HomeMy WebLinkAbout061319-CO2 - Construction-Related - Contract - The Fain Group, LLCCSC No. 61319-CO2
FORT WORTH. City of Fort Worth
Change Order Request
Project Name[ Citywide Miscellaneous Pavement Repair Unit Price Contract City Sec # 1 61319
Client Project #(s)[ Various Projects
Project Description Construction services on an as -needed (task order) basis for miscellaneous pavement rehabilitation projects throughout
the City.
Contractor[ The Fain Group, LLC Change Order# 2 Date[ 6/9/2026
City Project Mgr. Marwan Hafez City Inspectorl Omar Fri as
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
TPW
Totals
Contract Time
(CD)
$2,740,000.00
$2,740,000.00
$0.00
$0.00
$0.00
$2.740.000.00
$2.740.000.00
Revised Contract Amount $2,740,000.00 1 1 1 1 $2,740
Original Funds Available for Change Orders
Remaining Funds Available for this CO $0.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1 0.00% 1
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $3,425,000.00 71
JUSTIFICATION (REASONS) FOR CHANGE ORDER
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL furnish all labor, materials, equipment, and incidentals necessary to complete the work
described in Change Order No. 2. This change order adds a new bid item for the repair and reconstruction of existing vault tops located on the two bridges along White
Settlement Road and N. Henderson Street. Field observations identified deterioration of the existing vault tops and lids, requiring corrective action to restore the structures to a
safe and serviceable condition. The work includes removal of the existing vault lids, demolition of the deteriorated upper portion of the vault structures as necessary, cast -in -
place reconstruction of new vault tops, and installation of new vault lids. These repairs are necessary to address the deteriorated condition of the existing infrastructure, maintain
structural integrity, provide safe access, and ensure the continued reliable operation of the vaults.
Staff reviewed the proposed unit price, compared it with recent bid tabs and pricing for similar work, and determined the cost to be fair and reasonable.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractors Company Name
Contractor (Name) Contract Signature
Date
The Fain Group, LLC I
Larry Frazier (---
06/18/2026
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
-
06/11/2026
06/18/2026
Program Manager
Date
Senior Capital Pra'ect Officer
Date
eer.
06/18/2026
—
06/18/2026
Assistaot-Director De —
Date
Director, Contracting Department De t
Date
7028 10:50-16 C-)T)
06/25/2026
Z---Z—
06/25/2026
Assistant City Attorney
Date
Assistant City Manager
Date
D q],,e ,k(J� 30.xoeerocsM,WT
06/30/2026
07/08/2026
Council Action (if required)
aoovonnn M&C Number NIA
FOR? 1 a
ATTEST: OF.°°° °° .YaOd
Jannette Goodall, City Secretary 0� * a°
�aaQ4 nEap5a4�
M&C Date Approved N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORTWORTH City of Fort Worth
111,- Change Order Additions
Project Name Citywide Miscellaneous Pavement Repair Unit Price Contract City Sec # 61319
Client Project # Various Projects
Contractor The Fain Group, LLC PM Manvan Hafez Inspector.F Omar Frias
Change Order Submittal # Date 6/9/2026
AUUI I IONS
ITEM DESCRIPTION DEPT Oty Unit Unit Cost Total
83 9999.0011 Vault Top Repair TPW 0.00000000 EA $13,742.00 S0.00
TPW S0.00
Sub Total Additions S0.00
Change Order Additions Page 2 of 3
FOR rWoRi City of Fort Worth
V-- Change Order Deletions
Project Name I Citywide Miscellaneous Pavement Repair Unit Price Contract City Sec # 61319
Client Project # F Various Projects
Contractor The Fain Group, LLC PM Marwan Hafez Inspector Omar Fria,
Change Order Submittal # 0 Date 619I2026
Change Order Deletions Page 3 of 3
FORT WORTH
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: Citywide Miscellaneous Pavement Repair Unit Price Contract
— Change Order 2
M&C: 24-0242 CPN: Various CSO: 61319 DOC#:
Date: 06/09/2026
To:
Name
Department
Initials
Date Out
1
Ann Estes (BSP)
TPW
06/11/2026
2
Larry Frazier/The Fain Group, LLC
Vendor
06/18/2026
3
Omar Frias (Inspector)/Lorrie Pitts (Sr. Inspector)
TPW
OF
06/11 /2026
4
Marwan Hafez (PM)
TPW
/49
06/18/2026
5
Zelalem Are a (PGM)
TPW
06/18/2026
6
Mary Hanna (SCPO)
TPW
ht�
06/18/2026
7
Patricia Wadsack (AD)
TPW
p(,W
06/25/2026
8
Lauren Prieur (Director)
TPW
xxv P„e ,
06/25/2026
9
Doug Black (ACA)
Legal
Douglas 81ack �
06/30/2026
10
Jesica McEachern (ACM)
CMO
07/08/2026
11
Jannette Goodall CS
CSO
07/08/2026
12
TPW Contracts
TPW
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
ALSO List: - Bus Sppt: Ann Estes; Prg Mgr: Zelalem Areea; Sr CPO: Mary Hanna
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and
take the next steps.
NEEDS TO BE NOTARIZED
RUSH: DYES ®No
[—]YES ®No
SAME DAY: DYES ❑No NEXT DAY: DYES ®No
ROUTING TO CSO: ®YES ❑No
Action Required: ❑ Attach Signature, Initial and Notary Tabs
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
Return To: Please notify TPWContracts(i ,fortworthtexas.gov for pickup when complete. Call ext. 7233 or ext.
8363 with questions. Thank you!
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: The Fain Group, LLC
Subject of the Agreement: Change Order No. 2 to CSC No. 61319, a Unit Price Contract for Citywide
Miscellaneous Pavement Repair Projects
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
Expiration Date:
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No 8
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable.
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.