a minimum of two fire extinguishers shall
be available for each floor of construction.
G-25 CUTTING AND PATCHING. Wherever cutting and
removal of portions of the existing work is indicated, sucli �vork
shall be neatly sawed or cut by contractor in a manner that will
produce a neat straight line, parallei to adjacent surtaces or
plumb for verticai surfaces. Care should be exercised not to
damage any work that is to remain.
At no time shall any structural members be cut without written
consent from the Architect.
G-26 PROJECT CLOSEOUT.
Final Insnection. Record Drawinas: Attention is called to General
Conditions Section 1 entitled, "Payments and Completion."
Maintenance Manual: Sheets shail be 8'/s" x 11", except puli out
sheets may be neatly folded to 8'/z " x 11". Manuals shall be
bound in plastic covered, 3 ring, loose leaf binder wiih title of
project lettered on front and shall contain:
1) Name, address and trade of all sub-contractors.
2) Complete maintenance instructions; name, address, and
telephone number of installing Contractor, manufacturer's
local representative, for each piece of operative equipment.
3) Catalog data on plumbing fixtures, valves, water heaters,
heating and cooling equipment, temperature control, fan,
electrical panels, service entrance equipment and light
fixtures.
4) Manufacturer's name, type, color designation for resilient
floors, windows, doors, concrete block, paint, roofing, c+ther
materials.
Submit six copies of Maintenance Manual, prior to request for
final payment.
O�erational Insoection and Maintenance Instruction: The
Contractor shall provide at his expense, competent
manufacturer's representatives to completely check out all
mechanical and electricai systems and items covered by the
Drawings and Specifications. This requirement shall be
scheduled just prior to and during the initial st2rt up. After all
systems are functioning properly the representatives shall instruct
maintenance personnel of the Owner in the p�oper operation and
maintenance of each item.
G-27 GUARANTEE AND F�,XTENDED GUARANTEe. Upon
completion of the Project, prior to final payment, guarantees
required by technical divisions of Specifications shall be properly
executed in quadruplicate by subcontractors and submitted
through the Contractor to Architect. Delivery of guarantees shall
not relieve Contractor from any obligation assumed under
Contract.
The Contractor shall guarantee the entire Project for one year. In
addition, where separate guarantees, for certain portions of work,
are for longer periods, General Contractor's guarantee shall be
extended to cover such longer periods.
Guarantees shall become valid and operative and cemmence
upon issuance of Certificate of lnspection and Acceptance by
Owner. Guarantees shail not apply to work whsre damage is
result of abuse, neglect by Owner or his successor(s) in int�rest.
The Contractor agrees to warrant his work and m2terials provided
in accordance with this contract and the terms of the Technical
�
�
�
I�I
�
�
�
u
�
��
l.J
..
1�1
I:J
I�
�
�
�
I�I
�
Specifications contained herein. Unless supplemented by the
Technical Specifications or the manufacturers normal extended
warrantees, the Contractor shall warrant ail work materials, and
equipment against defects for a period of one year from the date
of final acceptance. The Contractor further agrees to bear all
costs of making good all work that is found to be defective or not
provided in accordance with the Contract Documents.
Additionally if the facility or contents are damaged due to
defective materials or workmanship of the Contractor, the
Contractor further agrees to bear all cost of repairing and/or
replacing damaged items and components to bring such items
back to at Ieast their original condition.
G-28 RECORD DRAWINGS. Upon completion of the Work
and prior to application for final payment, one print of each of the
drawings accumpanying this specification shall be neatly and
clearly marked in red by the Contractor to show variations
between the construction actually provided and that indicated or
specified in the Contract Documents. The annotated documents
shall be delivered to Architect. Where a choice of materials
and/or methods is permitted herein and where variations in the
scope or character of the work from the entire work indicated or
specified are permitted either by award of bidding items specified
for that purpose, or by subsequent change to the drawings, the
record drawings shall define the construction actually provided.
The representation of such variations shall conform to standard
drafting practice and shall include supplementary notes, legends
and details which may be necessary for legibility and clear
portrayal of the actual construction. The record drawings shall
indicate, in addition, the actual location of all sub-surface utility
lines, average depth below the surface and other appurtenances.
G-29 CONSTRUCTION FENCE. At the Contractor's option,
he may provide a substantial chain-link construction fence around
all or a part of the site. The fences and gates must be
maintained throughout the construction period. Remove the
fences and gates upon completion of the Project and restore the
site to the required original or contract condition.
G-30 PRODUCT DELIVERY. STORAGE. HANDLING. The
Contractor shall handle, store and protect materials and products,
including fabricated components, by methods and means which
will prevent damage, deterioration and loss, including theft (and
resulting delays), thereby ensuring highest quality results as the
work progresses. Control delivery schedules so as to minimize
unnecessary long-term storage at project site prior to installation.
G-31 AGE: In accordance with the policy ("Policy") of the
Executive Branch of the federal government, Contractor
covenants that neither it nor any of its officers, members, agents,
employees, program participants or subcontractors, while
engaged in pertorming this contract, shall, in connection with the
employment, advancement or discharge of employees or in
connection with the terms, conditions or privileges of their
employment, discriminate against persons because of their age
except on the basis of a bona fide occupational quatification,
retirement plan or statutory requirement.
Contractor further covenants that neither it nor its officers, mem-
bers, agents, employees, subcontractors, program participants,
or persons acting on their behalf, shail specify, in solicitations or
advertisements for employees to work on this contract, a
maximum age limit for such employment unless the specified
maximum age limit is based upon a bona fide occupational
qualification, retirement plan or statutory equipment.
Contractor warrants it will fully compiy with the Policy and will
defend, indemnify and hold City harmless against any claims or
allegations asserted by third parties or subcontractor against City
arisi�g out of Contractor's and/or its subcontractors' alieged
6l23/99
�
GC-11
failure to comply with the above referenced Policy concerning age
discrimination in the performance of this agreement.
G-32 DISABILITY: In accordance with the provisions of the
Americans With Disabilities Act of 1990 ("ADA"), Contractor
warrants that it and any and all of its subcontractors will not
unlawfully discriminate on the basis of disability in the provision of
services to the general public, nor in the availability, terms and/or
conditions of employment for appiicants for employment with, or
employees of Contractor or any of its subcontractors. Contractor
warrants it wili fully comply with ADA's provisions and any other
applicable federal, state and local laws concerning disability and
will defend, indemnify and hold City harmtess against any claims
or allegations asserted by third parties or subcontractors against
City arising out of Contractor's and/or its subcontractors' alteged
failure to comply with the above-referenced laws concerning
disability discrimination in the performance of this agreement.
SECTION H
CONTRACT TIME
H-1 DEFINITIONS. The Contract Time is the
period of time allotted in the Contract Documents for completion
of the Work.
The date of commencement of the Work is the date established
in the Notice to Proceed. If there is no notice to proceed, it shall
be the date of the Agreement or such other date as may be
established therein. ,
The Date of Substantial Completion of the Work or designated
portion thereof is the Date certified by the Architect with the
approval of the Owner that construction is sufficiently complete,
in accordance with the Contract Documents, so the Owner may
occupy the Work or designated portion thereof for the use for
which it is intended. Final acceptance of the completed Hlork or
any portion thereof can be made only by the City Council of the
City of Fort Worth or iYs designated Assistant City Manager, and
no other form of acceptance witl be binding upon the O�vner.
A calendar day constitutes 24 hours of time and is any one of the
seven days of a week, including Sunday, regardless of whether a
"Working Day" or not, and regardless of weather conditions or
any situation which might delay construction. An extension of
contract time shall be in accordance with this Section. Extensions
of time will be as recommended by the Architect avith flnal
approval by City of Fort Worth.
A working day is defined as a caiendar day, not including
Saturdays, Sundays, and legal holidays, in which weather or
other conditions not under the control of the Contractor permit the
performance of work for a continuous period of not I�ss than
seven hours between 7:00 a.m. and 6:00 p.m. However, nothing
in these Contract Documents shail be construed as prohibiting
the Contractor from working on Saturdays if he so dasires.
Should the Contractor choose to work on Saturdays, one day v�rill
be charged as contract working time when weather or other
conditions permit seven hours of work as delineated above. Legal
holidays are defined as being New Year's Day, Independence
Day, Labor Day, Thanksgiving Day, Christmas Day, Memorial
Day, and Vetgran's Day.
H-2 PROGRESS AND COMPLETION. All the time limits
stated in the Contract Documents are of essence to the Contract.
The Contractor shall begin the Work on the date o�
commencement as defined in this Section. He shall carry the
Work forward expeditiously with adequate forces and shall
complete it within the Contact Time.
�1
I
LR.7
{�.r
lJ
�
�
�
�
L�
�
�
�
��
�
�
L``!
�
'�1
H-3 DELAYS AND EXTENSIONS OF TIME. If the
Contractor is delayed at any time in the progress of the Work by
any act or neglect of the Owner or the Architect, or by any
employee of the Owner, or by any separate contractor employed
by the Owner, or �by any separate contractor employed by the
Owner, or by changes ordered in the Work, or by labor disputes,
fire, unusual delay in transportation, unavoidable casualties or
any causes beyond the Contractor's control, or by any cause
which the Architect determines may justify the delay, then the
contract time may be extended by Change Order for such
reasonable time as recommended by the Architect and approved
by the Owner. When the Contractor is delayed due to abnormal
weather conditions, the weather table provided as WT-1 in these
Contract Documents shali be used as the basis for providing a
fair and equitable adjustment of the contract time.
All claims for extension of time shall be made in writing to the
Architect no more than fifteen days after the occurrence of the
delay; otherwise they shall be waived.
If no schedule or agreement is made stating the dates upon
which written interpretations shall be furnished, then no claim for
delay shall be aliowed on account of failure to furnish such
interpretation until fifteen days after demand is made for them,
and not then unless such a claim is reasonable.
H�3 NO DAMAGE FOR DELAY. No payment,
compensation or adjustment or any kind (other than the
extensions of time provided for) shall be made to the contractor
for damages because of hindrances or delays from an cause in
the progress of the work, whether such hindrances or delays be
avoidable or unavoidable, and the contractor agrees that he will
make no claim for compensation, damages or mitigation of
liquidated damages for any such delays, and will accept in full
satisfaction for such delays said extension of time.
SECTION I
PAYMENTS AND COMPLETION
I-1 CONTRACT SUM. The Contract Sum is
stated in the proposal as accepted and is the toial amount
payable by the Owner to the Contractor for the performance of
the Work under the Contract Docume�ts.
I-2 SCHEDULE OF VALUES. Before the first
Applicable for Payment, the Contractor shall submit to the
Architect a Schedule of Values of the various portions of the
Work, including quantities if required by the Architect,
aggregating the total Contract Sum, divided so as to facilitate
payments to Sub-contractors, prepared in such form as specified
or as the Architect and the Contractor may agree upon, and
supported by such data to substantiate its correctness as the
Architect may require. Each item in the Schedule of Values shall
include its proper share of overhead and profit. This Schedule,
when approved by the Architect and the Owner, shall be used as
a basis for the Contractor's Applications for Payment.
i-3 ADJUSTMENT OF QUANTITIES. Where unit prices
and estimated quantities are used to compute the contract
amount, the Owner may increase the quantities by an amount
that is 20% of the total cost for that section. Unit prices for
adjustments to unit quantities in excess to 20% may be
negotiated at the request of either party.
I-4 PROGRESS PAYMENTS. On the first day of each
month after the first month's work has been completed, the
Contractor will make current estimates in writing for review by the
Architect of materials in place compiete and the amount of work
performed during the preceding month or period and the value
thereof at the prices contracted for as shown on the approved
Schedule of Values and Progress Schedule.
6/23/99
GC-12
If payments are to be made on account of materials or equipment
not incorporated in the Work but delivered and suitably stored at
the site or in an independent, bonded warehouse such payments
shall be conditioned upon submission by the Contractor of bills of
sale or such other procedures satisfactory to the Owner to
establish the Owner's title to such materials or equipment or
otherwise protect the Owner's interest including applicable
insurance and transportation to the site.
The Contractor warrants and guarantees that titie to all Work,
materials and equipment covered by an Application for Payment,
whether incorporated in the Project or not, will pass to the Owner
upon the receipt of such payment by the Contractor, free and
clear of all liens, claims, security interests or encumbrances
hereinafter referred to as "liens"; and that no Work, materiais or
equipment covered by an Application for Payment will have been
acquired by the Contractor, or by any other persons performing
the Work at the site or furnishing materials and equipment for the
Work, subject to an agreement under which an interest therein or
an encumbrance thereon is retained by the seller or otherNise
imposed by the Contractor or such other person.
The Contractor shall prepare each appiication for payment on AIA
Document G702, "Application and Certificate for Paymen;", and
attached thereto AIA Document G703, "Continuation SheeY, to
indicate the progress made to date and the period or month for
which payment is requested for each item listed in the Schedule
of Values. A copy of the revised monthly work progress schedule
must be attached before the pay request can be accepted.
I-5 CERTIFICATES FOR PAYMENT. If the Contractor
has made Appiication for Payment as above, the above, the
Architect will, with reasonable promptness but not more than
seven days after the receipt of the Application, pre�are a
Certificate of Payment, with a copy to the Contractor, for such
amount determined to be properly due, or state in writing reasons
for withholding a Certificate.
The issuance of a Certificate for Payment wiil constitute a
representation by the Architect to the Owner, based on the
Architect's observations at the site and the data compris+ng the
Appiication for Payment, that the Work has progressed to the
point indicated; that the quality of the Work is in accordance with
the Contract Documents (subject to an evaluation of the 1hJork as
a functioning whole upon Substantial Completion, to the results of
any subsequent tests required by the Contract Documents, to
minor deviations from the Contract Documents correctabfe prior
to completion, and to any specific Gualifications stated in the
Certificate); and recommendations to the Owner that the
Contractor be paid in the ameunt certified. In addition, the
Architect's approval of final payment assures the Owner that the
conditions precedent to the Contractor's being entitled to final
payment as set forth in this Section have been fulfilled.
After the Architect has issued a Certificate for Payment, the
Owner shall approve or disapprove same within ten days after it
has been delivered to the Director of the Department of
Transportation and Public Works. For contracts less than
$400,000, Owner shall pay 90% of the approved estimate to the
Contractor within seven days after its approval, and the remaining
10% of each such estimate will be retained by the Owner until the
final estimate is approved and the Work is accepted by the City
Council of the City of Fort WoRh. For contracts in excess of
$400,000, the Owner will retain only 5% of each estimate until the
final estimate is approved and work accepted by ihe Cir� Councit
of the City of Fort Worth.
No Certificate for a progress payment, nor any progress pa�ment,
nor any partial or entire use or occupancy of the Project by the
Owner, shall constitute an acceptance of any Work nct in
�
L�
0
i�
��
�
L�
l�lJ
��
�
IL7
�
l�'1
�
L�'
I�I
l�
�
�
�
i��
accordance with the Contract Documents, or relieve the
Contractor of liability in respect to any warranties or responsibility
for faulty materials or workmanship. The Contractor shall
promptly remedy any defects in the Work and pay for any
damage to other work resulting therefrom that shall appear within
a period of one year from the date of final acceptance of the
Work unless a longer period is specified.
1-6 PAYMENTS WITHHELD. The Architect may decline to
approve an Application for Payment and may withhoid his
Certificate in whofe or in part if in his opinion he is unable to make
the representations to the Owner as provided in this Section. The
Architect may also decline to approve any Applications for
Payment or, because of subsequently discovered evidence or
subsequent inspections, may nullify the whole or any part of any
Certificate for Payment previously issued to such extent as may
be necessary in his opinion to protect the Owner from loss
because of:
1) defective work not remedied;
2) claims filed or reasonable evidence indicating probable filing
of claims;
3) failure of the Contractor to make payments properly to
Subcontractors, or for labor, materials or equipment;
4) reasonable doubt that the Work can be completed for the
unpaid balance of the Contract Sum;
5) damage to another contractor;
6) reasonable indication that the Work will not be completed
within the Contract Time; or
7) unsatisfactory prosecution of the Work by the Contractor.
When such grounds for the refusal of payment are removed,
payment shall be made for amounts withheld because of them.
The Owner reserves the right to withhold the payment of any
monthly estimate, without payment of interest, if the Contractor
fails to perform the Work in accordance with the specifications or
instructions of the Architect.
I-7 UNRESOLVED CLAIMS: In the event a written claim
for damages against the Contractor or its subcontractors remains
unsettied at the time ali work on the project has been completed
to the satisfaction of the Director of the Transportation and Public
Works Department, as evidenced by a final inspection, flnal
payment to the Contractor shali not be recommended by the
Director of the Transportation and Public Works Department for a
period of 30 days after the date of such final inspection, unless
the Contractor shall submit written evidence satisfactory to the
Director that the claim has been settled and a release has been
obtained from the claimant involved.
Although the claim concerned remains unsettled at the expiration
of the above 30-day period, the Contractor may be deemed to be
entitled to a semi-final payment for work completed, such
semi-final payment to be in an amount equal to the total dollar
amount then due less the dollar value of any written claims
pending against the Contractor arising out of the performance of
such work, and such semi-final payment may then be
recommended by the Director.
The Director shall not recommend final payment to a Contractor
against whom such a claim for damages is outstanding for a
period of six months following the date of the acceptance of the
work performed unless the Contractor submits evidence in writing
satisfactory to the Director that:
1) The claim has been settled and a release has been obtained
from the claimant involved, or
6/23/99
2) Good faith efforts have been made to settle such out-
standing claims, and such good faith efforts have failed.
If condition (1) above is met at any time within the six month
period, the Director shall recommend that the final payment to the
Contractor be made. If condition (2) above is met at any time
within the six-month period, the Director may recommend tiiat the
final payment to the Contractor be made. At the expiration of the
six- month period the Director may recommend that final p�yment
be made if all other work has been performed and all other
obligations of the Contractor have been met to the satisfaction of
the Director.
The Director may, if he deems it appropriate, refuse to accept
bids on other Transportation and Public Works Department
contract work ' from a Contractor against whom a claim for
damages is outstanding as a result of work perFormed under a
City contract.
I-8 LIQUIDATED DAMAGES: The deducticn for liquidated
damages shall be as follows:
Amount of Contract Liquidated Damages Rer Dav
See Instructions To Bidders, Item �16.
1-9 FAILURE OF PAYMENT. If, without fault on the p2rt of
the Contractor, the Architect should fail to issue any Certificate
for Payment within seven days after receipt of the Contractor's
Application for Payment, if the Contractor's Application for
Payment, or if, without fault on the part of the Contractor, the
Owner should fail to approve such estimate or to pay to the
Contractor 90% or 95% (as applicable) of the amount thereo°
within the period of time specified, then the Contractor rc�ay, upon
seven (7) days additional written notice to tha Owner a�d to the
Architect, stop the Work until payment of the amount owi�g has
been received.
