F o p,- ` o R-F H City of Fort Worth
Change Order Request
Project Name: Trinity Boulevard Phase 2 -Salado Trail to Thames Trail City Sec No.: 61420
Project No.(s): 103280 DOE No. N/A CityProj.No.:l 103280
Project Description:
Trinity Boulevard Phase 2 Salado Trail to Thames Trail - Roadway, Drainage, Waterline, Landscape and Illumination
Imorovements
Contractor: I Jackson Construction, Ltd. Change Order # Date: 6/10/2026
City Project Mgr.1 Mitch Aiton/Preeti KC City Inspector: I Mark Kitts
Phone Number: 1 682-715-9424 Phone Number: (214) 746-5004
Dept. I Water I Sewer
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
981,705.00
37,870.79
019.575.79
TPW Totals Contract Time
(Calender days)
117,637.00 $12,099,342.00 730
$37,870.79
117,637.00 1 $12,137,212.79
Amount of Proposed Change Order
$0.00
$0.00
$0.00
3
Revised Contract Amount $5,019,575.79 $7,117,637.00
Original Funds Available for Change Orders $250,000.00 $550,000.00
Remaining Funds Available for this CO $212,129.21 $550,000.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$12,137,212.79
733
$800,000.00
$762,129.21
0.31 %
$15,124,177.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 4 will provide for the adjustment to the height of an above -ground air release valve in the
median. Due to the height of an existing waterline, an above -ground air release valve was needed, initially
designed to be 4.5' above ground. The height adjustment to the design will reduce the height by 3' to help not
distract from the additional landscaping and trees added by the TPW Trinity Boulevard project. The contractor has
requested 3 additional days to the contract.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Contractor Name Contractor Signature
Date
Jackson Construction, Ltd.
All Jones I Ali Jones (Jun 16, 2026 07:02.03 CDT)
06/18/2026
Inspector
Date
Project Manager
Date
Marx Kitts
Mark Kitts (Jun 17, 2026 12:53:41 CDT)
06/17/2026
-
06/22/2026
Director (Water Dept)
Date
Construction Supervisor (Water)
Date
rto her-earde�
Christopher Harder (Jun 26. 2026 14:44:37 CDT)
06/26/2026d>-<E�«a-ua�-
06/18/2026
Senio stant City Attorney
Date
Assistant City Manager
Date
&*e
:, zozs v:azw cono
06/26/2026 o-\ t%!. au
07/06/2026
_a.
FORTq>7
Council Action (If Required);
M&C Number N/A
ATTEST: M&C�°oa°� I N/A
Jannette Goodall, City Secretary aaanrezAs4`�
F[}YZ-r W"P,T-Y4 City of Fort Worth
Change Order Additions
Project Name I Trinity Boulevard Phase 2 - Salado Trail to Thames Trail City Sec No.: 1 61420
Project No.(s): F103280 DOE No. N/A City Proj. No.: 103280
Project
Description
Trinity Boulevard Phase 2 Salado Trail to Thames Trail - Roadway, Drainage, Waterline, Landscape and Illumination
Improvements
Contractor Jackson Construction, Ltd. I Change Order:® Date: 6/10/2026
City Project Mgr. Mitch Aiton/Preeti KC City Inspector FMark Kitts
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
II-45 Air Release Valve Adjustment Water 1.00 LS $14,362.21 $14,362.21
Water $14,362.21
Sewer
TPW
Page 1 of 1 Additions Sub Total
Fc)n-r W"H-u City of Fort Worth
Change Order Deletions
Project Name Trinity Boulevard Phase 2 - Salado Trail to Thames Trail
Project No.(s): 1 103280 DOE No. N/A
Project Description
City Sec No.: 61420
City Proj. No.: 103280
Trinity Boulevard Phase 2 Salado Trail to Thames Trail - Roadway, Drainage, Waterline, Landscape and
Illumination Improvements
Contractor Jackson Construction, Ltd. Change Order: ® Date 6/10/2026
City Project Mgr. Mitch Aiton/Preeti KC City Inspector: Mark Kitts
DELETIONS
ITEM IDESCRIPTION DEPT I Qty JUnit I Unit Cost ITotal
II-41 lWater Construction Allowance Water I 0.10 LS 1$150,000.00 1$14,362.21
Page 1 of 1
Water $14,362.21
Sewer
TPW
Deletions Sub Total $14,362.21
NIMBE Breakdown for this Change Order
Previous Change Orders
co#
DATE
AMOUNT
1
3/10/2025
$37,870.79
2
3/27/2025
$0.00
3
8/7/2025
$0.00
Total
$37,870.79
Page 1 of 1
103280-CNCO-Trinity Blvd Ph 2 CO #4
Interim Agreement Report 2026-06-17
Created: 2026-06-16
By: Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
Status: Draft
Transaction ID: CBJCHBCAABAAyEt7X3Xs4DJ_5klOG3di5DTEV08g52fX
Agreement History
Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will
be generated when the agreement is complete.
"103280-CNCO-Trinity Blvd Ph 2 CO #4" History
Li Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
2026-06-16 - 10:07:57 PM GMT- IP address: 204.10.90.100
FoRTWORTH. I P"""edisy
Adobe
Acrobat Sign
FORT WORM,
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: Trinity Blvd Ph 2 CO #4
M&C: N/A CPN: 103280 CSO: 61420 DOC#: N/A
Date: 6/10/2026
To:
Name
Department
Initials
Date Out
1.
Mitch Aiton
TPW - Approval
M
06/17/2026
2.
Ali Jones
Jackson - Signature
,!,
06/18/2026
3.
Mark Kitts (Inspector)
TPW - Signature
MMK
06/17/2026
4.
Cristobal Fuentes (Const Super)
TPW - Signature
4S
06/18/2026
5.
Preeti KC (PM Sign)
Water - Signature
preetiKC
06/22/2026
6.
Tony Sholola
Water - Approval
06/26/2026
7.
Chris Harder (Director)
Water — Signature
H�
06/26/2026
8.
Doug Black
Legal — Signature
AsBiack
06/26/2026
8.
Jesica McEachern (ACM)
Water — Signature
07/06/2026
10.
Jannette Goodall
CSO - Signature
eneGooda„
07/06/2026
11.
TPW Contracts
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW
Contracts
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and
take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ❑YES ®No SAME DAY: ❑YES ®No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required: ❑ Attach Signature, Initial and Notary Tabs
❑ As Requested
® For Your Information
® Signature/Routing and or Recording
® Comment
❑ File
Return To: Please notify TPWContracts(a)fortworthtexas.i!ov for pickup when complete. Call ext.
7233 or ext. 8363 with questions. Thank you!
F0 RT WO RT H
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Jackson Construction, Ltd.
Subject of the Agreement:
Air Release Valve on Line C.
This Change Order Request is to add the pay item for the adjustment of
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
61420
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No 8
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103280
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.