GC-13
I-10 SUBSTANTIAL COMPLETION AND FINAL
PAYMENT. Prior to the request for final payment, the Contractor
must meet all provisions for Project Closeout. When the
Contractor determines that the Work or a designated portion
thereof acceptable to the Owner is substantially complete, the
Contractor shall prepare the submission to the Architect a list of
items to be completed or corrected. The failure to include any
items on such list does not alter the responsibility of the
Contractor to complete all Work in accordance with the Contract
Documents. When the Architect, on the basis of an inspeciion,
determines that the Work is substantially complete, he then wilt
prepare a Certificate of Substantial Completion which, when
approved by the Owner, shall establish the Date of Substantial
Completion, shatl state the responsibilities of the Own�r and the
Contractor for maintenance, heat, utilities, and insurance, and
shall fix the time within which the.Contractor shail complete the
items listed therein, said time to be within the Contract time
unless extended.
Upon receipt of written notice that the Work is ready for final
inspection and acceptance and upon receipt of a final Appiication
for Payment and upon receipt of a final application for payment,
providing the record drawings have been received by the
Architect, the Architect will conduct such test and/or inspections
as he deems necessary, and if in his opinion the Work has been
completed in acccsrdance with the Contraci Qocumen;s, the
Architect will promptly issue a final Certificate of Completion
stating that to the best of his knowledge, information and belief,
and on the basis of his observations and inspections, the Work
has been completed in accordance with the terms and conditions
of the Contract Documents and that the entire balance found to
be due the Contractor is due and payable. Final acceptance can
�
C
�
L�J
�
I�
�
L�J
�.J
�
�
�
�
L�J
L�J
L�,
J
Architect, the Architect will conduct such test and/or inspections
as he deems necessary, and if in his opinion the Work has been
completed in accordance with the Contract Documents, the
Architect will promptly issue a final Certificate of Completion
stating that to the best of his knowledge, information and belief,
and on the basis of his observations and inspections, tHe Work
has been compteted in accordance with the terms and conditions
of the Contract Documents and that the entire balance found to
be due the Contractor is due and payable. Final acceptance can
be made by the City Council of the City of Fort Worth or iYs
designated representative, and no other form of acceptance will
be binding upon the Owner. Final payment and retease of the
retainage amount will become due within fifteen days following
approval of the City Council of the City of Fort Worth in accepting
the work as complete.
Neither the final payment nor the remaining retained percentage
shail become due until the Contractor submits to the Architect (1)
an Affidavit (G706) that all payrolls, bills for materials and
equipment, and other indebtedness connected with the Work for
which the Owner or his property might in any way be responsible,
have been paid or otherwise satisfied, (2) consent of surety
(G707), if any, to final payment and, (3) (G706A) if required by
the Owner, other data establishing payment or satisfaction of all
such obligations, such as receipts, releases and waivers of liens
arising out of the Contract, to the extent and in such form as may
be designated by the Owner. •
If any Subcontractor, materialman or laborer refuses to furnish a
release or waiver required by the Owner, the Contractor may, at
the election of the Owner, furnish a bond satisfactory to the
Owner to indemnify him against any right, claim or lien which
might be asserted by such Subcontractor, materialman or
laborer. If any such right, claim or lien remains unsatisfied after
all payments are made. The Contractor shalt refund to the Owner
all monies that the latter may be compelled to pay to discharging
such right, claim or lien, including all costs and reasonable
attorney's fees.
The acceptance of final payment shall constitute a waiver of all
claims by the Contractor except those previously made in writing
and still unsettled.
SECTION J
PROTECTION OF PERSONS AND,PROPERTY
J-1 SAFETY PRECAUTIONS AND PROGRAMS. The
Contractor shall be responsible for initiating, maintaining and
supervising all safety precautions and programs in connection
with the Work. The Contractor shall designate a responsible
member of his organization at the site whose duty shall be the
prevention of accidents. This person shall be the Contractor's
superintendent unless otherwise designated in writing by the
Contractor to the Architect.
J-2 SAFETY OF PERSONS AND PRO�ERTY. The
Contractor shall take all reasonable precautions or the safety of,
and shall provide all reasonable protection to prevent damage,
injury or loss to:
(1) all employees on the Work and ali other persons who may
be affected thereby;
(2) all the Work and all materials and equipment to be
incorporated therein, whether in storage on or-off the site,
under the care, custody or control of the Contractor or any of
his Subcontractors or Sub-contractors; and �
(3) other property at the site or adjacent thereto, including trees,
shrubs, lawns, walks, pavements, roadways, structures and
� 6/23/99
�
GC-14
utilities not designated for removal, relocation or
replacement in the course of construction.
Until acceptance of the Work, it shall be under the charge and
care of the Contractor, and he shall take every precaution against
injury or damage to the Work by the action of the elements or
from any other cause whatsoever, whether arising from the
execution or from the non-execution of the Work. The Contractor
shall rebuild, repair, restore and make good, at his own expense,
all injuries or damages to any portion of the Work occasioned by
any of the above, caused before its completion and acceptance.
The Contractor shall comply with alt applicable Laws,
Ordinances, Rules, Regulations and Orders of any pubtic
authority having jurisdiction for the safety of persons or property
or to protect them from damage, injury or loss. He shal! erect and
maintain, as required by existing conditions and progress of the
Work, all reasonable safeguards for safety and protec;ion,
including posting danger signs and other warnings against
hazards, promulgating safety regulations and notifying owr,ers
and users of adjacent utilities.
When the use or storage of explosives or other hazardous
materials or equipment is necessary for the execution of the
Work, the Contractor shall exercise the utmost care and shall
carry on such activities under the supervision of properly qualified
personnel.
All damage or loss to any property referred to in the preceding
paragraphs caused in whole or in part by the Contractor, any
Subcontractor, or anyone directly or indirectly employed by any of
them, or by anyone for whose acts any of them may be liable,
shall be remedied by the Contractor, including damage or loss
attributable to faulty Drawings or Specifications and acts or
omissions of the Architect or anyone empioyed by him or for
whose acts he may be liable, and not attributable to the `ault or
negligence of the Contractor or anyone claiming through the
Contractor for such damage or loss.
The Contractor shall not load or permit any part of the Work to be
loaded so as to endanger its safety.
J-3 HARD HATS. Hard Hats will be required at all
construction sites included in this Contract from start to
completion of work. Each Contractor, employee and visitor at
any construction site included in the Contract will be rsquired to
wear a hard hat. The Contractor shall enforce the wearing of hard
hats by Contractor, employees and visitors. These requirements
are in addition to the Accident Prevention Clause in the General
Conditions of the Contract. Contractor shall provide ten hard hats
for use by the consulting Architects and Engineers and visitors.
J-4 EMERGENCIES. In any emergency affecting the
safety oi persons or property, the Contractor shall act at his
discretion to prevent threatened damage, injury or loss. Any
additional compensation or extension of time claimed by the
Contractor on account of emergency work shail be determined as
provided in Changes in the Work.
SECTION K - INSURANCE
K-1 Insurance Reauired. The Contractor shall not
commence work under this Contract until he has obtai�ed all
insu�ance required under this Section and such insurance has
been approved by the City of Fort Worth, nor shall the Contractor
ailow any Subcontractor to commence work to be performed
under this Contract until all similar insurance of the Subcontractor
has been so obtained and approved.
K-1 Insurance Reauired. The Contractor shall not
commence work under this Contract until he has obtained ail
�
I'�
�
insurance required under this Section and such insurance has
been approved by the City of Fort Worth, nor shall the Contractor
allow any Subcontractor to commence work to be performed
under this Contract until all similar insurance of the Subcontractor
has been so obtained and approved.
K-2 Workers' Compensation Insurance:
1) General
� a) Contractor's Worker's Compensation Insurance.
Contractor agrees to provide to the Owner (City) a
certificate showing that it has obtained a policy of
workers compensation insurance covering each of its
D employees employed on the project in compliance with
state law. No Notice to Proceed will be issued until the
Contractor has complied with this section.
�
�
'�
� �I
1�'J
lJ
b) Subcontractor's Worker's Compensation Insurance.
Contractor agrees to require each and every
subcontractor who will perform work on the project to
provide to it a certificate from such subcontractor
stating that the subcontractor has a policy of workers
compensation insurance covering each employee
employed on the project. Contractor will not permit any
subcontractor to perform work on the project until such
certificate has been acquired. Contractor shall provide
a copy of all such certificates to the Owner (City).
c) By signing this contract or providing or causing to be
provided a certificate of coverage, the contractor is
representing to the City that all employees of the
contractor who will provide services on the project will
be covered by worker's compensation coverage for the
duration of the project, that the coverage wiil be based
on proper reporting of classification codes and payroll
amounts, and that all coverage agreements will be filed
with the appropriate insurance carrier or, in the case of
a self-insured, with the Texas Workers Compensation
Commission's Division of Self-Insurance Regulation.
Providing false or misleading information may subject
the contractor to administrative penalties, criminal
penalties, civil penalties or other civil actions.
d) The contractor's failure to comply with any of these
� provisions is a breach of contract by the contractor
which entitles the City to declare the contract void if the
contractor does not remedy the breach within ten days
after receipt of notice of breach from the City.
�
L�J
L�l
�
�
�
2) Definitions:
a) Certificate of coverage ("certificate"). A copy of a
certificate of insurance, a certificate of authority to self-
insure issued by the Texas Workers' Compensation
Commission, or a coverage agreement (TWCC-81,
TWCC-82, TWCC-83, or TWCC-84), showing statutory
workers' compensation insurance coverage for the
person's or entity's employees providing services on a
project, for the duration of the project.
b) Duration of the Project. Includes the time from the
beginning of the work on the project until the
contractor's/person's work on the project has been
completed and accepted by the City.
c) Persons providing services on the project
("subcontractor" in section 406.096)-includes all
persons or entities performing all or part of the services
the contractor has undertaken to perform on the
project, regardiess of whether that person contracted
directly with the contractor and regardless of whether
that person has employees. This includes, without
limiiation, independent contractors, subcontractors,
leasing companies, motor carriers, owner-operators,
6/23/99
D
GC-15
employees of any such entity, or employees of any
entity which furnishes persons to provide services on
the project. "Services" include, without limitation,
providing, hauling, or delivering equipment or materiais,
or providing labor, transportation, or other services
related to a project. "Services" does no: include
activities unrelated to the project, such as
food/beverage vendors, o�ce supply deliveries, and
delivery of portable toilets.
3) Requirements
a) The contractor shall provide coverage, based on proper
reporting of classification codes and payroli arnounts
and filing of any coverage ag�eements, which meets
the statutory requirements of Texas Labor Code,
Section 401.011(44) for ail employees of the contrac?or
providing services of the project, for the duration of the
project.
b) The Contractor must provide a certi5cate of coverage
to the governmental entity prior to being awarded the
contract.
c) If the coverage period shown on the con:ractor's
current ce�tificate of coverage ends during the duration
of the project, the contractor must, prior to the end of
the coverage period, file a new certificate of coverage
with the City showing that coverage has been
extended.
d) The contractor shall obtain from each person providing
services on a project, and provide to the City:
i) a certificate of coverage, prior to that person
beginning work on the project, so the
governmental entity will have on file certificates of
coverage showing coverage for al1 persons
providing services on the project; and
ii) no later than seven days after receipt by the
contractor, a new certificate of coverage shonring
extension of coverage, if the coverage period
shown on the current certificate of coverage ends
during the duration of the project.
e) The contractor shall retain all required certificates of
coverage for the duration of the project and fur one
year thereafter.
fl The contractor shall notify the City in writing by certified
mail or personal delivery, within ten (10) days after the
contractor knew or should have known, of any change
that materially affects the provision of coverage of any
person providing services on the project.
g) The contractor shali post on each project site a notice,
in the text, form and manner prescribed by the Texas
Worker's Compensation Commission, informing all
persons providing services on the project that they are
required to be covered, and stating how a person may
verify coverage and report lack of coverage.
h) The contractor shall contractually require each person
with whom it contracts to provide services on a project,
to:
i) provide coverage, based on proper repoRing on
the classification codes and payroll amounts and
filing of any coverage agreements, which meets
the statutory requirements of Texas labor Code,
Section 401.011(44) for all of its emplovees
providing services on the project, for ths duration
of the project;
O
�
�
L�,
�
ii) provide to the contractor, prior to that person
beginning work on the project, a certificate of
coverage showing that coverage is being provided
for all empioyees of the person providing services
on the project, for the duration of the project;
iii) provide the contractor, prior to the end of the
coverage period, a new certificate of coverage
showing extension of coverage, if the coverage
period shown on the current certificate of
coverage ends during the duration of the project;
iv) obtain from each other person with whom it
contracts, and provide to the contractor:
(1) a certificate of coverage, prior to the other
person beginning work on the project; and
� (2) a new certificate of coverage showing
extension of coverage, prior to the end of the
coverage period, if the coverage period
shown on the current certificate of coverage
ends during the duration of the project;
�
��1
�L�1
�
'��
',L��'
�I
����,
v) retain all required certificates of coverage on file
for the duration of the project and for one year
thereafter.
vi) notify the City in writing by certified mail or
personal delivery, within ten (10) days after the
person knew or should have known, of any
change that materially affects the provision of I
coverage of any person providing services on the
project; and
vii) contractually require each person with whom it
contracts, to perform as required by paragraphs h-
i) - vii), with the certificates of coverage to be
provided to the person for whom they are
providing services.
4) Posting o4 Required Worker's Compensation Coverage.
a) The contractor shall post a notice on each project site
informing all persons providing seroices on the project
that they are required to be covered, and stating how a
person may verify current coverage and report failure to
provide coverage. This notice does not satisfy other
posting requirements imposed by the Texas Worker's
Compensation Act or other Texas Worker's
Compensation Commission rules. This notice must be
printed with a title in at least 30 point bold type and text
in at least 19-point normal type, and shall be in both
English and Spanish and any other language common
to the worker population. The text for the notices shali
be the following text, without any additional words or
changes:
"REQUIRED WORKER'S COMPENSATION
COVERAGE
�
�
�
�
6/23/99
�
The law requires that each person working
on this site or providing services related to
this construction project must be covered by
worker's compensation insurance. This
includes persons providing, hauling, or
delivering equipment or materials, or
providing labor or transportation or other
service related to the project, regardless of
the identity of their employer or status as an
employee".
Call the Texas Worker's Compensation
Commission at 512-440-3789 to receive
information on the legal requirement for
coverage, to verify whether your employer
has provided the required coverage, or to
report an empioyer's failure to provide
coverage."
K-3 LIABILITY INSURANCE. The Contractor shall procure
and maintain during the term of this Contract such Liabiiity
Insurance as shall protect him, the City of Fort Worth and any
Subcontractor performing work covered by this Contract, From
claims of damage which may arise from operations under this
Contract, including blasting, when blasting is done on, or in
connection with the Work of the Project, whether such operations
be by himself or by any Subcontractor or by anyone directly or
indirectly employed by either of them 2nd the limits of such
insurance shall be not less than the following:
1) Automobile Liability: $1,000,000 each accident, or
reasonably equivalent split limits for bodily injury and
property damage. Coverage shall be on "any auto" including
leased, hired, owned, non-owned and borrowed vehicies
used in connection with this Contract.
2) Commercial General Liability: $1,000,000 each occurrence.
Coverage under the policy shall be as comprehensive as
that provided in a current Insurance Services Office (ISO)
policy form approved for use in Texas and the pciicy shall
have no exciusions by endorsement unless such are
approved by the City.
3) Asbestos Abatement Liability Insurance: When the Project
specifically requires the removal of Asbestos Cortaining
Materials, the Contractor shall be required to maint2in
Asbestos Abatement Liabiiity Insurance as f+�llows:
$1,000,000 per occurrence; $2,000,000 aggregate limit.
The coverage shall include any pollution exposure, including
environmentai impairment liability, associated with the
services and operations performed under this contract in
addition to sudden and accidental contamination or pollution
liability for gradual emissions and clean-up costs.
K-4 BUILDER'S RISK INSURANCE.
Unless stated otherwise in the Proposal or Invi;ation, the
Contractor shall procure, pay for and maintain at all times during
the term of this Contract, Builders Risk Insurance against the
perils of fire, lightning, windstorm, hurricane, hail, riot, explosion,
civic commotion, smoke, aircraft, land vehic!es, vandalism, and
malicious mischief, at a limit equal to 100% of the Contr2ct Sum.
The policy shali include coverage for materials and supplies while
in transit and while being stored on or off site. If specifically
required in the Instructions to Bidders, the policy shall include
coverage for flood and earthquake. Different subiimits for these
coverages must be approved by the City.
Consequential damage due to faulty workmanship and/or design
performed by the Contractor or his agents shall be covered.
Upon completion of the Work, the Contractor shall notify the City
of Fort Worth in writing before terminating this insurance.
K-5 PROOF OF CARRIAGE OF INSURANCE. The
Contractor shall provide a certificate of insurance documeniing
the Transportation and Public Works DepaRment, City of FoR
Worth as a"Certificate Holder", and noting the specific project(s)
covered by the Contractor's insurance as documented on the
certificate of insurance. More than one certificate may be
required of the Contractor depending upon the agents anlor
insurers for the Contractor's insurance coverages specif�ed for
the project(s).
K-6 OTHER INSURANCE RELATED REQUIREMENTS.
GC-16
�
ral
i�l
i�
�
�
fl
�.,
L�J
�
l�l
�
L��
�
L+�J
�
L'J
�
L�J
�1
1) The City of Fort Worth shall be an additional insured, by
endorsement, on all applicabie insurance policies.
2) Applicable insurance policies shall each be endorsed with a
waiver of subrogation in favor of the City of Fort Worth.
3) Insurers of policies maintained by Contractor and its
subcontractor(s), if applicable, shall be authorized to do
business in the State of Texas, or othervvise approved by the
City of Fort Worth, and such shall be acceptable to the City
of Fort Worth insofar as their financial strength and solvency
are concerned. Any company through which the insurance
is placed must have a rating of at least A:VII, as stated in
current edition of A. M. BesYs Key Rating Guide. At the
City's sole discretion, a less favorable rate may be accepted
by the Ciry.
4) Deductible limits on insurance policies and/or self insured
retentions exceeding $10,000 require approval of the City of
Fort Worth as respects this Contract.
5) The City of Fort Worth shall be notified in writing a minimum
of thirty days prior to an insurer's action in the event of
cancellation, non-renewal or material change in coverage
regarding any policy providing insurance coverage required
in this Contract.
6) Full limits of insurance shall be available for claims arising
out of this Contract with the City of Fort Worth.
7) Certificates of insurance shall be provided by the Contractor
to the City prior to commencement of operations pursuant to
this Contract. Any failure on part of the City of Fort Worth to
request such documentation shall not be construed as a
waiver of insurance requirements specified herein.
8) The City of Fort Worth shall be entitled, upon request and
without incurring expense, to review the insurance policies
including endorsements thereto and, at its discretion, to
require proof of payment for policy premiums.
9) The City of Fort Worth shall not be responsible for paying
the cost of insurance coverages required herein.
10) Notice of any actual or potential ciaim and/or litigation that
would affect insurance coverages required herein shall be
provided to the City in a timely manner.
11) "Other insurance" as referenced in any policy of insurance
providing coverages required herein shall not apply to any
insurance policy or program maintained by the City of Fort
Worth.
12) Contractor shall agree to either require its subcontractors to
maintain the same insurance coverages and limits thereof
as specified herein or such coverage on the Contractor's
subcontractors shali be provided by the Contractor.
SECTION L
CHANGES IN THE WORK
L-1 CHANGE ORDER. The Owner, without invalidating the
Contract, may order Changes in the Work within the general
scope of the Contract consisting of additions, deletions or other
revisions, the Contract Sum and the Contract Time being
adjusted accordingly. All Such Changes in the Work shall be
authorized by Change Order, and shall be executed under the
applicable conditions of the Contract Documents.
a
6/23/99
�
A Change Order is a written order to the Contractor signed by the
Contractor, Owner and the Architect, issued after the execution of
the Contract, authorizing a Change in the Work or adjustment in
the Contract Sum or the Contract Time. The Contract Sum and
the Contract Time may be changed only by Change Order.
Any changes in work required due to changed or unforeseen
conditions, or by request of either the Contractor or the City, shall
be coordinated with the Director, Department of Transportation
and Public Works. A change order must be written and duly
negotiated and executed prior to performing changed work.
The cost or credit to the Owner resulting from a Change in the
Fort Worth shali be determined in one or more of the following
ways:
1) by mutual acceptance of a lump sum property itemized,
including the ailowance to Contractor for overhead and profit
stipulated in the original contract proposal;
2) by unit prices stated in the Contract Documents or
subsequently agreed upon; or
3) by cost and a mutually acceptable £xed or percentage fee.
If none of the methods set forth herein above is agreed upon, the
Contractor, provided he receives a Change Order, sha?I promptly
proceed with the Work invotved. The cost of such work shzil then
be determined on the basis of the Contractor's reasonable
expenditures and savings, including a reasonable allowance for
overhead and proflt as indicted in the original contract oroposal.
In such cases, the Contractor shall keep and present, in such
form as the Architect shall prescribe, an itemized accounting
together with appropriate supporting data. Pending final
determination of cost to the Owner, payments on account shall
be made on the Architect's Certificate of Payment as approved
by the Owner. .
If after the contract has been executed, the Architect, requests a
price proposal from the Contractor for a proposed change in
scope of the work, Contractor shall process such proposai within
seven days of receipt and return the price quote to the Architect
in writing. The Architect shall review the price quotation and if
approval is recommended, forward the proposed change order
request and price proposal to the Owner for approval. If the
Architect will attempt to negotiaie with Contractor to revise the
proposal to a figure which is fair and reasonable and forvvard it on
to the Owner for approval. If the negotiations do not resuit in an
equitable solution, the Architect shall prepare a cost-plus type
Change Order with a price-not-to-exceed figure for appreval by
the City and require specific documentation to be provided by
Contractor in accordance with the paragraph above.
Contractor is advised that according to City of Fort Worth
Charter, that when the cumulative effect of Change Orders
results in an increase in cost of the contract amount by over
$3,000, the City Council must approve all such Chang2 Orders
which will exceed this limit. Normal processing time for the City
Staff to obtain City Council approval, once the recommended
change order has been received at the City, is approximately
thirty (30) days . Owner, Architect and Contractor shall endeavor
to identify Change Order items as early in the Construction
process as possibte to minimize their impact on the construetion
schedule.
If unit prices are stated in the Contract Decume�is or
subsequently agreed upon, and if the quantities originally
contemplated are so changed in a proposed Change Or�er that
application of the agreed unit prices to the quantities of Work
proposed will create a hardship on the Owner or the Contractor,
GC-17
�1
C
�
�
�
�
�
�
�
I�L1
ILJ
��J
LJ
�
l� l
�
l�1
�
the applicable unit prices shall be equitabiy adjusted to prevent
such hardship.
If the Contractor claims that additional cost or time is involved
because of (1) any written interpretation issued pursuant to
Section A, (2) any order by the Architect or Owner to stop the
Work pursuant to Section B, where the Contract was not at fault,
or (3) any written order for a minor change in the Work, the
Contractor shall make such claim.
L-2 CLAIMS FOR ADDITIONAL COST OR TIME. If the
Contractor wishes to make a claim for an increase in the Contract
Sum or an extension in the Contract Time, he shall give the
Architect written notice thereof within a reasonabie time after the
occurrence of the event that gave rise to such claim. This notice
shali be given by the Contractor before proceeding to execute the
Work, except in an emergency endangering life or property in
which case the Contractor shall proceed in accordance with
Section J. No such claim shall be valid unless so made. Any
change in the Contract Sum or Contract Time resulting from such
claim, if approved by the Owner, shatl be authorized by Change
Order.
L-3 OVERHEAD ALLOWANCES FOR CHANGES: Should
any change in the work or extra work be ordered, the following
applicable percentage shall be added to Materiai and Labor
costs to cover overhead and profit:
1. Allowance to the Contractor for overhead and profit for extra
work performed by the Contractor's own forces shall not exceed
fifteen percent 1l 5%).
2. Allowance to the Contractor for overhead and profit for extra
work performed by a Subcontractor and supervised by the
Contractor shall not exceed ten percent 10% .
L-4 MINOR CHANGES IN THE WORK. The Architect
shail have authority to order minor changes in the Work not
involving an adjustment in the Contract Sum or an extension of
the Contact Time and not inconsistent with the intent of the
Contract Documents. Such changes may be effected by Field
Order or by other written order. Such changes shall be confirmed
in writing by the Architect and shall be binding on the Owner and
the Contractor.
L-5 FIELD ORDERS. The Architect may issue written
Field Orders which interpret the Contract Documents in
accordance with Section A, or which order minor changes in the
Work in accordance with Section L without change in Contract
Sum or Contract Time. The Contractor shall carry out such Field
Orders promptly.
SECTION M
UNCOVERING AND CORI�ECTION OF WORK
M-1 UNCOVERING OF WORK. If any Work should be
covered contrary to the request of the Owner or Architect, it must
be uncovered for observation and replaced, at the Contractor's
expense.
If any other work has been covered which the Owner or Architect
have not specificalty requested to observe prior to being covered,
the Architect or the Owner may request to see such work and it
shall be uncovered by the Contractor. If such Work be found in
accordance with the Plans and Specifications, the cost of
uncovering and replacement shall, by appropriate Change Order,
be charged to the Owner. If such work be found not in
accordance with the Plans and Specifications, the Contractor
shall pay such costs unless it be found that this condition was
caused by a separate contractor emptoyed by the Owner.
6/23/99
�
GC-18
M-2 CORRECTION OF WORK. The Contractor shall
promptly correct all work rejected by the Owner or Architect as
defective or as failing to conform to the Plans and Specifications
whether observed before or after Substantiai Completion and
whether or not fabricated, installed or completed. The Contractor
shall bear ail costs of correcting such rejected Work, including
the cost of the ArchitecYs additional service thereby made
necessary.
If, within one year after the Date of Substantial Comple;ion or
within such longer period of time as may be prescribed by law or
by the terms of any applicable special guarantee required by the
Contract Documents, any of the work is found to be defective or
not in accordance with the Contract Documents, the Contractor
shall correct it promptly after receipt of a written notice from the
Owner to do so, unless the Owner has previousiy given the
Contractor a written acceptance of such condition, describing
same specifically and not generally. The Owner shall �ive such
notice promptiy after discovery of the condition.
All such defective or non-conforming work under the preceding
paragraphs shall be removed from the site where necessary, and
the work shali be corrected to comply with the Contract
Documents without cost to the Ov�mer.
The Contractor shall bear the cost of making good ali work of
separate contractors destroyed or damaged by such remaval or
correction.
If the Contractor does not remove such defective or non-
conforming work within a reasonabie time fixed by written notice
from the Architect or the Owner, the Owner may remove it and
may store the materials or equipment at the expenss of the
Contractor. If the Contractor does not pay ihe cost of such
removal and storage within ten days thereafter, the Owner may
upon ten additional days' written notice sell such work at s�uction
or at private sale and shall account for the net proceeds t�ereof,
after deducting all the costs that should have been borne by the
Contractor including compensation for additional architectural
services. If such proceeds of sale do not cover all costs that the
Contractor should have borne, the dif�erence shall be charged to
the Contractor and an appropriate Change Order shall bs issued.
If the payments then or thereafter due the Contractor are not
sufficient to cover such amount, the Contractor shali pay the
difference to the Owner.
If the Contractor fails to correct such defective or non-conforming
work, the Owner may correct it in accordance with Section G.
The obligation of the Contractor under this Section shall be in
addition to and not in limitation of any obligations imposed upon
him by special guarantees required by the Contract Documents
or otherwise prescribed by law.
M-3 ACCEPTANCE OF DEFECTIVE OR NON-
CONFORMING WORK. If the Owner prefers to accept defective
or non-conforming work, he may do so instead of requiring its
removal and correction, in which case a Change Order will be
issued to reflect an appropriate reduction in the Contract Sum, or,
if the amount is determined after final payment, it shall be paid by
the Contractor.
SECTION N
TERMINATION OF THE CONTRACT
N-1 TERMINATION BY THE CONTRACTOR. If 2he tivork is
stopped for a period of 30 days under an order or any court or
other public authority having jurisdiction, through no act or fault of
the Contractor or a Subcontractor or their agents or emp!oyees or
any other persons performing any of the work under a contract
with the Contractor, or if the work should be stopped for a period
L�JI
I■�I
L�
�
�
�
l�J
LJ
��1
�
��
L�J
�
LJ
L�1
LJ
L'J
�
of 30 days by the Contractor for the Owner's failure to make
payment thereon as provided in Section I, then the Contractor
may afterthe end of such period of 30 days and upon seven
additional days' written notice to the Owner and the Architect,
terminate the Contract.
N-2 TERMINATION BY THE OWNER. If the contractor is
adjudged as bankrupt, or if he makes a general assignment for
the benefit of his creditors, or if a receiver is appointed on
account of his insolvency, of if the Contractor refuses, except in
cases for which extension of time is provided, to supply enough
properly skilled workmen or proper materials, or if he fails to
make prompt payment to Subcontractors or for materials or labor,
or fails to comply with al Laws, Statutes, Charter, Ordinances,
Regulations or Orders of any public authority having jurisdiction,
or otherwise is guilty of a substantial violation of a provision of the
Contract Documents, then the Owner, on its own initiative or
upon certification by the Architect that sufficient cause exists to
justi�j such action, may, without prejudice to any rights or remedy
and after giving the Contractor and his surety, if any, seven (7)
days' written notice, terminate the employment of the Contractor
and take possession of the site and of all materials, equipment,
tools, construction equipment and machinery thereon owned by
the Contractor and may finish the work by whatever method he
may deem expedient. In such case the Contractor shall not be
entitled to receive any further payment until the Work is finished.
If the costs of finishing the Work, including compensation for the
ArchitecYs additional services., exceed the unpaid balance of the
Contract, the Contractor shall pay the difference to the Owner.
The City'of Fort Worth may terminate this contract in whole, or
from time to time, in part, whenever such termination is in the
best interest of the City. Termination will be effected by
delivering to the Contractor a notice of termination specifying to
what extent performance of the work of the contract is being
terminated and the effective date of termination. After receipt of
termination the contractor shall:
a) Stop work under the Contract on the date and to the extent
specified on the notice of termination.
b) Place no further orders or subcontracts except as may be
necessary for the completion of the work not terminated.
c) Termina;e all orders and subcontracts to the extent that they
relate to the performance of the work terminated by the
notice of termination.
After termination as above, the City will pay the contractor a
proportionate part of the contract price based on the work
completed; provided, however, that the amount of payment on
termination shall not exceed the total contract price as reduced
by the portion thereof allocatable to the work not completed and
further reduced by the amount of payments, if, any otherwise
made. Contractor shall submit its claim for amounts due after
tennination as provided in this paragraph within 30 days after
receipt of such claim. In the event of any dispute or controversy
as to the propriety or aliowability of all or any portion of such
claim under this paragraph, such dispute or controversy shall be
resolved and be decided by the City Council of the City of Fort
Worth, and the decision by the City Council of the City of Fort
WoRh shali be final and binding upon all parties to this contract
SECTION O
SIGNS
The Contractor shall construct and install the project designation
sign as required in the Contract Documents and in strict
accordance with the Specifications for "Project Designation
6/23/99
Signs." This sign shall be a part of this Contract and snall be
included in the Contractor's Base Bid for the Project.
SECTION P
TEMPORARY FACILITIES
P-1 SCOPE. The Contractor shall furnish, erect, and
maintain facilities and perform temporary work required in the
� performance of this Contract, inc�uding those shown and
specified.
P-2 USE OF TEMPORARY FACiLITIES. All temporary
facilities shall be made available for use by all workmen and
subcontractors employed on the project, subject to reasonable
directions by, the Contractor as to their proper and most efficient
utilization. I
P-3 MAINTENANCE AND REMOVAL. 7he Contractor
shal� maintain temporary facilities in a proper, safe operating and
sanitary condition for the duration of the Contract. Upon
completion of the Contract, all such temporary work and facilities
shall be removed from the premises and disposed of unless
otherwise directed or specified hereunder.
P-4 FIELD OFFICES AND SHED. The Contractcr shali
provide a temporary field office building for himse!f, his
subcontractors and use by ihe Architect. For const�uction
contracts with a bid price in excess of 51,OOO,Q00.00, the
Contractor shall provide a separate field o�ce for the City's field
representative (but the separate office may be in the same
structure). The buildings shall afford protection against the
weather, and each office shall have a lockable door, at least one
window, adequate eiectrical outlets and lighting, and a shelf large
enough to accommodate perusai of the project drawings.
Openings shall have suitabie locks. Field o�ces shall be
maintained for the full time during the operation of the work of the
Contract. During cold weather months, the field offices shail be
suitabiy insulated and equipped with a heating device to maintain
70 degree Fahrenheit temperature during the workday. During
warm weather the offices shall be equipped with an air
conditioning device to maintain temperature below 75 degrees F.
Upon completion of the work of the Contract, the Contractor shall
remove the building from the premises. In addition to the drawing
shelf, provide for the City field representatives office: one deck,
four chairs, plan rack and a four drawer filing cabinet (with lock).
Each o�ce shall contain not less than 120 square feet of floor
space.
The Contractor shail provide and maintain storage sheds, other
temporary buildings or trailers on the project site as required for
his use. Location of sheds and trailers shall be as approved by
the Architect. Remove sheds when work is completed, or as
directed.
P-5 TELEPHONE. The Contractor shali provide and pay
for telephone installation and service to the field offices described
above. Service shall be maintained for the duration of operations
under this contract. The Contractor shall provide for and pay for
an automatic telephone-answering device at the site o�ce for the
duration of the project. The contractor shall provide a separate
telephone line, and instrument for use by the City's fieid
representatives.
P-6 TOILET FACILITIES. The Contractor shaii provide
proper, sanitary and adequate toiiet facilities for the use of all
workmen and subcontractors employed on the prq�ect.
P-7 UTILITIES. Contractor shall make a!I necess2ry
arrangements and provide for temporary water and electricity
required during the construction. Contractor shall provic:e and
instail temporary utility meters during the contract construction
GC-19
l!'J
�
�
L�J
'�II
�
��
�'�
��'i
�
LJ
�
�
L
i�
(�
��
L�!J
��i
period. These meters will be read and the Contractor will be billed
on this actual use. The Contractor shall provide all labor and
materials required to tap into the utilities. The Contractor shall
make the connections and extend the service lines to the
construction area for use of all trades. Upon completion of the
work all utility lines shall be removed and repairs made to the
existing lines. Only utilities at existing voltages, pressures,
frequencies, etc. wilt be availabte to the Contractor.
Water. Provide an ample supply of potable water for all purposes
of construction at a point convenient to the project or as shown
on the Drawings. Pipe water from the source of suppiy to all
points where water will be required. Provide sufficient hose to
carry water to every required part of the construction and allow
the use of water facilities to subcontractors engaged on the work.
Provide pumps, tanks and compressors as may be required to
produce required pressures. '
Electric Service. Provide adequate etectric service for power and
lighting to all points where required. Temporary, electric service
shall be of sufficient capacity and characteristics to supply proper
current for various types of construction tools, motors, welding
machines, lights, heating plant, air conditioning system, pumps,
and other work required. Provide sufficient number of electric
outlets so that 50 foot long extension cords will reach all work
requiring light or power.
Li htin . Supply and maintain temporary lighting so that work of
ali trades may be properly and safely performed, in such areas
and at such time that day-lighting is inadequate. Provide at least
0.75 watts of incandescent lighting per squqr4e foot and maintain
a socket voltage of at least 110 volts. Use at least 100 watt
lamps. In any event, the lighting intensity shali not be less than 5
foot candles in the vicinity of work and traffic areas.
P-8 HEATING. Heating devices required under this
paragraph shall not be electric. The Contractor shall provide
heat, ventilation, fuel and services as required to protect all work
and materials and to keep the humidity down to the extent
required to prevent corrosion of any metal and to prevent
dampness or mildew which is potentialiy damaging to materials
and finishes. All such heating, ventilation and services shall be
provided and maintained until final acceptance of all work. In
addition, the Contractor shall provide heat ventilation prior and
during the following work operations as follows:
a) At all times during the placing, setting and curing of concrete
provide sufficient heat to insure the heating of the spaces
involved to not less than 40 F.
b) From the beginning of the application of drywall and during
the setting and curing period, provide sufficient heat to
produce a temperature in the spaces involved of not less
than 55 F.
c) For a period of seven (7) days previous to the placing of
interior finish materials and throughout the placing of finish
painting, decorating and laying of resilient flooring materials,
provide su�cient heat to produce a temperature of not less
than 60 F.
P-9 TEMPORARY CONSTRUCTION. EQUIPMENT AND
PROTECTION
The Contractor shall provide, maintain, and remove upon
completion of the work all temporary rigging, scaffoiding, hoisting
equipment, rubbish chutes, ladders to roof, barricades around
openings, and all other temporary work as required to complete
all work of the Contract. Contractor shall coordinate the use and
furnishing of scaffolds with his sub-contractors.
�
6/23/99
�
GC - 20
The Contractor shall provide, maintain, and remove upon
completion of the work, or sooner, if authorized by the Architect,
all fences, barricades, lights, shoring, pedestrian wal!<ways,
temporary fire escapes, and other protective structures or devices
necessary for the safety of workmen, City empioyees, equipment,
the public and property.
All temporary construction and equipment shall conform to all
reguiations, ordinances, laws and other requirements of the
authorities having jurisdiction, inciuding insurance companies,
with regards to safety precautions, operation and fire hazard.
The Contractor shall provide and maintain pumping facilities,
inciuding power, for keeping the site, all times, whether from
underground seepage, rainfall, drainage of broken lines.
The Contractor shall maintain provision for closing and iocking
the building at such time as possible to do so. If this is not
feasible, maintain a night
The Contractor shail provide and maintain all barricades or
enclosures, required to protect the work in progress from outside
elements, pusts, and other disturbances as a resuit of avork under
this Contract. Such protection shall be posi:ive, shalt meet the
approval of the Architect and shall be maintained for the duration
of the construction period or as required to provida for the
protection es specified.
P-10 PROJECT BULLETIN 80ARD. The Contractor shall
furnish, install and maintain during the life of the preject a
weather-tight bulletin board approximately 3 feet high by 5 feet
wide having not less than two hinged or sliding glass doors with
provisions for locking. The bulletin board shall be mounted where
and as approved by the Architect, in a prominent place
accessible to employees of the Contractor and sub-contractors,
and to applicants for employment. The bulietin board shall remain
the property bf the Contractor and shall be removed by him upon
completion of the Contract work. The following information which
will be furnished by the City to the Contractor, shall be poste� on
the bulletin board and shalt be maintaired by th� Contractor in
easily readable condition at all times for the duration of the
Contract.
a. The Equal Opportunity Poster and Notice
Nondescrimination of Employment (Standard Form 38).
b. Wage Rate Information Poster (Form SQL 155), �vith
the Contract Schedule of minimum �vage rates as
required by the Davis-Bacon Act.
c. Safety Posters.
SECTION Q
VENUE
Should any action arise out of the terms and conditions of this
contract, venue for said action shali lie in Tarrant County, Texas.
�
�
� A
L�J
L"�'JI
L�J
�
l�l
l'!'
��
L�J
�
LJ
L.'!l
l�l
l�
DEFINITIONS PROCEDURES AND
INTERPRETATIONS
GENERAL CONDITIONS
INDEX
A-1 Contract Documents
A-2 Entire Agreement
A-3 Work
A-4 Execution of the Contract Documents
A-5 Familiarity with Proposed Work
A-6 One Unified contract
A-7 Division of Work
A-8 Interpretations
A-9 Copies of Working Drawings and Specifications
A-10 Minority and Women's Business Enterprise Policy
A-11 Correlation and Intent
B IDENTITY OF ARCHITECT
B-1 Contract Administration
B-2 Termination and Suspension of Work
B-3 Duties of Architect
B-4 Architect as Representative of the Owner
B-5 Access to Job Site
B-6 Interpretations
B-7 Authority to Stop Work
B-8 Miscellaneous Duties of Architect
B-9 Termination of Architect
C OWNER
C-1 Identification
C-2 Duties of the Owner .
C-3 Instructions
C-h Access to Job Site
C-5 Progress Inspections
C-6 Authority to Stop Work
C-7 Substantial Completion Inspection
C-8 Right to Audit
D CONTRACTOR
D-1 Identification
D-2 Independent contractor
D-3 Subletting
D-4 Review of contract Documents
D-5 Supervision
D-6 Labor and Materials
D-7 Prevailing Wage Rate
D-8 Warranty
D-9 Taxes
D-10 Licenses, Notices and Fees
D-11 Cash Allowances
D-12 Superintendent
D-13 Responsibility for Employees and Sub-contractors
D-14 Failure to Commence work
D-15 Progress Schedule
D-16 Drawings and Specifications at the Site
D-17 Shop Drawings and Samples
D-18 Site Use
D-19 Safe Work Practices
D-20 Field O�ces and Sheds
D-21 Cutting and Patching of Work
D-22 Cleaning Up
D-23 Communications
a
6/23/99
�
SUBCONTRACTORS
GC-21
E-1 Definition
E-2 Award of Subcontracts
E-3 Terms of Subcontracts
E-4 Minority and Women's Business Entsrprise (M,'Vl•'BE)
E-5 Payments to Sub-Contractors
SEPARATE CONTRACTS
F-1 Owner's Right
F-2 Mutual Responsibility of Contractors
F-3 Cutting and Patching Under Separate Contracts
F-4 Owner's Right to Clean Up
G MISCELLANEOUS PROVISIONS
G-1
G-2
G-3
G-4
G-5
G-6
G-7
G-8
G-9
G-10
G-11
G-12
G-13
G-14
G-15
G-16
G-17
G-18
G-19
G-20
G-21
G-22
G-23
G-24
G-25
G-26
G-27
G-28
G-29
G-30
G-31
G-32
Conflict of Laws
Governing Laws
Personal Liability of Public Officials
Compliance with Laws
Indemnification
Successors and Assigns
Written Notice
Surety Bonds
Owner's Right to Carry Out the Work
Royalties and Patents
Tests
Interruption of Existing Utilities Services
Laying Out Work
Measurements
Existing Overhead or Underground Work
Alignment of Joints in Finish Materials
Integrating Existing Work
Hazardous Material Certification
Location of Equipment and Piping
Overloading
Manufacturer's Instruction
Cleaning Up
Dust Controi
Fire Protection
Cutting and Patching •
Project Closeout
Guarantee and Extended Guarantee
Record Drawings
Construction Fence
Product Deliver, Storage, Handling
Age
Disabiiity
H CONTRACT TIME
H-1 Definitions
H-2 Progress and Completion
H-3 Delays and Extension of Time
H-4 No Damage for Delay
I PAYMENTS AND COMPLETION
1-1
I-2
I-3
I-4
I-5
I-6
I-7
I-8
I-9
Contract Sum
Schedule of Values
Adjustment of Quantities
Progress Payments
Certi£cates for Payment
Payments Withheld
Unresolved Claims
Liquidated Damages
Failure of Payment
L
0
�
�
�
I�
�
�
L�J
L�
L�J
L�J
�J
�
I-10
J
J-1
J-2
J-3
J-4
K
K-1
K-2
K-3
K-4
K-5
K-6
L
L-1
L-2
l-3
L-4
L-5
M
M-1
M-2
M-3
N
N-1
N-2
O
P
P-1
P-2
P-3
P-4
P-5
P-6
P-7
P-8
P-9
P-10
Q
Q
�
0
Q
6/23l99
�
Substantial Completion and Final Payment
PROTECTION OF PERSONS AND PROPERTY
Safety Precautions and Programs
Safety of Persons and Property
Hard Nats
Emergencies
INSURANCE
Insurance Required
Workers' Compensation Insurance
Liability Insurance
Builders Risk Insurance
Proof of Insurance
Other Insurance Related Requirements
CHANGES IN THE WORK
Change Order
Claims for Additional Cost or Time
Overhead Allowance for Changes
Minor Changes in the Work
Field Orders
UNCOVERING AND CORRECTION OF WORK
Uncovering of Work
Correction of Work
Acceptance of Defective or Non-Conforming Work
TERMINATION OF THE CONTRACT
Termination by the Contractor
Termination by the Owner
S1GNS
TEMPORARY FACILITIES
Scope
Use of Temporary Facilities
Maintenance and Removal
Fieid Offices and Sheds
Telephone
Toilet Facilities
Utilities
Heating
Temporary Construction, Equipment and Protection
Project Bulletin Board
VENUE
00000
GC-22
C
���
�
l�'J
L"J
l�
L*'J
�
�
L��
L�l
�
l#J
��I
J
l�'
L'�J��
�i
f
Revisions
10/6/98 Flood and Earthquake not required in Builder's Risk
unless required by Notice to Bidders
6!4/99 Minor editing
6/23/99 Major revison of K-2, Workers Comp Insurance
� 6/23/99 GC - 23
�
a
0
�
�
�
�
D
�
a
�
�
Q
I�
�
�
�
�
�
�
WEATHER TABLE
Month Average Inches of Snow/Ice
Days of Rainfall Pellets
Rain
January 7 1.80 1
February 7 2.36 *
March 7 2.54 *
April 8 4.30 0
May 8 4.47 0
June 6 3.05 0
July 5 1.84 0
August 5 2.26 0
September 7 3.15 0
October 5 2.68 0
November 6 2.03 "
December 6 1.82 *
ANNUALLY I 77 ( 32.30 I 1 � I
(1) Mean number of days rainfall, 0.01" or more
(2) Average normal precipitation, in inches .
(3) Mean number of days 1.0 inch or more
` Less than 0.5 inches
This table is based on information reported from Dallas-Fort Worth Regional Airport, Texas. Latitude 32
deg 54 min north, longitude 97 deg 02 min West, elevation, (ground) 551 ft.
Average number of days of rain, snow, and ice are based on records covering 27 years. Precipitation is
based on record of 1941-1970 period.
This table is to be used as a basis for calculation of excess rain or weather days for projects with duration
in calendar days. If the site records indicate that the Contractor was unable to carry out operations due to
weather, it is counted as a weather day. If the number of weather days exceeds the number of average
rain days plus the snow/ice-pellet days for a given month, the contract period will be adjusted by Change
Order.
WT - 1
� City of Fort Worth
�
�
CLASSIFICATION
lJ
lJ
L�J
�
L'!J
�
L!'J
��I
L!'J
l�J
�
1994
BUILDING & CONSTRUCTION TRADES
STANDARD WAGE RATES
FOR TARRANT COUNTY
HOURLY RATE
BUILDING TRADES
AIR CONDITIONER MECHANIC
AIR CONDITIONER MECHANIC HELPER
BRICKLAYER/STONE MASON
BRICKLAYER/STONE MASON HELPER
CARPENTER
CARPENTER HELPER
CONCRETE FINISHER
CONCRETE FINISHER HELPER
CONCRETE FORM BUILDER
CONCRETE FORM BUILDER HELPER
DRYWALL INSTALLER
DRYWALL INSTALLER HELPER
DRYWALL TAPER
ELECTRICIAN (JOURNEY)
ELECTRICIAN HELPER
ELECTRONIC TECHNICIAN
FLOOR LAYER (RESILIENT)
FLOOR LAYER (CARPET)
FLOOR LAYER HELPER
GLAZIER 12.10
GLAZIER HELPER
INSULATOR
INSULATOR HELPER
LATHER 15.83
METAL BUILDING ASSEMBLER
METAL BUILDING ASSEMBLER HELPER
PAINTER 10.20
PAINTER HELPER
PLASTERER
PLASTERER HELPER
PLUMBER/ PIPE FITTER
PLUMBER/ PIPE FITTER HELPER
REINFORCING STEEL SETTER
REINFORCING STEEL SETTER HELPER
ROOFER
ROOFER HELPER
SHEET METAL WORKER
SHEET METAL WORKER HELPER
SPRINK�ER SYSTEM INSTALLER
STEEL WORKER STRUCTURAL
STEEL WORKER STRUCTURAL HELPER
LABORER SKILLED
LABORER COMMON
EQUIPMENT OPERATORS
� CRANE, CLAMSHELL, BACK HOE
DERRICK, DRAG LINE, SHOVEL
FORKLIFT
FOUNDATION DRILL OPERATOR
{"j FRONT END LOADER
� r TRUCK DRIVER
WELDER
WELDER HELPER
D
�
13.86
6.64
13.56
8.29
10.68
8.52
11.51
8.38
10.36
7.58
11.93
7.55
10.29
13.�0
8.22
8.75
13.17
13.17
6.44
7.26
10.83
8.70
9.06
7.22
6.52
15.48
9.00
12.18
8.57
9.77
6.98
10.49
7.95
10.47
7.34
9.72
13.24
8.40
7.65
6.47
7 0.20
10.20
9.27
10.53
9.89
8 06
11.83
8.59
WR- 1
� 07/06/99
a
�
�
�
D
�
�
a
�
�
�
�
�
a
0
�
�
a
�
WILL ROGERS AUDITORIUM
TECHNICAL SPECIFICATIONS
Division 1- Summary of Work
01010 Summary of Work
Division 2 — Surface Preparation
02060 Surface Preparation
Division 9 — Finishes
09200 Plaster
09900 Painting and Finishing
Report on Will Rogers Auditorium Paint Peeling Evaluation
e
Page
01010-1,2
02060-1,2
09200-1,2,3
09900-1,2,3
1-17
�
�
LJ
��
lJ
�
�
U
�
[��
I�J
�
LiJ
I�)
�
�
L"�J
u
��
L�J
01010 — SUMMARY OF WORK
SECTIQN 01010
01 PROJECT DESCRIPTION
A. The project consists of ail work to be executed as herein described
and as shown on the drawings entitled "Renovation to Wifl Rogers
Auditorium, Fort Worth, Texas", prepared by the City of Fort Worth,
dated June 1999.
B. The Base Bid work consists of renovation and restoration work in
the proscenium and front section of the auditorium to eliminate
deteriorating conditions including plaster and paint.
C. The existing building generally consist� of the Auditorium and
Balcony containing approximately 2,964 fixed seats, lobby, foyer,
stairwells and restrooms.
D. The construction generally consists of �elective paint and plaster
removal, plaster repair and resurfacing and painting as indicated on
the drawings. No acoustical ceiling tile or acoustical wall tile is
included in this scope of work.
E. Trial test area (8'x8') for plaster removal, plaster repair and paint
application to be approved by architect prior to work. (Paint
application may applied at a later date after plaster work has been
approved.)
F. Alternates shall be as follows:
Alternate No. 1: First floor level removal of paint layers,
plaster repair as required, paint one base coat, paint firvo
additional coats;
Auditorium side aisles including soffits, auditorium rear wall,
entry foyer, corridor #131, Stairs #11 &13 including ceiling.
All areas to include ceiling and/or soffits as required.
Underside of Balcony (ceiling at first level) and Balcony face.
01010 -1
lR�
t�i
�
LJ
2. Aiternate No. 2: Second floor level removai of paint
layers, plaster repair as required, paint one base coat, paint
two additional coats;
Balcony and landings, Restrooms: Men #301 & Women
#308. All areas to include ceiling and/or soffits.
Mezzanine and landings, Corridor #209, Restroom: #204 &
Lounge #120. All areas to include ceiling and/or soffits.
a
3. Alternate No.3: Tower Lobby & Hall removal of paint
� ' layers, praster repair as required, paint one base coat, paint
two additonal coats;
["� Tower Lobby, Hall and ceiling #
1,.J
02 CONTRACTOR USE OF PREMISES
�
�
L�J
l!J
L■.�
Isl
LJ
l�!
�
l�J
�
A. Special Considerations:
1. All operations in the interior of the facility will be coordinated
with the owner and cease as required by facility schedule.
� 2. $ase-pr•e}eet�r ^� �� ��contractor will have control of
facility without interruption for 42 days at a mutually agreed
upon start date.
�-.,� ��� R��ir�g-plas#�er�ael+tsr�rdust control and positive ventilation
shall be provided by the contractor.
4. Clean up and protection- Provide barriers, protective covers
and positive ventilation to ensure that no part of the
renovation is damaging to existing furnishings and finishes
during the construction period.
END OF SECTION
D01010 -2
�
�
�
�
L�
L�J
�
'�J
�
�!
l!J
�
LJ
�
LJ
L�J
�
L�J
SECTION 02060
Q2060 — SURFACE PREPARATION
01 SCOPE
02
A. Remove all paint layers and "yellow" piaster. The "yeilow" plaster
layer shall be totally removed to expose strong plaster base.
B. Remove deteriorated materials, plaster, lath, channels, etc. as far
back as necessary to reach firm areas. Clean existing lath and
plaster of all dust, dirt, powder residue, oil or other cor�taminants.
Rework metal lath as required. Dampen open areas and patch with
plaster or other approved patching compound. Sand areas to
match and blend with existing surfaces.
C. Care shall be taken to protect existing features from damage by
any tool, equipment or material. Repair will be at contractors
expense.
D. Contractor to review "Report of Will Rogers Auditorium Paint
Peeling Evaluation". Recommendations are shown on Page 15.
(Attached}
QUALITY STANDARDS
A.
B.
C.
Provide experienced, well-trained workers competent to complete
the work as specified.
03
All work shall comply with governing building and safety codes,
including personal safety.
Examine and verify that job conditions are satisfactory for speedy
and acceptable work.
PROTECTIVE BARRIERS AND COVERS
A. Provide demolition materials, barriers, protective covers to fixed
seats and carpet to complete the work as specified to ensure that
no part of the renovation is damaging to existing finishes and
equipment during the construction period.
B. Environmental Controls: Use water sprinkling, temporary
enclosures, and other methods to limit dust and dirt migration.
� 02060 -1
�
�
�
�
L�
�
�
�
�
�
l�,
�
L�J
�
�•J
l�J
L�J
�
�
�
Q4 DAMAGES
A. Promptly repair damages caused to adjacent facilities by demolition
work.
END OF SECTION
02060 -2
�
�
IJ
92200 — PLASTER
01 GENERAL
SECTION 92200
� Furnish all labor, materials, equipment, and services for a complete
installation of all plaster work, as shown on the drawings and as
� hereinafter specified, but not limited to the following:
� A. Plaster repair for proscenium, soffits, ceilings and walls as shown
on the drawings.
� B. Metallath.
C. All accessories implied or required.
�
��
�
��
�
�
L�J
lJ
��
�
�
�
�J
Q2 MATERIALS
A.
B.
C.
Plaster- Color and texture to match existing.
Portland cement, white cement, gypsum plaster, coloring materials
and lime shall be National Gypsum, U.S. gypsum Co. or Georgia
Pacific. Package materials shall be delivered in original containers,
unopened and bearing manufacturer's name and brand.
Water shall be drinkable from existing source at no cost.
D. Sand shall be clean, free from deleterious matter, and shall be
screened and well graded from fine to coarse to produce a smooth
working mix.
E
F.
Metal lath- Install lathing and furring materials indicated for gypsum
plaster to comply with ASTM C 841.
Metal trim- including but not limited to corner beads and grounds,
casing beads edge molds, etc. shall be galvanized.
03 INSTALLATION
A. Metal Lath and Trim
Furring, lath, and suspension; Install in accordance with the best
recommendations of the manufacturer. This practice shall also be
followed with all corner beads, corner lath, expansion joints, end
joints and casings.
09200 -1
�
�
�1
l�J
�
��
��
lwl
�
l�.l
��
���
L
��
L�
��
�
�
�
L'�
B. Plaster
1. Prior to beginning work all grounds shall be checked and
' inaccuracies shall be corrected.
2. Cutting and Patching: Cut, patch, point up, and repair
plaster as necessary to accommodate other work and to
restore cracks, dents, and imperFections. Repair or replace
work to eliminate blisters, buckles, excessive crazing and
check cracking, dry outs, efflorescence, sweat outs,. and
similar defects and where bond to substrate has faifed.
3. No work shall be applied unless the temperature is at least
50 degrees F. All work shall be kept damp in hot dry
weather for 24 hours after application.
4. Utilize plastic barriers to contain dust. Exhaus� ventilation to
be provided by contractor.
5. Plaster Base Coat Compositions: Comply with ASTM C8�2
and manufacturers directions for gypsum base coat
proportions that correspond to application methods and
plaster bases indicated below:
5.1 Three-coat work over metal lath:
5.1.1 Scratch Coat: 1 part gypsum plaster with not
less than 2 parts job-mixed sand.
5.1.2 Brown Coat: 1 part gypsum plaster with not
less than 3 parts job-mixed sand.
5.1.3 Finish coat: Gypsum Plaster: 1 part gypsum
plaster and 2 parts sand. Or, Gypsum Ready-Mixed
Finish Plaster: Mixed in accordance with
manufacturer's printed instructions.
.�
7
Lath shall be applied and well nailed or wired securely in
place.
The first coat shall be applied with a sufficient force to form
good keys on lath.
8. When the mortar of the first coat has become firm, but not
dry, the surface shall be scratched to form a rough bond for
the next coat.
09200 -2
�
�
l�l
lJ
���
9. The brown coat shall be brought to true uniform plane with a
straight edge of floating rule to within 3/8" to 1/2" of finished
surface and left rough to receive the finishing coat.
10. The Contractor shall be responsible for determining the most
effective procedure for curing and time lapse between
application of coats based on climatic and job conditions.
Plaster which has cracked or crazed due to improper timing
and curing will not be accepted. Remove and replace
defective plaster including plaster base materials, if
damaged during removal of defective plaster.
� 11. Cure time for plaster application to be 3 weeks prior to
painting. Test for condensation 2 weeks after completion by
placing an 18"x18" clear piece of poly film; duct tape a11
,� edges. Leave in place for 2-3 days. If condensation forms,
wait to apply paint.
I,�
C.
WORKMANSHIP
�J
�
L��
CJ
�
[�
�
�
�
�
I_!1
�
Lathing and stucco shall be done by skilled workmen und�r
the direction of a competent foreman.
CLEANING AND PROTECTION
1. Provide temporary covering and whatever other provision is
needed to minimize spattering of plaster on adjacent
finishes, seating or carpet. Contractor will be responsible for
cleaning of all seats and carpet to the satisfaction of the
manager. Promptly remove plaster from other surfaces.
When plastering work is completed, remove unused
materials, containers, equipment and plaster debris.
2. Ventilation: Ventilate building spaces as required to remove
water in excess of that required for hydration of plaster.
Begin ventilation immediately after plaster is applied and
continue until it sets.
3. Finish plaster must be complete prior to paint start.
END OF SECTION
�j 0920Q.-3
11
L�J
CJ
L1
�!.I
I�
L�
�
l�
�
LJ
,�
�
C�J
LJ
��
L*;
I �J
�
SECTION Q9900
09900 — PAINTING AND FINISHING
01
SCOPE
A. Furnish all materials, labor, equipment, and services necessary for
the surface preparation, complete painting and finishing as shown
on the drawings and specified herein.
B. Items included, but not limited to are interior walls, ceilings, soffits,
and fascias. Paint exposed plaster surFaces whether or not
designated on drawing, except where a surFace or material is
specifically indicated not to be painted or is to remain natural.
Where an item or surface is not specifically mentioned, paint the
same color as existing. �
C. The painting contractor shall examine the specifications for the
various other trades and shall thoroughly familiarize himself with all
provisions regarding their painting.
D. Plaster application to cure a minimum of 3 weeks prior to painting.
Test for condensation 2 weeks after completion by placing an
18"x18" clear piece of poly film; duct tape all edges. Leave in place
for 2-3 days. If condensation forms, wait to apply paint.
E. Items not to be painted include the following:
1. Acoustic tile wall and ceiling in Auditorium.
2. Vitreous tile trim on �ertical surFaces at auditorium ceiling.
3. Auditorium ceiling plaster, except at proscenium.
4. Exposed brick masonry, stone and marble.
5. Finish hardware, except hardware with existing painted
finish. .
5. All glass, light fixtures, metal trim, etc.
6. Doors, frames, handrails and wood trim.
02
03
SUBMITTALS
A. Color samples to match existing must be submitted to Architect for
approval prior to application.
QUALITY ASSURANCE
A. Single Source Responsibility: Provide primers and undercoat paint
produced by the same manufacturer as the finish coats.
� 09900 - 1
�
L1
L*i
Ifl
�
�,
�
�
04 PRODUCTS
A. Paint for plaster surfaces to be as follows, or equal with approval by
Architect:
Primer: Jones-Blair- #975 Multi-Purpose 100% Acrylic-1 coat,
apply at 3 mil wet or 1.5 mil dry.
Finish Coat: Jones-Blair- Wash & Wear Semi-Gloss Acrylic
Enamel- 2 coats at 3 mil wet, 1.5 mil dry per coat.
05 EXECUTION
A. Examine substrates and conditions under which painting will be
� performed for compliance with requirements for application of paint.
Do not begin paint application until unsatisfactory conditions have
been corrected. �
�
�
B. Contractor shall be responsible for verifying that the plaster
surfaces are sufficiently cured before the start of any paint
application.
C. Prior to the beginning of any work verify with the paint
� manufacturers' representative that the PH level and moisture
content of the plaster is in tolerance with the manufacturers
� recommended levels.
����
��J
r,�
u
LJ
L!�
�
05 PREPARATION
A. General Procedures: Remove hardware and hardware
accessories, plates, machined surfaces, lighting fixtures, and
similar items in place that are not to be painted, or provide surface-
applied protection prior to surface preparation and painting.
Remove these items if necessary for complete painting of the items
and adjacent surfaces. Following completion of painting operations
in each space or area, have items reinstalled by workers skilled in
the trades involved. ,
� 09900 - 2
IL�
� B. Lost, broken or damaged �xtures shall be replaced in kind by the
contractor. The architect shall approve any substitutions prior to
installation.
�
LI
�
l�
L�
�
C�!
�
ls!
�
��
I�J
�
�
�
L�
�:
07
B. Clean surface before applying paint or surface treatments.
Remove oil and grease prior to cleaning. Schedule cleaning and
painting so that dust and other contaminants from the cleaning
process will not fall on wet, newly painted surFace.
C. Plaster: Remove efflorescence, chalk, dust, dirt, grease, oils and
release agents. Roughen as required to remove glaze.
D. Minimum Coating Thickness: Apply materials at not less than the
manufacturer's recommended spreading rate. Provide a total dry
film thickness of 1.5 mil per coat as recommended by the
manufacturer.
CLEANING
A. Cleanup: At the end of each work day, remove empty cans, rags,
rubbish, and other discarded paint materials from the site.
B. Upon completion of painting, clean glass and paint-spattered
surfaces. Remove spattered paint by washing and scraping, using
care not to scratch or damage adjacent finished surFaces.
PROTECTION
A. Protect existing surfaces, fixed seating and carpet against damage
by painting. Correct damage by cleaning, repairing or replacing
and repainting as acceptable to Architect.
.
.
C
Provide "WET PAINT" signs to protect newly painted finishes.
At completion of construction activities, touch up and restore
damaged or defaced painted surFaces.
END OF SECTION
� 09900 - 3
�
1�
�.
�
�
�
�
�
�
L�J
�
L!
,�
�
�
�
��
lJ
�
02l16/S9 07:�0 2142410619
CFP� LABORATORY INC.
R�port on
�1! Rogers Auditorium Paint Peeling Evaluation
Wayne Britton
CPM Laboratory
Febtuary 2, 1997
PAGE 02
GPM LoDorttory, 12e0t Ste�tx�son� Ft+veWtay. S�it� a29, Fatmen 8ranch. TX 7502;i 9T2-?ri1-0374 Pa9. 1
�
L�J
�iJ
�
lR�
�
L■J
�
�
�
�
�
�
�L�
�
l�4
��l
L� I
e2/16/s5 �?:5� 21a2a1e619
� • • ti�:I n r ar i t•,
CFP� LABORATO�Y INC.
A general survey of the auditorium vras conducted to document locations where
paint faliures were oawrring, 8nd �o provide ath�r data which might be useful for
understanding this paiM pee) proWem. A floor plan af the faciEity i� appet�ded
and a summary of the data ftom � aurvey is provided in Table 1 below. The
tabla lists the locations evaluabed in the ordar which tt�y were examined starting
with the main entry� moving east up the stairs to the balcony, and then to the
west and finaly finishing on the rrtain floor.
The main entry to the auditorlism h�a� a!at of glass surface witfi a ticket room on
each side and relativeiy lirnited p�inted areas. The painted areas and doors ail
show good paint adhesion. 1IYth two exceptlons, the balc�y appears to be fr�ee
of paint failures. Much of the area is s�coustic bfe which does not seem to have
any pairrt failurea. One waN of the batcorty on tfie west side t�ad an obvious
water problem whic� we have di�ed previously in the lnitia! tour of the
facility. This area was rrot i�vestifgated furtfier.
The hallway behind the bak�ny had sed;ons which vrere sheetrodc and no
faUures were observed on this suFfaoe. Genetally the hallw�y was free of paint
failures until one moved toward the ataiMrelts at either end where the failures
began to st�aw up. ' .
The men's room on the aecond floor had a number pai�t failures but it is likely
that some of these are due to physic��l abrasion of the surfaEces.
Moving uq the west stairrvetl tttere are failures cbse to the bridc but faitures are
infrequent as you move away from the bridc on the upper s�ction of the walls.
1n the coat room on the eaat �ide tt�ete was a paint problem on a heat rogi3ter,
but this appears to be a unique situation--there is no plaster and the temperature
conditions on the regiater are �Icey to be different from the other problem areas.
In summary, the fai{ures are absExv4et� to oxur on outsicle walis, ceilings, and
interior walls, Many of the faiiure� appear in the stairvvell regions, on the main
levet east a�d west wai�� and on the vent cover on the ceiling in front of th�
stage. The frortt af the balcony faar� the sta�e had some failures and a several
problems existed on bath sides c� the wall behind tt�e tast row of c�airs an the
main floor. Sec;tiQna of the c�ili�lg atong the east and west islea of the main floor
alao have some problems. a�s we� � the east and west regions near the outside
doars on the main floor opposne t4�e stage.
Areas with few fa�ures indude ttte entry. af! the acoustie tih and sheetrocic
surtaces, and ths hallway behind the ny an the second floor. Wrth the
CPM Laborotory, 12aGt SMmmorw Froew�r. SaNe 429, F�m�sn &anah. TX 75023 974�41-8374 Pap.
PAGE 03
�
�
a
U
LJ
�
U
�
�
�
f
�
�
,�
I
�
�
�
�
�'
02/16/89 �7:50 2142410619
CPM LABORATORY INC.
exception of the acous�c tiie, these areas represent a relativety smatl percentage
of the painted area.
r�bie �
Summary of Palnt Cottditio� Throughout AudiLurium
L�ti�n s�1�tC �
Entry red/brown good
Entry � da�ic gray good
Entry light gray good
Entry doors red brown good
East Ticket Raom light gray good
East Ticket Roam- gray failure of paint
-heater vent
East balcony Stair dark gray > 4 failures
East balcony red/brown failurea
landing ceiling
men's room gray several failures
balcany east wali good
wood handrait
mount
projection room biadc, few 1a��er� few failu�s, ge�erally OK
balcony ceiling datk gray one failure �ear a vent
east balcony wali light gray failu�e, eftlorescence, water
west balcony failures
landing .
west balcony gray OK
handrait mount �
west balcony fallures
landing
west balcony failures
south wall
west baic�ny failures
c:eiling
acoustic tile in OK
balcony
west stairv+►ay redlblueigraylbtadc faifure
west stairvvay gray faiture
ceiling
west staitway �ed and b{ue failure
ceiling
CPM l.aborslcry, 12�1 Slernnw�a Froeway, SuNe 828. Famien Br�, TX 75023 972-241-0374 RaQe 3
PAGE 04
� 02/16/89 0�:5� 2142410619
■ ��
lJ
La�a�a
haliway behind
balcony, ceiling
hallway behind
balcony, wall
hallway behind
balcony near
stairs
down stalrweli
near brick an
outer and inne�
wa11
Main floor. inner
loge, walls and
ceilinga
west wing at end
of lower loge
east wa11 on main
floar--mostfy
abave ground
lavel
ceiiing over vent
above and away
from stage
column ceiling
near east wall
facia along
bal�ot�y
west outside wal!
an main floor
west outside wal{
on main floor
atairway on wsst
wall
CPM LABORATORY INC.
�L �si!!
gray, darfc aray, OK
red/brown. k�lue
light gray wailboard 4K
�
�
�
�
�
Li�J
�
r
�
�
L*�J
LJ
'�
�
�
above atairs on
inside wall of weat
stairway near
stage
ceiling above
columns near
west wall
effluorescance at ceiiing wafl
junction
effiuorescence on wall
effluarescence, water
dawnspout diredty opposite
stairway
water problems, effluorescenoe,
flat roof above, drains appear to
run onto roof
failures except fior last �ction
near erttry—this seGtion has a
roof above, othe�s do not
FAGE 05
CF'M l.aborRWry.12801 S�er�xT�Ons Freevray. SuIN 02A. Fi1m'lOrs BranCh, TX 75Q2J 97%241-8374 PaQe 4
�'��
failure
ail cobrs failure
I'�ght gray aome water btiaters, fallurea
failures all a{or�g ceiling, worse
toward stage, ceiling worse
#han walls
gray failures mo8tly to th� left sjde
faang stage
no failures
failurea
I
�
�
[1J
�
l�!
,��
L�J
�
L�I
�
L�l
L�1
�
�
L�l
L■
�
�
LJ
�
02/16/S9 07:50 214241�619
� � • � • :r. ri . ,r • .-.: . •r , c.�•a
CPM LABORATORY INC.
Eight pairs of palnt sampfes were scc�uired throughout the auditorium providing
representative sxamples of faiiurea and a corresponding good referenc� paint
sample for eaCh failure. In addition to the sample pairs, a fiew other examples of
paints failures were acqui�ed. A fx,�ure representi�g thc auditorium floorplan ia
appended which indudes the approxinra�e location of the sight samples:
The reference aampi�s wero acquired olose to the region where the faibd paint
samples were acquired, having the sarne orie�rtation (celling ve wa11}, proximity�
and paint colar as the samples. Tt�e goa! for selecctirig the samptes was ta
provide a representation of tt� types of paint tailures, 'rf indeed� more than one
failur� mechanism is operative. Samples were acquired from waEis and ceilings,
and from the west walt which had been reptastered and repair�ted in the (ast
renovatbn in 1980 or 1991. Sampfes and references were acquired by dritling
out i inch diameter oores of pa'tttt �td plaster.
�ach of the eight samples and re�erences were examined by Infrared
spectroscapy and by mkroscopy. Cros� sec�ar�s of the eight samples and
corresponding references werc mounted, polished, and examined
microscopically. Table II below provides a summary of the visual obaervations
made of tF�e sa�les which were acquit�ed. Some of the observations were
made under the m'�a�oscope and others witfi the una'tded eye.
Infrared spectrosoopy ptovides a pioture af the chemistry o# the samples. It is
particulariy useful for or�anic materials, but many inorganic arHons may be
identified with this technique. Infrared spectcoscopY is not �{e to identify the
metals which are present in sample�. ft was iMended at the onset to evafuate
the paint samples which were direetfy irnrohred in the peeling or fa�ure, however,
in nearly every case, a thin yeMow tayer on the top of the piastar latyer seemed to
be invohred in the failures. Tttie focus of tho investi�ation v�ras thenefore directed
at this yellow material to get an understanding of its chemistry ir� oMer to b�ter
understand the fadures. The pla� for the eght reference and sample sections
was analyzed by lnirared sped�osco�ty and aH were %u�d to be mixturea of
carbanate and auifate with differeM �atios of each. A comparison of the ra�o of
the carbonate peak size to the su�ia�e peak s"izs for the sampies and references
indicated no dN'fenence �r the two groups. f�frared spe�tra for the sample
reference p�astera are appended.
Microscopic examinatioEi of the samples i�volved recording the colors of the
layers af painVplaster whic;h appeared to be irnolved in f1�e failuro. In some
cases the colora of all of the paiM� which were bonded to the Rlasfier were
documented. A summary of this it�formatiort is provided in Table 11 bebw, Many
layers of paint were found on mo�t of the samples and refer+enoea and at least 8
CP1V1 Laboratory, 12�p1 SterlxnOM FteeWay. Suite 829, Famists Br�nth. �( 75029 972�41-a374 Paps $
PaGE 06
�
u
I�
'�
�
L�J
�
[�
LJ
UJ
�
�
�
�
�
l�'
I�I
LJ
��
02/16/89 07:50 214241�619
CPM LABORATORY INC.
layers were counted on one sample. The total paint thickness is estimated to be
about 20 mils on the thicker rt�uttiple pairit sampies.
The paint and plaster layers were probed while observing the sampie under the
microscape. VYhile thia is not a c�uarrt;tative technique, one can qualitatively
assoss the force necessary to scratch. move, or deform the coating layers while
observing the behavior of the ma�erial. �
r� ri • a • •.i+ •„•. ' I�� at=1l•:a•:r. �j
The laboratory identfication number and Iocations for the eight samples and
corresponding referonces are given m the table belaw and are depicted on tt�e
appended floor plan. A notatan on the paint color starting with the white plaster
layer is provided unci�er the comment heading of. the tabie.
. . : ts:; �; � . . � . : 1� . :
P�Int Samntea
K888 Center rear of
auditorium--No. 1
K887-Reference for
No. 1
K888 West wafl near
stair well-
efHuorescence-No. 2
K889 Reference €or
No. 2 effluorescence
K880 Reference ior
No. 2
K891 West wall ceiling
Na. 3
K892 Ref for No. 3
K893 lnner west wall
top of stairs No 4
K894 Reference for
No. 4
K895 fnner east waN
opposite door No. 5
K696 Refierence for
No. 5
�
white� yefJo�x� silver(aluminum), yelbw and silver
layers disbo�xling; yellow and vrhi�e plaster
diabonding
white, yellow, silver (Aluminum) �
gray on white only--paint puUs white away
gray on white substrate
white 9ray onfy-�raY pulls white away which may
be a primer-s�uita smaoth
white, yel.red,large chip with srnooth plaster
failune. Sorr�e yellow on plaster but mos�y
ptastier f�iluro
white. Yt�l, red� Ye�, aqua (Ya� aqua failure?�
Aqua layer tough, upper yel tough, some red
tayer expa�d and possibly failuro
gray on white--some paint faifure--chariry within
pairn layer. Some pai�t plaster bond failure
gray on wh�e only. Pairtt well bonded to wfiite
white, yel� red
white, yet, r�d
PAGE 07
CPM Laboratory, 12801 St.rtx�w�s Ft�eway. SuM BZg. F�m�eti BtancA, TX 780Q� 972-241-8374 P�ge 6
I�J
02/16/89 07:50
D �. �
��
�r',
�J
���
l�J
�
LiJ
L!1
L�l
�
u
L!J
L�J
L�J
�
�
�
��
2142410619
pe�nr s��r�
K897 East isle oeliing
between pillar 2 and 3
No. 6
K898 Ref for No. 6
K898 Top of east
stairs No. 7
K9U0 Reference for
No. 7
K901 Top east sta�r
ceiling No. 8
K902 Rei�re�ce for
No. 8
Ceiling ea�t iab, K9�3
K904 Tape Sample
K905 Coat room
sarnpl�
K9Q6
KS18
CPM LABORATORY INC.
�
white, y�l, aluminum
wh;te, y�, �luminum
whit�, yel, a�uminum
w�,ite, yei, a�uminum
yel r�d
�
w#tfite, yel, s�ver
ye�. red, broMm� Yel� rad, bro�m, �ue, red
yel, I� r�, �c red, ft bh1e, d!c blu�e� yei� wfitlte, $raY
whit�, It bf�e, yel, gray Failure of pta�ater. Piaster
�Y �
3ampRe kari .�adc Ourtiam-dk bk�e, � t�t,e� Yel,
�ray, cx� at yel blue ir�sfa�aa, n�tfY plastec
fa�ure, sa�bs ate a!I v�rt�te on the badc.
PAGE 08
The first paint sam�e vvas aoqui�ed fran the ma}n f{oor o� the auditotium behind
the last row o� seats. Th� lonatiq�n i� on an i�t�rior w�aq free af etfeats found on
wa91s adjacer�t to thQ bu�ding exk►�ior (effec�s euch a� pressuPe, moisture, and
temperaturo due to �xposure). The falied and retererwa pednia samples have a
yeibw layer on top o# t�e wh� p�aber which ia folto+�red by a� aihrer metallic
tayei. i'he pairtt and plaa�ar aea�t� � eas�y pull a�vay ftnm the a�lver tayer. A
sample of the ai�ver pa�nt waa t�at�d with a sodium hydroocide sot�ion and it
reacted vi9flfousiY evoivi�9 g�• This �S c�on�lsterzt with aiurrtinum metal, and it is
concluded this me�c tayer �a �nam paint Aluminum paint is sometimes
uaed to hide odora ihom srtwke a� a flro, but it �a not known if �ia ia the rcaaon
why this coating was u�eci here. Tiie pt� �nd the yelle�w layar vrero fourx! to
cons�t mainly of ctttbo�a�e a�nd su�te. The yetbw tay+er al�o cantains an
cxganic c�mpot�et�E--see bebw.
The second sample wras aoqudne�d it�irr� the wast waN near the a�ell in lir�e
with the stage. The west waiN is �que wi� t8spec# to tha rest af tfie building.
The plaat�� on this wa1! w�as r+ep�sd dwir�g the last rer►ov�ation, and therefore
this section does nat have the m�i� layera of pair�t, nor does it have the nearfy
ubiquitous y�Now paintlpls�t� t�per which is di� iu� bebw. There are
also other fe� about this waN �d the re�ion of the wa� v�hich must be
CF'M l.aboratory. 1�E01 8bnrno�» Freeir� 9t1� G78. Fartnets &anch, TX 75�OQ3 97�,241-037{ Ppe 7
�;
l�
�I
u
�
�
�
u
L�J
�
�
�
u
LJ
L�J
�2/16/89 �7:50 2142410619
CPM LABORATORY INC.
dlscussed. because it is believed these other featurea bea� on the paint fai1ure8
which exist here.
Two paint failures on th�a wal! ar�d a third failure above the atalrway on the east
side of tt�e hallway show evidence for efffuorescence. EHtuorescence ia a
deposit which fortns on the surfacr of masonry or near a paint failure o� the
masonry. The deposit is the resuR of movement of water through the masonry
carrying with it soluble salts wt�ich depasit on the surface as the water �
evaporates. The water movement is caused either by evaporation or hydrostatic
pressure. Effluorescent salts incwde carbonates and sulfates which are present
in this plaster. An infrared apcctrutn of the eftluorescent sample is shown in
Figure 1 below.
Ff�une T. FTlR Spectncsm of E�fuor�scence from Simple 2
.�
�
��
adoo �dbo �doo �dbo
Aeaotoance r wa�rammcer (c�t)
F1N / 6 = K86vV1!
VYb, K{l9.1�2 SMiAPLE. 6T11FP OU'f OF P/11NT. KBR. 01-2QY7
�sbo �abo sdo
�pW X-tootfl CURSOR
Rts�4ar�1
The large peak near 1040 wavenumi)er� in the sp�ctrum indicates the
� effiuo�escence contains mosUy sut�ate. Cart�onate is also preserrt which could
a{so be present in the etfluocescet�ce or it cou{d be from plaster contami�a�on.
These salts are probably derived fr�om the plaster� however they sometimea
� come ftom soil which can� an outer waH, and it is possible for aalts to mtgrate
several feet above grade.
�
L�l
�l
The effluorescence observed on the we�t waU has caused some bulqing of the
paint layer. Sample locstion no. 2 taken ne�r the bottom af tfie stairvvell which
shows effluo�nce is below g�ade and directfy opposite a drain spout which
ru�s from a section of the Rat roof above down the outside of the building.
c�n �r,tory, �seo� st�no�x Froaw.y, su�a a29, Famw� s�,a�. nc 7so2a 97Z-24t-aS74 �. 8
PAr,E 09
l�J
�
u
L�J
�
u
�2/16/89 �7:50
21n2a10619
CPM LABORATORY INC.
Another failur�e observed on the west wa{I was toward the nofth, about half way
along the wali. This failure appea�ed to be above tt� outside grade but it atso
showed evidence of ef�tuonesoenoe. This entire {ength of wall is below grade
level to some degEee, with a turf�aaa along the full length on the outside of the
building. The east wal! by contr'ast has a parking bt along its bngth a�d it is at
ground (pa�icing bt} level. The e�st wait does not show any evidence of
effluorescence.
aSamples no. 3 and 4 were taken h�om the ceiling reglon and from #he inner
hallway wal! above the staitway dose ta sa�tnple 2. Thia is an interior walf in
contrast with the aampb from no. 2, ho�wer sample 4 from the wall atso shows
� evidence fo� etfluorescence. Upon further inapecxion� this waN is diredly balow
ths Junciion of the fl�t one story roof and the three stary ou�s�de wal1. There
could be a water prablem hare af�o� as the draf� pipes delnrer the water down
Donto the flat roof. Based upon the bcation of the failures ar�d the observation of
efffuorescence, it is conduded that the paint problems in this area of the building
aEe probably relat�d to water. {t 'rs alao noted tfiat the sample no. 3 ftom the
� ceiUng has the soft ye{Iow ptaster fay�r at the intertace with the p�aint and multiple
layers of paint are found here. i'herefare othe� probl� may also be operativve
at this locabon.
LiJ
LJ
��
u
�
L�
I,�
u
I�
�l
I�I
f�
Sample no. 5 is from a bcation nearly opposite w�ere aample 4 was acquired
but on the east inner wall. Dlrecay oppoaiUe this lor.ation is a door which lea�ds to
the pa�icing lot outside. There is �o e�videnoe for effloresce�ce here, afthough
this section is alsa directly below a ftat one stary roof. The paint here covera a
yel(ow plaster fitm over the white plaster as we find in most othe� locations which
we have examined.
Sample no. 6 was acquired from the cei�a�g betvveen pillars 2�d 3 on the we�t
side of the seats on the main f�oor. To provide a raference, piliar no. 1 is dosest
to the sta-ge and pil(ar no. 4 ia near the badc of the tast row of soats on tf�e main
floor. No paint fa�e�res wero observed between pNtars 3 and 4� but several
failures were observed betwee� p�ars 1 and 3. The ceiHn� above plllars 1 to 3
ia below the one story ftat roof which was discussed eailier, hawever the ce�ling
above the regbn between pillara 3 at�d 4 is nat part of this sing{e fEoor flat roofed
ragion. The paint from no. 3(between piilara 2 and 3) and the reierence sample
(between piHars 3 and 4) appear to be the same. The plastef is fdlowe� by a
thin yellow layer which is foNowed 6y a� aluminum paint, s'itnila� to tttat for
sample 1. No evide�ce for efi�ore�soe�ce is notad for sample 6.
Sample no. 7 was aoqu'�red irom the oeiFin� r�ea� the end of the long halMray on
the second levei bebw �nd down from the balcony. This hallway seems to be
relatively free of failures except at the two ertda near the stairs. 7fiis pai�t
sampb and the referonce also sMow the ye�ow ptaster layer foNowed by tt�e
aluminum paint. Being nea� the staitwell, the encts of the halhKay may be subject
CPM LaborAtory. 12E01 Stertxnpn9 Fteaway. &uits 829, Fsm+ers 6romah. TX TSOZS 97Z-?A1-Q374 Pagq g
PAGE 10
L^1
1�'
L�1
C
�
�
��l
LJ
L]
L�J
�u
a2ii6isg e�:�e
�142410619
CPM LABORATORY INC.
to drafty conditior�s whlch may resu� in greater temperaturae extremes and
greater fluctuatiorts in moisture level.
Sample no. 8 was taken from the west oeiiing di�ectty below the roof. It also
appears to have ttte yelioW layer over the plaster followed by tfie aluminum paint.
i ' n,� .=, i�• :i ��;• �=.r .1
In addltion to the eight samples and references, five ott�er �aint samples were
acquired. Two of them wero from the vent co�er on tfio ceilmg above the stage,
and another was acquired from tt� tidcet room on the east side near the main
auditorium entry.
A sampfe of the plaster from the veM v+ras prepared ��d �he i�frared spectrum
acquired. The spectrum w#tich is shown below does not retreal at�y aignific:ant
differences from the other plaster samp�les which have been examined,
differences such ns tfie presence � att�er com�onents of absence of
comportertts. Th'is doe� not mest� that thts ptaste� does not have inferior
physical differenc�a. VYe do see a sanall hydrocacbon p�c in this spectrum.
The portion csf the hydroca�bon peak which is not obsc�tred by other components
of the pi�ater, i.e.� the region near 3400 wavenumbers� loQks mudt q'ke the a
9lycal, however there ar�e other possib�s. The s'�gnif�aEx� of this peak with
resp�ct to the fa�ure of this plaster i� nc�# known.
F�GE 11
� �--�----�----��-r-------�-------r----_- _�r.__----�--
� � � , ��°°r�w � �
i � � , r � i
i i i � �
a•_--^^' � ------ ' "^'^' � "-^---� -------� .__._^ � _^_"_ ' .
'i `i "i i i ..� _ ..�..
� � � � � I
� . _ � ' � .. � � � , � � . .. ' .. .. � ' _
� 1 1 �
A . - � - ' - ' .. . w ir� R�►w �an�iwfl �inp� - .. � _ Adhi�A_ .. ' ' ' �"'
� � � � �
� � � � � �
� i i i k� i
a •�--------�.__----'--------�-------'--___-- `---- � �-'--------'--
� � � , � � �
� � � � � �
� � � � �
• � � � � � � �
a. . .__-_.`- _-- -`----.._.._�...._---- '------- -�--------'-•
, ' '►�a«l:� � � � � � �
� � � � � � �
D . , . . . .
1 I ��..r� ��. � I 1 1 -
.1._��- -�-- -'�-ti"'.. -'-r'^-'- -�.." ".---�"`f-' -'
� � � � � � i
� � � � � � i
t 1 � � 1 I
1 I 1 1
� �_"..'_�'..►'..��.��r-�..���..��.��_��`�r.�������M'���'�..1-' • ���..r�.
� 7Y� �1M � HM 1M� fM
N��Arw /�MMMII�r (w►q
�—�
C��
l�l
CAM Laboratory. 12001 8lertar+oos Ftwrrap. 8u16� e29� FtrmKs 8rancfi. TX 75�Z3 972-241-0374 Ppe 10
���
�
L'J
l�l
�LJ
Gi,
�J
LJ
�
��
�
1�
l�
L�
l=_!
�—.'
LJ
I;J
�
�
02/16/89 �7:5� 2142410619
CPM LABORATORY INC.
PAGE 12
We do not have data on tt�te te�r�ers+t�.+res which may exist st the ptaster aver the
vents during heating. 7emperature� in the neighbott�ood of 125 deg F and
above are known to produce probiems with plaster whicfi oause water loss and
can change the chemistry of the plaster in ways whic�t make it weaker.
l= �•=_ -, •� �•
�ne reason for paying so much attenti�on to the yellow layer nea� the plaster is
that it appeats to be involved in many of the failures we see, and it is present in
most of the samples which were �cqu�red. Many of the samples which wer�e
examined and aoquired had th�s yellow layer exposed wfiere the paint layer had
falle� away. Infra�ed analysis of tt� yelbw layer has oanvit�ced us that this is
part of the plastet, but is impregrtated w�h an otga�ic material. The spectra for
the yeNow layer from one sample is compared with the sPectrum of a plaster
sample in the figure below. The water, hydrocarbon� carbona�te, and suifate
peaks are identifled �n the figure below.
� --'--'--r-^-"_'r-"_---r----�^- _^"��'-r"-'-"�--_"..'--'
� � � � '
I i I 1 1 1 �
/ I 1 / I I
1 � 1 1
� � �
s-_..___--�-�-----�------..,.__..�.,_-r-�----- --,...-�--------�--
� � � � . � �
� , � � i
� � � i � i
i i i i i �
,�..__. _�- ..�._►.tMrllMrrM�hMrtfW�--^'�_ F--_--' '
� � � � --�- --
� i � � � � }�
� � 1 1 � �
�•---'..-'a._.-�^���---�-���..-'--�^�..�^.� �W- -.adhM�_......_� �_.
� � 1 1 CyEpMI� � �
I�K 1 1 I � 1 �
. 1 1 � 1
� � 1 1 1 1 1
i• _ _ _ _ ` _ _ _ _ ' � ' L � _ .. .. � ' _ L � _ _ _ � _ ..l . _ .. . _ ' ..1 _ _ _ I_ _ _ _ _ .. .. .. � _ .
1 � 1 1 �
�� �r _ � � 1 1 � �
1 M_IImfJ1OOf1 l � 1 1
I 1 1 1 1 1
t._._.. _L..__ �_....4..����__�'___ ���' .` �_' _._!_'
1 � 1 1 � � �
I 1 1 1 1 I
1 � Y��OM 1�f *� No i II�IW10� 1 t �
� �
� � i
0 � � ^� ___��___^_____ )_�^_^_ J__�___ " �'«__���1�
' _ ' ' ' ' _ � •• � � �iM HM IN� !01 �
�M�AMr1Yr.�I1�MRpHj
Notice the absence of tha hydroc�t�bon peak !n the white piaster. Other than this
difference the two materia� looic es�entially the same chem'�calty. In ocder to
facii'itate id�rrtiflc�tion of the orgal�Ic componBM� the yeNow layer was carefully
remaved from two ditferent pairrt sampbs while working under the microscope.
The isolated ye�tow samples were then exVacted with an ar+ganic sotver�#, and
tfie solvent was re�rwve� by disti�ation. The residue leR ai'�er the sotvent was
removed was anafyzed by infrar� speetroscopy and the apec.�tra are presented
belaw.
CPM Laba�ory.12E01 Sierrmor» Ft�ewtsy. 8�ib b29. Fstrner� &and�. iX 750�3 972-2�1-8�74 Pa�ge 11
�
I�I
L�J
�I
��
�
�
�
�
02/16/89 �7:5� 214241061�
CFM LABORATORY INC.
� � � � � �
� , , , ,
� �
� , � , � �
.M.._._...,._.'."_•"'-r -'-'_..�.,......"-r-"--'•r-'-----r---. ..._�_.
i i �M�CI � Y�7N MYK � K�06-C�qflp OI�N�t NI� � �,
� 1 1 1 I I
1 1 1 1 1
1 1 I 1 1 1 1
.a'____"".___'___'_"__-� ,__-'_'_" '_� ^_ ' __ _______�_'
• i alhA. �
i i � i i
� � � i i i
� � � i i i
� � i � i � i
.Ot .- � -'---� - ------� ----- ^ -w ^"_' --�------ - _'-"^-'--�'----- ---�- •
I 1 1 1 1 I
� 1 1 I I
� 1 1 1 I I 1
1 I I I I 1
� �
�Q � �NK �'K�10f11 �+T�I(10a11 YII�1! I 1
1 � 1 � � � 1
� � ." "" '.�f' "" "... _ _ """' �.... _. �.... � ��' � � �...
-r �--�-r----'--r--- r r
� i � i � �
� � i
i i �
• i � i � i �
���'�1 i I 1 1
•.R."'.."_' '�_'__''" _ __^! ^___���•���..�___ _,�
i � � ; j ""�' 1 1
iW 100� 37�1 i!d /M0 UY �
N�A�w I W�.�w }f1)
D The spectfa from the two samp{e extracts are identifted as molecules from a
d�ss of compaunds called fatty aclds. An exampte of a fatty acid ia olelc acid.
Ttte extracffi do not cor�tsin styr�te, a common compo�� of tatex emutsions.
Q Nor do they appeat to contain ei4her acrylics or vinyis, atso used irt emulsions.
Fatty acids of this type are moro typical of o4der paint tschnology w3�ich was used
in the 193Q's and later. The acida hawever, wouid h�ve bee� in the torm of
Q esters and not the free acida which ane ir�dicated by thc apectra. Fatty acid
eaters may be tound alkyd paint, varnist�, linseed oil� or oth�r oaating retated
products. Th� fact that tt�is extrac! is an organic acid form and not an ester form
D probabty means that this compo�ent of the plaster fitlish has u�ergone
hydrolysis {addition of water) whid� bres�ks an ester into �n alcottol and a� ac,id.
Hydrolysis of esters to fo�rn adds ia catalyzed by either acids or bases. Wdh al!
Q of the carbonate in the plaster, it shouM be quke afkafine (basic), and a moist
plaster may provide the envirottrnetit tiec;essary fot tlte hydrolysis of an ester
coating or sealer, The alkalinity � the Plaste� was tested by vvetting a cxushed
� sample af with wate� and then we!ling a p'�ce of pH paper with water. The pH of
the water was grea#er than 8 whioh is cloarty in ttte ��caHne rar�ge, and
sufficieMly basic to hydrolyae esteis.
�
�
C�1
�l
A careful examinatlon was made of the yeRow layer wfiiie working under the
microscope. The coating was prvbed gentty with a amaN tool while observirtg the
integrity of the caadng. In every oase which was ex�nined� th�s yellow tayer had
(itHe strength or integrity. It was solt and d�alky and wouid dump up when the
probe was moved acxoss the suriaca. In cocrtrast, many of ine paint layers w�re
much ha�der, and consolidated. Vlfith enough pressuro� a good paint could be
CPeA L�borxtory,12801 Siar�mora FrewvaY, Suka a29, F�rm�s BranM, TX 75Q23 972-241-s37� Pap� 12
PAGE 13
�
�
�
L�J
u
LiJ
��
�
�
�
L�I
�,�
LJ
I�J
l�l
l�
L�J
LJ
��
02/16/89 07:��
214241�619
CFM LABORATORY INC.
scraped away, but R did not crumble or break away easi{y as was observed with
this yellow layer.
The re�son for the softness af tha yellaw pla�ter layer is not know with certainty,
but it could be related to the hydrolysis of the organic coating. The arganic
coating itself would no lange� have the strength it once had as an este�, sittce
the ester bonds t�e tt�e acids toge�hef into {ong chains wiiich ha�e greater �
dimension and strengtfi. Acids may also react with lime and carbonate in the
plaster reducing the bonding strength in the regio� whet�e these acids are
formed--at the firt paiM surtace. Whatever the reaaon fior tho so�fiess of the
yellow layer, the fact is that it has lit�e integrity and ia probably re�sponsible for
some of the paint failures.
To undersiand this better requiras a� understanding oi plaster, ibs methaf of
applica�on and ita physical t�ar�ctetts3lt:s. When a plaster is appl'ied, it is
finished by trowekng, which c�mpac�s the out,cer layer and r+emoves �ome of the
water. The conaequsnce is the outer layer becarnas hard �nd dense compared
with the lower plaster. This hard a1cM provides the support for the paint, and
withstanda the forces app�ed to it by the drying paint. Certain paints such as
epoxy whicfi fomn extremely hard and stro�g layers are some�mes abte to cause
plaster failure.
When multiple tayera of paint bu� up on a plaster surface, the forces axe�ted on
the p{aster increase� if far no otfier reason than just Qravity. F�owever, ttte
strength of the pair�t can incrsase to the point tha# it is stronger than the plaster.
The plaster fails. (n the case herc, the plaster ia not only subjecc:t�d to add'�ional
forces relatsd to multiple layers of paint� but its bonding surface has been
weakened. The failure is at the plaster pairtt interfaoe and the paint generally
pulls away witf�out much plasber �ttached_ Thia is what ia observad in many but
not a!{ of the cases.
PAGE 14
An exception to tt�e failure )ust described is observed or� the piaste� from the
surtace over the vent on the ceil�rtg abov� th� section just in fror�t of the stage.
We vrere unable to get up to the ceiliing arxi acquire samp�es, but one small
sample was found on the floof, ar�d a sec:ond aet of aamp{ea was provided by
Jadc Dufiam. Each of theae aamples waa observad to t�ave faifed not in the
paint layer or at the pai�t ptaster i�rfa�ce� but within the pt�as�er tayer itself. This
failuse is probably a spec�al case wlthln the building. Most of the failures we
observed in this r+egion of the bu�ding wero directly over the vant cover, but not
in adjacent regions which were not pan of the vent cover. Preliminary
diacussions revealed that this vent region has always had a paiM peeling
problem.
CPM Lsbotatary, 12D01 Sqmrfwns FrNwq, 3uIM E24, Fsm1�s &anc}f, TX 75�3 972.211-d374 PsQ� 13
CI
���
�
L�
��
�
�2/16/89 07:50
2142410619
CPM LABORATORY INC.
Another issue concems the existence af the aluminum paint adjac:errt the
alkaline plasier layer. As poirtte� out above, tt�is metaUic coating reacts
vigorousiy wi#h an al�caline soludon. tt seems aimost inconoeivable that ove� the
course of time (preaumably 60 years tirrne), so�me m�tature haa �ot condensed in
this interfacial region, di�sc�lvving sorr�e of the alka�ne plaster a�d then reacfing
with tt�e metalfic paicrt. We loolced carefully for evid� of this twt we have
nathi�g direct to offer, other than the obvious failures of �is interface.
QWith aluminum pre�e� at the pla�ter surface, there is the possfbility of formation
of a minerai called ettringite (CazAl�(SO4).x HZQ wttiore x= 0 to 34} which ia a
dimensionally unst�ble materiai tha! can iorm in plaster. The presence af
4 aluminum paint could l�ad to iom�ation of ettringite crystals which can lead to
paint failure.
� In reviewing our data on the plss�er, some fruitfu! discussior�s were had with Mr.
Ed Jacacki with US Gypsum Cor}�ortati�on. Mr. Jacacici has c�siderabte
experience badc to the time that the 1M11 Rogers Auditorium was construCted.
�] One poirrt that he ma�e is that plastef has a�nite IN�etime, .from 5(f to 100 years.
�= The question arises is the plaster ne�ar �he end of its useful 1'�'e? tt does not have
the hard outer layer as lt shouki. Th!s �ayer has been degraded possibly through
� the decomposition of an otganic cornponent in the pt�sber. Since this yellow
layer has Imla physical ir�teDrity, and since thete ate so many paint layera�on top
of the ptaster� the minimum recomrn�idation wou{d be to remove�e�erything
� down to and below the yef�ow �ayer. This wouk! irtclude a!I of the aluminum paint
as well. It is recbmmended that US Gypsum and Mr. Jacada be contac.ted ior
re:cnmmendations on a surface tr�atrnent for the expos�d piaster. There are
� many products on the market which contain ofganic polymer whiah may provide
a satisiactory coating for the plas�r tio provide a base for �aint. .
�
�
The vent over the auditorium is another s'rtuation. Here the plasber is failing. tt is
not ce�tain if this is due to he�t atress or some other probl�n. A reinforced
plaster may be in order at thia bcatior�. and US Gypsum c�n make some spec'�fcc
recommendations here.
Finally, the west wall nnd ceiling on tfie main floo� showed evidence f�or a wate�
� problem. We suspect ttw�p ia waier infiltratio� in H�ese �egions and th3s shoutd
be inve�s�gated and corrected. The outer +nral! below the ground level may need
to be seated.
��i
LiJ
�
L�J
In summary, severa! problems ar paientia! problams have beer� identified. These
ace:
� A degraded iow inbagrity yellow p}aster layer exists undet' most of the paint
PAGE 15
�
� •
�
�
�
L�J
�
02/16/89 08:02 2142�10619
CPM LABORATORY INC.
• Water problems are evident on the west waii which have caused at least two
of the paint failures there
• Aluminum paint is found directly over the plaster in severai location� wfiich
couid decompo�e under alkali�e conditi�ons pr+esent in tfie piaster
+ The failures over the vent area on the c�iling in f�ont af tt� st�ge a�� due to
plaster faiiure and not paint failure. Thfs region may be too hot causing loss
of strengih of the plaator
a-ih•111f=f •:= i�f
0
� • Remove all p�int and yeNow plas�er. Qbtai� recommerxlations from U.S.
Gypsum about refinishirtg the remaining plaster in thesp locatans. �btain
raecommendatans from the pa�t manufacturer for a sui#able paint.
l�l
�
�
��1
LJ
L�
l�!J
�'
L�J
�
1=J
��J
• The water problems on the was! wall need to be itivestigaUed fu�ther before
any acction can be taken.
• The use of a simple plaster otier the c��ing vent in frorrt of the stage st�ould
be reconsidered. This IocatiQn may ca11 far a spec�a�/ formulated plaster
co�taining modifiers whict� would provide bettertemperature �tability. US
Gypsum (sea appendix io� caitact and number) has a variety of produ�ts
availabie which might be suibed for this focation, and perhaeps other iocations
as weli. Other conside�ttiorts indude uae of rein�orcit�g plasters.
CPM Laboritory, t280/ Siorrxnons Fre�r�p. 3u1� 828. F�rrr�.rs e�and�. TX 790�3 G72,?�41-03t4 PsW 1b
PAGE 01
a�.
�
�
�
�
�
�
�
�
�
�
�
�
0�
Q
�
�
�
�
02/16/89 03:02` 2142410619
, ..
�
CPM LABORATORY INC.
2. Floor Ptan of Vifiil Rogers Aud'e�r�m wiitt �ampling �ites t�ited
r+-�'''r-
� � � �
! i � � � � - �rr.'"'� ' _
�_...L � f , r
��5�
`
��
�
.�3 � � �.,�;� (� � .-� �
5
�
�� � . � .
. � , ,. I `�, �
� - - �
CPM LaDor9tory,12801 Stemme�ns Froew+�r. $Pu� 629� Fans�ero gfanch, 7X 75023 9T2-Y41�8374 Page �r
PGGE 03
�
�� _
E
�
�
�
�.._
I�
�
C�l
CITY OF FORT WORTH, TEXAS
CONSTRUCTION CONTRACT
THE STATE OF TEXAS
COUNTY OF TARRANT
KNOW ALL MEN BY THESE PRESENTS:
This agreement made and entered into this the 5�' day of October AD, 19 99 , by
� and befinreen the CITY OF FORT WORTH, a municipal corporation of Tarrant County, Texas, organized and
existing under and by virtue of a special charter adopted by the qualified voters within said City on the 11th
day of December, A.D. 1924, under the authority (vested in said voters by the "Home Rule" provision) of the
a Constitution of Texas, and in accordance with a resolution duly passed at a regular meeting of the City
Council of said city, hereinafter called OWNER, and Phoenix I Restoration & Construction. Ltd. of the
City of Dallas County of Dallas State of Texas hereinafter called CONTRACTOR.
a
�
�
�
[i
L�l
LRl
�
L1
LJ
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned to be
made and performed by the Owner, and under the conditions expressed in the bond bearing even date
herewith, the said Contractor hereby agrees with the said Owner to commence and complete the
construction of certain improvements described as follows:
PAINT AND PLASTER REPAIR
WILL ROGERS AUDITORIUM
WILL ROGERS MEMORIAL CENTER
That the work herein contemplated shall consist of furnishing as an independent contractor all labor, tools,
appliances and materials necessary for the construction and completion of said project in accordance with
the Plans and Specifications and Contract Documents adopted by the City Council of the City of Fort Worth,
which Plans and Specifications and Contract Documents are hereto attached and made a part of this
contract the same as if written herein.
The Contractor hereby agrees and binds himself to commence the construction of said work within ten (10)
days after being notified in writing to do so by the Owner.
The Contractor hereby agrees to prosecute said work with reasonable diligence after the commencement
thereof and to fully complete and finish the same ready for the inspection and approval of the Transportation
and Public Works Director of the City of Fort Worth and the City Council of the City of Fort Worth within a
period of 42 calendar days.
City agrees and binds itself to pay, and the said Contractor agrees to receive, for all of the aforesaid work,
and for stated additions thereto or deductions therefrom, the price shown on the Proposal submitted by the
successful bidder hereto attached and made a part hereof. Payment will be made in monthly installments
upon actual work completed by contractor and accepted by the Owner and receipt of invoice from the
Contractor.
The agreed upon total contract amount shall be $455.485.00 and includes the base bid and Alternates 1& 2.
Contractor agrees to complete the project, suitable for occupancy and beneficial use, within 42 calendar
days.
�'j The Contractor will provide a Certificate of Insurance listing the Transportation and Public Works Department
U as certificate holder, showing the required General Contractors Liability coverage, Auto Liability, Builder's
Risk and Worker's Compensation coverage. If this Contract is in excess of $25,000, the Contractor shall
a provide Payment Bond. �If the Contractor is in excess of $100,000, the Contractor shall provide both
Payment and Pertormance Bonds for the full amount of the contract. Contractor shall apply for all City of Fort
�
C-1
LJ
GI
�
r�
�
Worth Permits and for any other permits required by this project. City of Fort Worth Permit fees are waived.
Separate permits will be required for each facility.
If the Contractor should fail to complete the work as set forth in the Plans and Specifications and Contract
Documents within the time so stipulated, plus any additional time allowed as provided in the General Condi-
tions, there shall be deducted from any monies due or which may thereafter become due him, the liquidated
damages outlined in the General Conditions, not as a penalty but as liquidated damages, the Contractor and
his Surety shall be liable to the Owner for such deficiency.
IN WITNESS WHEREOF, the City of Fort Worth has caused this instrument to be signed in SIX (6)
counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with the
corporate seal of the City of Fort Worth attached. The Contractor has executed this instrument through its
duly authorized officers in SIX (6l counterparts with its corporate seal attached.
Done in Fort Worth, Texas, this the 5`h day of
��}c 1. ,�7a,C�¢-Tioh( 5i , � C.�
. �.
--�Con rac or�
APPROVIE : �! /
� � �,
� p�
� � i � �I i�
By: ,: `l; ��,.%" ;._ , � . � __ _ _
� � Assistant�ty Manager
By: �l ,�a- / [= C. .� //�,C'- S
Name
�2 E5 /'ZZ="l�lT
Office
October , AD, 19 99 .
� APPROVAL RECOMMENDED: RECORDED:
'a� �
���� �`� �, d��� .
By: � � � By: � '�� �!-�%d�.�-C��--
� Trans ortation and 1��fblic Works Cit creta
P �aZ. Y rY
1
�
�
�
'
1
�
�
APPROVED AS TO FORM AND LEGALITY:
By:
Assistant ' Attorney
�0�-:�` �'9
Date
C'2
Cr - %'"/ l� `��_..-..�.
Cozitract Authorization
�, �l�...����� --
Uate
�
L�I
C
L
C
�
J
L�J
�
I■
C
I■.
�
�I
�
�
�J
�
�
� Bond No. 22-000-201
THE STATE OF TEXAS
COUNTY OF TARRANT
KNOW ALL MEN
Restoration & Construction. Ltd.
PERFORMANCE BONI)
BY TI�SE PRESENT: That we (1) Phoenix I
(2) Companv of Texas hereinafter called Principal
and (3) Libertv Mutual Insurance Co�anv
, a corporation organized and existing under the laws of the State
and fully authorized to transact business in the State of Texas, as Surety, are held and firmly bound unto
the City of Fort Worth, a municipal corporation organized and existing under the laws of the State of
Texas hereinafter called Owner, in the penal sum of:
Four Hundred Fiftv Five Thousand, Four Hundred Ei�htv Five Dollars & No Cents
$455.485.00 Dollars in lawful money of the United States, to be paid in Fort Worth, Tarrant County,
Texas, for the payment of which sum well and truly be made, we hereby bind ourselves, our heirs,
executors, administrators, and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a
certain contraGt with the City of Fort Worth, the Owner, dated the Sth � day of October , 1999 , a
copy of which is hereto attached and made a part hereof, for the construction of:
PAINT AND PLASTER REPAIR
WILL ROGERS AUDITORIUM
WILLROGERS MEMORIAL CENTER
designated as Project Number C192-020192065009 , a copy of which contract is
hereto attached, referred to, and made a part hereof as fully and to the same extent as if copies at length
herein, such project and construction being hereinafter referred to as the "work".
NOW TI�REFORE, if the Principal shall well, truly and faithfully perform the work in
accordance with the plans, specification, and contract document during the original term thereof, and any
extensions thereof which may be granted by the Owner, with or without notice to the Surety, and if he
shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save
harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and
shall reimburse and repay the owner all outlay and expense which the Owner may incur in making good
any default, then this obligation shall be void; otherwise to remain in full force and effect.
PROVIDED FURTHER, that if ariy legal action be fled upon this bond, venue shall lie in
Tarrant County, State of Texas. �
AND PROVIDED FURTHER, that the said Surety, for value received, hereby stipulates and
agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work
to be performed thereunder or the specifications accompanying the same shall in any wise affect its
obligation on this bond, and it does hereby waive notice of any such change, extension of time alteration
or addition to the terms of the contract or to the work or to the specifications.
,
A:14PERBOND.FRM
�.
�
�
�
�
.�-
�
�
r
��
�,
�
�,
r
�.,
�
r
�
IN WITNESS WHEREOF, this instrument is executed in 6 Counterparts each one of which
shall be deemed an original, this the Sth day of October , 1999.
ATTEST:
�/�I/k cPa � ��t�
(Principal) Secretary
(SEAL)
12750 M�erit Drive. #710
(Address)
Dallas, TX 75251
�: WI'PNFSS :
(��.i .l "J�-+��... �� ���
(Surety) Secretary
(SEAL) , % '�
�.�_ '\
� — .� 1�` ... A 1�r�. ' � 1 � J;hi "" k� ,'i
Witness as to Surety � �
A:14PERBOND.FRM
Phoenix I Restoration & Constzuction, Ltd.
Principal (4)
By: .� .li�',/�
- �
�q lE C. �JEl� G �'
(Printed ame/Title)
6822 Maple Avenue
ADDRESS
Dallas, Tx 75235
CITY/STATE/ZIP
Liberty Mutual Insurance Conmanv
(Surety)
� � — /
/<� � /�-�
By: C_ �� , �-i�� ,_ -��. : ,
(Attorney-in-Fact) (5)
Elnora Cruthis
(Printed Attorney-in-Fact)
No�e:
(1)
i1)
(3)
(4J
(5)
Da�e of Bond mus� not be prior to date oj
Conlracl
Correct name ojContractor
A Corporalion, a Partnership or and
Individual, as case may be
Correct Name of Surety
If Conlracto� is parinership all Partners
should execute bond
A true copy of Potiver of Attorney shall be
anached to bond by At�orney-in-Fac1
J
�
�
�J
�
I�l
u
�
Bond No. 22-000-201
THE STATE OF�TEXAS
COUNTY OF TARRANT
;
PAYMENT BOND
BOND NO. 141503264
, KNOW ALL MEN BY THESES PRESENTS: That we, Phoenix I Restoration &
Construction. Ltd. a corporation of Dallas County, Texas , hereinafter called
Principal and (3) Libertv Mutual Insurance Co�x-uzv
, a corporation organized and existing under the laws of the State and fully
authorized to transact business in the State of Texas, as Surety, are held and firmly bound unto the City
of Fort Worth, a municipal corporation organized and existing under the laws of the State of Texas,
hereinafter called Owner, and unto all persons, firms, and corporations who may furnish materials for, or
perform labor upon, the building or improvements hereinafter referred to in the penal sum of:
Four Hundred Fiftv Five Thousand, Four Hundred Eightv Five Dollars �& No Cents
$455.485.00 lawful money of the United States, to, be paid in Fort Wo�th, Tarrant County, Texas, for the
payment of which sum well and truly be made, we bind ourselves, o�r heirs, executors, administrators
and successors jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a
� certain contract with the City of Fort Worth, the Owner dated the 5t� day of October , 1999,
a copy of which is hereto attached and made a part hereof, for the construction of:
�
C
Ci
PAINT AND, PLASTER REPAIR �
WILL ROGERS ALIDITORIUM
WILLROGERS MEMORIAL CEI�TER
. i
designated as Project Number C192-020192065009 copy of which contract is hereto
attached, referred to, and made a part hereof as fully and to the same extent as if copied at length herein,
such project and construction being hereinafter referred to as the "works".
NOW, THEREFORE, the condition of the obligation is such that, if the Principal shall promptly
� make payment to all claimants as defined in Article 5160 of the Revised Civil Statutes of Texas,
supplying labor and materials in the prosecution of the work provided for in said Contract, then this
obligation shall be null and void, otherwise it shall remain in full forc�.and effect.
Iel
�
THIS BOND IS MADE AND ENTERED into solely for the protection of all claimants supplying
labor and material in the prosecution of the work provided for in said Contract, as claimants are defined
in said Article 5160, and all such claimants shall have a direct right of action under the bond as provided
in Article 5160 of the Revised,Civil Statutes.
PROVIDED FURTHER, that if any legal action be filed upon this bond, venue shall lie in
aTarrant County, State of Texas, and that the said Surety, for value received, hereby stipulates and agrees
that no change extension of time, alteration or addition to the terms of the contract or to the work to be
performed thereunder or the specification accompanying the same shall in any wise affect its obligations
� on this bond, and it does hereby waive notice of any such change, extensiori of time, alterati.on� or
addition to the terms of the contract or to the work or the specifications.
� A:15PAYBOND.FRM
�
�
�
��.
�
PROVIDED FURTHER, that no final settlement between the Owner and the Contractor shall
abridge the right of any beneficiary hereunder whose claim shall be unsatisfied.
IN WITNESSETH WHEREOF, this instrument is executed in 6 counterparts, each one of which
shall be deemed an original, this the Sth day of October , 1999.
� ATTEST:
������vu sf�p �`�iti� C�tJ
� (Principal) S c� retary
� (SEAL)
�.
r� .
L,
�
�
� ,
1..+
12750 Nl�rit Drive, #710, Dallas, TX
(Address) /���1
� WI'I'iVESS :
!�� � �� ,Y��� ��' I � C�� �
(Surety) Secretary
(SEA ��
�`�� -� � ; �' �� f
i � �_ i�, �-i� � _ 1 _� ����1 k �i ��
� Witness as ko Surety
Phoenix I Restoration & Construction, Ltd.
Principal (4)
Y: d-�. C.._.
�r l�y41c�'. �ll�=e�, ��2C`=,�ivcJ�/;
(Printed Name/Title)
6822 Maple Avenue
ADDRESS
Dallas, TX 75235
CITY/STATE/ZIP
Liberty Mutual Insurance Canpany
(Surety)
� �,
, �,%
By: C �,. .1�� ;?� ��r�-:��
(Attorney-in-Fact) (5)
Elnora Cruthis
(Printed Attorney-in-Fact)
Note:
(1)
(2)
(j)
(4)
Date oj Bond must nol be prior to date of
Conlract
Correct name of Contractor
A Corporation, a Partnership or and
Individual, as case may be
Correct Name oJSurety
Ij Con�ractor is Partnership all Partners
shou/d execute bond
�
.,
�
�
THIS POWER OF ATTORNEY IS NOT VALID UNLESS IT IS PRINTED ON RED BACKGROUND. C�^ O� C
J �-f J
This Power of Attorney limits the act of those named herein, and they have no authority to bind the Company except in the
manner and to the extent herein stated.
LIBERTY MUTUAL INSURANCE COMPANY
BOSTON,MASSACHUSETTS
POWER OF ATTORNEY
�
KNOW ALL PERSONS BY THESE PRESENTS: That Liberty Mutual Insurance Company (the "Company"), a Massachusetts
mutual insurance company, pursuant to and by authority of the By-law and Authorization hereinafter set forth, does hereby name,
constitute and appoint, SHEILA M. YOUNG, ELNORA CRUTHIS, DERRELL C. DODSON, DOUGLAS MOORE,
SAM J. MULLIS, JR., LUKE J. NOLAN, JR., ALL OF THE CITY OF DALLAS, STATE OF TEXAS ................................
...............................................................................................................................................................................................
� ...............................................................................................................................................................................................
...............................................................................................................................................................................................
, each individually if there be more than one named, its true and lawful attorney-in-fact to make, execute, seal, acknowledge and deliver, for and on its
�"�� behalf as surety and as its act and deed, any and all undertakings, bonds, recognizances and other surety obligations in the penal sum not exceeding
! TVUENTY FIVE MILLION AND 00/10;i • •�'**"***** DOLLARS ($ 25,000,000.00****'` ) each, and the execution of such bonds or
� undertakings, in pursuance of these presents, shall be as binding upon the Company as if they had been duly signed by the president and attested by
w the secretary of the Company in their own proper persons.
�
�N
C �
�- ..
c
i •�
4:,, �
�3
i�
� �
tC
'-� >
+ �
��
�
.y
�� d
y o
�
�
,�
��
d
� �
O R
a
v
�� �
O`
� 3
C�
That this power is made and executed pursuant to and by authority of the following By-law and Authorization:
ARTICLE XVI - Execution of Contracts: Section 5. Surety Bonds and Undertakings.
Any officer or other official of the company authorized for that purpose in writing by the chairman or the president, and subject to such
limitations as the chairman or the president may prescribe, shall appoint such attorneys-in-fact, as may be necessary to act in behalf of the
company to make, execute, seal, acknowledge and deliver as surety any and all undertakings, bonds, recognizances and other surety
obligations. Such attorneys-in-fact, subject to the limitations set forth in their respective powers of attorney, shall have full power to bind the
company by their signature and execution of any such instruments and to attach thereto the seal of the company. When so executed such
instruments shall be as binding as if signed by the president and attested by the secretary.
By the following instrument the chairman or the president has authorized the officer or other official named therein to appoint attorneys-in-fact:
Pursuant to Article XVI, Section 5 of the By-laws, Assistant Secretary Garnet W. Elliott is hereby authorized to appoint such attorneys-in-fact
as may be necessary to act in behalf of the company to make, execute, seal, acknowledge and deliver as surety any and all undertakings,
bonds, recognizances and other surety obligations.
That the By-law and the Authorization above set forth are true copies thereof and are now in full force and effect.
IN WITN�SS iNrIERF'OF, ;his instrument has been subscribed by its authorized officer and the corporate seal of the said Liberty Mutual Insurance
Company has been a�lixed th�r�to in Plymouth Meeting, Pennsylvania this 19th day of Map , 1�q .
'� � �`j LIBERTY MUTUA� INSURANCE COMPANY
gy 1774rt+✓t„� i� Gs:e%Le.'vl�
Garnet 1N. E!liott, Assist�n, SPcretary
COMMONWEALTH OF PENNSYLVANIA ss
COUNTY OF MONTGOMERY
On this 1�h day of May , q.p, 1999 , before me, a Notary Pubiic, personally came the individual, known to
me to be the therein desc ' �yidual and officer of Liberty Mutual lnsurance Company who executed the preceding instrument, and he acknowled-
ged that he executed �arne at��,tFfaT the seal affixed to the said preceding instrument is the corporate seal of said company; and that said corporate
seal and his signatu �'��,� t�,"e'��was duly affixed and subscribed to the said instrument by authority and direction of the said company.
� IN TESTIMO �
�
4
=OF, I t� set my hand and affix my official seal at Plymou Meeting, P, the day and year first above written.
�`� ' ` ? /,��f�%vYt�t i; fl���gJ
� � � � :�� 3 , ., �; � � Notary Public
i � ,.•-« r .hrt F ( > zt ..� -�
�iBL?1#�'����� � „_ �R�"t�r�ia�'E �
I, the undersigne , �ta&i�'�retary of Liberty Mutual Insurance Company, do hereby certify that the original power of attorney of which the
foregoing is a full, true and c c copy, is in full force and effect on the date of this certificate; and I do further certify that the officer who executed the
� said power of attorney was one of the officers specially authorized by the chairman or the president to appoint any attorney-in-fact as provided in Article
XVI, Section 5 of the By-laws of Liberty Mutual Insurance Company.
This certificate may be signed by facsimile under and by authority of the following vote of the board of directors of Liberty Mutual Insurance
Company at a meeting duly called and held on the 12th day of March, 1980.
E, VOTED that the facsimile or mechanically reproduced signature of ary assistant secretary of the company wherever appearing upon a certified
���+ copy of any power of attorney issued by the company, shall be �ralid and tinding upon the company with the same force and effect as
though manually affixed.
IN TESTIMONY WHEREOF, I have hereunto subscribed my name and affix�d the corporate seai of the said company, this 5�
� : OCtn}-�r , 1 A �3 A . , �,
i �-`,
'' �
� �' , ��� sistant ecPetary
�' THIS POWER OF ATTORNEY MAY NOT BE USED TO EXECUTE ANY BOND WITH AN INCEPTI E AFTER Mav 19
day of
, 20 ��
C�
�Certificate Holder:
Date: � '
Project Name:
�Project Number:
This is to certify that:
Address:
C�RTIFICA�'E OF INSURANCE
City of Fort Worth
October 5,1999 '' �
Paint and Plaster Repair — Will Rogers Auditorium
C192-020192065009 ' -
Phoenix I Restoration & Construction, Ltd.
6822 Maple Avenue � .
� Dallas, Tegas 75235 �
is at the date of this certificate, insured,by this company with respect to the business operations hereinafter described, for the
�type of insurance and in accordance with the provisions of the standard policies used 6y this Company, and further
hereinafter described. Exceptions to standard policy noted on reverse side thereof. � �
Tvne ofInsurance
� POLICY NO.
aWorkers Compensation ' y�K9100899-
, Comprehensive General
LiabilityInsurance� KK09100837
� (Public Liability)
� Blasting
QCollapse of Buildings
or structures adjacent to
excavations
�
�'
E�crrvE ExriuEs
04-1-99
04--1-99
04�1-00
04�1-00
LIMITS OF LiABILTTY
Statutory 500,000 EL
Bodily Injurj+: $
Each Occumnce. �See xever:�e
Property Damage: �
Each Occurrence: S
included above in general l:.ability
included above �.n general l:.ability
Each Occurcence $
Each Occwrence $
Damagetounderground included above in general 1=.ability
Utilities
Buildec'sRisk �09100837 . 04-1-99 04-1-00
Comprehensive
AutomobileLiability KK09100837-1
^ Contractual Liability
4�
� Other
Each Occurrence
Bodily Injury
04-1-99 04-1-00 �hPerson
• Each Occurrence
'Propecty Damage
. • Each Occurrence
Bodily Injury
included above in general ].iability EachOccunence
Property Damage
Each Occurrence
$
$ 1,000,000 Combined�
s Single
Limits
S
S
S
KK09100837 04-1-99 04-L=00 $2,500,000 Any or.e job-$1,OOq,000'Frame
Locations covered: Paint and Plaster Repair - Will Rogers Auditorium, Ft . Worth , Texas
�Description ofoperations covered: Commercial construction operations including paint & plaster repair
The above policies either in the body� thereof or by appropriate endorsement provide that they may not be changed or canceled by the
insurer in less than five (5) days after the insured has received written notice of such change or cancellations. �
� Where applicable local laws or regulations require more than fi ) days a 1 no ' e f change or cancellation to be assured, the above
policies contain such special requirements, either in the body ther� by op ' orsement thereto attached. �
�' Agency Dodson-Bateman & Company "`
`'� Fort �ti/orth Agent By; Douglas Moore
Address 8350 Meadow Rd, Ste 181 Title: Vice President
aDallas, Tx 75231 .
n A:121NSURAN.FRM
6„J
0
General Liability Limits:
$1,000,000 Occurrence
$2,000,000 General Aggr'egate �
$2,000,000 Products/Completed Operations Aggregate
$1,000,000 Personal & Adv. Injury .
$100,000 Fire Damage Legal Liability
$10,000 Medical Expense `
This is to certify that the policies of insurance listed have been issued to the
insured named for tlie policy period indicated, notwitfista�ding any requizement, term
or condition of any contract or other document with respect to which this certificate
may.be.issued or may pertain.�The insurance afforded by the policies described
herein is subject to all the terms, exclusions and cortditions of such policies.
Limits shown may have been reduced by paid claims.
Exceptions ta standard policies:
Commerical General Liability:�
- Exclude Nuclear Energy Liabil�.ty
- Intercompany Products Lawsuits Exclusion
Issu7�ng Comp�n�,es : �
Wozkers Compens�ti�on -- St, ��.ul Insurance Co�
General Liabil�,ty �'St� Paul Fire & Mar�ne �ns�rance Co.
Builders Risk -- St. Paul ��.re & Maxine Insurance Co:
�utomobile L�,a�il�ty � �t. �aul Guardian Tnsurance Co.
a
�
�
�
�
CONTRACTOR COMPLIANCE WITH
WORKER'S COMPENSATION LAW
Pursuant to Article 8308-3.23 of Vernon's Annotated Civil Statutes, Contractor, Phoenix I
Restoration & Construction. Ltd. certifies that it provides worker's compensation insurance
coverage for all of its employees employed on City of Fort Worth project Paint and Plaster
Renair — Will Ro�ers Aditorium project number, C192-020192065009.
� � ����
�9/cG��l�-�zs� ,�,�,�,�,-
Title
to 1 ��-1 4S
Date
STATE OF TEXAS 3
� COUNTY OF TARRANT 3
BEFORE ME, the undersigned authority, on this day personally appeared
� �_7�4 I r L. � l I�S , known to me to be the
person whose name is subscribed to the foregoing instrument, and acknowledged to me that he
� executed the same as the act and deed of
�� !�5�cx�4n�� �:� C'a��reucT�o�: �7v , for the purposes
� and considerations therein expressed and in the capacity therein stated.
� GIVEN LTNDER MY HAND AND SEAL OF OFFICE this /� day of
� U c j , 19 `� 1.
�
:
/--7 /�
� ��
N ary Public, State ot 7exaa tary Public in and for the State of Texas
�O'� My Commission Expires OS-13-20
`-' (a) Contractor agrees to provide to the City a certificate showing that it has obtained a policy
�"'� of workers compensation insurance covering each of its employees on the project in compliance
� with state law. No Notice to Proceed will be issued until the Contractor has complied with this
section.
� (b) Contractor agrees to require each and every subcontractor who will perform work on the
project to provide to it a certifcate from such subcontractor stating that the subcontractor has a
� policy of workers compensation insurance covering each employee employed on the project.
Contractor will not permit any subcontractor to perform work on the project until such certificate
� has been acquired. Contractor shall provide a copy of all such certificates to the City.
A:13WORKCOM.FRM
�
City of Fort Worth, Texas
�1►�Ay�r a�ttd C�aunc�l �,arr�mun���,��on
DATE REFERENCE NUMBER LOG NAME PAGE
10/5/99 **C-�7676 I 20PHOENIX I 1 of 2
SUBJECT AWARD OF CONSTRUCTION CONTRACT TO PHOENIX I RESTORATION AND
CONSTRUCTION, LTD. FOR PAINT AND PLASTER REPAIR OF THE WILL ROGERS'
AUDITORIUM
RECOMMENDATION:
It is recommended that the City Council approve the execution of a consXruction contract with Phoenix I
Restoration and Construction, Ltd. for the paint and plaster repair of the Will Rogers Auditorium in the
amount of $455,485.00 with a contract duration of 42 calendar days for the Base Bid. The contract
includes two alternates.
DISCUSSION:
With the renovation of the Fort Worth Convention Genter and the removal of the JFK Theater, the Will
Rogers Auditorium becomes the �emaining venue for stage produc�ion. The interior paint requires
restoration to maintain the appearance of this historic building.
The existing paint consists of eight layers of old paint, some of which contain lead. The paint will be
completely removed and the plaster surface prepared for the new paint. Several aceas will require
additional plaster patch and repair.
The project was divided into three sections to provide flexibility in award:
• The Base Bid includes the paint of the• proscenium. (To be completed in 42 days,
since the auditorium will not be usable.) .
• Alternate #1 includes the first floor level lobby, aisles, stairs to the second level and
the ceiling under the balcony.
• Alternate #2 includes the mezzanine and the balcony level.
Alternates #1 and #2 can be accomplished subsequent to the proscenium work.
The City of Fort Worth Architectural Services Section prepared the construction documents.
The project was advertised in the Fort Worth Star-Telegram July 8 and 15, 1999. On August 5, 1999,
the following bids were received: -
BIDDER
Phoenix I Restoration
and Construction, Ltd.
Architectural Utilities
BASE BID
$1�77,965.00
$371,000.00
ALTERNATE #1 ALTERNATE #2
$186,150.00 $ 91,370.00
$520,000.00 $160,000.00
TOTAL
$ 455.485.00
$1,051,000.00
Phoenix I Restoration and Construction, Ltd., is in compliance with the City's M/WBE Ordinance by
committing to 27% M/WBE participation. The City's goal on this project is 26%.
This project will•not have an operational impact on the General Fund budget.
� K.
The Will Rogers Auditorium is in COUNCIL DISTRICT 7.
City of Fort Worth, Texas
A or Af1� aunc�l ammun�cAt�an
�� y C C
DATE REFERENCE NUMBER LOG NAME PAGE
10/5/99 **C-17676 20PHbENIX I � 2 of �
SUBJECT AWARD �F CONSTRUCTION CONTRACT TO PHOENIX I RESTORATION AND
CONSTRUCTION, LTD. FOR PAINT AND PLASTER REPAIR OF THE WILL ROGERS
AUDITORIUM
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds required for this expenditure are available� in the current capital
budgets, as appropriated, of the Culture and Tourism Fund and the Public Events Improvements Fund.
MG:j
�
Submitted for City Manager's
Office by:
Mike Groomer 6140
Origin'ating Department Head:
Hugo Malanga � , 7801
Additional Information Contact:
Hugo'Malanga 7801
I FUND I ACCOUNT I CENTER I AMOUNT
� (t�)
I
�
�
� (from)
IGG04 541600 0240600 $406,038.00
C192 541200 020192065009 $ 60,000.00
CITY SECRETARY
APPROVED
CITY COUNCIL
OCT K 1999
({�,W., �a�.r�.�"
�� �,.��p of t2te
Cit'! ci Fort Worth, 7l'e�►s